This is a Section 02 41 00 Demolition specification document for federal construction contracting, dated 05/10, that establishes requirements for demolition and deconstruction work on government facilities.

The specification mandates that contractors prepare and submit a detailed Demolition Plan for approval by the Contracting Officer before work begins, including procedures for salvage, demolition, removal, utility disconnection, and sequencing. Work must comply with EM 385-1-1 (U.S. Army Corps of Engineers Safety and Health Requirements Manual), ASSP A10.6 (Safety & Health Program Requirements for Demolition Operations), 40 CFR 61 (National Emission Standards for Hazardous Air Pollutants), and FAA AC 70/7460-1 (Obstruction Marking and Lighting). Contractors must remove rubbish and debris daily, maximize salvage and recycling value, protect remaining structures and utilities, maintain airfield pavements free of foreign object debris (FOD), and provide protective measures including traffic control signage and temporary obstruction lighting for structures exceeding 100 feet. The specification covers specific removal procedures for structures, utilities, chain link fencing, paving, masonry, concrete, structural steel, miscellaneous metals, and airfield lighting, with requirements for saw cutting, patching, and restoration of damaged surfaces. Materials become contractor property upon Contracting Officer approval of demolition procedures, except for items designated for salvage or reuse. Disposal must comply with federal, state, and local regulations specified in a Waste Management Plan, and burning of materials on government property is prohibited.

View the file

Other files

File Type Posted
W911SG27BA002 Full Abstract of Offers.pdf PDF
Solicitation Amendment W911SG27BA0020003 SF 30.pdf PDF
W911SG27BA002 Second List of RFI Questions and Answers.pdf PDF
Solicitation Amendment W911SG27BA0020002 SF 30.pdf PDF
W911SG27BA002 Instructions to Bidders 3 September 2026.pdf PDF
Solicitation Amendment - W911SG27BA0020002.pdf PDF
Solicitation Amendment W911SG27BA002 0001 SF 30.pdf PDF
W911SG27BA002 Instructions to Bidders (Revised).pdf PDF
Solicitation Amendment - W911SG27BA002 0001.pdf PDF
Bid Schedule_PAVE_FE 10011 0J_PavingNM.pdf PDF
Bid Schedule_PAVE_FE 10011 0J_PavingTX.pdf PDF
W911SG27BA002 Statement of Work (2).pdf PDF
GSA Categories of Labor.pdf PDF
Attachment A - The Army Radiation Permit ARP.pdf PDF
Attachment D - Contractor Requirements Document.pdf PDF
Attachment K - Site Clearance and Line Marking Permit.pdf PDF
Attachment L - NMDOT Spec.pdf PDF
Attachment L - TXDOT Spec.pdf PDF
Attachment N - UFGS 03 30 00 Cast-in-Place Concrete.pdf PDF
Attachment N - UFGS 05 52 00 Metal Railings.pdf PDF
Attachment N - UFGS 31 11 00 Clearing and Grubbing.pdf PDF
Attachment N - UFGS 32 17 23 Pavement Markings.pdf PDF
Wage Determination TX20260293 (El Paso Highway).pdf PDF
Attachment C - Construction and Demolition Sample Report.pdf PDF
Attachment F - DPW-RFI Template Blank Form.pdf PDF
Attachment H - Fire Prevention Construction Guide 2025.pdf PDF
Attachment N - UFGS 32 01 11.51 Rubber and Paint Removal -Airfield.pdf PDF
Attachment N - UFGS 32 01 16.71 Cold Milling Asphalt Paving.pdf PDF
Attachment N - UFGS 32 01 16.75 Heater Scarifying of Asphalt Paving.pdf PDF
Attachment N - UFGS 32 01 17.61 Sealing Cracks in Asphalt Paving.pdf PDF
Attachment N - UFGS 32 12 13 Bituminous Tack and Prime Coats.pdf PDF
Attachment N - UFGS 32 12 16 Hot-Mix Asphalt HMA for Roads.pdf PDF
Attachment N - UFGS 32 84 23 Underground Sprinkler Systems.pdf PDF
Attachment N - UFGS 32 93 00 Exterior Improvements Plants (1).pdf PDF
Attachment N - UFGS 34 71 13.16 Vehicle Crash Barriers.pdf PDF
Solicitation - W911SG27BA002.pdf PDF
W911SG27BA002 Statement of Work.pdf PDF
Wage Determination NM20260035 (Dona Ana and San Juan Highway).pdf PDF
Attachment B - As-built Requirements.pdf PDF
Attachment E - DD1354 Form.pdf PDF
Attachment I - iWATCH Training for Contractors.pdf PDF
Attachment J - SF 1413 Statement and Acknowledgement for Subcontractors.pdf PDF
Attachment N - UFGS 10 14 53 Traffic Signage.pdf PDF
Attachment N - UFGS 32 01 13.62 Asphalt Surface Treatment.pdf PDF
Attachment N - UFGS 32 01 19.61 Sealing Cracks in Asphalt Paving.pdf PDF
Attachment N - UFGS 32 12 15.13 Asphalt Paving for Airfields.pdf PDF
Attachment N - UFGS 32 16 19 Concrete Curbs Gutters and Sidewalks.pdf PDF
Attachment N - UFGS 33 40 00 Storm Drainage Utilities.pdf PDF
W911SG27BA002 Instructions to Bidders.pdf PDF
eCRAFT Professional Categories List.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 02 41 00 Page 2

SECTION TABLE OF CONTENTS DIVISION 02 - EXISTING CONDITIONS SECTION 02 41 00

DEMOLITION

05/10

Table of Contents

PART 1 GENERAL

1.1 REFERENCES

1.2 PROJECT DESCRIPTION

1.2.1 Definitions

1.2.3 General Requirements

1.4 BURNING

1.5 SUBMITTALS

1.6 QUALITY ASSURANCE

1.7 PROTECTION

1.8 FOREIGN OBJECT DAMAGE (FOD)

1.9 RELOCATIONS

1.10 EXISTING CONDITIONS

PART 2 PRODUCTS

2.1 FILL MATERIAL

PART 3 EXECUTION

3.1 EXISTING FACILITIES TO BE REMOVED

3.2 CONCURRENT EARTH-MOVING OPERATIONS

3.3 DISPOSITION OF MATERIAL

3.4 CLEANUP

3.5 DISPOSAL OF REMOVED MATERIALS

SECTION 02 41 00 Page 3

PART 1 GENERAL.

1.1 REFERENCES.

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AIR-CONDITIONING, HEATING AND REFRIGERATION INSTITUTE (AHRI)

AHRI Guideline K (2009) Guideline for Containers for Recovered

Non-Flammable Fluorocarbon Refrigerants

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS

(AASHTO)

AASHTO M 145 (1991; R 2012) Standard Specification for

Classification of Soils and Soil-Aggregate

Mixtures for Highway Construction Purposes

AASHTO T 180 (2017) Standard Method of Test for Moisture-

Density Relations of Soils Using a 4.54-kg

(10-lb) Rammer and a 457-mm

(18-in.) Drop

AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)

ASSP A10.6 (2006) Safety & Health Program Requirements for Demolition Operations - American National

Standard for Construction and Demolition

Operations

CARPET AND RUG INSTITUTE (CRI)

CRI 104 (2015) Carpet Installation Standard for

Comnmercial Carpet

CRI 105 (2015) Carpet Installation Standard for

Residential Carpet

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

U.S. DEFENSE LOGISTICS AGENCY (DLA)

DLA 4145.25 (Jun 2000; Reaffirmed Oct 2010) Storage and

Handling of Liquefied and Gaseous Compressed

Gases and Their Full and Empty Cylinders http://www.aviation.dla.mil/UserWeb/aviatione ngineeri

U.S. DEPARTMENT OF DEFENSE (DOD)

DOD 4000.25-1-M (2006) MILSTRIP - Military Standard http://www.aviation.dla.mil/UserWeb/aviationengineeri http://www.aviation.dla.mil/UserWeb/aviationengineeri

SECTION 02 41 00 Page 4

Requisitioning and Issue Procedures

MIL-STD-129 (2014; Rev R; Change 1 2018; Change 2

2019) Military Marking for Shipment and

Storage

U.S. FEDERAL AVIATION ADMINISTRATION (FAA)

FAA AC 70/7460-1 (2015; Rev L) Obstruction Marking and

Lighting

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

40 CFR 61 National Emission Standards for Hazardous Air

Pollutants

40 CFR 82 Protection of Stratospheric Ozone

49 CFR 173.301 Shipment of Compressed Gases in Cylinders and

Spherical Pressure Vessels

1.2 PROJECT DESCRIPTION.

1.2.1 Definitions.

1.2.1.1 Demolition

Demolition is the process of wrecking or taking out any load-supporting structural member of a facility together with any related handling and disposal operations.

1.2.1.2 Deconstruction

Deconstruction is the process of taking apart a facility with the primary goal of preserving the value of all useful building materials.

1.2.1.3 Demolition Plan

Demolition Plan is the planned steps and processes for managing demolition activities and identifying the required sequencing activities and disposal mechanisms.

1.2.1.4 Deconstruction Plan

Deconstruction Plan is the planned steps and processes for dismantling all or portions of a structure or assembly, to include managing sequencing activities, storage, re-installation activities, salvage and disposal mechanisms.

1.2.2 Demolition

Prepare a Demolition Plan and submit proposed salvage, demolition, and removal procedures for approval before work is started. Include in the plan procedures for careful removal and disposition of materials specified to be salvaged, coordination with other work in progress, a disconnection schedule of utility services, and airfield lighting, a detailed description of methods and equipment to be used for each operation and of the sequence of operations. Identify components and materials to be salvaged for reuse or recycling with reference to paragraph Existing Facilities to be Removed.

Append tracking forms for all removed materials indicating type, quantities, SECTION 02 41 00 Page 5 condition, destination, and end use. Provide procedures for safe conduct of the work in accordance with EM 385-1-1. Plan shall be approved by Contracting

Officer prior to work beginning.

1.2.3 General Requirements.

Do not begin demolition or deconstruction until authorization is received from the Contracting Officer. The work of this section is to be performed in a manner that maximizes the value derived from the salvage and recycling of materials. Remove rubbish and debris from the project site daily; do not allow accumulations on site or on airfield pavements. The work includes demolition, salvage of identified items and materials, and removal of resulting rubbish and debris. Remove rubbish and debris from Government property daily, unless otherwise directed. Store materials that cannot be removed daily in areas specified by the Contracting Officer. In the interest of occupational safety and health, perform the work in accordance with EM 385-1-1, Section 23, Demolition, and other applicable

Sections.

1.3 ITEMS TO REMAIN IN PLACE.

Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the Contracting Officer. Coordinate the work of this section with all other work indicated. Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Increase structural supports or add new supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract. Do not overload [structural elements] [pavements to remain]. Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the Contracting Officer prior to performing such work.

1.3.1 Existing Construction Limits and Protection

Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction. Provide temporary shoring and bracing for support of building components to prevent settlement or other movement.

Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove dust, dirt, and debris from work areas daily.

1.3.2 Weather Protection

For portions of the building to remain, protect building interior and materials and equipment from the weather at all times. Where removal of existing roofing is necessary to accomplish work, have materials and workmen ready to provide adequate and temporary covering of exposed areas.

1.3.3 Trees

Protect trees within the project site which might be damaged during demolition or deconstruction, and which are indicated to be left in place, by a 6 foot high fence. Erect and secure fence a minimum of 5 feet from the trunk of individual trees or follow the outer perimeter of branches or clumps of trees. Replace any tree designated to remain that is damaged during the work under this contract with like-kind or as approved by the Contracting

Officer.

1.3.4 Utility Service

SECTION 02 41 00 Page 6

Maintain existing utilities indicated to stay in service and protect against damage during demolition and deconstruction operations. Prior to start of work, the Government will disconnect and seal utilities serving each area of alteration or removal upon written request from the Contractor.

1.3.5 Facilities

Protect electrical and mechanical services and utilities. Where removal of existing utilities and pavement is specified or indicated, provide approved barricades, temporary covering of exposed areas, and temporary services or connections for electrical and mechanical utilities. Floors, roofs, walls, columns, pilasters, and other structural components that are designed and constructed to stand without lateral support or shoring, and are determined to be in stable condition, must remain standing without additional bracing, shoring, or lateral support until demolished or deconstructed, unless directed otherwise by the Contracting Officer. Ensure that no elements determined to be unstable are left unsupported and place and secure bracing, shoring, or lateral supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract.

1.4 BURNING.

The use of burning at the project site for the disposal of refuse and debris will not be permitted. Where burning is permitted, adhere to federal, state, and local regulations.

1.5 SUBMITTALS.

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the government officer that will review the submittal for the Government.

SD-01 Preconstruction Submittals

Demolition Plan; G, COR

Existing Conditions

Photographs

SD-07 Certificates

Notification; G, COR

Notification of Demolition

SD-11 Closeout Submittals

Receipts

1.6 QUALITY ASSURANCE.

Submit timely notification of demolition projects to Federal, State, regional, and local authorities in accordance with 40 CFR 61, Subpart M.

Notify the [Regional Office of the United States Environmental Protection

Agency (USEPA)] [State's environmental protection agency] [local air pollution control district/agency] and the Contracting Officer in writing 10 working days prior to the commencement of work in accordance with 40 CFR 61, Subpart M. Comply with federal, state, and local hauling and disposal regulations. In addition to the requirements of the "Contract Clauses," conform to the safety requirements contained in ASSP A10.6. Comply with the

Environmental Protection Agency requirements specified. Use of explosives

SECTION 02 41 00 Page 7 will not be permitted.

1.6.1 Dust and Debris Control

Prevent the spread of dust and debris to occupied portions of the project site and avoid the creation of a nuisance or hazard in the surrounding area.

Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution. Sweep airfield pavements as often as necessary to control the spread of FOD (foreign object debri) that may result in FOD damage potential to aircraft.

1.7 PROTECTION.

1.7.1 Traffic Control Signs

Where pedestrian and driver or aircraft safety is endangered in the area of removal work, use traffic barricades with flashing lights. If in airfield, Anchor barricades in a manner to prevent displacement by wind, jet or prop blast. If in airfield, barricades must be approved by airfield safety officer. Notify the Contracting Officer prior to beginning such work.

For airfield, provide a minimum of 2 FAA type L-810 steady burning red obstruction lights on temporary structures (including cranes) over 100 feet, but less than 200 ft, above ground level. The use of LED based obstruction lights are not permitted. For temporary structures (including cranes) over

200 ft above ground level provide obstruction lighting in accordance with FAA

AC 70/7460-1. Light construction and installation shall comply with FAA AC

70/7460-1. Lights shall be operational during periods of reduced visibility, darkness, and as directed by the Contracting Officer. Maintain the temporary services during the period of construction and remove only after permanent services have been installed and tested and are in operation.

1.7.2 Protection of Personnel

Before, during and after the demolition work continuously evaluate the condition of the structure being demolished and take immediate action to protect all personnel working in and around the project site. No area, section, or component of floors, roofs, walls, columns, pilasters, or other structural element will be allowed to be left standing without sufficient bracing, shoring, or lateral support to prevent collapse or failure while workmen remove debris or perform other work in the immediate area.

1.8 FOREIGN OBJECT DAMAGE (FOD).

Aircraft and aircraft engines are subject to FOD from debris and waste material lying on airfield pavements. Remove all such materials that may appear on operational aircraft pavements due to the Contractor's operations.

If necessary, the Contracting Officer may require the Contractor to install a temporary barricade at the Contractor's expense to control the spread of FOD potential debris. The barricade shall include a fence covered with a fabric designed to stop the spread of debris. Anchor the fence and fabric to prevent displacement by winds or jet/prop blasts. Remove barricade when no longer required.

1.9 RELOCATIONS.

Perform the removal and reinstallation of relocated items as indicated with workmen skilled in the trades involved. Repair or replace items to be relocated which are damaged by the Contractor with new undamaged items as

SECTION 02 41 00 Page 8 approved by the Contracting Officer.

1.10 EXISTING CONDITIONS.

Before beginning any demolition or deconstruction work, survey the site and examine the drawings and specifications to determine the extent of the work.

Record existing conditions in the presence of the Contracting Officer showing the condition of structures and other facilities adjacent to areas of alteration or removal. Digital Photographs sized 4 inch will be acceptable as a record of existing conditions. Include in the record the elevation of the top of foundation walls, finish floor elevations, possible conflicting electrical conduits, plumbing lines, alarms systems, the location and extent of existing cracks and other damage and description of surface conditions that exist prior to before starting work. It is the Contractor's responsibility to verify and document all required outages which will be required during the course of work, and to note these outages on the record document. Submit survey results.

PART 2 PRODUCTS.

2.1 FILL MATERIAL.

a. Comply with excavating, backfilling, and compacting procedures for soils used as backfill material to fill basements, voids, depressions or excavations resulting from demolition or deconstruction of structures.

b. Fill material shall conform to the definition of satisfactory soil material as defined in AASHTO M 145, Soil Classification Groups A-

1, A-2-4, A-2-5 and A-3. In addition, fill material shall be free from roots and other organic matter, trash, debris, frozen materials, and stones larger than 2 inches in any dimension.

c. Proposed fill material must be sampled and tested by an approved soil testing laboratory, as follows:

Soil classification AASHTO M 145

Moisture-density relations AASHTO T 180, Method B or D

PART 3 EXECUTION.

3.1 EXISTING FACILITIES TO BE REMOVED.

Inspect and evaluate existing structures onsite for reuse. Existing construction scheduled to be removed for reuse shall be disassembled.

Dismantled and removed materials are to be separated, set aside, and prepared as specified, and stored or delivered to a collection point for reuse, remanufacture, recycling, or other disposal, as specified.

Materials shall be designated for reuse onsite whenever possible.

3.1.1 Structures

a. Remove existing structures as indicated in drawings. Completely remove sidewalks, curbs, gutters and street light bases as indicated in drawings.

SECTION 02 41 00 Page 9

b. Demolish structures in a systematic manner from the top of the structure to the ground. Complete demolition work above each tier or floor before the supporting members on the lower level are disturbed. Demolish concrete and masonry walls in small sections. Remove structural framing members and lower to ground by means of derricks, platforms hoists, or other suitable methods as approved by the Contracting Officer.

c. Locate demolition and deconstruction equipment throughout the structure and remove materials so as to not impose excessive loads to supporting walls, floors, or framing.

d. Building, or the remaining portions thereof, not exceeding 80 feet in height may be demolished by the mechanical method of demolition

3.1.2 Utilities and Related Equipment

3.1.2.1 General Requirements

Do not interrupt existing utilities serving occupied or used facilities, except when authorized in writing by the Contracting Officer. Do not interrupt existing utilities serving facilities occupied and used by the

Government except when approved in writing and then only after temporary utility services have been approved and provided. Do not begin demolition or deconstruction work until all utility disconnections have been made.

Shut off and cap utilities for future use, as indicated.

3.1.2.2 Disconnecting Existing Utilities

Remove existing utilities, as indicated and terminate in a manner conforming to the nationally recognized code covering the specific utility and approved by the Contracting Officer. When utility lines are encountered but are not indicated on the drawings, notify the Contracting Officer prior to further work in that area. Remove meters and related equipment and deliver to a location in accordance with instructions of the Contracting Officer.

3.1.3 Chain Link Fencing

Remove chain link fencing, gates and other related salvaged items scheduled for removal and transport to designated areas. Remove gates as whole units. Cut chain link fabric to 25 foot lengths and store in rolls off the ground.

3.1.4 Paving and Slabs

Remove saw cut concrete and asphaltic concrete paving and slabs as indicated in drawings. Provide neat saw cuts at limits of pavement removal as indicated. Pavement and slabs designated to be recycled and utilized in this project shall be moved, ground and stored as directed by the Contracting

Officer. Pavement and slabs not to be used in this project shall be removed from the Installation at Contractor's expense.

3.1.5 Masonry

Saw cut and remove masonry so as to prevent damage to surfaces to remain.

Where new masonry adjoins existing, the new work shall abut or tie into the existing construction as indicated. Provide square, straight edges and corners where existing masonry adjoins new work and other locations.

SECTION 02 41 00 Page 10

3.1.6 Concrete

Saw concrete along straight lines to a depth of a minimum 3 inch. Make each cut in walls perpendicular to the face and in alignment with the cut in the opposite face. Break out the remainder of the concrete provided that the broken area is concealed in the finished work, and the remaining concrete is sound. At locations where the broken face cannot be concealed, grind smooth or saw cut entirely through the concrete.

3.1.7 Structural Steel

Dismantle structural steel at field connections and in a manner that will prevent bending or damage. Salvage for recycle structural steel, steel joists, girders, angles, plates, columns and shapes. Transport steel joists and girders as whole units and not dismantled. Transport structural steel shapes to a designated recycling facility, stacked according to size, type of member and length, and stored off the ground, protected from the weather.

3.1.8 Miscellaneous Metal

Salvage shop-fabricated items such as access doors and frames, steel gratings, metal ladders, wire mesh partitions, metal railings, metal windows and similar items as whole units. Salvage light-gage and cold-formed metal framing, such as steel studs, steel trusses, metal gutters, roofing and siding, metal toilet partitions, toilet accessories and similar items. [Scrap metal shall become the Contractor's property.]

Recycle scrap metal as part of demolition and deconstruction operations.

Provide separate containers to collect scrap metal and transport to a scrap metal collection or recycling facility, in accordance with the Waste

Management Plan.

3.1.9 Airfield Lighting

Remove existing airfield lighting as indicated and terminate in a manner satisfactory to the Contracting Officer and Safety Officer.

3.1.10 Patching

Where removals leave holes and damaged surfaces exposed in the finished work, patch and repair these holes and damaged surfaces to match adjacent finished surfaces, using on-site materials when available. Where new work is to be applied to existing surfaces, perform removals and patching in a manner to produce surfaces suitable for receiving new work. Finished surfaces of patched area shall be flush with the adjacent existing surface and shall match the existing adjacent surface as closely as possible as to texture and finish. Patching shall be as specified and indicated, and shall include:

a. Concrete and Masonry: Completely fill holes and depressions, [caused by previous physical damage or] left as a result of removals in existing masonry walls to remain, with an approved masonry patching material, applied in accordance with the manufacturer's printed instructions.

3.2 CONCURRENT EARTH-MOVING OPERATIONS.

Do not begin excavation, filling, and other earth-moving operations that are sequential to demolition work in areas occupied by structures to be demolished or deconstructed until all demolition and deconstruction in the

SECTION 02 41 00 Page 11 area has been completed and debris removed. Fill holes, open basements and other hazardous openings.

3.3 DISPOSITION OF MATERIAL.

3.3.1 Title to Materials

Except for salvaged items specified in related Sections, and for materials or equipment scheduled for salvage, all materials and equipment removed and not reused or salvaged, shall become the property of the Contractor and shall be removed from Government property. Title to materials resulting from demolition and deconstruction, and materials and equipment to be removed, is vested in the Contractor upon approval by the Contracting Officer of the

Contractor's demolition, deconstruction, and removal procedures, and authorization by the Contracting Officer to begin demolition and deconstruction. The Government will not be responsible for the condition or loss of, or damage to, such property after contract award. Showing for sale or selling materials and equipment on site is prohibited.

3.4 CLEANUP.

Remove debris and rubbish from basement and similar excavations. Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.

3.5 DISPOSAL OF REMOVED MATERIALS.

3.5.1 Regulation of Removed Materials

Dispose of debris, rubbish, scrap, and other nonsalvageable materials resulting from removal operations with all applicable federal, state and local regulations as contractually specified in the Waste Management Plan.

3.5.2 Burning on Government Property

Burning of materials removed from demolished and deconstructed structures will not be permitted on Government property.

3.5.3 Removal to Spoil Areas on Government Property

Transport noncombustible materials removed from demolition and deconstruction structures to designated spoil areas on Government property.

3.5.4 Removal from Government Property

Transport waste materials removed from demolished and deconstructed structures, except waste soil, from Government property for legal disposal.

Dispose of waste soil as directed by ED (Environmental Division).

3.6 REUSE OF SALVAGED ITEMS.

Recondition salvaged materials and equipment designated for reuse before installation. Replace items damaged during removal and salvage operations or restore them as necessary to usable condition.

-- End of Section --