W16ROE30148256
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
a. Incorporate Revised Specifications and Draw ings
b. Incorporate Responses to Questions (For Informational Purpose Only)
c. Incorporate Site Visit Attendance List
Proposal due date remains the same as 18 June 2013 at 2:00 P.M. EST.
NOTE: Offeror must acknow ledge receipt of this amendment by the date specified in the proposal (or as amended) by one of the follow ing methods: in the space provided on the SF 1442, by separates letters, or by telegram by signing block 15 below . FAILURE TO ACKNOWLDEGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS (FAR 15.208).
1. CONTRACT ID CODE PAGE OF PAGES
J 1 16
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 11-Jun-2013
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS-13-R-0017
X 9B. DATED (SEE ITEM 11)
02-May-2013
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
11-Jun-2013
CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 1843
NEW YORK NY 10278-0090
W912DS 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DS-13-R-0017
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0004
AMENDMENT 0004 TO THE DRAWINGS AND SPECIFICATIONS FOR CERDEC Flight Activity Facility, Lakehurst, NEW JERSEY; W912DS-13-R-0017
TO OFFERORS
The following changes shall be made to the drawings and specifications.
DRAWINGS
1. The following drawings have been ADDED;
NUMBER TITLE DATE
NONE
2. The following drawings are REVISED and REISSUED:
NUMBER TITLE DATE
C-501 Civil Details 4 June 13 C-509 Civil Details 4 June 13 H101 Decorative Hardscape Layout Plan 3 June 13 H102 Decorative Hardscape Details 3 June 13
LA101 Landscape Plan 3 June 13 LA103 Landscape Details and Notes 3 June 13 A-105 Floor Plan - Area D (Revision 2) 4 June 13 A-406 Millwork Sections & High Density Storage Elevations 4 June 13
SPECIFICATIONS
1. The following specifications are ADDED to the specification and issued with this amendment:
SECTION TITLE DATE
10 75 16 FLAGPOLES 30 May 13
2. The following specifications are REVISED and REISSUED:
SECTION TITLE DATE
08 71 00 DOOR HARDWARE 30 May 13
3. The following specifications are REVISED but NOT REISSUED:
None
BIDDER’S QUESTIONS AND GOVERNMENT REPLY
(Questions that may be of general interest of all bidders/Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or clarify and simplify the question(s). Questions and answers are issued to the Offerors/Bidders for information only.)
Q064: Drawing detail 7/C-501 which is the new to existing condition shows as the only location where tack and prime per specification 321210 Bituminous Tack and Prime Coats. Paragraph
3.4.3 clearly states for the tack coat “apply tack coat at the locations shown on the drawings”.
Others details such as 1 through 6 on C-501 and 7/C-509 do not show any tack coat or prime coat. If details such as 1 through 6 on C-501 and 7/C-509 do require tack coat and prime coat, please indicate them.
A064: Prime and tack coat will be used for all asphalt paving sections. Refer to attached revised sheets C-501 and C-509 for more information.
Q065: Specification 311100 Clearing & Grubbing paragraph 3.2 please concur that there are no trees that are to be trimmed as all trees within the boundary limits as indicated on drawing CD- 100 are coming out.
A065: Concur, no trees to be trimmed are to remain on site; all trees within the boundary limits are to be removed entirely.
Q066: The A200 series drawings indicate FWP 1, 2, 3 along with composite wall panel. The 074263 Fabricated Wall Panel Assemblies specifications have composite wall panel and only one performance spec for a FWP (Formed wall panel). We will need to know more specifically the design intent of each panel other than what is in paragraph 2.1.1, i.e. is it 2" thick foamed place or corrugated, etc. The only information provided in specification 090690 paragraph
2.2.1.3 is only the color.
A066:
FWP1 – Basis of Design: Centria Versawall 2.75” Planked
FWP2 – Basis of Design: Centria Versawall 2.75” Planked FWP3 – Basis of Design: Centria Formawall 2” Horizontal Flat FWP4 – Basis of Design: Centria Versawall 2.75” Planked
Q067:
Reference Specifications Volume 2, Section 23 08 00.00 10, Paragraph 1.5.1 Specifications Volume 2, Section 26 08 10, Paragraph 1.5(b) Specifications Volume 1, Section 01 91 10 Specifications Volume 1, Section 07 08 00 Specifications Volume 1, Section 08 08 00
Discussion Per Division 23 specifications, “the government will provide the services related to the commissioning authority.” Per Division 26 specifications, “the Owner has contracted with a commissioning authority (CxA) to oversee certain commissioning activities on this project.”
Question Specifications in Division 01, Division 07, and Division 08 do not address who is furnishing the CxA. Will the Offeror furnish and pay for the CxA or will the Government furnish and pay for the CxA? Will this be addressed in an amendment?
A067: 4. The Government will provide the CxA; this is not a contractor requirement.
Q068:
Reference Section 00010
Question In Option 15, the contractor is required to furnish and install a wash system / equipment. There is no section listed in the specification for this work. Will a section for this work be added by amendment?
A068: Wash Rack and Wash Water Reclaim System is specified in Section 23 00 00, paragraph 2.14
Q069:
Reference Section 00010
Question In Option 25, the contractor is required to furnish and install a paint booth. There is no section listed in the specification for this work. Will a section for this work be added by amendment?
A069: Paint Booth is specified in Section 23 35 19.00 20, paragraph 2.3.
Q070:
Specifications Volume 1, Section 10 56 26
Question In reference to Division 10 specifications, motorized mobile storage system, where are these units located on the drawings, which rooms, and what are the sizes?
A070: Refer to Sheet Keynotes 12, 18, 19, 20 and 21 on Sheet A-105 for location of Manual Mobile Storage System.
Q071:
Reference Drawings A-105 and A-106
Question In reference to Drawing A-105, room #147, ALSE Support Storage, what are the units that are called out in Notes #18, 19, 20, and 21 and are detailed on drawing A-406 detail #5, 6, 7, and 8? And, are these the motorized mobile storage systems units?
A071: The units called out as indicated are the Manual Mobile Storage System units. The front elevations of details 5, 6, 7 and 8 on sheet A-406 elevate one module of each unit.
Q072:
Reference Drawings A-105 and A-406
Question In reference to Drawing A-105, room #121, Special Tools Room, what are these units that are called out in Note #12 and are detailed on drawing A-406 detail #4? And, are these the motorized mobile storage systems units?
A072: Sheet A-105 has been revised to reflect changes to the elevation of Manual Mobile Storage System units (see attached). Refer to Sheet Keynote 22 for information on the Manual Mobile Storage System units in room #121, Special Tools Room. Detail 9 on Sheet A-406 has been added to show the elevations of the Manual Mobile Storage System units. The 3’-0” module occurs once and the 4’-0” module occurs twice in every row.
Q073:
Reference Drawings A-105 and A-406
Question In reference to Drawing A-105, room #120, Tech Supplies, what are these units that are called out in note #12 and are detailed on Drawing A-406, detail #4? And are these the motorized mobile storage systems units?
A073: The units called out as indicated are the Manual Mobile Storage System units.
The front elevation of detail 4 on sheet A-406 elevate one module of each unit.
Q074:
Drawing A-406
Question In reference to Drawing A-406, detail #4, 5, 6, 7, and 8, what material are these storage units made from (wood, metal, or plastic)?
A074: Refer to Specification Section 10 56 26 (Manual Mobile Storage System) Paragraph
2.1 for information on the materials of the storage system.
Q075:
Reference Drawing A-110
Question Drawing A-110 roof plan G shows a roof hatch. There is no section listed in the specification for this work, or a basis of design, will a section for this work be added by amendment?
A075: Refer to Specification Section 05 50 13 (Miscellaneous Metal Fabrications) Paragraph 2.8 for information on the roof hatch.
Q076: Is there a borrow pit on the air station that the general contractor can use for this project?
A076: 13. There are no borrow pits on the air station available for the general contractor’s use, Q077: Is there a dump site for waste on the air station that the general contractor can use for this project?
A077: 14. There are no dump sites on the air station available for the general contractor’s use. See paragraphs 1.q.2 and 53 of Section 00 80 00, Special Contract Requirements.
Q078: Drawing C-508 shows a flag pole. There is no section listed in the specification for this work, or a basis of design, will a section for this work is added by amendment?
A078: 15. A specification section for the flagpole has been added. See attached Section 10 75 16, Flagpoles.
Q079: Drawing A-509 shows a bicycle rack. There is no section listed in the specification for this work, or a basis of design, will a section for this work is added by amendment?
A079: 16. No specification section will be added for the bicycle rack. Provide a bicycle rack that complies with detail 3/C-509.
Q080:
Reference Section 00 21 11, Paragraph 2.2
Question Is the electronic submission requirement for 1 CD containing the complete proposal (both volumes), or 2 CDs total (1 CD for each volume)?
A080: The government intends to issue its response to this question in a forthcoming amendment.
Q081:
Reference Section 00 21 11, Paragraph 2.3
Question Do the page limitations exclude front matter such as title page, table of contents, and cover/transmittal letter?
A081: The government intends to issue its response to this question in a forthcoming amendment.
Q082:
Reference Section 00 21 11, Paragraph 3.2.1
Question Would the Government please clarify which items specifically (Tabs A-E) should be included in the bound copies (Volume II Price) and which in the sealed envelope (Volume II Pro Forma Information)?
A082: The government intends to issue its response to this question in a forthcoming amendment.
Q083:
Reference Section 00 21 11, Paragraph 3.2.2.2
Question Are signed/completed Acknowledgement of Amendments (if any) to be included with the SF1442 under Tab A?
A083: The government intends to issue its response to this question in a forthcoming amendment.
Q084:
Reference SF1442 Block 13A; Section 00 22 11 Paragraphs 2.7 and 3.2.1
Discussion SF1442 instructs submission of 1 original and 5 copies. Instructions paragraph 2.7 requires 1 original and 6 copies. Instructions paragraph 3.2.1 require 4 copies of the bound price volume and 1 copy of the Pro Forma Information.
Question Would the Government please clarify the required number of original/copies for Volume I (Technical), Volume II (Price), and Volume II (Pro Forma)?
A084: This has been addressed and clarified in amendment 2.
Q085: Per specification section 07 42 63, 2.1 Panel Material, please identify the following:
Q085.1. For material Tag FWP 1:
a. Type of Metal
b. Gauge of Metal
c. Type and Thickness of Insulated Metal Panel
d. Smooth or Embossed metal finish.
e. Flat or Striated panels.
f. Finish System A085.1:
85.1.a. G90 Galvanized Steel 85.1.b. 22 gage face / 22 gage liner 85.1.c. 2 ¾” insulated (R-20) 85.1.d. Embossed 85.1.e. Planked 85.1.f. Refer to Specification Section 07 42 63 (Fabricated Wall Panel Assemblies) Paragraph 2.1.2 for finish system
Q085.2. For material Tag FWP 2:
a. Type of Metal
b. Gauge of Metal
c. Type and Thickness of Insulated Metal Panel
d. Smooth or Embossed metal finish.
e. Flat or Striated panels.
f. Finish System A085.2:
85.2.a. G90 Galvanized Steel 85.2.b. 22 gage face / 22 gage liner 85.2.c. 2 ¾” insulated (R-20) 85.2.d. Embossed 85.2.e. Planked 85.2.f. Refer to Specification Section 07 42 63 (Fabricated Wall Panel Assemblies) Paragraph 2.1.2 for finish system
Q085.3. For material Tag FWP 3:
a. Type of Metal
b. Gauge of Metal
c. Type and Thickness of Insulated Metal Panel
d. Smooth or Embossed metal finish.
e. Flat or Striated panels.
f. Finish System
A085.3:
85.3.a. G90 Galvanized Steel 85.3.b. 22 gage face / 22 gage liner
85.3.c. 2” insulated (R-14) 85.3.d. Smooth 85.3.e. Flat 85.3.f. Refer to Specification Section 07 42 63 (Fabricated Wall Panel Assemblies) Paragraph 2.1.2 for finish system
Q085.4. For material Tag FWP 4:
a. Type of Metal
b. Gauge of Metal
c. Type and Thickness of Insulated Metal Panel
d. Smooth or Embossed metal finish.
e. Flat or Striated panels.
f. Finish System / Color
g. Horizontal or Vertical orientation of panels
A085.4:
85.4.a. G90 Galvanized Steel 85.4.b. 22 gage face / 26 gage liner 85.4.c. 2 ¾” insulated (R-20) 85.4.d. Embossed 85.4.e. Planked 85.4.f. Refer to Specification Section 07 42 63 (Fabricated Wall Panel Assemblies) Paragraph 2.1.2 for finish system / Color:
Centria; #978 Hunter Green 85.4.g. Vertical (wall and soffit conditions)
Q085.5: For material Tag ACM 1:
a. Finish System
A085.5:
85.5.a. Refer to Specification Section 07 42 43 (Aluminum Composite Wall Panels) Paragraph 2.1.1.2 for finish system
A085.6:
Q085.6: I believe FWP1 and FWP 2 would be our 2 3/4" Versawall Vertical Insulated Metal Panel, R-20, G90 Galvanized Steel, 22ga front and 26 Ga. back liner, 2 coat, Kynar finish, embossed flat, Color 1 and Color 2. (Smooth is only available in Formawall Dimension Series and a 22 Ga. front is required for Flat Versawall) Is this correct?
A085.6. Correct, except both face and liner gages to be 22 gage and the face sheet is planked.
Q085.7: I believe FWP 3 is FWDS 3"T Formawall Horizontal Insulated Metal Panel, R-22, G90 Galvanized Steel, 22ga front and back liner, 2 coat Kynar finish Exterior, smooth flat. Is this correct?
A085.7: Correct, except the thickness is 2” (R-14).
Q085.8 I am not sure what FWP 4 is.
A085.8: FWP4 basis of design is Centria Versawall Vertical Insulated Metal Panel, R-20, G90 Galvanized Steel, 22 gage face and 22 gage liner, 2 coat Kynar finish, embossed planked.
Q086: The specification 328424 has reference to irrigation, but there are no drawings indicating what gets irrigated. Does the entire site have an irrigations system?
A086: As indicated in Section 32 05 33, the temporary irrigation system described in Section 328424 is only required for the one year irrigation establishment period.
Q087: Drawings HA101 and LA101 have reference to Pink Granite. We cannot seem to find a distributor for this material. During the design, who did the AE contact at the local level for this and can you provide a name and phone number.
A087: 24. Hardscape material has been changed to a product that should be more readily available locally. Refer to attached revised drawings HA101, HA102 and LA101 for more information.
Q088: The landscape bed re quire Cyprus mulch. We cannot seem to find a distributor for this material. During the design, who did the AE contact at the local level for this and can you provide a name and phone number.
A088: Mulch has been changed to a produce that should be more readily available locally. Refer to attached revised Sheet LA103 for more information.
Q089: On Access Control door 100B, 007A, who terminates wall mount actuators by others?
These devices would normally be integrated with the access control system. Define parameters of operation. Will a valid card read activate the push button to actuate the door?
A089: The wall mounted actuators along with all other components associated with the automated door operators are to be provided and installed by the contractor. The contractor shall make all terminations required for a fully operational system. The design intent is to inhibit the operation of the automatic door operator while the door is locked. Once the door is unlocked, pressing the wall mounted actuator shall cause the door to automatically open.
Q090: Is Remote Activation Switch noted in Door Set #19 Reception/Security room 157 by Access Control?
A090: There shall be a set of remote activation switches located in Reception/Security 157, Director’s Reception/Waiting 133, and Tech Supply 120. These switches shall be located within easy reach of the person seated at each work station. The remote activation switch(es) in Tech Supply 120 shall be capable of “buzzing in” someone at Vestibule 119 and the west vehicle gate (keynote 23 on ES101). The remote activation switch(es) in Reception/Security 157 shall be capable of “buzzing in” someone at Vestibule 100 and the west vehicle gate. The remote activation switch(es) in Director’s Reception/Waiting 133 shall be capable of “buzzing in” someone at Vestibule 100, Vestibule 119, or the west vehicle gate. Please note that detail 1 on ET508 applies to both the east and west vehicle gates. The automatic controls for the east gate are associated with bid option 9. The east vehicle gate is not to be part of the remote “buzz in” process from Reception/Security 157, Director’s Reception/Waiting 133, or Tech Supply 120. The remote activation switches shall only unlock on door or vehicle gate. The remote activation switches shall be considered part of the access controls system and shall be contractor furnished and installed. The contractor shall confirm the final location of each remote activation switch with the contracting officer’s representative.
Q091: Door Set #33 – Note: Cards for Access Control Card Readers shall operate Stand-Alone Trim. How is this to be achieved without a card reader present?
A091: 28. The cards for the card reader system mentioned in Set Nos. 18-30 and 36-38 shall also operate the stand-alone trim in Set No. 33. The stand-alone trim is itself the card reader.
Q092: Door Set #27 – Section 08-71-00 reference a Card Reader by Access Control but not shown in typical #2Typical Exit Door Only. Please clarify if this door receives a card reader.
A092: 29. The doors indicated to have Set No. 27 shall have card readers.
Q093: Door Set #28 – Hardware includes an Electric Strike which does not provide a request to exit signal upon leaving the space. Should a request to exit motion be included for a complete door system?
A093: 30. We have revised hardware set to add monitoring feature to electric strike to provide request to exit capability. Electric strike will monitor latch bolt to shunt alarm.
Reference attached revised Specification Section 08 71 00 for more information.
Q094: Section 2.4.17.1 ACS Software shall support responses to alarms entering the system.
a. Please define the MFG/Product of CCTV system for interface compatibility.
b. Please define DVR event recording to include DVR Model and events.
c. Please define floor-plan graphical map file types to be provided.
d. Please define the number of networked PC workstations that would be concurrently connected to the ACS software.
A094: The government intends to issue its response to this question in a forthcoming amendment.
Q095.1 I see where a Safety Cover valve box is required at each tank and that the valve box is to house the tank valves and electric water heater. However no dimensions are specified. What would be the required dimensions of the " valve box"?
Drawing #C-512 shows the tank details. The drawing shows copper heat recirc. piping and PVC pump test return piping. NFPA-22 does not recognize anything but carbon steel piping. Can these items be provided as Schedule 40 carbon steel pipe?
Spec section 33 16 15, page 8, sub section 2.2.1.5 Balconies. Normally Balconies are only used on Elevated Water Towers to allow access around the perimeter of the tank 100' plus feet in the air and are not used for Ground mounted Water Tanks since there is access around the tank on the ground. Therefore, is a Balcony required?
A095.1a. Size of the enclosure should be determined by the tank manufacturer. Tank manufacturer shall size heated enclosure as necessary to house equipment and as necessary for clearances in Specification Section 33 16 15.
A095.1b. Steel pipe is allowed, but not preferred. Any steel pipe used must have appropriate corrosion protection measures.
A095.1c. A balcony is not required but is allowed. If a balcony is used by the tank manufacturer, it must conform to the requirements of paragraph 2.2.1.5.
Q095.2 Please provide a spec for the 1" thick R-5 rigid board insulation under the hangar slabs.
All we can find in the specs is for the R-10 insulation for block but not for the slab. Need to know what PSI it needs to be.
A095.2. Rigid insulation under the hangar slabs needs to be 100 psi compressive strength. Basis of design is Owens Corning Foamular 1000 Extruded Polystyrene (XPS) Rigid Foam Insulation, 1 1/2" thick, R-value of 7.8.
Q096 :Key Note 10 on Drawing A-103 specifies a mesh lid, but Key note #17 does not. Please confirm that the wire mesh partition indicated by Key Note 17 between Column lines 2 and 3 does not receive a mesh lid.
A096: The wire mesh partition indicated by Sheet Keynote 17 on drawing A-103 does not require a mesh lid.
Q097: Standard Form 1442 block 13.D requires the contractor and its subcontractors and suppliers to hold their bid for 120 days after the bid submission date. In this volatile economy and the unstable commodities market this is extremely hard to do and to predict where the pricing may go. Please consider 60 days for the Government to make their selection for the contractor on this project.
A097: At this instance the government has heard from only one entity regarding this issue and for this reason it is not inclined at this time to alter this requirement.
Q098: The State of New Jersey along with the New Jersey DOT both have acknowledged that any project in NJ is subject to the asphalt and fuel price index. Please concur that this project too is subject to the asphalt and fuel price index.
A098: The US Army Corps of Engineer neither collects nor interprets state tax codes and law; it is the responsibility of each individual Offer and his subcontractors to determine his or her tax liabilities.
Q099: Ms George we are receipt of Amendment 0001 and do not see answers to the below questions which have been sent by a potential teaming partner we are working with as well as our attached e-mail from 5/14 . Speaking with a number of other small businesses interested in this project who also sent in similar questions. Please explain why the ACOE has not responded to those questions.
a. Can an Offeror working with a Major Teaming Partner subcontractor, with a executed signed Teaming Agreement submit the qualifications of their Teaming Partner to satisfy the requirements of Factor 1 CONTRACTOR PAST RELEVANT EXPERIENCE?
b. Factor 1, paragraph 3.1.1 states that the Offeror must submit at least two (2) projects but no more than four (4) that are both at least 50,000 square feet and with a $25 million contract value. We feel that requiring a small business to submit projects of this magnitude seriously limits the number of contractors capable of submitting acceptable qualifications.
Would the USACOE consider projects that meet some but not all qualifications?
c. Can you please provide some clarification in terms of what past performance criteria can be submitted for the teaming partner subcontractors? Factor 2 mentions, “past client’s input regarding their firm’s and/or that of any past Team Association or sub-contractor’s past performance.” but there is no mention of this under Factor 1 therefore we are unsure what is allowable. We have projects that meet the required criteria but if they cannot be considered as acceptable under Factor 1 Contractor Past Performance Experience / Factor 2 Contractor Past Performance we may be unable to submit a proposal with a teaming partner.
A099:
a. Large/Small business JVs except for “Mentor-Protégé Agreements, approved by the
SBA” will not be allowed to submit a proposal as a qualified bidder.
b. The Offeror (s) submitting on this solicitation is expected to meet all the criteria as stated in this solicitation and any amendments.
c. This question has been sufficiently answered between this and previous amendments.
Q100: On the Sheet Keynotes for Drawings ET402, ET502 and ET503, there’s requirement that states the intrusion detection system wiring, equipment and control panels shall be GFGI.
Question: Does this mean that the Government will come directly to Advantor for the intrusion detection system?
A100: The contractor is not responsible for providing or installing the intrusion detection system (IDS) wiring or control equipment. The IDS wiring and control equipment will be provided and installed by others. The exact make and model of control equipment is to be determined by government
Q101:
Reference Section 00800, Special Contract Requirements – Paragraph 42 ENVIRONMENTAL
RESPONSIBILITY (10-8-99)
Discussion Paragraph 42 states:
The Contractor shall immediately take all appropriate actions to minimize the consequences of any and all environmental incidents resulting from actions taken to execute this contract.
Environmental incidents, include, but are not limited to, spillage of oil and other HAZMAT; solid and/or hazardous waste removal, handling and disposal; lead and/or asbestos abatement, removal, handling and disposal; and spillage or release of any other pollutants. Appropriate actions include, but are not limited to, notification, evacuation, control, containment, cleanup, removal, disposal and remediation as conducted in accordance with all applicable Federal, State, and local laws and regulations at NO ADDITIONAL COST TO THE GOVERNMENT.
Question Please advise how the contractor is to price this contract requirement in a fixed price contract when no lead, asbestos, or other hazardous materials are indicated in the contract documents.
A101: This requirement simply stated places the responsibility on the contractor for his actions under the contract. If for example, the contractor is removing asbestos as part of his work or simply refueling his vehicles and there is a spill, the contractor is responsible for cleaning or otherwise removing the spilled materials.
ATTENDANCE LIST CERDEC FLIGHT ACTIVITY FACILITY
SITE VISIT on 22 MAY 2013
NAME
COMPANY NAME
Yan Girlya
Sambe Const. Co.
1650 Hylton RD., Pennsauken, NJ 08110
James A. Moench
Geothermal Services, Inc., PO Box 427, 5435 Harding Hwy., Mays Landing, NJ 08330
Robert W. Shimko
Local Union 400 I.B.E.W.
Francis J. Marmer
American Crane and Equip Corp.
531 Old Swede Rd Douglassville, PA 19518
Jim Wright
C. Pyramid Enterprises, Inc.
115 North Gold Dr.
Robbinsville, NJ 08691
Eric VanCleaf
C. Pyramid Enterprises
Phil Schroeder
Wayne Norman
Barbara Stella Lange
Stella Contracting, Inc.
586 RT 40, PO Box 902, Elmer, NJ 08318
Darin M. Zohn
Sodon’s Electric, Inc.
25 West Highlands Ave., Atlantic Hightlands, NJ 07716
Barry Rogers
Rogers-Cipollono Electric, Inc.
499 S. White Horse Pike, Atco, NJ 08004
Russ Hinkel
Rogers-Cipollono Electric, Inc.
Tom Viviano
Lippincott Jacobs Consulting Engineers
Shyamal Shah
Intercontinental Const., Contracting, Inc.
180 Lexington Ave., Fl. 2 Passaic, NJ 07055
Bernard J. Mazza
Holophane Lighting 627 Chapel Rd.
Cinnaminson, NJ 08077
David M. Pires
Fitzpatrick & Associates 1115 Pine Brook Rd.
Tinton Falls, NJ 07724
Bruce D. Shaw
Garton’s Rigging 3436 N. Mill Rd.
Vineland, NJ 08360
F. Dwayne Yates
Wyndham Const., LLC & Engineering, Inc.
188 Fries Mill Road Suite M-1 Turnersville, NJ 08012
Frederick J. Shapiro
Boro Construction 400 Feheley Drive King of Prussia, PA 19406
Andrew P. Harper
A & L Trucking Co., Inc.
PO Box 356, New Egypt, NJ 08533
Gary J. Riebel, Sr.
Haines & Kibblehouse, Inc., NJ Division 204 Harding Ave.
Bellmawr, NJ 08031
Carolyn Woodruff Fair Lite Electric 360 White Horse Pike Atco, NJ 08004
Scott Shisler American Industrial 11 Enterprise Court Sewell, NJ 08080
Colin Shaughnessy Jackson Geothermal and B&S Sheetmetal 608 Nolan Ave Morrisville, PA 19067
Michael Bruce Patriot Elevator 12 North Ave W Suite 3R Cranford, NJ 07016
Daniel R. Tranchina
Scalfo Electric, Inc.
3539 N. Mill Rd.
Leon Steven Pflaster
Arnold Steel Co., Inc.
79 Randolph Rd.
Howell, NJ 07731
David D’Onofrio
Stanker & Galetto, Inc.
317 W. Elmer Rd.
Sean F. Manning
BRADY-Fluor LLC 131 Matthews Station St. Suite 2C Matthews, NC 28105
Andrew Bedwell
The Bedwell Co.
13802 Wilmington Pike West Chester, PA 19382
Samantha Twining Saunders
Wu and Associates, Inc.
597 Deer Road Cherry Hill, NJ 08034
(End of Summary of Changes)