Amendment 0008_W912DS19R0019 (002).pdf

PDF 755 KB Posted

Attached to
Cyber Engineering and Academic Center (CEAC), United States Military Academy, West Point, NY
Solicitation number
W912DS19R0019
Issued by

About this file

This solicitation requests proposals for a firm fixed-price construction contract to build the Cyber Engineering and Academic Center (CEAC) at the United States Military Academy in West Point, New York. The 136,000 square foot, four-story CEAC building will house three engineering departments and include a 450-stall underground parking structure. Additional project elements comprise a pedestrian bridge connecting CEAC to Mahan Hall, signature meeting spaces on the fourth floor, and extensive rock removal of 300,000 cubic yards during site preparation. The period of performance is approximately 1,461 calendar days from notice to proceed. Liquidated damages of $4,979 per day will be assessed for delays in completion. The solicitation is issued by the U.S. Army Corps of Engineers, New York District, and proposals are due electronically by the date specified in the solicitation. Interested parties must register with beta.SAM.gov and the System for Award Management to access solicitation documents and any amendments. The procurement method is a best value tradeoff request for proposal.

View the file

Other files

File Type Posted
West Point_Mahan_Hall_HAZMAT_Report_190409.pdf PDF
CEAC_Amended for Matrix of Glazing-Caulking.pdf PDF
CEAC_Cut-Sheets_Glass Wall Systems 2 and 3.pdf PDF
CEAC_Amendment 8_Drawings.pdf PDF
CEAC_Amendment 8_Specs.pdf PDF
Amendment 0007_W912DS19R0019.pdf PDF
Amendment 0007_Drawings.pdf PDF
Amendment 0007_Specifications.pdf PDF
Approved JA_Monaco Fire Alarm System for CEAC_Redacted.pdf PDF
Approved JA_ Motorola Communication System for CEAC_Redacted.pdf PDF
Approved JA_Best Hardware Lock Cylinders and Cores for CEAC_Redacted.pdf PDF
Approved JA_Tapestry Granite for CEAC_Redacted.pdf PDF
Amendment 0006_FFE Responsibility Matrix_RTA Govt Submission FIN.PDF PDF
Amendment 0006_Specifications.pdf PDF
Amendment 0006_NYR11G658.pdf PDF
Amendment 0006_W912DS19R0019.pdf PDF
Amendment 0006_Drawings.pdf PDF
Amendment 0006_HighDensity XH-Technical FFE Spec.pdf PDF
Amendment 0005_W912DS19C0019.pdf PDF
Amendment 0005_DA Permit 0-00412 Issued to USMA for Rock Loading Temp Pier in Hudson River 18JUN2020.pdf PDF
Amendment 0004_CEAC_FIO_Renderings.pdf PDF
Amendment 0004_W912DS19R0019.pdf PDF
Amendment 0004_CEAC_Site_Visit_Sign_In_18Jun2020.pdf PDF
Amendment 0003_W912DS19R0019.pdf PDF
Amendment 0002_W912DS19R0019.pdf PDF
Amendment 0002_CEAC_Drawings.pdf PDF
Amendment 0002_01 33 29.pdf PDF
Amendment 0002_CEAC_Spec 01 11 00.pdf PDF
Amendment 0001_W912DS19R0019.pdf PDF
CEAC_RTA Submission_Drawings_Vol 5C_2020-05-21.pdf PDF
Solicitation_W912DS19R0019.pdf PDF
CEAC_RTA Submission_Specs_Volume 3 of 4_2020-05-21.pdf PDF
CEAC_RTA Submission_Drawings_Vol 3_2020-05-21.pdf PDF
CEAC_RTA Submission_Drawings_Vol 1B_2020-05-21.pdf PDF
CEAC_RTA Submission_Drawings_Vol 6B_2020-05-21.pdf PDF
CEAC_RTA Submission_Specs_Volume 1 of 4_2020-05-21.pdf PDF
CEAC_RTA Submission_Drawings_Vol 5B_2020-05-21.pdf PDF
CEAC_RTA Submission_Specs_Volume 4 of 4_2020-05-21.pdf PDF
CLP site plan.pdf PDF
2020-05-20 SWPPP Submission Drawings.pdf PDF
CEAC_RTA Submission_Drawings_Vol 4A 2020-05-21.pdf PDF
CEAC_RTA Submission_Drawings_Vol 2_2020-05-21.pdf PDF
2020-05-20 SWPPP Documents.pdf PDF
CEAC_RTA Submission_Drawings_Vol 5A_2020-05-21.pdf PDF
Signiture Page FONSI for CEAC EA.PDF PDF
CEAC_Sustainability Record Card.pdf PDF
CEAC_RTA Submission_Drawings_Vol 4B_2020-05-21.pdf PDF
NYSDEC POC.pdf PDF
CEAC_RTA Submission_Drawings_Vol 1A_2020-05-21.pdf PDF
NAN-2020-00412-WCR dtd 30APR20-22MAY20 FINAL.pdf PDF
Show 40 more

Latest 50 of 53 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W16ROE91754737

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1. revise liquidated damages clause 52.211-12

2. Revise and reissue Draw ings

3. Add Specs 4 Revise and reissue Specs

5. Answ er questions from prospective offerors for informational purposes only

NOTE: Offeror must acknow ledge receipt of this amendment by the date specif ied in the proposal (or as amended) by one of the follow ing methods: In the space provided on SF1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS (FAR 15.208).

1. CONTRACT ID CODE PAGE OF PAGES

1 26

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 16-Jul-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS19R0019

X 9B. DATED (SEE ITEM 11)

03-Jun-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

16-Jul-2020

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 16-300

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS19R0019

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0008

DRAWINGS

1. The following DRAWINGS have been REVISED and REISSUED:

CD-101

CD-102

CU-102

C-502

S-11AA

S-508 A-11A A-112L.A A-113E A-230 A-231 A-350 A-411E.51 A-530 A-552 A-610 A-611 A-612 A-613 A-614 A-615.A A-745.A A-747.A I-102L.A I-128.A I-501

EP-400

EP-401

EP-402

E-601 E-611 E-621 E-622

EL-601

EL-602

T-11A T-11A.A T-111E T-503 T-509 T-510

T-601 T-602 T-603 T-605 T-606

2. The following DRAWINGS have been ADDED: None.

3. The following DRAWINGS have been DELETED: None

4. The following DRAWINGS have been REVISED but NOT REISSUED: None.

SPECIFICATIONS:

1. The following SPECIFICATION SECTIONS have been ADDED and are provided in their entirety herein:

07 24 00 – EXTERIOR STUCCO FINISH

2. The following SPECIFICATIONS SECTIONS have been DELETED in their entirety: None.

3. The following SPECIFICATION SECTIONS have been REVISED and REISSUED:

00 75 95 01 30 00 01 91 00.15 04 20 00 07 22 00 07 27 19.01 07 27 26 07 27 36 07 52 00 08 11 16 08 41 13 08 51 23 08 71 00 09 29 00 09 30 10 09 66 23 22 00 00 27 10 00 31 62 20.50

4. The following SPECIFICATION SECTIONS have been REVISED but NOT REISSUED:

None.

(Questions that may be of general interest to all Offerors and/or the Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s). Questions and answers are issued to the Offerors

“for information only ”and do not revise the solicitation, plans or specifications.).

Question 1:

The interior door schedule shows door #EC-4S1.1 as a steel door (spec 081113) with a 90 minute fire rating in stainless steel frame, and then on drawing A-611. Interior window frame 4S1.1 is shown as aluminum with non-rated GL-11 type glass. Please advise the correct material and rating for this location.

Government Response 1:

The door and window are stainless steel. The rating at the stair is 90 minutes. The door schedule and window schedule have been revised and reissued in this amendment.

Question 2:

Please provide specification section for Intumescent Paint.

Government Response 2:

Intumescent fireproofing is specified in section 07 81 00 Spray-Applied Fireproofing. For extents of intumescent fire proofing see A-004.1 and A-004.2. In all other locations use cementitious or fiber based fireproofing materials.

Question 3:

Based on Amendment # 5 the Bid Date Submission has been split into; Technical Portion of the Proposal due July 20th 2pm and the Price Portion of the Proposal due July 29th 2pm. There are many variables of the Price Submission which are dependent upon the specifics of the Technical Submission (i.e. teaming agreement/utilization plan etc). By splitting the the bid submission and having the Technical Proposal first we feel this may have an affect on being able to provide the most competitive Price Proposal. We kindly request the Owner reconsider and move the Technical Submission to the same date as the Price Proposal.

Government Response 3:

The Government understands and acknowledges the concern. The Government encourages Offerors to write their Technical Proposal in a way which reflects the Offeror's best understanding at the time the Technical Proposal is submitted. When writing the Technical Proposal, the Offeror may avoid imposing unnecessary restrictions on the Offeror's ability to submit the best possible Price Proposal nine days later.

The Government is not considering extending either deadline at this time.

Question 4:

Please provide a specification for the roof substrate boards shown in assemblies RS-1A, RS-1B & RS-5 on A-551.

Government Response 4:

Refer to specification section 07 22 00 2.2.1 for roof cover board and protection requirements.

Question 5:

Please confirm specification 078100 is for intumescent fireproofing as shown on pages A-004.1 & A-004.2.

Government Response 5:

Intumescent fireproofing is specified in section 07 81 00 Spray-Applied Fireproofing. For extents of intumescent fire proofing see A-004.1 and A-004.2. In all other locations use cementitious or fiber based fireproofing materials.

Question 6:

Specification 078100 – Spray-Applied Fireproofing seems to reference cementitious or fiber based fireproofing materials, but also references Spray-Applied Intumescent Epoxy Coating System in section 2.4. Please clarify which type of product we are to use.

Government Response 6:

Intumescent fireproofing is specified in section 07 81 00 Spray-Applied Fireproofing. For extents of intumescent fire proofing see A-004.1 and A-004.2. In all other locations use cementitious or fiber based fireproofing materials.

Question 7:

Please provide a spec for the following shelving:

XH1A;

XH1B;

XH1.2A;

XH12B (this is likely a typo and is supposed to be XH1.2B).

Government Response 7:

The items listed 'XH' are GFGI (Government Furnished/Government Installed).

Furniture Location Plans are shown for reference only for tight coordination with other work. An Amendment has already been issued that includes the "FF&E Responsibility Matrix" as a reference for those items that require coordination with Contractor. The manually operated High Density Storage 'XH' components are the exception and requires some scope installed by Contractor in coordination with the Government. Contractor to install the structural ramp/platform (for anticipated heavier rolling loads) and specified floor finish after the Government installs the surface mounted rails. Government to install HD carriages and all other components of system once flooring is complete.

Refer to floor ramp detail on Sheet F5/I-502. Contractor to coordinate scope and scheduling.

Question 8:

Please provide a spec for the following shelving;

FS1 – two elevations are shown, require spec and room #'s to obtain layout.

Government Response 8:

The items listed are GFGI (Government Furnished/Government Installed). Furniture Location Plans are shown for reference only for tight coordination with other work and all specified furniture is tagged with a code on the Furniture plans and shown as dashed on elevations in the A-400 Series drawings.

An Amendment has already been issued that includes the "FF&E Responsibility Matrix" as a reference for those items that require coordination with Contractor scope and scheduling for clarification.

Question 9:

Please provide a spec for the following shelving;

XH3A – Two elevations are shown, require spec and room #'s to obtain layout.

Government Response 9:

The items listed are GFGI (Government Furnished/Government Installed). Furniture Location Plans are shown for reference only for tight coordination with other work and all specified furniture is tagged with a code on the Furniture plans and shown as dashed on elevations in the A-400 Series drawings.

An Amendment has already been issued that includes the "FF&E Responsibility Matrix" as a reference for those items that require coordination with Contractor scope and scheduling for clarification.

Question 10:

Confirm who High Density Shelving System is being quoted to; the GC or GSA under government contract. If GSA, confirm the due date for this piece.

Government Response 10:

The items listed 'XH' High-Density Storage Systems are GFGI (Government Furnished/Government Installed).

The manually operated High Density Storage 'XH' components requires some scope installed by Contractor in coordination with the Government. Contractor to install the structural ramp/platform (for anticipated heavier rolling loads) and specified floor finish after the Government installs the surface mounted rails. Government to install HD carriages and all other components of system once flooring is complete. Refer to floor ramp detail on Sheet F5/I-502.

Contractor to coordinate scope and scheduling. The Contractor may identify the "required on job" dates for the Government furnished pieces within the Offeror's technical proposal.

Question 11:

Where are the lock power supplies going to be installed? at the door or in the closet it does not show on the door typicals?

Government Response 11:

Power supplies for the door locks and security system will be on the wall in the Telecom Rooms under the security wireway.

Question 12:

Can a wire mesh material by a different manufacturer with equivalent or better strength properties be substituted for Maccaferri 6x8 type?

Government Response 12:

Maccaferri or an approved equivalent will be acceptable, as specified.

Question 13:

Is the geotechnical report or design basis available for the rock anchor/wire mesh rock slope support system?

Government Response 13:

The Geotechnical Report is provided in the specifications, as an attachment to 01 11 00.

Question 14:

The proposed detail for the spike plate over a rock anchor bearing plate will not secure the mesh to the slope, as the bearing plate will prevent any contact between the spike plate and rock slope. Is this the intent? Typically the spike plates are secured directly to the slope to engage the mesh against the slope.

Government Response 14:

Please bid as specified.

Question 15:

Is it the design intent that each rock anchor provide enough pullout resistance within the rock anchor free length to resist the 113 kip max design load? Due to overlapping rock cones with the 7'x 6' grid anchor spacing, a rock column length of about 32' is needed to provide a factor of safety of 2 against rock cone pullout for every anchor.

Government Response 15:

Yes, that is the intent. Please bid as specified.

Question 16:

Please advise as to who is responsible for hiring the Commissioning Agent for the Total Building Commissioning, the Owner or the GC.

Government Response 16:

The Government will contract directly with the independent Commissioning Agent.

Question 17:

There will be several different scenarios for the rock removal scope of work. For example by trucking haul off, barging, the construction of the temporary pier, a combination of options, etc. Each scenario is thoroughly being considered as well as an internal cost evaluation of each. The Technical Portion due July 20 will require the project technical approach as indicated in Factor 3: Organizational / Technical Approach. Depending on the scenario chosen it will affect scheduling, material/equipment delivery and management, labor management, cost management, site security, documentation and quality control. To provide the most competitive costs scenario, we will not know unit the after July 20 when the pricing is due from the subcontractor trades.

We are requesting the Technical Portion of the proposal be due at the same time as the Pricing Proposals due on July 29 so we can provide the best competitive approach to the rock removal scope.

Government Response 17:

The Government understands and acknowledges the concern. The Government encourages Offerors to write their Technical Proposal in a way which reflects the Offeror's best understanding at the time the Technical Proposal is submitted. When writing the Technical Proposal, the Offeror may avoid imposing unnecessary restrictions on the Offeror's ability to submit the best possible Price Proposal nine days later.

The Government is not considering extending either deadline at this time.

Question 18:

Please provide a basis of design for the precast concrete access vault.

Government Response 18:

The design of the access vault can be found on Sheets C-503 thru C-506 Question 19:

Please confirm that the Owner has already hired 3rd Party firm for Sustainability Reporting.

Government Response 19:

The Contractor shall bear all costs associated with constructing and demonstrating that the project complies with approved Third Party Certification requirements. The Government has not hired a firm to assist the Contractor with sustainability reporting.

See section 01 33 29, paragraph 1.4.4 for contractor responsibilities.

Question 20:

Drawing C-001, GRADING NOTES: 14 States"Mass Rock Excavation shall extend to below site improvement and utilities as required. Excavated rock shall be processed to approved fill gradations to bring the site to rough grade.

Excess rock to be removed."

Q#1 : Is the intention to have the blasted rock operation to be performed to the lowest utility depth and than brought back up to rough grade.

Q#2: Can the blasted rock be processed on site for back filling operations or does this operation need to be performed off site.

Government Response 20:

1. The intent of the note is to allow the removed rock to be processed in accordance with the Select Granular Fill specification, and used as structural fill in areas of over excavation, excluding under building foundations and footings

2. On-site processing is permitted Question 21:

The basis of design for ST-1 is RockCast. We spoke to the m today and they informed us they can not produce the specified finish as well as the profiles including return corners. Please advise.

Government Response 21:

ST-1 is limestone.

Question 22:

How will the proposal for materials on Addendum #6 FF&E Responsibility Matrix be procured? Will this be through GSA contract or some other vehicle such as FedBid?

Government Response 22:

The details of the other acquisitions are not known at this time.

Question 23:

Is it a requirement of the contract to provide for Regular ( bi- weekly) inspections for temporary provisions in place for the SWPPP Plan?

Government Response 23:

Yes. Follow the SWPPP which was provided in the solicitation.

Question 24:

Dimensional stone pieces ST-3 and ST-4 by Reading Rock can process the following finishes: Smooth, Chiseled, Split or Chamfer. Each finish has a different pricing points, please provide required finish.

Government Response 24:

ST-3 is to be smooth.

ST-4 is to be chiseled.

Question 25:

Specification Section 01 57 19 Temporary Environmental Controls/ 1.5.4 Environmental Manager states" Appoint in writing an Environmental Manager for the project site" Can one of the individual(s) in the key personnel listed in Spec Section 01 30 00 also serve as this individual ( dual roles) being the meet the requirements of the specs?

Government Response 25:

Yes the Environmental Manager may have a dual role.

Question 26:

What is the anticipated award date and what is the anticipated notice to proceed date for this project?

Government Response 26:

We currently anticipate awarding the contract at the end of September 2020. The issuance of the NTP is based on other factors after award including receipt of payment and performance bonds from the awardee.

Question 27:

Drawing I001 calls out Kewaunee, specifically for the basis of design for the lab casework, which conflicts with the specs calling out a variety of other manufacturers and models for various casework. Please confirm the acceptable manufacturers for the lab casework package.

Government Response 27:

Spec Section 12 31 00 - Manufactured Metal Casework is a performance based spec and does not call out manufacturers, the only reference to the Basis of Design is on the Sheet I-001 – General Note #22 which clarifies the Basis of Design as Kewaunee / Style: "Steel Research Collection" and notes the finishes. Acceptable manufacturers would need to comply with all aspects of the written spec and drawing details that the named basis of design meets.

Question 28:

Drawing A113L.A. shows an ADA lift to be installed where the bridge ties into Mahan hall, adjacent to the stairway down. The specifications/drawings are unspecific as to what is required here, please provide a basis of design, and how this is to tie into Mahan Hall (electrical, architectural, etc.)

Government Response 28:

The lift is specified in 14.24.13 – Hydraulic Freight Elevators as a 'commercial wheelchair lift'. See specification

14.24.13 section 2.11.

Question 29:

Please clarify the extent of the new finishes to be installed in the existing to remain spaces within Mahan Hall, as part of the alternate. A113L.A./A112.L.A.

Government Response 29:

Sheets A112L.A and A113L.A include further clarification on extent of new finishes in Amendment #2. All new work to match existing unless noted otherwise when in the Mahan Building as per Keynote No. 11 on Finish Location Plans.

Question 30:

Reference CD101, 102, 103 and 104. There are 4 houses on campus to be razed. Quarters; 5, 6, 7 & 8. Quarters 5, 6 & 7 are wood framed. Quarters 8 is brick. It is not clear if this demolition will be by the GC, or by others. Note 13 on CD101 says "TBR" (To Be Removed). Note 11 on CD102 says "TBR BY OTHERS". Are Demolition of these Structures in the General Contractors scope of work?

Government Response 30:

Concur Quarters 8 is brick. Demolition of Quarters 5, 6, 7 and 8 is to be performed by the Contractor. Note 11 on CD102 was corrected in Amendment 7.

Question 31:

Reference Division 2. There are Asbestos/ Lead Surveys (with Bulk Sampling) in Div. 2 for Quarters 5, 6 & 7. Nothing for Quarters 8, which is also scheduled to be demolished. Are we to conclude there are no Hazmats contained in Quarters 8? If not, kindly provide an Asbestos/ Lead Survey for Quarters 8.

Government Response 31:

A HazMat report is not available for Quarters 8. Contractor is to assume similar HazMat conditions for Quarters 8 as has been reported for Quarters 7.

Question 32:

The specs show 25 seismograph monitoring locations but they do not indicate how long the seismographs need to be onsite. We will need that information to determine pricing.

Government Response 32:

Seismographs will need to be in place for the duration of rock blasting and excavation and any activities that could potentially cause vibrations above the specified threshold value.

Question 33:

What are the blast rating and requirements for aluminum systems?

Government Response 33:

If this comment is referring the aluminum framed window and doors systems there are no blast ratings and blast requirements.

Question 34:

What is the STC rating desired for at the interior aluminum systems?

Government Response 34:

The aluminum curtainwall system (08.44.00) is specified to have an STC of not less than

40. Aluminum windows are based on Kawneer Trifab which has an 38 STC when glazed with an insulated glass unit.

The GL-11 glass that is called out for the interior windows is nominal 1/4" glass (1/8" glass + interlayer + 1/8" glass) to achieve an STC of 35. The STC of the entire assembly will vary depending on size, number of divisions, etc.

Question 35:

Drawing I-103D does not label the room located west of Elec EC-308 and south of room EC-310, photonics supports.

Please provide a label and finish designations for this room.

Government Response 35:

This is unfinished/unoccupied space.

Question 36:

Please provide clarification regarding CLIN's 007 & 008. Drawing A745.A was revised in Amendment #06, showing that add alt #02 (CLIN 007) affects the stair landings/treads associated with add alternate #03. CLIN 007 requests the cost difference between providing terrazzo as the finished stair product for the treads and landings, in lieu of the polished concrete. However this CLIN would be affected if CLIN 008 is accepted, as it adds another floor to this stair.

Please clarify if CLIN 007 should include the terrazzo pricing from floors 1 through 4, or just the base bid floors 1 through 3. If the 4th floor is required, it should be priced as a sub-CLIN, that can only be accepted if CLIN 008 is accepted.

Government Response 36:

The Government understands and acknowledges the concern, but the direction is to bid as shown on the drawings.

If both Optional CLINs 0007 & 0008 are exercised, the stair will be terrazzo up until and including the 3rd floor landing, and above the 3rd floor landing will be sealed concrete floor.

Question 37:

Please confirm stairs are to receive Terrazzo treads only at stair #3, tread & risers at stair #4, no TZ finish at stair 1.

Government Response 37:

Confirmed. See base bid documents for terrazzo finish at Stair #3. See Add Alternate #02 "Terrazzo Throughout North Stair" for terrazzo extents at stair #4.

Question 38:

Is refinishing of any existing terrazzo in the Mahan Building included?

Government Response 38:

Refinishing of existing finishes in the Mahan Building would only be required if disturbed or damaged by new work and all new work to match existing unless noted otherwise. Refer to Sheets A112L.A and A113L.A for clarification on extent of new finishes in Amendment #2.

Question 39:

Spec Section 230000 page 17 2.9.1.4-Duct Pressure Classifications and Construction Paragraph a, Item #1 says supply ducts between AHU and Fire or Smoke Dampers is 10 inch WG. There aren't any Smoke Dampers shown and some systems don't have any Fire/Fire Smoke dampers in them and others have them coming out of the shafts or somewhere downstream. For clarification, please indicate or summarize exactly where the 10 WG duct is required.

Government Response 39:

This pressure class requirement applies to ductwork between the respective AHU discharge and the first fire damper, or combination fire/smoke damper, indicated in the respective mains. Refer to the interstitial space ductwork plans (Drawings MH-114 - Sectors D through J) for damper locations.

Question 40:

Duct pressure classifications differ from spec section 230000 and drawing M-003-i.e. the specifications call for the supply duct between the AHU and Air Volume Control Box to be 6 inch WG. Drawing M-003 Note #8 says supply duct to Air Volume Control Boxes is 6 inch WG when the external static pressures are 3 to 5 inches which would only apply to AHU-4. All other AHU's would be either 3" or 4" WG. Please clarify which specification to follow.

Government Response 40:

The more stringent criteria shall apply. Follow specification 23 30 00. All supply ductwork between the AHUs and Air Volume Control Boxes shall be 6" w.g. (minimum).

Question 41:

On drawing M-003 Note #33 says Exposed duct in all areas shall be double wall. Is this required for this project? If so, does this apply to MH-111D-Exposed duct in loading dock and AHU-1 return and drawing M-112D-AHU-1 exposed supply and return duct?

On drawing MH-111F is the exposed duct in High End Fabrications and the electrical rooms double wall? On drawings MH-111E, MH-111F, MH-111J, MH-112E and MH-112F much of the duct is above a Strut Grid Ceiling System-Is this duct considered exposed and required to be double wall?

Government Response 41:

Yes, double-wall ductwork is required for this project. It is intended to protect ductwork insulation in occupied spaces where it may be prone to damage.

Yes, this applies to exposed duct (requiring insulation) in the loading dock on Drawing MH-111D.

Yes, this applies to exposed duct (requiring insulation) associated with AHU-1 (supply and return) on Drawing MH- 112D.

No, this does not apply to ductwork above the unistrut grid ceiling in High End Fabrication and ductwork in the electrical rooms on Drawing MH-111F unless specifically stated otherwise.

No, this does not apply to ductwork above the unistrut grid ceiling on drawings MH-111E, MH-111F, MH-111J, MH- 112E and MH-112F unless specifically stated otherwise.

Question 42:

On drawing M-003 Note #53 Item I says the first 5' of duct after the Volume Control Boxes is to be double wall. Is this a requirement on this project?

Government Response 42:

Yes, this is a project requirement for sound attenuation. Refer also to detail E5/M503.

Question 43:

Spec section 230000 2.9.1.4-Duct Pressure Classifications and Construction Paragraph a, Item #5 says dust collection supply ducts between the dust collector outlet and the explosion isolation valve is 22 inch WG positive. On drawing M-601 the dust collector schedule note #5 indicates there will be isolation valves on DC-4 and 5. Please indicate where the valves are to be located in the ductwork so the extent of the 22 WG duct can be determined. Just to verify, are these the only 2 dust collectors that will require isolation valves and 22 WG duct?

Government Response 43:

Refer to ductwork plans MH-111F and M403 for explosion isolation valve locations. Yes, only dust collectors DC-4 & DC-5 have explosion isolation valves and 22" w.g. ductwork.

Question 44:

Drawing MS108.A has an add Alternate #4 that increases the size of the Chiller and the Chilled Water and Condenser Water Pumps. Should the size of the Cooling Tower be increased too? Please provide a schedule if required.

Government Response 44:

The size of the cooling tower CT-7 is not changed as a result of Alternate #4.

Question 45:

There are clocks shown on the drawings but there is no spec. section. Please advise.

Government Response 45:

CLOCK SYSTEM SHALL BE COMPATIBLE WITH WEST POINTS STANDARD CLOCK

SYSTEM FROM SAPLING AS PER T-606.

Question 46:

Please confirm if the security system is by the owner, we cannot locate a spec section. Please advise.

Government Response 46:

Security system electronics and headend are Government Furnished Government Installed (GFGI). Rough-ins for conduits with pullstrings and backboxes are contractor furnished contractor installed (CFCI).

Question 47:

The summary of work mentions a solar array on roof but nothing can be located in the documents. Please Advise Government Response 47:

The solar array will be located on the roof of the south stair tower. The panels are government furnished government installed (GFGI). The infrastructure for the array is contractor furnished contractor installed (CFCI).

Question 48:

Provide final quantity of duct smoke detectors, combination fire/smoke dampers, and motorized dampers required for mechanical ductwork / HVAC system.

Government Response 48:

The Government cannot provide quantities for those components to the bidders. Quantities are the responsibility of the bidding contractor. The Contractor shall quantify smoke detectors, combination fire/smoke dampers, and motorized dampers, as necessary, based upon the contract documents. Refer to all plans, sections, details, flow diagrams, controls diagrams, sheet notes, and specifications for required locations.

Question 49:

Will MI cable be required for fire alarm backbone circuitry? Is CIC (circuit integrity cable) acceptable?

Government Response 49:

CIC is acceptable to be used for the fire alarm backbone circuitry.

Question 50:

Will fire suppression system pre-action control panel be furnished and installed by Division 21?

Government Response 50:

Yes, pre-action control panel to be furnished and installed by Division 21.

Question 51:

Will clean agent suppression system control panel be furnished and installed by Division 21?

Government Response 51:

Yes, clean agent suppression system control panel to be furnished and installed by Division 21.

Question 52:

Circuitry designations for elevator power modules are not shown, please provide panel/ckt. information.

Government Response 52:

Elevator power module wiring is indicated on the single line diagram E601

Question 53:

Will Division 23 / 25 be responsible for furnishing and installing all VFD cable from loose VFD's to mechanical / HVAC equipment?

Government Response 53:

Division 26 shall install VFDs with their integral corresponding line reactors (LRs) and/or harmonic passive filters (HPFs) that are not factory mounted with the equipment. Div 26 shall provide all wiring, connections and mounting methods in accordance with equipment installation requirements.

Question 54:

Are tamper-resistant receptacles required (per NEC Art. 406)? Please indicate locations and quantities.

Government Response 54:

Tamper resistant receptacles are not required

Question 55:

Provide a completed conduit and wire size column on the mechanical schedules. Indicate which items are to be provided with a dedicated 20A circuit vs. a branch 20A circuit.

Government Response 55:

Refer to electrical drawings for equipment circuiting requirements

Question 56:

Confirm WAP's, telephones, network switches, routers, gateways, UPS's, PC's are provided and installed outside of the Division 27 contract

Government Response 56:

Electronic network/telephone devices are government furnished government installed (GFGI).

Question 57:

Confirm full and complete working low voltage communications systems (i.e. devices, equipment, cabling, testing/startup) are required for voice/data, cable TV, intercom, master clock, emergency communications, public address, and audio-visual will be required by Division 27.

Government Response 57:

Correct all systems indicated above will be contractor furnished contractor installed (CFCI), compete and functional, except for audio-visual. Audio visual equipment is government furnished / government installed; the related audio visual infrastructure as depicted in the drawings is contractor furnished / contractor installed.

Question 58:

Confirm full and complete working low voltage security systems (i.e. devices, equipment, cabling, testing/startup) are required for access control, video surveillance, intrusion detection) are required as part of the Division 28 contract.

Government Response 58:

Security system electronics and cabling is government furnished government installed (GFGI). Rough-in conduits, pull strings and back-boxes are contractor furnished contractor installed (CFCI).

Question 59:

Will access control and video surveillance systems be stand-alone or integrated together?

Government Response 59:

Access Control and CCTV electronics and controls will be government furnished government installed (GFGI) and any integrations will be determined by the government.

Question 60:

Will electrical and communications duct banks require bare copper ground wire (#4/0awg)?

Government Response 60:

Reference Drawing T509 for communication ductbank requirements.

Question 61:

Confirm technology service incoming copper and fiber optic cabling is provided outside of Division 27.

Government Response 61:

Outside fiber and copper cable plant is contractor furnished contractor installed (CFCI) per 'T' drawings and specifications.

Question 62:

Provide clarity on the following low voltage system acronyms – WREN, EECS, EIN, which appear on drawing T-605.

Government Response 62:

Reference T-001 abbreviations for acronyms Question 63:

Please confirm that amount of roofing materials to be removed/abated in Quarter 5, 6 and 7.

Government Response 63:

The contractor shall remove/abate all roofing materials in Quarter 5, 6 and 7. Refer to Division 2 Specifications for additional information.

Question 64:

Please provide the following quantities to be abated at Mahan Hall: Vapor barrier mastic & associated with the exterior wall and interior wall (Location and Quantity?); Sprayed On Fire Proofing of I-Beam (Location and Quantity);

and Exterior Window Caulking (Gray) has trace amount of asbestos - not ACM, will this need to be abated?

Government Response 64:

02 81 00 Attachment B is provided to inform bidders of typical HAZMAT conditions found within Mahan Hall. If CLIN 0006 is exercised, the contractor shall abate the typical HAZMATs within the immediate area of disturbance only as needed to execute Add Alternate #1. The bidding contractor is responsible for determining quantities. If CLIN 0006 is exercised, the contractor shall remove and properly dispose of Exterior Window Caulking only as required to execute Add Alternate #1. Section 02 82 13.00 10 defines the requirements for handling ACM and non-ACM disposal.

Question 65:

Civil drawing # C-210 provides two profiles A1 and D1 , These two profiles show 2EA -Jacking pits sizes 35'x20'x32' deep and 35'x20'x28' deep and 02 EA receiving pits sizes 10' x 10' x 8.5' and 10' x 10'x 7.5'respectively , We couldn't find any structural details regarding those pits , please advise on which drawings can we find these details ?

Government Response 65:

No details for the jacking and receiving pits are needed. Provide excavations and shoring as required for the auger bore operations. Refer to Specification 31 00 00 Earthwork for shoring requirements.

Question 66:

Site Demolition drawings CD-101 and CD-102 call for removal of asphalt pavement/ walkway , concrete paving and walkway, retaining wall , rip rap , timber wall .

No information for pavement thickness and or wall thickness to be removed , Is it possible to get more information for exist pavement thickness , wall thickness and height .

Government Response 66:

Refer to the boring logs BB101 - BB511 for available information on pavement thicknesses. No additional information on existing wall construction is available.

Question 67:

Spec Section 230000 page 17 2.9.1.4-Duct Pressure Classifications and Construction Paragraph a, Item #1 says supply ducts between AHU and Fire or Smoke Dampers is 10 inch WG. There aren't any Smoke Dampers shown and some systems don't have any Fire/Fire Smoke dampers in them and others have them coming out of the shafts or somewhere downstream. For clarification, please indicate or summarize exactly where the 10 WG duct is required.

Government Response 67:

This pressure class requirement applies to ductwork between the respective AHU discharge and the first fire damper, or combination fire/smoke damper, indicated in the respective mains. Refer to the interstitial space ductwork plans (Drawings MH-114 - Sectors D through J) for damper locations.

Question 68:

Duct pressure classifications differ from spec section 230000 and drawing M-003-i.e. the specifications call for the supply duct between the AHU and Air Volume Control Box to be 6 inch WG. Drawing M-003 Note #8 says supply duct to Air Volume Control Boxes is 6 inch WG when the external static pressures are 3 to 5 inches which would only apply to AHU-4. All other AHU's would be either 3" or 4" WG. Please clarify which specification to follow.

Government Response 68:

The more stringent criteria shall apply. Follow specification 23 30 00. All supply ductwork between the AHUs and Air Volume Control Boxes shall be 6" w.g. (minimum).

Question 69:

On drawing M-003 Note #33 says Exposed duct in all areas shall be double wall. Is this required for this project? If so, does this apply to MH-111D-Exposed duct in loading dock and AHU-1 return and drawing M-112D-AHU-1 exposed supply and return duct? On drawing MH-111F is the exposed duct in High End Fabrications and the electrical rooms double wall? On drawings MH-111E, MH-111F, MH-111J, MH-112E and MH-112F much of the duct is above a Strut Grid Ceiling System-Is this duct considered exposed and required to be double wall?

Government Response 69:

Yes, double-wall ductwork is required for this project. It is intended to protect ductwork insulation in occupied spaces where it may be prone to damage.

Yes, this applies to exposed duct (requiring insulation) in the loading dock on Drawing MH-111D.

Yes, this applies to exposed duct (requiring insulation) associated with AHU-1 (supply and return) on Drawing MH- 112D.

No, this does not apply to ductwork above the unistrut grid ceiling in High End Fabrication and ductwork in the electrical rooms on Drawing MH-111F unless specifically stated otherwise.

No, this does not apply to ductwork above the unistrut grid ceiling on drawings MH-111E, MH-111F, MH-111J, MH- 112E and MH-112F unless specifically stated otherwise.

Question 70:

On drawing M-003 Note #53 Item I says the first 5' of duct after the Volume Control Boxes is to be double wall. Is this a requirement on this project?

Government Response 70:

Yes, this is a project requirement for sound attenuation. Refer also to detail E5/M503.

Question 71:

Paragraph 2.1.2 lists Abuse Resistant Gypsum Board but a criteria for its use has not been outlined either in the specs nor the partition schedule. Is there a requirement for abuse board on this project, if so where?

Government Response 71:

Abuse Resistant Gypsum Board is not used on the project.

Question 72:

Spec section 230000 2.9.1.4-Duct Pressure Classifications and Construction Paragraph a, Item #5 says dust collection supply ducts between the dust collector outlet and the explosion isolation valve is 22 inch WG positive. On drawing M-601 the dust collector schedule note #5 indicates there will be isolation valves on DC-4 and 5. Please indicate where the valves are to be located in the ductwork so the extent of the 22 WG duct can be determined. Just to verify, are these the only 2 dust collectors that will require isolation valves and 22 WG duct?

Government Response 72:

Refer to ductwork plans MH-111F and M403 for explosion isolation valve locations. Yes, only dust collectors DC-4 & DC-5 have explosion isolation valves and 22" w.g. ductwork.

Question 73:

Drawing MS108.A has an add Alternate #4 that increases the size of the Chiller and the Chilled Water and Condenser Water Pumps. Should the size of the Cooling Tower be increased too? Please provide a schedule if required.

Government Response 73:

The size of the cooling tower CT-7 is not changed as a result of Alternate #4.

Question 74:

According to the solicitation, under the technical proposal factor 2, there will a summary schedule, please advise on the following questions related to the requested schedule:

a. Please confirm that PDF version of the schedule is acceptable and that the government doesn't require any other electronic version of the schedule like P-6 or similar software.

b. Please confirm the schedule pages sizes, can we utilize full size schedule page or are we limited to 11*17?

c. Please advise if the government would like to see the add options as part of the schedule or only limit to the schedule to the base bid scope? or should the government allow for 2 schedules, one with options and one only for base bid? and if that is desirable, can you please increase the page limit under factor 2?

Government Response 74:

a. Submission shall be in Adobe PDF format. The Government will not evaluate a schedule submitted in any other format.

b. Pages containing text shall be submitted electronically on standard 8-1/2 x 11 inch size paper. Schedules, Drawings and/or sketches may be submitted electronically on paper not exceeding 11 x 17 inch paper, (each 11 x 17 counts as two pages).

c. The proposal shall include one schedule. The Government cannot speculate as to how an Offeror's proposal will be evaluated. The contents of the submitted schedule is allowed to exceed the minimum requirements noted in the Solicitation. Schedules which offer advantage(s) to the Government will receive additional consideration. The Government will evaluate the Offeror's capability to schedule the complete project within the proposed contract duration and the realism of the schedule.

Question 75:

Please confirm that the onsite testing agency will be hired and paid for by the contractor and that the base bid should include that cost.

Government Response 75:

Yes the contractor shall provide and pay for testing as required by the drawings and specifications.

Question 76:

According to specification section 019100.15, total building commissioning, the government will retain, hire and pay for commissioning agency during construction, from prior experience working on base, we have always seen the commissioning agency during construction is an agency retained, hired and paid for by the contractor, please clarify

Government Response 76:

The Government will contract directly with the independent Commissioning Agent.

Question 77:

Provide a wall section for retaining wall RW20.

Government Response 77:

Site retaining wall schedule and detail are shown on S-501.

Question 78:

On drawing C502 wall sections for stone walls #3A (D7), #3B (A6) and #4 (A8). What is the 4" stone face material and what pattern is it set in?

Government Response 78:

Stone face shall be the same material and pattern as the new granite building facade.

Question 79:

Please provide a wall section for this decorative dry laid retaining wall.

Government Response 79:

See Detail D7, Sheet C-509

Question 80:

Drawing L302 - A1 - Upper Plaza paving pattern Enlargement. Provide wall sections for the plaza planters.

What size are the granite boulder pavers?

Schedule on L004 calls for 24" x 36" is this correct?

Government Response 80:

Plaza planter wall section included on F1/L-602. 24"x36" granite pavers are correct.

Question 81:

Drawing L301 - A1 - North Outdoor Classroom Provide a wall section of transition step to granite pavers at north cadet entrance.

Government Response 81:

Granite clad step section and detail included on D6/L-502, A8/L-603.

Question 82:

Provide a back up wall section of column line 14 (from first floor to fourth floor). (FYI - A1/A533 only shows 8" cmu interior)

Government Response 82:

A1/A533 is a specialty detail for an isolated acoustical floor. It is not intended to show exterior wall conditions or column conditions. For column details at column line 14 see the A100 series and quadrant F.

Question 83:

For telecom, will we need to provide any enclosures for the outdoor waps?

Government Response 83:

The WAPs are government furnished government installed (GFGI). The outlet box and jack mounted outside will be in a weatherproof enclosure (WP) as indicated on drawings.

Question 84:

on the interstitial area of the 4th floor outside of the add alternate space. Is that area included in the scope for DAS coverage?

Government Response 84:

DAS is not required in the interstitial area

Question 85:

Section 33 82 00 page 21 indicates soil density test on the OSP. are these results to be submitted with the OSP Close outs?

Government Response 85:

They shall be submitted for review when taken and again at close-out.

Question 86:

in the cut over of the existing OSP to the OSP in the new duct bank, what is the maximum allowed time for services to be down?

Government Response 86:

Refer to spec section 01 14 00 for allowed outage requirements.

Question 87:

What type of fiber is the 48 strand MM from B600 to B626? 62.5 or 50 micron?

Government Response 87:

On T-602 the 48 strand MMF is 62.5 cable

Question 88:

Please confirm there is adequate space in the existing duct banks leading into building 600?

Government Response 88:

It is understood that space within the existing ductbank system is available for new cables.

However, contractor shall coordinate and confirm with the government COR the final location and routing prior to ordering and installing cables as multiple projects and work are on going at West Point.

Question 89:

Are scheduled road closures permitted for installation of the OSP?

Government Response 89:

Yes, in accordance with Division 01 requirements.

Question 90:

Is the ECS infrastructure required to be in point to point conduit?

Government Response 90:

Provide conduit configuration as required by NFPA 72 and 1221 and manufacturer recommendations as indicated on T-603 notes

Question 91:

Is the ECS infrastructure required to be enclosed in a 2 hour rated pathway?

Government Response 91:

Room EC-332 which houses the ECS equipment is to have 2 hour rated walls as well as the path to the exterior antenna. Provide infrastructure as required by NFPA 72 and 1221 and as recommended by manufacturer indicated on T-603 notes.

Drawing(s) to reflect the 2 hr rated wall and the door schedule are revised in this amendment.

Question 92:

Please confirm all RFI's and responses posted on ProjNet will ultimately be published in a formal Amendment.

Or is the intention of Project to supplement the responses included in the Amendments. There are a significant amount of responses already posted to RFI's on ProjNet that have yet to be posted formally in an Amendment.

Please advise.

Government Response 92:

Yes. All RFI's and responses posted on ProjNet have been published in this and in the preceding Amendments.

Question 93:

Regarding the triangular skylight on S-11MH, If add alternate #03 is accepted it would be omitted at this elevation and raised to the higher elevation as shown on S-115H.A, correct?

Government Response 93:

Correct.

Question 94:

Please confirm if the Metal Partition System is Contractor supplied/Owner installed or Owner supplied/Owner installed.

Government Response 94:

The scope of work shown on A-411D.26 is to be provided by the contractor. The metal partition system is contractor furnished and contractor installed.

Question 95:

The previously answered RFI ID 8653135 didn't address the question, regarding the statement in the solicitation 5.1.2 that requires minimum of 2 projects showing example rock excavation ...etc., can we suggest that the government allow the offeror if using a specialized experience subcontractor under a teaming agreement that this subcontractor can demonstrate such special experience such as the rock scope utilizing 2 projects for his specialty only, while that subcontractor special experience gets counted only as one of the 5 offeror relevant experience? Since the specialty subcontractor on this case being the rock subcontractor as example special experience will not be lengthy and it will only cover the rock scope, in that case we accommodate the government request and demonstrate relevant experience on that specific aspect. Please advise if suggestion is acceptable?

Government Response 95:

The Government cannot offer speculation as to how an Offeror's experience would be evaluated.

Past Performance Relevancy Ratings will be assigned in accordance with Table 1, which appears on page 24 of the Solicitation dated 3-June-2020. As indicated on Table 1, past performance efforts may be rated Very Relevant, Relevant, Somewhat Relevant, or Not Relevant.

Question 96:

Please confirm the unit price / LF for micropile is to be one single price that includes both the bearing socket length and the cased shaft length. Micropile Section 31 62 20.50, 1.1.1.1.2 states separate measurements shall be made for bearing socket lengths and cased shaft lengths.

Solicitation - Section 00 10 00, amendment 2, lists a quantity that does not differentiate the lengths. Item 0006AB.

Micropile Section 31 62 20.50, 1.1.2b. is a list of pay items.

Government Response 96:

Micropiles shall be measured by micropile lengths from cut-off to tip including bearing socket and the cased shaft length. CLIN 0006AB is one unit price inclusive of all costs necessary to install actual length of micropiles accepted in place by the Geotechnical Engineer who is hired by the Contractor. 31 62 20.50 para 1.1 has been revised in this amendment.

Question 97:

Detail A5 on Drawing A-530 calls for K-13 sprayed acoustic insulation over intumescent fireproofed steel.