Exhibit E- 013300 Submittals.pdf

PDF 160 KB Posted

Attached to
Main Ring Electrical P-F3 to P-F4 15KV Cable Installation, FESS Project 3-7-103B
Solicitation number
375108-CD
Issued by

About this file

This document is a Submittals section (013300) from Fermi Forward Discovery Group, LLC, dated January 2025, detailing the requirements for submitting project-related documentation. The section outlines comprehensive procedures for shop drawings, material samples, and operations maintenance manuals, including specific requirements for subcontractors. Key submission guidelines include: submitting six copies of operation and maintenance manuals, using a standardized "Submittal for Review Transmittal" form, maintaining as-built drawings during construction, and following a detailed review process where FFDG will respond within 10 working days with actions such as "No Exception Taken", "Revise & Resubmit", or "Rejected". The document also provides instructions for material substitutions, requiring detailed comparisons and potential design change explanations when proposing alternative products.

View the file

Other files

File Type Posted
Amend 03 to RFP 375018-CD.pdf PDF
375108-CD Amendmant 2 Revised Response to Questions.pdf PDF
375108-CD Amendment 2 Revised Exhibit R - Proposal Form.pdf PDF
375108-CD Amendment 2 Revised Drawings.pdf PDF
Amend 02 to RFP 375108-CD.pdf PDF
375108-CD Amendment 1 Revised Exhibit R - Proposal Form.pdf PDF
375108-CD Amendment 1 Revised Drawings.pdf PDF
375108-CD Amendmant 1 Response to Questions.pdf PDF
Amend 01 to RFP 375108-CD.pdf PDF
Exhibit B2- Section 16121 Medium Voltgage Cable.pdf PDF
Exhibit H - 2025 Construction Insurance Requirements.pdf PDF
Exhibit I - Bond Bid FL-41.pdf PDF
Exhibit M - Fermilab Subcontractor Safety Information Questionnaire.pdf PDF
Exhibit P- Davis Bacon Wage Rates.pdf PDF
1.0 RFP 375108-CD.pdf PDF
Exhibit B1- Section 16010 General Electrical Requirements.pdf PDF
Exhibit B3- Section 16125 15KV Cable Installation.pdf PDF
Exhibit C- 010010 General Requirements.pdf PDF
Exhibit G- FFDG General Terms and Conditions for Construction (08.2025).pdf PDF
Exhibit J - Bond Payment FL-42.pdf PDF
Exhibit K- Bond Performance FL-40.pdf PDF
Exhibit L - Statement of Acknowledgment (SF-1413).pdf PDF
Exhibit Q- Summary of Required RFP Submittal Documents.pdf PDF
Exhibit A- P-F3 TO P-F4 15KV Cable Installation SOW.pdf PDF
Exhibit N - SARC_Subcontractor Annual RepsCerts Rev 4_FFDG.pdf PDF
Exhibit O - Proposal Certifications Form PUR-466_FFDG.pdf PDF
Exhibit S- Sample Firm-Fixed-Price Subcontract.pdf PDF
Exhibit B Drawings.pdf PDF
Exhibit B4- Section 16450 Grounding and Bonding.pdf PDF
Exhibit B5- Section 16950 Testing Electrical Systems.pdf PDF
Exhibit D- 013100 ESH Requirements.pdf PDF
Exhibit F- 014100 Quality Requirements.pdf PDF
Exhibit R - Proposal Form 375018-CD F3 to F4 15KV Cable Installation.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Fermi Forward Discovery Group, LLC Submittals January 2025

SUBMITTALS 013300 - 1

SECTION 013300 – SUBMITTALS

PART 1 GENERAL

1.1 PURPOSE

This section specifics general methods and requirements of project work related submittals. Additionally detailed submittal requirements may be found in the bid design and/or technical specification sections.

1.2 REFERENCES

The publications listed below form a part of this subcontract to the extent referenced.

010010 General Requirements 013100 Environment, Safety, and Health Requirements

1.3 SHOP DRAWINGS, MATERIAL SAMPLES, AND OPERATIONS MAINTENANCE

MANUALS

Subcontractor shall submit for all materials and assemblies used on the project which are normally required in the construction industry. In addition, project schedules shall be submitted using the “Submittal for Review Transmittal” found in Attachment A and logged as part of the submittal file.

Refer Construction Subcontract Terms and Conditions, for additional information on shop drawing submittals.

The Subcontractor shall supply six (6) copies of all operation and maintenance manuals or an electronic PDF version for equipment furnished by the Subcontractor or their Sub-tier contractor prior to final acceptance of the project by Fermi Forward Discovery Group, LLC (FFDG).

The Subcontractor shall complete the "Submittal for Review Transmittal" form for each shop drawing submittal, reference Attachment A.

Shop drawings and schedules of all trades shall be submitted by the Subcontractor, who shall indicate by signed stamp on the drawings, that he has checked the shop drawings and that the work shown is in accordance with the Subcontract requirements and that it has been checked for dimension and relationship with the work of all trades. These drawings shall be submitted not later than the approved schedule for shop drawing transmittal, shall contain all required detailed information, and shall be submitted in logical order to facilitate proper review.

Shop drawings which relate to a complete assembly, structure or system with various parts shall not be submitted until all drawings required to completely detail that assembly, structure or system are complete, so that they may be checked in relation to each other.

SUBMITTALS 013300 - 2

1.4 IN LIEU OF THE AS-BUILT SHOP DRAWINGS

As specified in FFDG Construction Subcontract Terms and Conditions, the Subcontractor shall furnish As-Built drawings as outlined below.

The Subcontractor shall maintain a set of prints of the Subcontract drawings in the construction office at the job site. A daily record, in red, shall be kept on these prints of the work installed with all modifications or changes thereon. This set of prints shall be available to FFDG for inspection at all times and print copies provided upon request to FFDG within 24 hours of the request being made. The CMO and the Subcontractor's superintendent shall review the as-built drawings, and the scheduling of a progress payment update will be contingent on whether the as-built mark-up set is current and accurate.

Upon completion of all work, the Subcontractor shall transmit the above set of marked-up prints to FFDG. Prior to submittal, the Subcontractor shall sign them to indicate that the work was installed as shown thereon.

1.5 FFDG’S ROLES

FFDG shall be the final judge of the acceptability of any and all drawings. Final acceptance of the work is contingent on the receipt and FFDG's approval of the complete set of As-Built prints.

The Following distribution of drawing and technical specifications will be made by FFDG to the Subcontractor:

After the award of the Subcontract and prior to Notice to Proceed, FFDG will make available five (5) sets of conformed Drawings and Technical Specifications;

For any change as defined under FFDG Construction Subcontract Terms and Conditions, FFDG will make available three (3) copies of all revised Drawings and/or Technical Specifications;

Additional copies of either the conformed bid documents or any revised documents issued under the "Changes" provision shall be the responsibility of the Subcontractor.

1.6 USING THE SUBMITTAL FOR REVIEW FORM

Submittals shall be submitted to FFDG, reference 010010 for contact information.

1.7 SUBMITTAL PROCESS

FFDG will review the submittals and return one copy of all shop drawings within 10 (ten) working days with one of the following actions:

“No exception Taken” response on the Subcontractor’s shop drawings submittal and “NET” as shown on the Submittal for Review Transmittal form indicates the Subcontractor may proceed with procurement, fabrication, manufacture and installation of the material and/or product;

“Revise & Resubmit – Fabrication May Proceed” on the Subcontractor’s shop drawing submittal and “R/R” as shown on the Submittal for Review Transmittal form indicates the Subcontractor may proceed with procurement, SUBMITTALS 013300 - 3 fabrication, and manufacture of the material and/or product assuming the noted items on the submittal are incorporated into the final design and/or product. The Subcontractor will revise the shop drawings and resubmit them to FFDG for approval, but will not be able to erect and/or install any material until he has received either the “No Exception Taken (NET)” or the “Make Corrections and Proceed (MCP)” action by FFDG;

“Make Corrections & Proceed” response on the Subcontractor’s shop drawing submittal and “MCP” as shown on the “Submittal for Review Transmittal” form indicates the Subcontractor may proceed with procurement, fabrication, manufacture and installation of the material and/or product assuming the noted items on the submittal are incorporated into the final design and/or product;

With the “Rejected” response on the Subcontractor’s shop drawing submittal and “R” as shown on the “Submittal for Review Transmittal” form, the reasons for the disapproval will be stated on the shop drawing submittal.

The Subcontractor will revise the shop drawing submittal to conform to the drawings and specifications and resubmit them to FFDG for approval. No procurement, fabrication, manufacture or installation shall be performed by the Subcontractor until one of the above actions listed above is received;

“For Information Only” response on the Subcontractor’s shop drawing submittal and “FIO” on the “Submittal for Review Transmittal” form acknowledges receipt of such items as test results, professional engineering calculations, welding certificates and inspection reports.

1.8 MATERIAL SUBSTITUTIONS

Products or materials which are equal to, or the equivalent of, those specified will be considered for approval by FFDG. The submittal procedure will be the same as above, with the following additional conditions: In addition to the required information for the substitute material, the submittal shall contain the same information pertaining to a product named in the specification for purposes of comparison.

The submittal shall explain fully the differences, if any, between the proposed product and those named in the specification.

Any change to the drawings or specifications for related work required for proper installation of the proposed substitute product shall be indicated in the submittal.

If the proposed substitute product requires alterations of any kind to other equipment or to the building or necessitates any engineering design changes for its proper installation, such alterations and engineering design changes shall be accomplished at no cost to

FFDG.

PART 2 PRODUCTS - Not Used

PART 3 EXECUTION – Not Used

END OF SECTION

013300 -ST- 1

ATTACHMENT A

013300 -ST- 1

Submittal for Review Transmittal

TO: Fermi National Accelerator Laboratory Submittal No.:<XX-XX-XXX-XXX> P.O. Box 500, MS-214 Batavia, Illinois 60510

FROM: <Subcontractor’s Name>

<Subcontractor’s Address> <Subcontractor’s City and State>

Date: Project No.: <XX-XX-XXX>

Attn:

Project Name:

Submittal Item

No.

Specification Section or

Drawing No.

(If Applicable)

Description

Comments: