This is a specification section for earthwork construction work (Section 31 00 00) establishing technical requirements and procedures for excavation, fill, backfill, and grading operations.
The specification defines measurement procedures for excavation and borrow materials computed by average end area method in cubic yards, with separate provisions for piping trench excavation measured in linear feet and select granular material measured as actual cubic yards in place. Material requirements include offsite soils that must be free of Total Petroleum Hydrocarbons (TPH) exceeding 100 ppm and Benzene/Toluene/Ethyl Benzene/Xylene (BTEX) exceeding 10 ppm, with testing performed per EPA methods. Buried utility warning tape must be polyethylene plastic with metallic core or foil backing, color-coded by utility type, minimum 3 inches width, buried 12 inches below finished grade or 6 inches below subgrade under pavements. Detection wire for non-metallic piping must be 12 AWG solid copper insulated wire. Pipe casing must conform to ASTM A139/A139M Grade B or ASTM A252 Grade 2 specifications. Execution requirements address general excavation procedures, trench specifications with width and depth constraints based on pipe size, dewatering and drainage controls maintaining water levels 3 feet below working elevation, and shoring requirements for excavations exceeding 4.5 feet height, with a Shoring and Sheeting plan required 15 days prior to work commencement. Backfill and compaction requirements vary by material type and application: 90 percent maximum density for cohesive materials and 95 percent for cohesionless materials in most applications, with moisture content maintained at -2 to +2 percent of optimum. Testing requirements mandate minimum testing frequencies including one test per 500 cubic yards for material gradation, one test per 5,000 square feet for in-place densities, and field density determination per ASTM D6938 with calibration checks using ASTM D1556/D1556M sand cone method.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 31 00 00 Page 1
SECTION TABLE OF CONTENTS DIVISION 31 - EARTHWORK SECTION 31 00 00 EARTHWORK
08/08
Table of Contents
PART 1 GENERAL
1.1 MEASUREMENT PROCEDURES
1.2 REFERENCES
1.3 DEFINITIONS
1.4 SUBMITTALS
PART 2 PRODUCTS
2.1 REQUIREMENTS FOR OFFSITE SOILS
2.2 BURIED WARNING AND IDENTIFICATION TAPE
2.3 DETECTION WIRE FOR NON-METALLIC PIPING
2.4 MATERIAL FOR RIP-RAP
2.5 PIPE CASING
PART 3 EXECUTION
3.1 GENERAL EXCAVATION
3.2 SELECTION OF BORROW MATERIAL
3.3 OPENING AND DRAINAGE OF EXCAVATION AND BORROW PITS
3.4 SHORING
3.5 FINAL GRADE OF SURFACES TO SUPPORT CONCRETE
3.6 GROUND SURFACE PREPARATION
3.7 UTILIZATION OF EXCAVATED MATERIALS
3.8 BURIED TAPE AND DETECTION WIRE
3.9 BACKFILLING AND COMPACTION
3.10 SPECIAL REQUIREMENTS
3.11 EMBANKMENTS
3.12 SUBGRADE PREPARATION
3.13 SHOULDER CONSTRUCTION
3.14 FINISHING
3.15 TESTING
3.16 DISPOSITION OF SURPLUS MATERIAL
SECTION 31 00 00 Page 2
PART 1 GENERAL.
1.1 MEASUREMENT PROCEDURES.
1.1.1 Excavation
The unit of measurement for excavation and borrow will be the cubic meter yard, computed by the average end area method from cross sections taken before and after the excavation and borrow operations, including the excavation for ditches, gutters, and channel changes, when the material is acceptably utilized or disposed of as herein specified. The measurements will include authorized excavation of rock (except for piping trenches that is covered below), authorized excavation of unsatisfactory subgrade soil, and the volume of loose, scattered rocks and boulders collected within the limits of the work; allowance will be made on the same basis for selected backfill ordered as replacement. The measurement will not include the volume of subgrade material or other material that is scarified or plowed and reused in-place, and will not include the volume excavated without authorization or the volume of any material used for purposes other than directed. The volume of overburden stripped from borrow pits and the volume of excavation for ditches to drain borrow pits, unless used as borrow material, will not be measured for payment. The measurement will not include the volume of any excavation performed prior to the taking of elevations and measurements of the undisturbed grade.
1.1.2 Piping Trench Excavation
Measure trench excavation by the number of linear feet along the centerline of the trench and excavate to the depths and widths specified for the particular size of pipe. Replace unstable trench bottoms with a selected granular material. Include the additional width at manholes and similar structures, the furnishing, placing and removal of sheeting and bracing, pumping and bailing, and all incidentals necessary to complete the work required by this section.
1.1.3 Select Granular Material
Measure select granular material in place as the actual cubic yards replacing wet or unstable material in trench bottoms within the limits shown. Provide unit prices which include furnishing and placing the granular material, excavation and disposal of unsatisfactory material, and additional requirements for sheeting and bracing, pumping, bailing, cleaning, and other incidentals necessary to complete the work.
1.2 REFERENCES.
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO)
AASHTO T 180 (2017) Standard Method of Test for
Moisture-Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and a 457-mm
(18-in.) Drop
SECTION 31 00 00 Page 3
AASHTO T 224 (2010) Standard Method of Test for
Correction for Coarse Particles in the
Soil Compaction Test
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA C600 (2017) Installation of Ductile-Iron Mains and Their Appurtenances
AMERICAN WELDING SOCIETY (AWS)
AWS D1.1/D1.1M (2020) Structural Welding Code - Steel
AMERICAN WOOD PROTECTION ASSOCIATION (AWPA)
AWPA P5 (2015) Standard for Waterborne
Preservatives
ASTM INTERNATIONAL (ASTM)
ASTM A139/A139M (2016) Standard Specification for
Electric-Fusion (ARC)-Welded Steel Pipe
(NPS 4 and over)
ASTM A252 (2010) Standard Specification for Welded and Seamless Steel Pipe Piles
ASTM C33/C33M (2018) Standard Specification for Concrete
Aggregates
ASTM C136/C136M (2019) Standard Test Method for Sieve
Analysis of Fine and Coarse Aggregates
ASTM D698 (2012; E 2014; E 2015) Laboratory
Compaction Characteristics of Soil Using
Standard Effort (12,400 ft-lbf/cu. ft.
(600 kN-m/cu. m.))
ASTM D1140 (2017) Standard Test Methods for
Determining the Amount of Material Finer than 75-µm (No. 200) Sieve in Soils by
Washing
ASTM D1556/D1556M (2015; E 2016) Standard Test Method for
Density and Unit Weight of Soil in Place by Sand-Cone Method
ASTM D1557 (2012; E 2015) Standard Test Methods for
Laboratory Compaction Characteristics of
Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3)
ASTM D1883 (2016) Standard Test Method for California
Bearing Ratio (CBR) of
Laboratory-Compacted Soils
ASTM D2167 (2015) Density and Unit Weight of Soil in
Place by the Rubber Balloon Method
ASTM D2434 (1968; R 2006) Permeability of Granular
SECTION 31 00 00 Page 4
Soils (Constant Head)
ASTM D2487 (2017; E 2020) Standard Practice for
Classification of Soils for Engineering
Purposes (Unified Soil Classification
System)
ASTM D2937 (2017; E 2017; E 2018) Standard Test
Method for Density of Soil in Place by the
Drive-Cylinder Method
ASTM D4318 (2017; E 2018) Standard Test Methods for
Liquid Limit, Plastic Limit, and
Plasticity Index of Soils
ASTM D6938 (2017a) Standard Test Method for In-Place
Density and Water Content of Soil and
Soil-Aggregate by Nuclear Methods (Shallow
Depth)
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements
Manual
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA 600/4-79/020 (1983) Methods for Chemical Analysis of
Water and Wastes
EPA SW-846.3-3 (1999, Third Edition, Update III-A) Test
Methods for Evaluating Solid Waste:
Physical/Chemical Methods
U.S. GENERAL SERVICES ADMINISTRATION (GSA)
CID A-A-203 (Rev C; Notice 3) Paper, Kraft, Untreated
1.3 DEFINITIONS.
1.3.1 Satisfactory Materials
Satisfactory Materials. Satisfactory materials comprise any materials classified by ASTM D2487 as GW, GP, GM, GP-GM, GW-GM, GC, GP-GC, GM-
GC, SW, SP, SM, SW-SM, SC, SW-SC, SP-SM, SP-SC, and CL. Satisfactory materials for grading comprise stones less than 8 inches, except for fill material for pavements which comprise stones less than 3 inches in any dimension.
1.3.2 Unsatisfactory Materials
Materials which do not comply with the requirements for satisfactory materials are unsatisfactory. Unsatisfactory materials also include man-made fills; trash; refuse; backfills from previous construction; and material classified as satisfactory which contains root and other organic matter or frozen material. Notify the Contracting Officer when
SECTION 31 00 00 Page 5 encountering any contaminated materials.
1.3.3 Cohesionless and Cohesive Materials
Cohesionless materials include materials classified in ASTM D2487 as GW, GP, SW, and SP. Cohesive materials include materials classified as GC, SC, ML, CL, MH, and CH. Materials classified as GM and SM will be identified as cohesionless only when the fines are nonplastic. Perform testing, required for classifying materials, in accordance with ASTM D4318, ASTM C136/C136M and ASTM D1140.
1.3.4 Degree of Compaction
Degree of compaction required, except as noted in the second sentence, is expressed as a percentage of the maximum density obtained by the test procedure presented in ASTM D1557 abbreviated as a percent of laboratory maximum density. Since ASTM D1557 applies only to soils that have 30 percent or less by weight of their particles retained on the 3/4 inch sieve, express the degree of compaction for material having more than
30 percent by weight of their particles retained on the 3/4 inch sieve as a percentage of the maximum density in accordance with
AASHTO T 180 and corrected with AASHTO T 224. To maintain the same percentage of coarse material, use the "remove and replace" procedure as described in NOTE 8 of Paragraph 7.2 in AASHTO T 180.
1.3.5 Topsoil
Material suitable for topsoils obtained from offsite areas or areas indicated on the drawings is defined as: Natural, friable soil representative of productive, well-drained soils in the area, free of subsoil, stumps, rocks larger than 25 mm one inch diameter, brush, weeds, toxic substances, and other material detrimental to plant growth. Amend topsoil pH range to obtain a pH of 5.5 to 7.
1.3.6 Hard/Unyielding Materials
Hard/Unyielding materials comprise weathered rock, dense consolidated deposits, or conglomerate materials which are not included in the definition of "rock" with stones greater than 3 inch in any dimension or as defined by the pipe manufacturer, whichever is smaller. These materials usually require the use of heavy excavation equipment, ripper teeth, or jack hammers for removal.
1.3.7 Rock
Solid homogeneous interlocking crystalline material with firmly cemented, laminated, or foliated masses or conglomerate deposits, neither of which can be removed without systematic drilling and blasting, drilling and the use of expansion jacks or feather wedges, or the use of backhoe-mounted pneumatic hole punchers or rock breakers; also large boulders, buried masonry, or concrete other than pavement exceeding 1/2 cubic yard in volume. Removal of hard material will not be considered rock excavation because of intermittent drilling and blasting that is performed merely to increase production.
1.3.8 Unstable Material
Unstable materials are too wet to properly support the utility pipe, conduit, or appurtenant structure.
1.3.9 Select Granular Material
SECTION 31 00 00 Page 6
1.3.9.1 General Requirements
General Requirements. Select granular material consist of materials classified as SM, SC, or SP-SM by ASTM D2487 where indicated. The liquid limit of such material must not exceed 35 percent when tested in accordance with ASTM D4318. The plasticity index must not be greater than 20 percent when tested in accordance with ASTM D4318, and not more than 50 percent by weight may be finer than No. 200 sieve when tested in accordance with
ASTM D1140. Provide a minimum coefficient of permeability of 0.002 feet per minute when tested in accordance with ASTM D2434.
1.3.10 Initial Backfill Material
Initial Backfill Material. Initial backfill consists of select granular material or satisfactory materials free from rocks or free from rocks of such size as recommended by the pipe manufacturer.
1.4 SUBMITTALS.
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the government officer that will review the submittal for the Government.
SD-01 Preconstruction Submittals
Shoring; G (If required)
Dewatering Work Plan; G (If required)
SD-03 Product Data
Utilization of Excavated Materials; G
Shoulder Construction
SD-06 Test Reports
Testing
SD-07 Certificates
Testing
PART 2 PRODUCTS.
2.1 REQUIREMENTS FOR OFFSITE SOILS.
offsite soils brought in for use as backfill shall be free of Total
Petroleum Hydrocarbons (TPH), Benzene, Toluene, Ethyl Benzene, and
Xylene (BTEX) and full Toxicity Characteristic Leaching Procedure
(TCLP) including ignitability, corrosivity and reactivity. Backfill shall contain a maximum of 100 parts per million (ppm) of total petroleum hydrocarbons (TPH) and a maximum of 10 ppm of the sum of
Benzene, Toluene, Ethyl Benzene, and Xylene (BTEX) and shall pass the
TCPL test. Determine TPH concentrations by using EPA 600/4-79/020
SECTION 31 00 00 Page 7
Method 418.1. Determine BTEX concentrations by using EPA SW-846.3-3
Method 5030/8020. Perform TCLP in accordance with EPA SW-846.3-3 Method
1311.
2.2 BURIED WARNING AND IDENTIFICATION TAPE.
Provide polyethylene plastic and metallic core or metallic-faced, acid-and alkali-resistant, polyethylene plastic warning tape manufactured specifically for warning and identification of buried utility lines.
Provide tape on rolls, 75 mm 3 inches minimum width, color coded as specified below for the intended utility with warning and identification imprinted in bold black letters continuously over the entire tape length. Warning and identification to read, "CAUTION, BURIED (intended service) LINE BELOW" or similar wording. Provide permanent color and printing, unaffected by moisture or soil.
Warning Tape Color Codes
Red Electric
Yellow Gas, Oil; Dangerous Materials
Orange Telephone and Other Communications
Blue Water Systems
Green Sewer Systems
White Steam Systems
Gray Compressed Air
2.2.1 Warning Tape for Metallic Piping
Provide acid and alkali-resistant polyethylene plastic tape conforming to the width, color, and printing requirements specified above, with a minimum thickness of 0.003 inch and a minimum strength of 1500 psi lengthwise, and 1250 psi crosswise, with a maximum 350 percent elongation.
2.2.2 Detectable Warning Tape for Non-Metallic Piping
Provide polyethylene plastic tape conforming to the width, color, and printing requirements specified above, with a minimum thickness of 0.004 inch, and a minimum strength of 1500 psi lengthwise and 1250 psi crosswise. Manufacture tape with integral wires, foil backing, or other means of enabling detection by a metal detector when tape is buried up to
3 feet deep. Encase metallic element of the tape in a protective jacket or provide with other means of corrosion protection.
2.3 DETECTION WIRE FOR NON-METALLIC PIPING.
Insulate a single strand, solid copper detection wire with a minimum of 12
AWG.
2.4 MATERIAL FOR RIP-RAP.
Provide Bedding material,grout, filter fabric, and rock conforming to
Department of Transportation State Standards for construction if indicated in the drawings.
SECTION 31 00 00 Page 8
2.4.1 Bedding Material
Provide bedding material consisting of sand, gravel, or crushed rock, well graded, or poorly graded with a maximum particle size of 2 inches. Compose material of tough, durable particles. Allow fines passing the No. 200 standard sieve with a plasticity index less than six.
2.4.2 Grout
Provide durable grout composed of cement, water, an air-entraining admixture, and sand mixed in proportions of one part portland cement to two parts of sand, sufficient water to produce a workable mixture, and an amount of admixture which will entrain sufficient air, as determined by the
Contracting Officer. Mix grout in a concrete mixer. Allow a sufficient mixing time to produce a mixture having a consistency permitting gravity flow into the interstices of the rip-rap with limited spading and brooming.Rock
Provide rock fragments sufficiently durable to ensure permanence in the structure and the environment in which it is to be used. Use rock fragments free from cracks, seams, and other defects that would increase the risk of deterioration from natural causes. Provide fragments sized so that no individual fragment exceeds a weight of 150 pounds and that no more than 10 percent of the mixture, by weight, consists of fragments weighing 2 pounds or less each. Provide rock with a minimum specific gravity of 2.50. Do not permit the inclusion of more than clay, and rock fines.
2.5 PIPE CASING.
2.5.1 Casing Pipe
ASTM A139/A139M, Grade B, or ASTM A252, Grade 2, smooth wall pipe. Match casing size to the outside diameter and wall thickness as indicated on drawings. Protective coating is not required on casing pipe.
PART 3 EXECUTION
PART 3 EXECUTION.
3.1 GENERAL EXCAVATION.
Perform excavation of every type of material encountered within the limits of the project to the lines, grades, and elevations indicated and as specified. Perform the grading in accordance with the typical sections shown and the tolerances specified in paragraph FINISHING. Transport satisfactory excavated materials and place in fill or embankment within the limits of the work. Excavate unsatisfactory materials encountered within the limits of the work below grade and replace with satisfactory materials as directed. Include such excavated material and the satisfactory material ordered as replacement in excavation. Dispose surplus satisfactory excavated material not required for fill or embankment in areas approved for surplus material storage or designated waste areas. Dispose unsatisfactory excavated material in designated waste or spoil areas. During construction, perform excavation and fill in a manner and sequence that will provide proper drainage at all times.
Excavate material required for fill or embankment in excess of that
SECTION 31 00 00 Page 9 produced by excavation within the grading limits from the borrow areas indicated or from other approved areas selected by the Contractor as specified.
3.1.1 Ditches, Gutters, and Channel Changes
Finish excavation of ditches, gutters, and channel changes by cutting accurately to the cross sections, grades, and elevations shown on Drawings.
Do not excavate ditches and gutters below grades shown. Backfill the excessive open ditch or gutter excavation with satisfactory, thoroughly compacted, material or with suitable stone or cobble to grades shown.
Dispose excavated material as shown or as directed, except in no case allow material be deposited a maximum 4 feet from edge of a ditch. Maintain excavations free from detrimental quantities of leaves, brush, sticks, trash, and other debris until final acceptance of the work.
3.1.2 Drainage Structures
Make excavations to the lines, grades, and elevations shown, or as directed.
Provide trenches and foundation pits of sufficient size to permit the placement and removal of forms for the full length and width of structure footings and foundations as shown. Clean rock or other hard foundation material of loose debris and cut to a firm, level, stepped, or serrated surface. Remove loose disintegrated rock and thin strata. Do not disturb the bottom of the excavation when concrete or masonry is to be placed in an excavated area. Do not excavate to the final grade level until just before the concrete or masonry is to be placed. Where pile foundations are to be used, stop the excavation of each pit at an elevation 1 foot above the base of the footing, as specified, before piles are driven. After the pile driving has been completed, remove loose and displaced material and complete excavation, leaving a smooth, solid, undisturbed surface to receive the concrete or masonry.
3.1.3 Drainage
Provide for the collection and disposal of surface and subsurface water encountered during construction. Completely drain construction site during periods of construction to keep soil materials sufficiently dry. Construct storm drainage features (ponds/basins) at the earliest stages of site development, and throughout construction grade the construction area to provide positive surface water runoff away from the construction activity or provide temporary ditches, swales, and other drainage features and equipment as required to maintain dry soils. When unsuitable working platforms for equipment operation and unsuitable soil support for subsequent construction features develop, remove unsuitable material and provide new soil material as specified herein. It is the responsibility of the Contractor to assess the soil and ground water conditions presented by the plans and specifications and to employ necessary measures to permit construction to proceed.
3.1.4 Dewatering
Control groundwater flowing toward or into excavations to prevent sloughing of excavation slopes and walls, boils, uplift and heave in the excavation and to eliminate interference with orderly progress of construction. Do not permit French drains, sumps, ditches or trenches within 3 feet of the foundation of any structure, except with specific written approval, and after specific contractual provisions for restoration of the foundation area have been made. Take control measures by the time the excavation reaches the
SECTION 31 00 00 Page 10 water level in order to maintain the integrity of the in situ material.
While the excavation is open, maintain the water level continuously, at least 3 feet below the working level. Operate dewatering system continuously until construction work below existing water levels is complete. Submit performance records weekly. Measure and record performance of dewatering system at same time each day by use of observation wells or piezometers installed in conjunction with the dewatering system. Relieve hydrostatic head in previous zones below subgrade elevation in layered soils to prevent uplift.
3.1.5 Trench Excavation Requirements
Excavate the trench as recommended by the manufacturer of the pipe to be installed. Slope trench walls below the top of the pipe, or make vertical, and of such width as recommended in the manufacturer's printed installation manual. Provide vertical trench walls where no manufacturer's printed installation manual is available. Shore trench walls more than 4.5 feet high, cut back to a stable slope, or provide with equivalent means of protection for employees who may be exposed to moving ground or cave in.
Shore vertical trench walls more than 5 feet high. Excavate trench walls which are cut back to at least the angle of repose of the soil. Give special attention to slopes which may be adversely affected by weather or moisture content. Do not exceed the trench width below the pipe top of 24 inches plus pipe outside diameter (O.D.) for pipes of less than 24 inches inside diameter, and do not exceed 36 inches plus pipe outside diameter for sizes larger than 24 inches inside diameter. Where recommended trench widths are exceeded, provide redesign, stronger pipe, or special installation procedures by the Contractor. The Contractor is responsible for the cost of redesign, stronger pipe, or special installation procedures without any additional cost to the Government.
3.1.5.1 Removal of Unyielding Material
Where overdepth is not indicated and unyielding material is encountered in the bottom of the trench, remove such material 6 inch below the required grade and replaced with suitable materials as provided in paragraph
BACKFILLING AND COMPACTION.
3.1.5.2 Excavation for Appurtenances
Provide excavation for manholes, catch-basins, inlets, or similar structures sufficient to leave at least 12 inches clear between the outer structure surfaces and the face of the excavation or support members.
Clean rock or loose debris and cut to a firm surface either level, stepped, or serrated, as shown or as directed. Remove loose disintegrated rock and thin strata. Specify removal of unstable material. When concrete or masonry is to be placed in an excavated area, take special care not to disturb the bottom of the excavation. Do not excavate to the final grad grade level until just before the concrete or masonry is to be placed.
3.1.5.3 Jacking, Boring, and Tunneling
Unless otherwise indicated, provide excavation by open cut except that sections of a trench may be jacked, bored, or tunneled if, in the opinion of the Contracting Officer, the pipe, cable, or duct can be safely and properly installed and backfill can be properly compacted in such sections.
3.1.6 Underground Utilities
SECTION 31 00 00 Page 11
The Contractor is responsible for movement of construction machinery and equipment over pipes and utilities during construction. Perform work adjacent to non-Government utilities as indicated in accordance with procedures outlined by utility company. Excavation made with power-driven equipment is not permitted within 5 feet of known Government-owned utility or subsurface construction. For work immediately adjacent to or for excavations exposing a utility or other buried obstruction, excavate by hand. Start hand excavation on each side of the indicated obstruction and continue until the obstruction is uncovered or until clearance for the new grade is assured. Support uncovered lines or other existing work affected by the contract excavation until approval for backfill is granted by the
Contracting Officer. Report damage to utility lines or subsurface construction immediately to the Contracting Officer.
3.1.7 Structural Excavation
Ensure that footing subgrades have been inspected and approved by the
Contracting Officer prior to concrete placement. Excavate to bottom of pile cap prior to placing or driving piles, unless authorized otherwise by the
Contracting Officer. Backfill and compact over excavations and changes in grade due to pile driving operations to 95 percent of ASTM D698 maximum density.
3.2 SELECTION OF BORROW MATERIAL.
Select borrow material to meet the requirements and conditions of the particular fill or embankment for which it is to be used. Obtain borrow material from the borrow areas shown on Drawings. Unless otherwise provided in the contract, the Contractor is responsible for obtaining the right to procure material, pay royalties and other charges involved, and bear the expense of developing the sources, including rights-of-way for hauling from the owners. Borrow material from approved sources on Government-controlled land may be obtained without payment of royalties. Unless specifically provided, do not obtain borrow within the limits of the project site without prior written approval. Consider necessary clearing, grubbing, and satisfactory drainage of borrow pits and the disposal of debris thereon related operations to the borrow excavation.
3.3 OPENING AND DRAINAGE OF EXCAVATION AND BORROW PITS.
Notify the Contracting Officer sufficiently in advance of the opening of any excavation or borrow pit or borrow areas to permit elevations and measurements of the undisturbed ground surface to be taken. Except as otherwise permitted, excavate borrow pits and other excavation areas providing adequate drainage. Transport overburden and other spoil material to designated spoil areas or otherwise dispose of as directed.
Provide neatly trimmed and drained borrow pits after the excavation is completed. Ensure that excavation of any area, operation of borrow pits, or dumping of spoil material results in minimum detrimental effects on natural environmental conditions.
3.4 SHORING.
3.4.1 General Requirements
Submit a Shoring and Sheeting plan for approval 15 days prior to starting work. Submit drawings and calculations, certified by a registered professional engineer, describing the methods for shoring and sheeting of
SECTION 31 00 00 Page 12 excavations. Finish shoring, including sheet piling, and install as necessary to protect workmen, banks, adjacent paving, structures, and utilities. Remove shoring, bracing, and sheeting as excavations are backfilled, in a manner to prevent caving.
3.5 FINAL GRADE OF SURFACES TO SUPPORT CONCRETE.
Do not excavate to final grade until just before concrete is to be placed. Only use excavation methods that will leave the foundation rock in a solid and unshattered condition. Roughen the level surfaces, and cut the sloped surfaces, as indicated, into rough steps or benches to provide a satisfactory bond. Protect shales from slaking and all surfaces from erosion resulting from ponding or water flow.
3.6 GROUND SURFACE PREPARATION.
3.6.1 General Requirements
Remove and replace unsatisfactory material with satisfactory materials, as directed by the Contracting Officer, in surfaces to receive fill or in excavated areas. Scarify the surface to a depth of 6 inches before the fill is started. Plow, step, bench, or break up sloped surfaces steeper than 1 vertical to 4 horizontal so that the fill material will bond with the existing material. When subgrades are less than the specified density, break up the ground surface to a minimum depth of 6 inches, pulverizing, and compacting to the specified density. When the subgrade is part fill and part excavation or natural ground, scarify the excavated or natural ground portion to a depth of 12 inches and compact it as specified for the adjacent fill.
3.6.2 Frozen Material
Do not place material on surfaces that are muddy, frozen, or contain frost. Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, or other approved equipment well suited to the soil being compacted. Moisten material as necessary to plus or minus 2 percent of optimum moisture.
3.7 UTILIZATION OF EXCAVATED MATERIALS.
Dispose unsatisfactory materials removing from excavations into designated waste disposal or spoil areas. Use satisfactory material removed from excavations, insofar as practicable, in the construction of fills, embankments, subgrades, shoulders, bedding (as backfill), and for similar purposes. Submit procedure and location for disposal of unused satisfactory material. Submit proposed source of borrow material. Do not waste any satisfactory excavated material without specific written authorization. Dispose of satisfactory material, authorized to be wasted, in designated areas approved for surplus material storage or designated waste areas as directed. Clear and grub newly designated waste areas on
Government-controlled land before disposal of waste material thereon.
Stockpile and use coarse rock from excavations for constructing slopes or embankments adjacent to streams, or sides and bottoms of channels and for protecting against erosion. Do not dispose excavated material to obstruct the flow of any stream, endanger a partly finished structure, impair the efficiency or appearance of any structure, or be detrimental to the completed work in any way.
3.8 BURIED TAPE AND DETECTION WIRE.
3.8.1 Buried Warning and Identification Tape
SECTION 31 00 00 Page 13
Provide buried utility lines with utility identification tape. Bury tape
12 inches below finished grade; under pavements and slabs, bury tape
6 inches below top of subgrade.
3.8.2 Buried Detection Wire
Bury detection wire directly above non-metallic piping at a distance not to exceed 12 inches above the top of pipe. Extend the wire continuously and unbroken, from manhole to manhole. Terminate the ends of the wire inside the manholes at each end of the pipe, with a minimum of 3 feet of wire, coiled, remaining accessible in each manhole. Furnish insulated wire over its entire length. Install wires at manholes between the top of the corbel and the frame, and extend up through the chimney seal between the frame and the chimney seal. For force mains, terminate the wire in the valve pit at the pump station end of the pipe.
3.9 BACKFILLING AND COMPACTION.
Place backfill adjacent to any and all types of structures, in successive horizontal layers of loose materia not more than 8 inches in depth.
Compact to at least 90 percent laboratory maximum density for cohesive materials or 95 percent laboratory maximum density for cohesionless materials, to prevent wedging action or eccentric loading upon or against the structure. Backfill material must be within the range of -2 to +2 percent of optimum moisture content at the time of compaction.
Prepare ground surface on which backfill is to be placed and provide compaction requirements for backfill materials in conformance with the applicable portions of paragraphs GROUND SURFACE PREPARATION. Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment.
3.9.1 Trench Backfill
Backfill trenches to the grade shown.
3.9.1.1 Replacement of Unyielding Material
Replace unyielding material removed from the bottom of the trench with select granular material or initial backfill material.
3.9.1.2 Replacement of Unstable Material
Replace unstable material removed from the bottom of the trench or excavation with select granular material placed in layers not exceeding
6 inches loose thickness.
3.9.1.3 Bedding and Initial Backfill
Bedding and Initial Backfill. Place initial backfill material and compact it with approved tampers to a height of at least one foot above the utility pipe or conduit. Bring up the backfill evenly on both sides of the pipe for the full length of the pipe. Take care to ensure thorough compaction of the fill under the haunches of the pipe. Except as specified otherwise in the individual piping section, provide bedding for buried piping in accordance with AWWA C600, Type 4, except as specified herein. Compact backfill to top of pipe to 95 percent of ASTM D698 maximum density. Provide plastic piping with bedding to spring line of pipe. Provide materials as follows:
SECTION 31 00 00 Page 14
3.9.1.3.1 Class I
Angular, 0.25 to 1.5 inch, graded stone, including a number of fill materials that have regional significance such as coral, slag, cinders, crushed stone, and crushed shells.
3.9.1.3.2 Class II
Coarse sands and gravels with maximum particle size of 1.5 inch, including various graded sands and gravels containing small percentages of fines, generally granular and noncohesive, either wet or dry. Soil Types
GW, GP, SW, and SP are included in this class as specified in ASTM D2487.
3.9.1.3.3 Sand
Clean, coarse-grained sand.
3.9.1.3.4 Gravel and Crushed Stone
Gravel and Crushed Stone - Clean, coarsely graded natural gravel, crushed stone or a combination thereof in accordance with Section Excavation and
Fill 31 23 00.00 20, gradation to standards of the state Department of
Transportation or having a classification of GW/GP in accordance with ASTM
D2487 for bedding and backfill as indicated. Do not exceed maximum particle size of 2 inches.
3.9.1.4 Final Backfill
Fill the remainder of the trench, except for special materials for roadways, railroads and airfields, with satisfactory material. Place backfill material and compact as follows:
3.9.1.4.1 Roadways, Railroads, and Airfields
Place backfill up to the required elevation as specified. Do not permit water flooding or jetting methods of compaction.
3.9.1.4.2 Sidewalks, Turfed or Seeded Areas and Miscellaneous Areas
Sidewalks, Turfed or Seeded Areas and Miscellaneous Areas. Deposit backfill in layers of a maximum of 12 inches loose thickness, and compact it to 85 percent maximum density for cohesive soils and 90 percent maximum density for cohesionless soils. Apply this requirement to all other areas not specifically designated above.
3.9.2 Backfill for Appurtenances
After the manhole, catchbasin, inlet, or similar structure has been constructed and the concrete has been allowed to cure for 7 days, place backfill in such a manner that the structure is not be damaged by the shock of falling earth. Deposit the backfill material, compact it as specified for final backfill, and bring up the backfill evenly on all sides of the structure to prevent eccentric loading and excessive stress.
3.10 SPECIAL REQUIREMENTS.
3.10.1 Pipeline Casing
Provide new smooth wall steel pipeline casing under existing railroad and pavement in a trench by the boring and jacking method of installation.
Provide each new pipeline casing, where indicated and to the lengths and dimensions shown, complete and suitable for use with the new piped utility
SECTION 31 00 00 Page 15 as indicated. Install pipeline casing by dry boring and jacking method as follows:
3.10.1.1 Bore Holes
Mechanically bore holes and case through the soil with a cutting head on a continuous auger mounted inside the casing pipe. Weld lengths of pipe together in accordance with AWS D1.1/D1.1M. Do not use water or other fluids in connection with the boring operation.
3.10.1.2 Cleaning
Clean inside of the pipeline casing of dirt, weld splatters, and other foreign matter which would interfere with insertion of the piped utilities by attaching a pipe cleaning plug to the boring rig and passing it through the pipe.
3.10.1.3 End Seals
After installation of piped utilities in pipeline casing, provide watertight end seals at each end of pipeline casing between pipeline casing and piping utilities. Provide watertight segmented elastomeric end seals.
3.10.2 Rip-Rap Construction
Construct rip-rap in accordance with DOT in the areas indicated. Trim and dress indicated areas to conform to cross sections, lines and grades shown within a tolerance of 0.1 foot.
3.10.2.1 Bedding Placement
Spread filter fabric bedding material uniformly to a thickness of at least 3 inches on prepared subgrade as indicated. Compaction of bedding is not required. Finish bedding to present even surface free from mounds and windrows.
3.10.2.2 Stone Placement
Place rock for rip-rap on prepared bedding material to produce a well graded mass with the minimum practicable percentage of voids in conformance with lines and grades indicated. Distribute larger rock fragments, with dimensions extending the full depth of the rip-rap throughout the entire mass and eliminate "pockets" of small rock fragments. Rearrange individual pieces by mechanical equipment or by hand as necessary to obtain the distribution of fragment sizes specified above. For grouted rip-rap, hand-place surface rock with open joints to facilitate grouting and do not fill smaller spaces between surface rock with finer material. Provide at least one "weep hole" through grouted rip-rap for every 50 square feet of finished surface. Provide weep holes with columns of bedding material, 4 inches in diameter, extending up to the rip-rap surface without grout.
3.10.2.3 Grouting
Prior to grouting, wet rip-rap surfaces. Grout rip-rap in successive longitudinal strips, approximately 10 feet in width, commencing at the lowest strip and working up the slope. Distribute grout to place of final deposit and work into place between stones with brooms, spades, trowels, or vibrating equipment. Take precautions to prevent grout from penetrating bedding layer. Protect and cure surface for a minimum of 7
SECTION 31 00 00 Page 16 days.
3.11 EMBANKMENTS.
3.11.1 Earth Embankments
Construct earth embankments from satisfactory materials free of organic or frozen material and rocks with any dimension greater than 3 inches. Place the material in successive horizontal layers of loose material not more than 8 inches in depth. Spread each layer uniformly on a soil surface that has been moistened or aerated as necessary, and scarified or otherwise broken up so that the fill will bond with the surface on which it is placed. After spreading, plow, disk, or otherwise break up each layer;
moisten or aerate as necessary; thoroughly mix; and compact to at least 90 percent laboratory maximum density for cohesive materials or 95 percent laboratory maximum density for cohesionless materials. Backfill material must be within the range of -2 to +2 percent of optimum moisture content at the time of compaction.
Compaction requirements for the upper portion of earth embankments forming subgrade for pavements are identical with those requirements specified in paragraph SUBGRADE PREPARATION. Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment.
3.12 SUBGRADE PREPARATION.
3.12.1 Construction
Shape subgrade to line, grade, and cross section, and compact as specified.
Include plowing, disking, and any moistening or aerating required to obtain specified compaction for this operation. Remove soft or otherwise unsatisfactory material and replace with satisfactory excavated material or other approved material as directed. Excavate rock encountered in the cut section to a depth of 6 inches below finished grade for the subgrade. Bring up low areas resulting from removal of unsatisfactory material or excavation of rock to required grade with satisfactory materials, and shape the entire subgrade to line, grade, and cross section and compact as specified. After rolling, the surface of the subgrade for airfields shall not show deviations greater than 1/2 inch when tested with a 12-foot straightedge applied both parallel and at right angles to the centerline of the area. Do not vary the elevation of the finish subgrade the established grade and cross section.
3.12.2 Compaction
Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment. Except for paved areas, compact each layer of the embankment to at least 90 percent of laboratory maximum density.
3.12.2.1 Subgrade for Railroads
Compact subgrade for railroads to at least 90 percent laboratory maximum density for cohesive materials or 95 percent laboratory maximum density for cohesionless materials.
SECTION 31 00 00 Page 17
3.12.2.2 Subgrade for Pavements
Compact top 6-inches of subgrade to 95 percent ASTM D1557; compact fill and backfill material to 95 percent ASTM D1557. All moisture contents shall be
-2 to +2 percent of optimum moisture content.
3.12.2.3 Subgrade for Shoulders
3.12.2.4 Subgrade for Airfield Pavements
3.13 SHOULDER CONSTRUCTION.
Construct shoulders of satisfactory excavated material or as otherwise shown or specified. Construct shoulders immediately after adjacent paving is complete. In the case of rigid pavements, do not construct shoulders until permission of the Contracting Officer has been obtained. Compact the entire shoulder area to at least the percentage of maximum density as specified in paragraph SUBGRADE PREPARATION above, for specific ranges of depth below the surface of the shoulder. Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment. Finish shoulder construction in proper sequence in such a manner that adjacent ditches will be drained effectively and that no damage of any kind is done to the adjacent completed pavement. Align the completed shoulders true to grade and shaped to drain in conformity with the cross section shown.
3.14 FINISHING.
Finish the surface of excavations, embankments, and subgrades to a smooth and compact surface in accordance with the lines, grades, and cross sections or elevations shown. Provide the degree of finish for graded areas within 0.1 foot of the grades and elevations indicated except that the degree of finish for subgrades specified in paragraph SUBGRADE
PREPARATION. Finish gutters and ditches in a manner that will result in effective drainage. Finish the surface of areas to be turfed from settlement or washing to a smoothness suitable for the application of turfing materials. Repair graded, topsoiled, or backfilled areas prior to acceptance of the work, and re-established grades to the required elevations and slopes.
3.14.1 Subgrade and Embankments
During construction, keep embankments and excavations shaped and drained.
Maintain ditches and drains along subgrade to drain effectively at all times. Do not disturb the finished subgrade by traffic or other operation. Protect and maintain the finished subgrade in a satisfactory condition until ballast, subbase, base, or pavement is placed. Do not permit the storage or stockpiling of materials on the finished subgrade.
Do not lay subbase, base course, ballast, or pavement until the subgrade has been checked and approved, and in no case place subbase, base, surfacing, pavement, or ballast on a muddy, spongy, or frozen subgrade.
SECTION 31 00 00 Page 18
3.15 TESTING.
Testing. Perform testing by a certified commercial testing laboratory or the Contractor's validated testing facility. Submit qualifications to the
COR and if the Contractor elects to establish testing facilities, do not permit work requiring testing until the Contractor's facilities have been inspected and approved by the Contracting Officer.
a. Determine field in-place density in accordance with ASTM D6938. When ASTM D6938 is used, check the calibration curves and adjust using only the sand cone method as described in ASTM D1556/D1556M. ASTM D6938 results in a wet unit weight of soil in determining the moisture content of the soil when using this method.
b. Check the calibration curves furnished with the moisture gauges along with density calibration checks as described in ASTM D6938; check the calibration of both the density and moisture gauges at the beginning of a job on each different type of material encountered and at intervals as directed by the Contracting Officer. When test results indicate, as determined by the Contracting Officer, that compaction is not as specified, remove the material, replace and recompact to meet specification requirements.
c. Perform tests on recompacted areas to determine conformance with specification requirements. Appoint a registered professional civil engineer to certify inspections and test results. These certifications shall state that the tests and observations were performed by or under the direct supervision of the engineer and that the results are representative of the materials or conditions being certified by the tests. The following number of tests, if performed at the appropriate time, will be the minimum acceptable for each type operation.
3.15.1 Fill and Backfill Material Gradation
One test per 500 cubic yards stockpiled or in-place source material. Determine gradation of fill and backfill material in accordance with ASTM D1140.
3.15.2 In-Place Densities
a. One test per 5000 square feet, or fraction thereof, of each lift of fill or backfill areas compacted by other than hand-operated machines. COR must be notified 24 hrs prior to testing.
b. One test per 5000 square feet, or fraction thereof, of each lift of fill or backfill areas compacted by hand-operated machines. OR must be notified 24 hrs prior to testing.
c. One test per 150 linear feet, or fraction thereof, of each lift of embankment or backfill for roads. COR must be notified 24 hrs prior to testing.
d. One test per 1000 linear feet, or fraction thereof, of each lift of embankment or backfill for railroads. COR must be notified 24 hrs prior to testing.
3.15.3 Moisture Contents
In the stockpile, excavation, or borrow areas, perform a minimum of two tests per day per type of material or source of material being placed during stable weather conditions. During unstable weather, perform tests as dictated by local conditions and approved by the Contracting Officer.
SECTION 31 00 00 Page 19
3.15.4 Optimum Moisture and Laboratory Maximum Density
Perform tests for each type material or source of material to determine the optimum moisture and laboratory maximum density values. One representative test per 500 cubic yards of fill and backfill, each 5,000 square feet of compacted subgrade for paved areas or when any change in material occurs which may affect the optimum moisture content or laboratory maximum density.
3.15.5 Tolerance Tests for Subgrades
Perform continuous checks on the degree of finish specified in paragraph
SUBGRADE PREPARATION during construction of the subgrades.
3.15.6 Displacement of Sewers
After other required tests have been performed and the trench backfill compacted to 2 feet above the top of the pipe, inspect the pipe to determine whether significant displacement has occurred. Conduct this inspection in the presence of the Contracting Officer. Inspect pipe sizes larger than 36 inches, while inspecting smaller diameter pipe by shining a light or laser between manholes or manhole locations, or by the use of television cameras passed through the pipe. If, in the judgment of the Contracting Officer, the interior of the pipe shows poor alignment or any other defects that would cause improper functioning of the system, replace or repair the defects as directed at no additional cost to the Government.
3.16 DISPOSITION OF SURPLUS MATERIAL.
Remove surplus material or other soil material not required or suitable for filling or backfilling, and brush, refuse, stumps, roots, and timber from
Government property to an approved location.
-- End of Section --