This is a Questions and Answers document for a federal construction contract opportunity covering Fort Bliss and surrounding areas in Texas and New Mexico.

The contract is an IDIQ (Indefinite Delivery/Indefinite Quantity) vehicle covering construction and maintenance services at Fort Bliss main cantonment area, William Beaumont Army Medical Center, Biggs Army Airfield, East Bliss, Logan Heights areas in El Paso County Texas, McGregor Range in New Mexico, Dona Ana Camp in New Mexico, and various ranges in Dona Ana and Otero counties, New Mexico. Key scope clarifications include: fill material does not include compaction (paid separately); the Government will not provide fill and base-course materials; the contractor must furnish all materials; civil demolition includes loading, hauling, dumping, and disposal but excludes surface restoration; ADA ramps are paid by concrete volume (CY); electrical scope is limited to bid schedule items only; underground electrical work (trenching, backfill, concrete encasement, pavement restoration) is paid separately via IDIQ line items; and all travel, mobilization, and subsistence costs must be fully burdened into the unit prices with no separate travel line item. Hazardous materials testing and abatement will be issued as non-priced line items when needed. A Stormwater Pollution Prevention Plan (SWPPP) is required only when construction and staging areas exceed one acre. Temporary fencing is not universally required unless specified in individual task orders, with placement prioritized near schools and high pedestrian traffic areas. For New Mexico work, contractors may select either applicable wage determination during bid preparation; however, task orders will use the appropriate wage determination for the specific region where work is performed. An on-site office is not required, and prior RFPs will not be issued for hazardous materials situations.

View the file

Other files

File Type Posted
W911SG27BA002 Full Abstract of Offers.pdf PDF
Solicitation Amendment W911SG27BA0020003 SF 30.pdf PDF
Solicitation Amendment - W911SG27BA0020003.pdf PDF
Solicitation Amendment W911SG27BA0020002 SF 30.pdf PDF
W911SG27BA002 Instructions to Bidders 3 September 2026.pdf PDF
W911SG27BA002 Solicitation RFI Questions and Answers.pdf PDF
Bid Schedule_PAVE_FE 10011 0J_Paving IDIQ.xlsx XLSX spreadsheet
Solicitation Amendment - W911SG27BA0020002.pdf PDF
W911SG27BA002 Instructions to Bidders (Revised).pdf PDF
Bid Schedule_PAVE_FE 10011 0J_PavingNM.pdf PDF
Solicitation Amendment - W911SG27BA002 0001.pdf PDF
Solicitation Amendment W911SG27BA002 0001 SF 30.pdf PDF
Bid Schedule_PAVE_FE 10011 0J_PavingTX.pdf PDF
W911SG27BA002 Statement of Work (2).pdf PDF
Attachment N - UFGS 32 01 16.71 Cold Milling Asphalt Paving.pdf PDF
Attachment N - UFGS 32 01 16.75 Heater Scarifying of Asphalt Paving.pdf PDF
Attachment N - UFGS 32 84 23 Underground Sprinkler Systems.pdf PDF
Attachment N - UFGS 32 17 23 Pavement Markings.pdf PDF
Attachment H - Fire Prevention Construction Guide 2025.pdf PDF
Attachment N - UFGS 32 01 13.62 Asphalt Surface Treatment.pdf PDF
Attachment L - NMDOT Spec.pdf PDF
W911SG27BA002 Statement of Work.pdf PDF
Attachment N - UFGS 26 00 00 Electrical.pdf PDF
W911SG27BA002 Instructions to Bidders.pdf PDF
Attachment N - UFGS 32 11 20 Base Course.pdf PDF
Attachment F - DPW-RFI Template Blank Form.pdf PDF
Attachment N - UFGS 03 45 33 Precast Structural Concrete.pdf PDF
Attachment K - Site Clearance and Line Marking Permit.pdf PDF
Attachment A - The Army Radiation Permit ARP.pdf PDF
Attachment D - Contractor Requirements Document.pdf PDF
GSA Categories of Labor.pdf PDF
Attachment N - UFGS 32 13 13.06 Portland Cement Concrete Pavement for Roads.pdf PDF
Attachment N - UFGS 32 11 33.13 Cement Stabilized Soil (1).pdf PDF
Attachment N - UFGS 32 01 11.51 Rubber and Paint Removal -Airfield.pdf PDF
Attachment N - UFGS 32 93 00 Exterior Improvements Plants (1).pdf PDF
Attachment N - UFGS 31 00 00 Earthwork.pdf PDF
Wage Determination TX20260293 (El Paso Highway).pdf PDF
Attachment N - UFGS 32 01 17.61 Sealing Cracks in Asphalt Paving.pdf PDF
Attachment L - TXDOT Spec.pdf PDF
Attachment N - UFGS 03 30 00 Cast-in-Place Concrete.pdf PDF
Attachment N - UFGS 05 52 00 Metal Railings.pdf PDF
Attachment N - UFGS 32 12 13 Bituminous Tack and Prime Coats.pdf PDF
Attachment N - UFGS 32 12 16 Hot-Mix Asphalt HMA for Roads.pdf PDF
Attachment N - UFGS 02 41 00 Demolition.pdf PDF
Attachment N - UFGS 34 71 13.16 Vehicle Crash Barriers.pdf PDF
Wage Determination NM20260036 (Multiple NM Highway).pdf PDF
eCRAFT Professional Categories List.pdf PDF
Attachment G - DPW SUBMITTAL FORM V.1.pdf PDF
Attachment C - Construction and Demolition Sample Report.pdf PDF
Attachment N - UFGS 32 31 13 Chain Link Fences and gates.pdf PDF
Show 40 more

Latest 50 of 62 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS:

1. Does fill material include compaction, or will compaction be paid separately?

Correct. Fill material does not include compaction,

2. Will the Government provide fill and base-course materials, or must the contractor furnish them?

Government will not provide fill and base-course materials.

3. Does civil demolition include excavation, backfill, compaction, and surface restoration?

I don’t know exactly which line items you are referring to but I’m assuming it might be one of the following ones:

Demo-Reinf concrete pavement, incld loading, hauling, dumping, disposal

Demo-asphalt pavement, up to 3" thick, incld loading, hauling, dumping,& disposal

These line items include the loading, hauling, dumping, & disposal of material and it doesn’t include any surface restoration.

4. Are ADA ramps paid by concrete volume or as complete installations?

The ADA ramps are paid by concrete volume (CY)

5. Is the electrical scope limited to the Bid Schedule items or does it include the complete electrical specification?

The electrical scope is limited to the Bid Schedule items.

6. For underground electrical work, will trenching, backfill, concrete encasement, and pavement restoration be paid separately?

Yes, it will be paid separately by using the IDIQ Line items.

7. Is travel expected to be lump summed into the IDIQ price?

Yes. Travel costs will not be paid as a separate, standalone line item. The contractor must fully burden and incorporate all anticipated travel, mobilization, and subsistence costs directly into the contract unit prices for the established line items.

8. What bases or areas would we be working at specifically in Texas and New Mexico?

In the Narrative you can find the following paragraph:

Performance: For the purposes of the RSCA, the performance area will be Fort Bliss main cantonment area, William Beaumont Army Medical Center areas, Biggs Army Airfield areas, East Bliss, Logan Heights areas in El Paso County Texas, McGregor Range N.M., Dona Ana Camp N.M., and various ranges located in Dona Ana and Otero counties, New Mexico.

9. In paragraph 4.11 in the SOW states the contractor is to test and abate with approval any Hazardous Materials, there is line for this task in the bid schedule’s. Would an RFP be established when these situations arise?

No, but if we need to test and abate that will be a non-priced line item.

10. Is it required for the contractor to have an office at the locations?

No, it’s not required.

11. Will a SWPPP be required for each task as they are assigned?

SWPPP will not be required for each of the task orders. It will apply if the construction area and staging is bigger than 1 acre.

12. Is it required for the contractor to have temporary fencing around each job site?

No, it is not required to place temporary fence in all projects, unless stated in the task order. The majority of the fences will be placed in areas close to school or high pedestrian traffic.

13. In paragraph 4.78.7.d in the SOW states 8” thick, f’c=4,000 PSI and in the bid schedule there is no line stating 8” thick concrete. Please confirm the contractor is to bid per the verbiage in the bid schedules.

Please follow the bid schedule

14. For the New Mexico Bid Package how would you like to receive the New Mexico Bid being that there are two Wage Determinations for the different locations? There is one bid schedule and the solicitation has one section for each year for the New Mexico proposals and two wage determinations. Please clarify.

The contractor may choose which Wage Determination they use for the New Mexico Bid. It is up to the Contractor’s discretion which Wage Determination they use for building their bid as the Government cannot influence this decision. When a task order is issued, it will use the appropriate Wage Determination for the region in which work is done.