W16ROE30148256
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
a. Incorporate Revised Plans and Specs.
b. Incorporate the Work Breakdow n Sheet (WBS)
c. Incorporate Responses to Questions (For Informational Purpose Only)
Proposal due date is changed FROM: 18 June 2013 at 2:00 P.M. EST TO: 25 June 2013 at 2:00 P.M. EST.
NOTE: Offeror must acknow ledge receipt of this amendment by the date specified in the solicitation (or as amended) by signing block 15 of the SF 30 and emailing to the identified point of contacts. FAILURE TO ACKNOWLDEGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF
PROPOSALS (FAR 15.208).
1. CONTRACT ID CODE PAGE OF PAGES
J 1 7
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 12-Jun-2013
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS-13-R-0017
X 9B. DATED (SEE ITEM 11)
02-May-2013
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
12-Jun-2013
CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 1843
NEW YORK NY 10278-0090
W912DS 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DS-13-R-0017
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0005
AMENDMENT 0005 TO THE DRAWINGS AND SPECIFICATIONS FOR CERDEC Flight Activity Facility, Lakehurst, NEW JERSEY; W912DS-13-R-0017
TO OFFERORS
The following changes shall be made to the drawings and specifications.
DRAWINGS
1. The following drawings have been ADDED;
NUMBER TITLE DATE
NONE
2. The following drawings which were listed in Amendment 4 as revised but were not posted to the FEDBIZOPS website are posted with this amendment:
NUMBER TITLE DATE
C-501 Civil Details 4 June 13 C-509 Civil Details 4 June 13 H101 Decorative Hardscape Layout Plan 3 June 13 H102 Decorative Hardscape Details 3 June 13
LA101 Landscape Plan 3 June 13 LA103 Landscape Details and Notes 3 June 13
A-406 Millwork Sections & High Density Storage Elevations 4 June 13
SPECIFICATIONS
1. The following specifications are ADDED to the specification and issued with this amendment:
SECTION TITLE DATE
00100 Work Breakdown Structure (WBS) NA
2. The following specifications are REVISED and REISSUED:
NONE
3. The following specification is DELETED in its entirety (and from the index) without
REPLACEMENT:
4. The following specifications are REVISED but NOT REISSUED:
Paragraph 2.2 of section 00 22 11 is deleted in its entirety and replaced by the following:
“2.2 Electronic Submission: Electronic Submission.
In addition to the hard copies required in this solicitation, all Offerors shall submit Volume I and Tabs B, C and E of Volume II of their proposal on CD ROM (one CD for each volume). Written portions of the proposal shall be in MS Word or Adobe Acrobat PDF format. The electronic version shall be either a single file tabbed in the same order as the hard copy or multiple files hyperlinked to a single table of contents. Any portion of the proposal not available in electronic format, i.e. cut sheets, if applicable, should be scanned in Adobe Acrobat PDF format, thus making it available electronically. The CD-ROM must be clearly labeled by solicitation number, project name, installation, volume number and offeror’s name. The CD-ROM shall be marked with a label stating “Unclassified//Controlled Unclassified Info.” In the event of any conflict between the electronic submission and the hard copy submission, the hard copy submission will govern and will be the material upon which the Government bases its evaluation and ultimately, its decision. Electronic media may be submitted in an un-editable format.”
Paragraph 3.1 of section 00 22 11 replace “(4) Heavy industrial Concrete foundations or Concrete floors;” where it appears replace this wording with the following: “(4) Heavy industrial Concrete foundations or Concrete floors or pavements 8” or greater in thickness;”
Paragraph 3.2.1 of section 00 22 11 as it appears in amendment 2 is deleted in its entirety and replaced by the following:
“3.2.1. GENERAL
The price proposal shall be submitted in a separate binder labeled "Volume II - Price Proposal".
The sections shall parallel the submission requirements identified in the bid schedule. Provide five (5) copies of bound written material (folded and bound in Volume II). Submit Tab B, C and E of the Pro Forma information in a separate envelope labeled: “Volume II - Pro Forma Requirements (Tab B, C and E). Provide a CD ROM only for Tabs B, C and E.”
Paragraph 3.2.4.1(2) of section 00 22 11; delete the word “certified” where it appears without replacement.
BIDDER’S QUESTIONS AND GOVERNMENT REPLY
(Questions that may be of general interest of all bidders/Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or clarify and simplify the question(s). Questions and answers are issued to the Offerors/Bidders for information only.)
Q036: What is the Pro Forma information requested bound and folded in Vol. II?
A036: Pro Forma information is the information requested in Tabs B, C, D and E of Volume II. Note revisions that appear above in this amendment.
Q038: The following portions of SECTION 00 22 11 FACTORS FOR EVALUATION, BASIS OF
AWARD, EVALUATION CRITERIA, RATING SYSTEM AND DEFINITIONS 00 22 11 SECTION)
are to be replaced with the following language:
Factor 1 states the Prime Contractor shall demonstrate not less than two previous buildings of "Similar Size" 50,000sf or more and having two previous projects having to have been "similar magnitude of $25,000,000 or more.
In a teaming arrangement do the above mentioned requirements have to be from the prime bidder or can they be submitted by our primary teaming partner subcontractor. If not, can the standards be lowered? Requiring a small business to have two projects of that size and valve is unreasonable and will seriously limit competition. Also under Similar Scope, #3 - Can other similar concrete pavement projects that were designed for heavy duty truck aprons, government vehicle storage yards etc that are 8" thick be considered because they are basically the same as 8" Airfield Pavement?
A038: No; this standard will remain unchanged. Offeror are reminded that Large/Small business JVs except for “Mentor-Protégés agreements officially approved by the SBA” will not be allowed to submit a proposal as a qualified bidder.
Yes; See revisions that appear above in this amendment which addresses a change “Similar Scope” to include pavements 8” and greater.
Q042:
Reference Section 00 21 11, Paragraph 3.2.5 - 3.2.5.2
Question Would the Government please clarify what specific information is to be included in the Offeror's proposal under Tab D, Work Breakdown Structure Sheet, as well as the required format for that information?
A042: The Work Breakdown Structure Sheet that is issued with this amendment is to be provided under Tab D.
Q046:
Reference Section 00 22 11 Paragraph 2.7 and Clause 52.236-28 item (a.2)
Question The Preparation of Proposals clause and the instructions require manual/original (“blue ink”) signatures for proposals. Would the Government clarify which volumes/tabs this requirement applies to, and whether this applies only to the original binder or to the copies as well?
A046: The original must be marked “Original” and marked in blue ink. The blue ink applies to both Volumes I and Volume II.
Q047 & Q048: What is the Pro Forma information requested bound and folded in Vol. II?
A047 & A048: See Q036 and its response.
Q080: Reference Section 00 21 11, Paragraph 2.2
Question Is the electronic submission requirement for 1 CD containing the complete proposal (both volumes), or 2 CDs total (1 CD for each volume)?
A080: Paragraph 2.2 has been revised under this amendment and addresses this question as well as others.
Q081: Reference Section 00 21 11, Paragraph 2.3
Question Do the page limitations exclude front matter such as title page, table of contents, and cover/transmittal letter?
A081: Front matter such as title page, table of contents, and cover/transmittal letter are not part of the 75 page limit.
Q082: Reference Section 00 21 11, Paragraph 3.2.1
Question Would the Government please clarify which items specifically (Tabs A-E) should be included in the bound copies (Volume II Price) and which in the sealed envelope (Volume II Pro Forma Information)?
A082: Paragraph 3.2.1 has been revised under this amendment and addresses this question as well as others.
Q083: Reference Section 00 21 11, Paragraph 3.2.2.2
Question Are signed/completed Acknowledgement of Amendments (if any) to be included with the SF1442 under Tab A?
A083: Yes.
Q094: Section 2.4.17.1 ACS Software shall support responses to alarms entering the system.
a. Please define the MFG/Product of CCTV system for interface compatibility.
b. Please define DVR event recording to include DVR Model and events.
c. Please define floor-plan graphical map file types to be provided.
d. Please define the number of networked PC workstations that would be concurrently connected to the ACS software.
A094:
a. The exact make and model of the CCTV system has yet to be determined by the government. After award, the successful Offeror will have to coordinate with contracting officer’s representative to obtain this information.
b. The design intent is to have the access controls system notify the CCTV system to record on a specific camera when the local door records an event. Events include any signal received from local door controller such as card swiped, door opened, door propped open, door forced open, etc. The make and model of the DVR recorder has yet to be determined by the government. After award, the successful Offeror will have to coordinate with contracting officer’s representative to obtain this information.
c. The file types for the graphical floor plan need to be coordinated with the CCTV and IDS vendor. After award the successful Offeror shall coordinate file types with these vendors via contracting officer’s representative.
d. Unlimited.
Q102: Solicitation page 20 of 116 paragraph 2.2, please concur that the CD‐ROM is only required for Volume 1 Technical Proposal. It will be virtually impossible to burn a CD for Volume 2 Price Proposal and Pro Forma Information just before due time/date of the bid unless the Proposal Bid Schedule can be left out from the CD‐ROM. Please know that most subcontractor numbers arrive sometime 30‐45 minutes before deadline time.
A102: See revision to paragraph 2.2 and other paragraphs which appear above under this amendment.
Q103: Solicitation page 29 of 116 paragraph 3.2.5.2, please concur that as of this moment, there is nothing to submit for TAB D under Volume 2.
A103: See revisions which appear above under this amendment and the Work Breakdown Structure Sheet that has been issued with this amendment.
Q104: Solicitation page 29 of 116 paragraph 3.2.1(2) (understood to mean “3.3.4.1 (2)”) is the term “certified” meant to mean a notarized signature to the prime contractor statement or just a prime contractor signed and seal document or both.
A104: The word “certified” has been removed from this paragraph. Offerors must submit statement listing required items.
Q105: Are there any temporary utilities available on site for the contractor’s use? If yes, than please provide the details of available services and also clarify the responsibility of usage charges for the same.
A105: Offerors are directed to paragraph 17 of section 00 80 00 (Special Contract Requirements), titled “Availability and Use of Utility Services and Permits (Apr 1984)” and the Topographic Survey drawings V-101 through V-115.
(End of Summary of Changes)