Exhibit B5- Section 16950 Testing Electrical Systems.pdf

PDF 254 KB Posted

Attached to
Main Ring Electrical P-F3 to P-F4 15KV Cable Installation, FESS Project 3-7-103B
Solicitation number
375108-CD
Issued by

About this file

This document is a comprehensive electrical systems testing specification for a 15kV cable installation project. The specification (Section 16950) provides detailed guidelines for inspection, testing, and quality control of electrical systems, focusing on medium voltage cable installation, termination, and grounding. Key requirements include performing DC high potential tests on cables, documenting cable pulling and splice inspections, checking grounding/earthing systems, and completing multiple standardized inspection checklists (Forms 65F1100 series) to verify compliance with technical standards.

The document outlines specific testing procedures for various electrical components, including requirements for cable installation, termination inspections, insulation resistance testing, and motor run-in tests. Multiple attachments provide inspection checklist templates covering underground conduit, cable pulling, cable terminations, grounding systems, and panelboard inspections. The specification references standards from ANSI, IEEE, NEMA, and NETA, and emphasizes the importance of thorough documentation, safety precautions, and adherence to manufacturer's instructions throughout the electrical installation process.

View the file

Other files

File Type Posted
Amend 03 to RFP 375018-CD.pdf PDF
Amend 02 to RFP 375108-CD.pdf PDF
375108-CD Amendmant 2 Revised Response to Questions.pdf PDF
375108-CD Amendment 2 Revised Exhibit R - Proposal Form.pdf PDF
375108-CD Amendment 2 Revised Drawings.pdf PDF
375108-CD Amendment 1 Revised Exhibit R - Proposal Form.pdf PDF
375108-CD Amendment 1 Revised Drawings.pdf PDF
375108-CD Amendmant 1 Response to Questions.pdf PDF
Amend 01 to RFP 375108-CD.pdf PDF
Exhibit B Drawings.pdf PDF
Exhibit B4- Section 16450 Grounding and Bonding.pdf PDF
Exhibit D- 013100 ESH Requirements.pdf PDF
Exhibit F- 014100 Quality Requirements.pdf PDF
Exhibit R - Proposal Form 375018-CD F3 to F4 15KV Cable Installation.pdf PDF
1.0 RFP 375108-CD.pdf PDF
Exhibit B1- Section 16010 General Electrical Requirements.pdf PDF
Exhibit B3- Section 16125 15KV Cable Installation.pdf PDF
Exhibit C- 010010 General Requirements.pdf PDF
Exhibit G- FFDG General Terms and Conditions for Construction (08.2025).pdf PDF
Exhibit J - Bond Payment FL-42.pdf PDF
Exhibit K- Bond Performance FL-40.pdf PDF
Exhibit L - Statement of Acknowledgment (SF-1413).pdf PDF
Exhibit Q- Summary of Required RFP Submittal Documents.pdf PDF
Exhibit B2- Section 16121 Medium Voltgage Cable.pdf PDF
Exhibit H - 2025 Construction Insurance Requirements.pdf PDF
Exhibit I - Bond Bid FL-41.pdf PDF
Exhibit M - Fermilab Subcontractor Safety Information Questionnaire.pdf PDF
Exhibit P- Davis Bacon Wage Rates.pdf PDF
Exhibit A- P-F3 TO P-F4 15KV Cable Installation SOW.pdf PDF
Exhibit E- 013300 Submittals.pdf PDF
Exhibit N - SARC_Subcontractor Annual RepsCerts Rev 4_FFDG.pdf PDF
Exhibit O - Proposal Certifications Form PUR-466_FFDG.pdf PDF
Exhibit S- Sample Firm-Fixed-Price Subcontract.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P-F3 TO P-F4 15KV CABLE INSTALLATION 3-7-103B

TESTING ELECTRICAL SYSTEMS 29 JANUARY 2020 16950-1

SECTION 16950 - TESTING ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. This section prescribes the basic minimum requirements for field testing and inspection of electrical equipment and work.

1.02 RELATED WORK SPECIFIED ELSEWHERE

A. Refer to previous Sections which describe items of related Work. Coordinate Work prescribed by this Section with Work prescribed in previous sections.

1.03 RELATED TECHICAL REQUIREMENTS

A. Project sections.

B. Subcontract drawings.

C. Manufacturer’s instruction manuals, drawings, and information applicable to the apparatus, equipment and systems.

1.04 RELATED WORK

A. Examine all portions of the Subcontract documents for work related to the work of this Section. Provide all work hereunder as required for the support and accommodation of related work.

PART 2 - CONDITIONS

2.01 GENERAL

A. The work of this section is subject to the FRA Construction Subcontract Terms and Condition.

2.02 APPLICABLE STANDARDS

A. The publications listed below form part of this Section. Each publication shall be the latest revision and addendum in effect on the date of subcontract award, unless noted otherwise. Except as specifically modified by the requirements specified herein or the details on the drawings, the Work included under this Section shall conform to the provisions of these publications:

1. ANSI (American National Standards Institute):

a. ANSI/IEE 400 Guide for Making High Direct Voltage Tests on Power Cable Systems in the Field.

P-F3 TO P-F4 15KV CABLE INSTALLATION 3-7-103B

TESTING ELECTRICAL SYSTEMS 29 JANUARY 2020 16950-2

2. IEEE (Institute of Electrical and Electronics Engineers).

3. NEMA (National Electrical Manufacturers Association).

4. NETA (National Electrical Testing Association).

PART 3 - EXECUTION

3.01 GENERAL

A. This Section provides guidelines for the inspection, testing, and checkout of the electrical systems to ensure that the electrical installation is in accordance with the design sections, drawings, and manufacturer's instructions.

B. The listings and descriptions of the inspections, tests, and checks described herein shall not be considered as complete and all inclusive. Additional normal standard construction (and sometimes repetitive) checks and tests may be necessary throughout the course of the Work.

C. Medium voltage cable testing shall be performed by an independent subcontractor paid by the Subcontractor in accordance with NETA (National Electrical Testing Association).

1. Coordination of cable testing shall be arranged under this subcontract (cable installation subcontract) to provide FRA and testing subcontractor with ample time and notice. Cable installation subcontractor shall provide the FRA Construction Coordinator 24-hours notice of time and period available for cable testing.

2. Cable installation subcontractor shall provide a knowledgeable workman to be present at all times during the cable testing. Workman's duties and responsibilities shall include, but not be limited to, verification of cables to be tested, removal of end boots or seals, verification of all safety precautions, keeping manholes free from water and acting as subcontractor's representative for verification of cable test results.

3. Independent cable testing subcontractor is responsible for hi-pot testing as cables (only) as described on Form #65F1104, attached.

4. All other testing and reporting as described herein shall be the responsibility of the cable installation subcontractor.

D. The checks and tests shall be documented on the attached Quality Control Forms. Quality Control Forms shall be available for FRA review at any time during the Subcontract. Completed Quality Control Forms shall be given to the FRA Construction Coordinator at the conclusion of the Subcontract.

E. Subcontractor shall be responsible for all inspection and test activities. The detail implementation plan shall be reviewed and approved by the FRA Construction Coordinator.

P-F3 TO P-F4 15KV CABLE INSTALLATION 3-7-103B

TESTING ELECTRICAL SYSTEMS 29 JANUARY 2020 16950-3

F. Equipment or circuitry shall not be energized, de-energized, or tied-in to a system without prior review and approval of the test plan and procedure, prepared and submitted by the Subcontractor.

3.02 TESTING AND INSPECTION OF EQUIPMENT AND CABLE

A. Preparation:

1. A detailed plan and schedule shall be prepared for inspection and testing activities.

2. Manufacturer, make, model and serial numbers of the instruments used shall be recorded on the test forms.

3. Testing and checkout work shall be performed with fully qualified personnel skilled in the particular tests being conducted. This is essential for obtaining and properly evaluating data while the tests are in progress, and for ensuring that important facts and questionable data are reported.

4. The test supervisor shall ensure that testing and checkout work is conducted in a safe manner. Special safety precautions such as the following shall be utilized:

a. Lockout and tagout procedures.

b. Barricades.

c. De-energization or isolation of equipment before testing.

d. Review of procedures with safety personnel.

e. Erection of warning signs.

f. Stationing of guards and watchmen.

g. Maintenance of voice communications.

h. Personnel orientation.

i. Project Hazard Analysis and Job Hazard Analysis as required.

5. The test apparatus shall be of the proper voltage class and rating for the test being performed. Care shall be taken that the installation shall not be overstressed.

6. At any stage of construction and/or when electrical equipment or systems are determined to be damaged, faulty, or requiring repairs, the electrical equipment or systems shall be reported to the FRA Construction Coordinator. Corrective action may require prior approval.

P-F3 TO P-F4 15KV CABLE INSTALLATION 3-7-103B

TESTING ELECTRICAL SYSTEMS 29 JANUARY 2020 16950-4

3.03 INSPECTION AND TEST OF ELECTRICAL INSTALLATION

A. Additional inspections may be carried out by FRA. FRA inspection shall not alleviate the requirement for inspection as defined herein.

PART 4 - ATTACHMENTS

Attachment 6:

Form: 65F1300: Electrical Punch List Record

Attachment 7:

Form: 65F1200: Underground Conduit (Duct Bank) Inspection Checklist

Attachment 9:

Form: 65F1202: Aboveground Conduit Inspection Checklist

Attachment 10:

Form: 65F1100: Conduit Sealing Inspection Record

Attachment 12:

Form: 65F1204: Cable Pulling Inspection Checklist

Attachment 13:

Form: 65F1101: Insulation Resistance Test Record

Attachment 15:

Form: 65F1205: Medium and High Voltage Cable Termination Inspection Checklist

Attachment 16:

Form: 65F1103: Medium and High Voltage Cable Splice Inspection Record

Attachment 17:

Form: 65F1104: DC High Potential Test (Medium Voltage Cable) Test Record

Attachment 18:

Form: 65F1105: Ground/Earthing System (Grid or Loop Type System) Inspection Record

Attachment 21:

Form: 65F1108: Ground Continuity (Non-electrical Equipment/Structures) Test Record

Attachment 23:

Form: 65F1110: Panelboard Inspection Record

Attachment 42:

Form: 65F1129: Electric Motor Run-In Test Record

P-F3 TO P-F4 15KV CABLE INSTALLATION 3-7-103B

TESTING ELECTRICAL SYSTEMS 29 JANUARY 2020 16950-5

SECTION 16950

ATTACHMENT 6

FORM: 65F1300

ELECTRICAL PUNCH LIST RECORD

DATE: REV.: REF. DWG.:

Item No

Identification & Location Remarks Date

Corrected Supervisor’s

Approval

DISTRIBUTION SUBCONTRACTOR/DATE

P-F3 TO P-F4 15KV CABLE INSTALLATION 3-7-103B

TESTING ELECTRICAL SYSTEMS 29 JANUARY 2020 16950-6

ATTACHMENT 7

FORM: 65F1200

UNDERGROUND CONDUIT (DUCT BANK) INSPECTION CHECKLIST

DATE: REV.:

NOTE: THIS CHECKLIST SHALL BE USED DURING THE INSPECTION OF

UNDERGROUND UTILITIES

1. Trenching checked for location, elevation and forming. Check for conflicts with other construction.

2. Conduit size, type and location checked for conformance to Sections and drawings

3. Minimum concrete coverage will be in accordance with Sections on all sides of conduits.

4. Conduit spacing, supports and tie-downs correct.

5 Stub-up dimensions and location checked.

6. Field bend radius correct in accordance with drawings/Section bends free of deformities.

7. Pipe caps on all ends

8 All conduit connections tightly made.

9 Reinforcing bars installed when specified.

10. All field changes recorded on as-built drawings

11. Trench or forms free of debris

12. Concrete coverage adequate, spacers not left exposed.

13. Concrete color in accordance with Sections.

14. Stub-up concrete encasement correct.

15. Backfill and compaction correct

16. Conduits free of such things as stoppages and grout leakage.

P-F3 TO P-F4 15KV CABLE INSTALLATION 3-7-103B

TESTING ELECTRICAL SYSTEMS 29 JANUARY 2020 16950-7

ATTACHMENT 9

FORM: 65F1202

ABOVEGROUND CONDUIT INSPECTION CHECKLIST

DATE: REV.:

NOTE: THIS CHECKLIST SHALL BE USED DURING THE INSPECTION OF CONDUIT

1 Supports and spacing in accordance with Sections, codes & drawings

2. Supports adjacent to terminal fittings.

3. Conduits clean, stub-ups protected, open ends plugged, damage during construction repaired

4. Field bend radius correct in accordance with Sections and codes. Bends free of deformities.

5. Expansion joints as required.

6. Installation neat and evenly spaced

7. Conduit permanently and effectively grounded, unless Sections permit otherwise. Bonding jumpers installed around inspection joints.

8. Proper fittings installed with threads fully engaged; no wrench cuts, conduit ends have bushings and covers installed

9. Drains installed in accordance with Sections.

10. RGS, PVC or PVC-coated conduit installed when specified on drawings

11. Flexible conduits installed with proper bending radius and with standard fittings.

12. Junction boxes leveled and supported with proper hubs, locknuts and bushings installed, in accordance with drawings. Junction boxes properly identified.

13. Adequate number of pulling points.

P-F3 TO P-F4 15KV CABLE INSTALLATION 3-7-103B

TESTING ELECTRICAL SYSTEMS 29 JANUARY 2020 16950-8

P-F3 TO P-F4 15KV CABLE INSTALLATION 3-7-103B

TESTING ELECTRICAL SYSTEMS 29 JANUARY 2020 16950-9

ATTACHMENT 10

FORM: 65F1100

CONDUIT SEALING INSPECTION RECORD

DATE: REV:

BUILDING: AREA/UNIT: PANEL BOARD TAG:

NOTE: THIS CHECKLIST SHALL BE USED DURING THE INSPECTION OF CONDUIT SEALS

1. Receiving Operations/Inspection complete.

2. Equipment Protection Program instituted and documented.

3. Check assembly for any missing parts.

4. Enclosure approved for area classification.

5. Panelboard circuit schedule filled out.

6. Correct circuit breaker fuse size and location.

7. Neutral wire correctly color-coded.

8. Grounding/earthing installed and connected. Test Record, Form 000.265.F1109.

9. Ground Continuity Test Record (Electrical Equipment & Ground Test Bars), completed.

10. Seals installed (if required).

11. Check for breather and drain.

12. Check panel load balance.

13. Check color-coding of branch circuit conductors.

14. Clean out.

15. Check mounting and supports.

16. Fixtures and receptacles are correct type and installed as per drawings.

17. Fixtures and receptacles on correct circuit.

18. Nameplate, number of circuits and panelboard location per drawing.

19. Correct glands installed (i.e., flameproof glands on explosion-proof enclosures.).

20. Megger buses including neutral. Record results on Form 65F1124.

21. Insulation Resistance (Equipment) Test Record. Main disconnect & outgoing circuits should be open.

22. Equipment Protection Program completed and documented.

23. Final inspection complete. Punch items on Form 65F1300, Electrical.

24. Punch List Record, cleared.

P-F3 TO P-F4 15KV CABLE INSTALLATION 3-7-103B

TESTING ELECTRICAL SYSTEMS 29 JANUARY 2020 16950-10

P-F3 TO P-F4 15KV CABLE INSTALLATION 3-7-103B

TESTING ELECTRICAL SYSTEMS 29 JANUARY 2020 16950-11

ATTACHMENT 12

FORM: 65F1204

CABLE PULLING INSPECTION CHECKLIST

DATE: REV.: REF. DWG.:

NOTE: This Inspection Checklist shall be used for cable pulling in conduit and ducts.

1. Check that conduit has been swabbed-out and any standing water removed.

2. Check that number of pulling points is adequate and the number of bends between pulling points does not exceed Section or code requirements.

3. Check cable reel assignments and cutting schedules.

4. Check cable voltage rating, minimum pulling temperature and type of pulling compound.

5. Inspect cables for jacket damage.

6. Ambient temperature within manufacturer’s recommended installation limits.

7. Monitor pulling tension on critical pulls and verify that maximum permitted tension not exceeded in accordance with tension data.

8. Perform DC High Potential Test (hypot) on medium and high voltage cables (rated over 2000 volts) and record on Test Record, Form 65F1104, DC High Potential Test Record (Medium Voltage Cable).

9. Bend radius of trained cable is in accordance with Sections and cable is free of kinks.

10. Installation is neat and cable lay (maintained spacing) in accordance with Sections.

11. Cables identified in accordance with Sections and drawings.

12. Cable ends sealed after cutting.

13. Manhole grounding system installed.

14. Cable neutral conductors grounded.

15. Cables firewrapped in manholes.

P-F3 TO P-F4 15KV CABLE INSTALLATION 3-7-103B

TESTING ELECTRICAL SYSTEMS 29 JANUARY 2020 16950-12

ATTACHMENT 13

FORM: 65F1101

INSULATION RESISTANCE TEST RECORD

TEST EQUIPMENT:

TEST VOLTAGE:

AMBIENT TEMPERATURE: º C º F

Panel No.

Feeder No.

Circuit No.

Wire Tagging

Cable-rated

Voltage Quantity Size From To

Insulation Resistance

(Megaohms) Initials

Cable-rated voltage (ohms) Test duration Resistance for cable quality Cable/wire size or amperage (megaohms) Resistance when cable connected to equipment

P-F3 TO P-F4 15KV CABLE INSTALLATION 3-7-103B

TESTING ELECTRICAL SYSTEMS 29 JANUARY 2020 16950-13

ATTACHMENT 15

FORM: 65F1205

MEDIUM AND HIGH VOLTAGE CABLE TERMINATION INSPECTION CHECKLIST

NOTE: This Inspection Checklist shall be used for terminations rated greater than 2000 volts. Inspection Record

CIRCUIT NO.: DWG.:

KIT MANUFACTURER: KIT NO.:

Check Item

1. Cable size, type, location, installation and routing in accordance with drawings.

2. Bend radius in accordance with specifications and cable jacket free of kinks.

3. Cable termination supports and support spacing in accordance with drawings and specifications.

4. Installation neat and evenly spaced.

5. Cable free of surface damage.

6. Termination kit/materials installed in accordance with manufacturer’s instructions.

7. Document DC High Potential Test (hypot) on Form 65.F1104, DC High Potential Test Record (Medium Voltage Cable), or obtain appropriate documentation from testing Subcontractor.

8. Cable terminated in accordance with equipment manufacturer’s instructions including torquing of bolted connections.

9. Check phase location and marking: Left to Right, Top to Bottom, or Front to Rear, in accordance with specifications requirements.

A. Acceptable

B. Acceptable

C. Acceptable

10. Metallic Sheaths/Shields/Armor grounded/earthed in accordance with manufacturers recommendations.

P-F3 TO P-F4 15KV CABLE INSTALLATION 3-7-103B

TESTING ELECTRICAL SYSTEMS 29 JANUARY 2020 16950-14

ATTACHMENT 16

FORM: 65F1103

MEDIUM AND HIGH VOLTAGE CABLE SPLICE INSPECTION TEST RECORD

NOTE: This Inspection Record shall be used for cables rated greater than 2000 volts. INITIAL/DATE

REFERENCE DWG. SPLICE NO.

SPLICE KIT MANUFACTURER

KIT NO KIT NO

CIRCUIT NO

FROM TO

CABLE RATED VOLTAGE CABLE TYPE

1. Location

Manhole Number

2. Splice Make-up:

A. Acceptable

B. Acceptable

C. Acceptable

Neutral Acceptable

3. Document DC High Potential Test (hypot) on Form 65F1104, DC High Potential.

Test Record (Medium voltage Cable), or obtain appropriate documentation from testing Subcontractor.

4. Sheath grounded/earthed, as required

5. Field changes recorded on as-built drawings.

6. Splice markers installed.

P-F3 TO P-F4 15KV CABLE INSTALLATION 3-7-103B

TESTING ELECTRICAL SYSTEMS 29 JANUARY 2020 16950-15

ATTACHMENT 17

FORM: 66F1104

DC HIGH POTENTIAL TEST (MEDIUM VOLTAGE CABLE) TEST RECORD

CIRCUIT NUMBER: REF DWG.:

CABLE SIZE: (SQMM) (MCM)FROM: TO:

NUMBER OF CONDUCTORS: NUMBER OF SPLICES:

CABLE LENGTH MANUFACTURER:

INSULATION TYPE: THICKNESS:

JACKETMATERIAL:

WEATHER: TEMP: º C º F HUMIDITY: %DATE:

TEST EQUIPMENT USED:

NOTES:

1. The test voltage shown below shall be reached in 10 equal voltage increments.

2. After each voltage increase, the leakage current shall be allowed to stabilize during a 1 minute interval. If 1 minute intervals are insufficient to stabilize the current, the cable shall be discharged, and the test repeated with new time intervals of greater, but still equal duration

3. Record the stabilized leakage current, in microamps, at the end of each time interval.

4. Allow the voltage to remain constant at the full test voltage and record the leakage current for 5 minutes for unshielded cables and 15 minutes for shielded cables.

5. Read test equipment instruction manual prior to testing cable

6. When Project specifies the plotting of test results, attach 2ND sheet with separate plot for each phase. Note leakage current, in microamps, on “y” axis. Note step-voltage increase on “x” axis, followed by time, in minutes, for the dielectric absorption portion of the test.

7. All other phases and shields to be grounded.

P-F3 TO P-F4 15KV CABLE INSTALLATION 3-7-103B

TESTING ELECTRICAL SYSTEMS 29 JANUARY 2020 16950-16

Voltage Hold Time

At Each Step:

sec Kv Kv Kv Kv Kv Kv Kv Kv Kv

∅A

∅B

∅C

Time

At Kv sec min min min min min min min min min min min min min min min

CABLE RATED VOLTAGE (kilovolts) TEST VOLTAGE (kilovolts)

Tester’s Initials Date

P-F3 TO P-F4 15KV CABLE INSTALLATION 3-7-103B

TESTING ELECTRICAL SYSTEMS 29 JANUARY 2020 16950-17

ATTACHMENT 18

FORM: 65F1105

GROUNDING/EARTHING SYSTEM INSPECTION RECORD

(GRID OR LOOP-TYPE SYSTEM)

DATE: REV.: REF. DWG.:

NOTE: This Inspection Checklist shall be used for installation and checking of Main

Grounding/Earthing System.

1. Primary conductor is correct size and type in accordance with drawings.

2. Ground/earthing conductor burial depth and routing per drawings and Sections.

3. Thermal/compression connections checked (no cold joints or burn-outs).

4. Thermal/compression connection insulation checked.

5. Ground/earthing anode locations and installation per drawing.

6. Ground/earthing anode connections checked.

7. Location, type, size and insulation color of equipment taps per drawings and protected during construction.

8. System ground/earthing anode resistance-to-earth checked and recorded on

Form 65F1106, Ground/Earthing Anode Testing Test Record (Attachment 19).

9. All field Revisions recorded on as-built drawings.

P-F3 TO P-F4 15KV CABLE INSTALLATION 3-7-103B

TESTING ELECTRICAL SYSTEMS 29 JANUARY 2020 16950-18

ATTACHMENT 21

FORM: 65F1108

GROUNDING CONTINUITY TEST RECORD

(NON-ELECTRICAL EQUIPMENT/STRUCTURES)

DATE: REV.: REF. DWG.:

TEST EQUIPMENT

USED: WEATHER:

1.3 Equipment Tag No. Or

Structure Drawing Measured Resistance (ohms)

Initials & Date

P-F3 TO P-F4 15KV CABLE INSTALLATION 3-7-103B

TESTING ELECTRICAL SYSTEMS 29 JANUARY 2020 16950-19

ATTACHMENT 23

FORM: 65F1110

PANELBOARD INSPECTION RECORD

DATE: REV.:

BUILDING: AREA/UNIT: PANEL BOARD TAG:

1. Receiving Operations/Inspection complete.

2. Check assembly for any missing parts.

3. Enclosure approved for area of installation.

4. Panelboard circuit schedule filled out.

5. Correct circuit breaker and location.

6. Neutral and phase conductors correctly color-coded.

7. Grounding/earthing installed and connected. Test Record, (Form 54F1109, Attachment 22) Ground Continuity Test Record (Electrical Equipment and Ground Test Bars), completed.

8. Check panel load balance.

9. Check color-coding of branch circuit conductors.

10. Clean out.

11. Check mounting and supports.

12. Fixtures and receptacles are correct type and installed as per drawings.

13. Fixtures and receptacles on correct circuit.

14. Nameplate, number of circuits and panelboard location per drawing.

15. Megger buses (including neutral). Record results on Form 65F1124 (Attachment 37), Insulation Resistance (Equipment) Test Record. Main disconnect and outgoing circuits should be open.

16. Final inspection complete. Punch items on Form 65F1300, Electrical Punch List Record, cleared

PIP-II Utility Corridor 4-3-2B

TESTING ELECTRICAL SYSTEMS 18 JANUARY 2019 16950-20

ATTACHMENT 42

FORM: 65F1129

ELECTRIC MOTOR RUN-IN TEST RECORD

DATE: REV.:

MOTOR TAG NO.: TEST EQUIPMENT:

REF. DWG.:

Notes:

1. Duration of tests to comply with Subcontract Selections.

2. Complete Form 65F1127, Electric Motor – Electrical Activities Inspection Record, prior to energizing motor.

TEST REMARKS INITIALS/DATE

RESISTANCE (in ohms):

Bonding resistance measured from motor frame to Main ground/earth system tap.

VOLTAGE (in volts):

Actual voltage measured at Motor Control Center

ROTATION CHECK:

Bump motor to verify rotation. Motor shall be Uncoupled.

NO LOAD CURRENT (in aamps):

At beginning of test:

At end of test:

TEMPERATURE OF BEARING:

Check bearing for high temperature:

Before start:

15 minutes after start:

30 minutes after start:

1 hour after start:

2 hours after start:

3hours after start:

VIBRATION:

Make visual inspection during run-test.

Record any unusual vibration in remarks column.

NOISE:

Record any unusual noise in remarks column.

END OF SECTION 16950