This document is a technical specification for 15kV cable installation, detailing requirements for electrical cable work, primarily for a project involving cable installation between P-F3 and P-F4 locations. The specification covers comprehensive requirements for cable materials, installation procedures, testing, termination, and identification, with specific instructions for the subcontractor regarding cable handling, grounding, splicing, and equipment identification.

Key technical requirements include using specific cable splice and termination kits from manufacturers like 3M and Elastimold, installing cable with precise procedures for handling, bending, and pulling, and conducting high-potential (hi-pot) electrical testing. The document mandates detailed cable identification using machine-engraved lamocoid nametags with specific color and lettering requirements, and provides instructions for grounding, cable supports, and disposition of removed cables. FFGD (presumably the contracting organization) will provide cable and splice kits, with the subcontractor responsible for installation, wiring, and adherence to detailed technical specifications outlined in the document.

View the file

Other files

File Type Posted
Amend 03 to RFP 375018-CD.pdf PDF
375108-CD Amendmant 2 Revised Response to Questions.pdf PDF
375108-CD Amendment 2 Revised Exhibit R - Proposal Form.pdf PDF
Amend 02 to RFP 375108-CD.pdf PDF
375108-CD Amendment 2 Revised Drawings.pdf PDF
375108-CD Amendment 1 Revised Exhibit R - Proposal Form.pdf PDF
375108-CD Amendment 1 Revised Drawings.pdf PDF
375108-CD Amendmant 1 Response to Questions.pdf PDF
Amend 01 to RFP 375108-CD.pdf PDF
Exhibit B2- Section 16121 Medium Voltgage Cable.pdf PDF
Exhibit H - 2025 Construction Insurance Requirements.pdf PDF
Exhibit I - Bond Bid FL-41.pdf PDF
Exhibit M - Fermilab Subcontractor Safety Information Questionnaire.pdf PDF
Exhibit P- Davis Bacon Wage Rates.pdf PDF
1.0 RFP 375108-CD.pdf PDF
Exhibit B1- Section 16010 General Electrical Requirements.pdf PDF
Exhibit C- 010010 General Requirements.pdf PDF
Exhibit G- FFDG General Terms and Conditions for Construction (08.2025).pdf PDF
Exhibit J - Bond Payment FL-42.pdf PDF
Exhibit K- Bond Performance FL-40.pdf PDF
Exhibit L - Statement of Acknowledgment (SF-1413).pdf PDF
Exhibit Q- Summary of Required RFP Submittal Documents.pdf PDF
Exhibit B Drawings.pdf PDF
Exhibit B4- Section 16450 Grounding and Bonding.pdf PDF
Exhibit B5- Section 16950 Testing Electrical Systems.pdf PDF
Exhibit D- 013100 ESH Requirements.pdf PDF
Exhibit F- 014100 Quality Requirements.pdf PDF
Exhibit R - Proposal Form 375018-CD F3 to F4 15KV Cable Installation.pdf PDF
Exhibit A- P-F3 TO P-F4 15KV Cable Installation SOW.pdf PDF
Exhibit E- 013300 Submittals.pdf PDF
Exhibit N - SARC_Subcontractor Annual RepsCerts Rev 4_FFDG.pdf PDF
Exhibit O - Proposal Certifications Form PUR-466_FFDG.pdf PDF
Exhibit S- Sample Firm-Fixed-Price Subcontract.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P-F3 TO P-F4 15KV CABLE INSTALLATION 3-7-103B

15KV CABLE INSTALLATION 17 AUGUST 2021 16125-1

SECTION 16125 - 15KV CABLE INSTALLATION

PART 1 - GENERAL

1.01 SCOPE OF WORK

A. This Section prescribes the general requirements for 15kV CABLE INSTALLATION. Subcontractor shall furnish the materials, installation, terminating, splicing, testing and all related work for the complete and functional 15kV cable system, as specified herein and as shown on the Subcontract drawings.

B. This Section prescribes the general requirements for 15kV switches.

Subcontractor shall furnish, installation, connection, testing and all related work for the complete and functional 15kV distribution system, as specified herein and as shown on the Subcontract drawings.

C. Connection of ground conductors to the electrical equipment shall be included as part of this Work.

D. The drawings and Sections are meant to complement each other; however, in case of conflicts, the sections shall govern, since they are intended to identify all materials and equipment required for the construction of the facility. Any deviation from the Sections or drawings shall be authorized by the FFGD Construction Coordinator prior to purchase or installation.

E. Any apparatus, appliance, material, or work not shown on drawings or indicated in the Sections, but necessary to make the work complete and ready for operation shall be furnished, delivered, and installed by Subcontractor without additional expense to FFGD.

F. The 15 kV cable and splice kits will be provided by FFGD, installed and wired by Electrical Contractor.

1.02 RELATED WORK: Examine all other portions of the Subcontract documents for work related to the work of this Section. Provide all work hereunder as required for the support and accommodation of related work.

1.03 RELATED WORK SPECIFIED ELSEWHERE: The following Sections prescribe items of related Work. Coordinate Work prescribed by this Section with Work prescribed by these Sections:

A. Section 16010 - General Electrical Requirements

B. Section 16121 – Medium Voltage Cable

C. Section 16450 - Grounding and Bonding

D. Section 16950 – Testing Electrical Systems

15KV CABLE INSTALLATION 17 AUGUST 2021 16125-2

1.04 APPLICABLE STANDARDS: The publications listed below form part of this Section.

Each publication shall be the latest revision and addendum in effect on the date of the subcontract award, unless noted otherwise. Except as specifically modified by the requirements specified herein or the details on the drawings, the Work included under this Section shall conform to the provisions of these publications:

A. ANSI (American National Standards Institute)

1. ANSI C2 (National Electrical Safety Code)

B. ICEA (Insulated Cable Engineers Association)

C. IEEE (Institute of Electrical and Electronics Engineers)

D. NEMA (National Electrical Manufacturers Association)

E. NETA (National Electrical Testing Association)

F. NFPA (National Fire Protection Association)

1. NFPA 70 (National Electrical Code)

G. OSHA (Occupational Safety and Health Administration)

H. UL (Underwriters’ Laboratories, Inc.)

1.05 QUALITY ASSURANCE AND CONTROL:

A. Subcontractor shall be responsible for quality control and construction inspection in accordance with Section 010010.

B. All work is subject to the final acceptance by FFGD. Strict conformance to the drawings and sections shall be required.

C. Performance Guarantee:

1. Installation of electrical systems shall be completed to the satisfaction of FFGD Construction Coordinator. The Subcontractor, at no additional cost to the FFGD, shall correct work performed by the Subcontractor judged not to be to the satisfaction of the FFGD Construction Coordinator.

2. It shall be the sole responsibility of the Subcontractor that the electrical systems are installed to the satisfaction of FFGD.

3. Subcontractor shall guarantee all Subcontractor equipment, material, and installation provided by Subcontractor to be free from defects.

4. Subcontractor shall assign persons in direct charge of the work who are thoroughly experienced in the class of construction required. All labor shall be performed in a workmanlike manner by skilled workmen under supervision of a competent foreman.

D. Electrical Equipment:

3-7-103B

15KV CABLE INSTALLATION 17 AUGUST 2021 16125-3

P-F3 TO P-F4 15KV CABLE INSTALLATION

1. FFGD will perform any and all cable de-energization. Subcontractor is prohibited from performing any circuit switching.

PART 2 - PRODUCTS

2.01 MATERIAL

A. Terminal Lugs and Hardware:

1. Subcontractor shall furnish and install lugs and silicon bronze hardware for the termination of power cables at electrical equipment (except oil switch terminations). Terminal lugs shall be un-insulated, aluminum compression terminal with NEMA 2-hole pattern. Lugs shall be suitable for aluminum cable and shall be as manufactured by Burndy. Terminal lugs shall be as follows:

a) Conductor Size: 750 MCM Straight Connector: YA39AM2 Angle (45°) Connector: YA39AM2-45

b) Hardware:

(1) Silicone Bronze - Bolt, Nut, Lock Washer, Flat Washer

(2) Stainless Steel - Belleville Washer

B. Termination Kits-Air:

1. Termination kits for new air switches or transformer terminations shall be 3M Company Cold Shrink QT III Termination Kits and as follows:

15kV Concentric and Jacketed Concentric Cable Kits:

Conductor Size: 500 MCM – 1000 MCM Conductor Insulation O.D. Range: 1.05”-1.80” Indoor Kit Number: 7645-T-110 Outdoor Kit Number: 7655-S-4

2. Outdoor kits shall be utilized when the termination is exposed to the weather.

3. Termination kits shall be furnished and installed by Subcontractor.

Subcontractor shall exercise extreme care in conductor preparation and insulation strip lengths.

C. Cable Splice Kits:

1. Cable splice kits shall be as manufactured by Elastimold as follows:

a) In-Line Splice Kits:

Conductor Size: 750 MCM Conductor Size Range: 1.370”-1.630” Splice Kit Number: 650S-M0380-M0380

15KV CABLE INSTALLATION 17 AUGUST 2021 16125-4

Splice Barrel Length: 6.75”

2. Splice kits shall be furnished by FFGD and installed by Subcontractor.

Subcontractor shall exercise extreme care in conductor preparation and insulation strip lengths.

D. Raceways and Concrete Pads:

1. Subcontractor shall furnish and install 15kV concrete encased, electrical duct banks and concrete pads as shown on the Subcontract drawings.

DI. Core Drills:

1. Subcontractor shall provide all requirements for the core drilling of existing manholes where duct terminators are not available.

2. Subcontractor shall:

a) Furnish and install conduit end bells for all conduits terminating in a manhole. End bells shall be grouted with lean grout.

b) Furnish a sketch of proposed locations of all core drills to the FFGD Construction Coordination prior to the beginning of any many manhole cores.

DII. Firewrapping:

1. All power cables in manholes and cable vaults shall be suitably protected against fire. Entire length of exposed cable in the manhole (including splices and/or wye splices) shall be firewrapped. Cable firewrapping shall be furnished and installed by the Subcontractor.

2. Firewrapping shall be as manufactured by 3M Company (3M-77) or FFGD approved equal.

DIII. Grounding Materials:

1. Bonding and grounding conductors shall be ASTM B1 solid, bare copper for sizes #8 AWG and smaller and shall be ASTM B8 Class B stranded copper for sizes #6AWG and larger.

PART 3 - EXECUTION

3.01 All bus, insulators and other exposed hardware shall be cleaned by the Subcontractor.

3.02 Subcontractor shall take the necessary construction and safety precautions during the installation of the new cables in the manholes or other areas where the energized feeders are located.

3.03 The drawings indicate the general layout of the electrical systems, arrangement of feeders, substations, and other work. Electrical plans are by nature diagrammatic.

15KV CABLE INSTALLATION 17 AUGUST 2021 16125-5

P-F3 TO P-F4 15KV CABLE INSTALLATION

A. Subcontractor shall bring to FRA’s attention any discrepancies between the drawings and the “As-Constructed” conditions. Subcontractor shall not deviate from the drawings without written approval from the FFGD Construction Coordinator.

B. Subcontractor shall verify the location and method for connecting to each item of equipment.

C. Subcontractor shall install equipment and material in accordance with the Subcontract requirements. Materials or equipment improperly installed shall be removed and reinstalled to the satisfaction of FFGD Construction Coordinator, at Subcontractor’s expense

D. All cables shall be routed for ease of maintenance, serviceability, and installation of future cables.

E. Whenever possible, cables routed in manholes shall enter and exit the manholes penetrations through corresponding conduits on the opposite sides of the manhole.

3.04 Cable Reel Movement:

A. Reels of cable shall not be dropped from any heights. Particular care shall be exercised when handling reels from trucks or other transporting equipment.

B. Reels shall be lifted utilizing the following methods:

1. When using a crane or boom type equipment, insert a heavy rod or pipe through the reel hub and lift with slings on shaft, preferably using a spreader bar or yoke to reduce or avoid side pressure against the reel flange.

2. Fork lift type equipment may be used to move smaller, narrower width reels. Fork tines shall be placed such that the lift pressure is on the reel flange and not on any part of the cable and the tines shall reach across the reel on both flanges of the reel.

3. Reels may be rolled short distances by rolling. Reels shall be rolled in the direction of the arrows marked on the reel flanges. Surfaces over which the reels are rolled shall be firm, clear of debris, and clear of protruding stones, humps, etc. which might otherwise damage the cable.

3.05 Cable Storage:

A. Should the cable end seals be damaged or removed, Subcontractor shall install new seals to prevent entry of moisture. Cable seals shall be sealed using RayChem heat shrink end seals.

B. Whenever possible, factory installed lagging (protective cover), if provided, shall be left in place. Additional covering shall be provided and installed by the Subcontractor if the cable reels are stored outdoors for excessively long periods (more than seven calendar days) or in dirty or dusty areas.

15KV CABLE INSTALLATION 17 AUGUST 2021 16125-6

C. Cable reels shall be stored on a firm surface with planking to prevent settling of the cable reels into soft ground.

D. Any area of cable reel storage shall have adequate drainage. Subcontractor shall relocate any and all cable reels located in areas of inadequate drainage.

1. Fencing or other barriers shall be provided by the Subcontractor to protect reels against damage.

3.06 Cable Placement:

A. Conductor/cable installation shall be in accordance with the cable manufacturer’s recommendations and the following requirements:

1. Cable shall not be handled when the cable temperature is below 32°F (0°C). If cable heating is required prior to placement, the cable shall be stored in a heated building in accordance with the manufacturer’s recommendations for a minimum of 24 hours. Cable shall be pulled the same day it is removed from the heated storage. Subcontractor shall provide temporary shelter and heating for cables and reels.

2. If at any time during the progress of the work the Subcontractor finds raceways that appear inadequate to accommodate the assigned cable, he shall notify FFGD at once and shall discontinue any further work on the questionable raceway until advised by FFGD as to how to proceed.

3. Immediately prior to the placement of each cable or cable group, the raceway and manhole route to be followed shall be inspected and ascertained to be complete in installation and free of all materials detrimental to the cable or its placement. All cable assigned to a particular conduit shall be grouped and pulled in simultaneously using cable grips or other approved methods and acceptable lubricants.

a) Subcontractor shall pull an appropriately sized mandrel through conduits prior to pulling any cables.

4. All cable shall be carefully checked both as to size and length before being pulled into conduits. Cable pulled into the wrong conduit or cut too short to rack, train, and splice as specified herein shall be removed and replaced by and at the expense of the Subcontractor. Cable removed from one conduit shall not be pulled into another conduit.

3.07 Cable Pulling:

A. Damaged cable shall be removed and replaced by and at the expense of the Subcontractor.

B. Pulling eyes on conductors or a basket weave grip shall be used for pulling cable. Woven wire cable grips shall be used to pull all single conductor cable where pulling eyes are not available. All sharp points and edges on the hardware attaching the pulling rope to the cable shall be taped to prevent

15KV CABLE INSTALLATION 17 AUGUST 2021 16125-7

snagging or damaging the raceway. Pulling eye only shall be utilized for pulling of 15kV 750kcmil cables.

C. When a cable grip or pulling eye is used for pulling, the area of the cable covered by the grip or seal plus 6” shall be cut off and discarded when the pull is completed. When pulling loops are used, the entire loop shall be cut off and discarded when the pull is completed.

D. A nonfreezing type of swivel, or swivel connection, shall be inserted between the pulling rope and the cable pulling eye, grip, or loop to prevent twisting under strain and to allow for free rotation of the cable during pulling.

E. Cable pulling compounds shall not contain microball spheres, ethylene glycol or mineral oil. Acceptable pulling compound shall be as manufactured by American Polywater Corp. (Polywater J) or FFGD approved equal.

F. As soon as the cable is pulled into place, the pulling eyes, cable grips, or pulling loops shall be removed. Any cable which was scaled shall be resealed.

1. Cables pulled with ends pulled to a point above normal grade elevation shall be resealed with a minimum of three (3) wraps of 2” Scotch #23 (or FFGD approved equal) rubber splicing tape. Exposed cables ends shall be carefully wrapped in such a manner as to prevent unintentional water entry from weather exposure. Exposed cable ends shall be wrapped prior to the end of the work day.

2. Cables pulled with ends pulled to a point below normal grade elevation (manholes or vaults) shall be resealed with appropriately sized RayChem heat shrink end seal boots. Exposed cables ends shall be sealed in such a manner as to prevent unintentional water entry from weather or water filled manholes or vaults. Exposed cable ends shall be sealed prior to the end of the workday.

3.08 Pulling Tension:

A. The pulling tension of any cable shall not exceed the maximum tension recommended by the cable manufacturer. Pulling mechanisms of both the manual and power types used by the Subcontractor shall have the rated capacity in tons clearly marked on the mechanism. Whenever the capacity of the pulling mechanism exceeds the recommended pulling tension of the cable as given by the cable manufacturer, a dynamometer shall be used to show the tension on the cable and the indicator shall be constantly watched. If any excessive strain develops, the pulling operation shall be stopped at once and the difficulty determined and corrected.

3.09 Sidewall Pressure:

A. To avoid insulation damage from excessive sidewall pressure at bends, the pulling tension in pounds at a bend shall not exceed 300 times the radius of the bend in feet.

3.10 Cable Bends:

15KV CABLE INSTALLATION 17 AUGUST 2021 16125-8

A. Cable shall not be bent to a radius of less than 12 times the overall cable diameter.

3.11 Hi-Pot Testing:

A. All cables shall be tested in accordance with the requirements of Section 16950:

TESTING ELECTRICAL SYSTEMS.

B. Hi-pot test voltages shall be as follows, unless directed otherwise by the FFGD Construction Coordinator:

1. 15kV Unjacketed Cable: 65kV in 10 increments of 6500V.

2. 15kV Jacketed Cable: 55kV in 10 increments of 5500V.

C. Cable testing shall be performed under this Subcontract and shall meet the requirements of NETA (National Electrical Testing Association). See Section 16950: Testing Electrical System and Inspection for cable testing parameters and requirements to be provided under this Subcontract.

3.12 Terminations:

A. Cable shall be terminated in accordance with the following requirements:

1. Cable shall be neatly trained in place and cut squarely to the required length. Sharp bends shall be avoided.

2. Remove necessary amount of cable jacket and insulation without damage to the conductor.

3. Install terminals or terminal connectors as required, ensuring a firm metal-to-metal contact.

3.13 Cable Supports-General:

A. Cable supports and securing devices shall be installed to provide adequate support without deformation of the cable jackets or insulation.

B. Adequate cable end lengths shall be provided and properly placed in manholes to avoid longitudinal strains and distorting pressures on the cable.

C. Cable routing in manholes shall be subject to the approval of the FFGD Construction Coordinator.

1. Cables shall be routed within the manhole such that adequate working space is provided within the manhole for cable splicing and for the installation of future cables.

D. Cables shall be tied through the use of cable ties, however, installation shall not impede horizontal movement of cables during ambient variations and short circuit forces.

15KV CABLE INSTALLATION 17 AUGUST 2021 16125-9

P-F3 TO P-F4 15KV CABLE INSTALLATION

E. Final inspection shall be made after all cable is in place and, where supports or raceway fittings deform the cable jacket, additional supports shall be provided as directed by FFGD. Additional cable protection such as a wrapping of light rubber belting, friction tape or similar material shall be provided where required.

3.14 Lacing:

A. Nylon ties shall be used to neatly lace together conductors entering manholes, handholes and similar locations after the conductors have emerged from their raceway.

3.15 Grounding:

A. Concentric neutrals shall be grounded at all splice points and at all termination points.

B. Concentric neutrals shall be pulled back, twisted together and connected to the grounding conductor using a compression type ground lug.

C. Concentric neutral from splice or termination shall be grounded to the system ground through the use of a 500 kcmil bare copper ground cable.

D. Ground conductors shall not be looped between pieces of cable. Each cable ground point shall have a direct connection to the ground system.

E. All contact surfaces shall be thoroughly cleaned of dirt or oil.

F. Grounding circuit connections shall be such that grounding resistance may be checked at anytime.

3.16 Cable Identification:

A. Subcontractor shall identify furnish and install cable identification markers near each termination point and at each manhole or handhole of all conductors.

B. Each cable shall bear the number of the circuit and the “from” - “to” routing of the cable. For example:

FDR 31

PHP P-115 TO MS2

Nameplate engraving shall be subject to the approval of the FFGD Construction Coordinator.

C. All cables shall be identified with machine engraved lamocoid nametags with white letters on red background and shall be firmly attached to the cable with non-metallic cable ties.

D. Each nameplate shall be provided with a ¼” diameter hole for securing the nameplate to the cable.

15KV CABLE INSTALLATION 17 AUGUST 2021 16125-10

E. Nametags shall be approximately 1½” wide and of sufficient length to accommodate the lettering requirements. Lettering shall be as follows:

First line (Feeder number): ½” lettering.

Second line (From-To): ⅜” lettering.

F. Phase identification tags shall be provided at all termination points. Phase identification shall be as follows:

1. A Ø (Ungrounded conductor): Black

2. B Ø (Ungrounded conductor): Red

3. C Ø (Ungrounded conductor): Blue

G. Equipment Identification: All electrical equipment and enclosures shall be identified with nameplates. Nameplates shall be machine engraved lamocoid with white letters on black background. Nameplates shall be attached with 3M 9500PC, double side, adhesive tape for indoor locations and with self-tapping stainless screws for outdoor locations. Nameplates shall be as follows:

H. 4-Way Disconnect Switch:

1. Master Nameplate:

a) Nameplate Size: 6” x 3” x ¼” Lettering Size: ¾”

b) Nameplate shall be attached on disconnect such that the nameplate of the transformer and nameplate of disconnect switch can be viewed from the same direction.

c) All disconnect switches requiring termination of 15kV cables and conductors shall be provided with nameplates.

d) Nameplate engraving and location shall be subject to the approval of the FFGD Construction Coordinator.

2. Quadrant or Compartment Nameplate

a) Each disconnect switch, as described above, shall be furnished with an additional nameplates for each compartment. One (1) nameplate shall be installed on each switch compartment.

Disconnect Switches Compartment:

Nameplate Size: 4” x 2” Lettering Size: 1/2”

b) Nameplate shall be provided with the feeder number and the destination of the cable terminated at the switch. For example, one of the compartments of disconnect switch MDW shall be

15KV CABLE INSTALLATION 17 AUGUST 2021 16125-11

furnished with the following nameplate:

Compartment 1: Compartment 2:

FDR. 31 FDR. 30

MASTER SUB MASTER SUB

Compartment 3: Compartment 4:

FDR. TO FDR. TO

ML-6 ML-5, 10, 14

All nameplate engraving and location shall be subject to the approval of the FFGD Construction Coordinator.

3.17 Cable and Cable Reel Disposition:

A. Any cable removed shall remain the property of FFGD.

1. Subcontractor shall coordinate removal of cable with the FFGD Construction Coordinator for the determination of posted radiological areas.

2. All other excess (removed) aluminum or copper cable shall be cut into approximately 6 foot pieces and placed into FFGD designated containers.

B. Subcontractor shall return steel cable reels to the railyard storage area. FFGD will return the empty reels to the Manufacturer at the end of the Subcontract for reel deposit.

1. Empty wood cable reels shall be demolished and disposed by the Subcontractor.

END OF SECTION 16125