A07 TE 3.1 Snow and Ice Removal Standard Operating revised20200805.pdf

PDF 159 KB Posted

Attached to
Base Operations Support Services on the Rock Island Arsenal, Rock Island, Illinois
Solicitation number
W52P1J-20-R-5001
Issued by

About this file

This document outlines standard operating procedures for snow and ice removal services at Rock Island Arsenal in Illinois. Key details include:

  • The contractor must develop a snow and ice removal plan covering removal from critical areas within 45 minutes of notification, roads, parking lots, sidewalks, and building entrances. Priorities and minimum standards for residual snow and ice depths are provided.

  • Services also include inspecting roofs for snow/ice, removing icicles and downspout ice, and providing supplies like shovels and deicer at building entrances. Response is required 24/7 when weather conditions require.

  • Acceptable deicers and application methods are specified for different surfaces. Contractors must track and report all costs associated with abrasives, chemicals and their application.

  • A related solicitation seeks market research for base operations support services at Rock Island Arsenal, including the snow and ice removal detailed in the standard operating procedures document. The estimated period of performance is one base year plus four option years beginning January 2021.

View the file

Other files

File Type Posted
A07 Amendment 00006.pdf PDF
A07 Pricing Matrix RIA Base Ops Rev L 16 Feb 2021.xlsx XLSX spreadsheet
A07 RIA Overarching revised 11 September 2020.pdf PDF
Contractor Questions 2.pdf PDF
Contractor Questions 1.xlsx XLSX spreadsheet
Contractor Questions 4.pdf PDF
Contractor Questions 3.pdf PDF
A07 TE 10.3 Bridge Maintenance Procedures (SOP) 20200807.pdf PDF
A07 TE 1.7 Government Furnished Facilities revised 20200807.pdf PDF
A07 Att 4 Facility Maintenance Vertical revised 20200805.pdf PDF
A07 Att 5 Facility Maintenance Army Family Housing revised 20200807.pdf PDF
A07 Att 1 Definitions Acronyms and Regulations revised 20200821.pdf PDF
A07 Att 2 Grounds Maintenance revised 20200808.pdf PDF
A07 RIA Overarching (OA) PWS BASEOPS revised 20200805.pdf PDF
A07 Att 3 Pavement Clearance revised 20200808.pdf PDF
DRAFT EVALUATION CRITERIA.pdf PDF
A07 ATTACHMENT 0006 Access Control Record Check Request Form.pdf PDF
A07 DRAFT SITE VISIT SCHEDULE AND RESERVATIONS.pdf PDF
A07 DRAFT SOLICITATION 10 JUNE 2020.pdf PDF
A07 Attachment 0008 ContractorVendor Guide - Contract Opportunities - beta.sam.gov - a Compi.._.pptx PPTX presentation
A07 TE 4.12 Electrical System Maintenance Procedures.pdf PDF
A07 TE 6.8 Auxiliary Emergency Generators.xlsx XLSX spreadsheet
A07 TE 6.3 RIA Sign Inventory.xlsx XLSX spreadsheet
A07 TE 6.7 Electrical Distribution Equip.xlsx XLSX spreadsheet
A07 TE 9.3 Specific Operator Maintenance Requirements.xlsx XLSX spreadsheet
A07 TE 4.15 Fire Alarm Systems.xlsx XLSX spreadsheet
A07 TE 7.20 Stormwater Observation Report.pdf PDF
A07 TE 1.7 Government Furnished Facilities.pdf PDF
A07 TE 4.13 Electrical System Equipment.xlsx XLSX spreadsheet
A07 TE 10.2 Bridge Operating Procedures (SOP).pdf PDF
A07 TE 5.6 Recreational Areas and Playgrounds AFH.pdf PDF
A07 TE 4.18 Playground Equipment.pdf PDF
A07 Att 1 Definitions Acronyms and Regulations.pdf PDF
A07 Att 6 Facility Maint Horizontal.pdf PDF
A07 TE 4.4 Eye Washes and Safety Showers.pdf PDF
A07 TE 4.7 List of Air Compressors.xlsx XLSX spreadsheet
A07 Att 7 Water Wastewater Stormwater Ops and Maint.pdf PDF
A07 TE 4.9 Hot Water Tanks.pdf PDF
A07 TE 7.3 Unidirectional Flushing Plan.pdf PDF
A07 TE 5.5 Off Post Housing Adequacy Checklist.pdf PDF
A07 DRAFT Pricing Matrix 12 May 2020.xlsx XLSX spreadsheet
A07 TE 5.8 Change of Occupancy Checklist Pest Control.pdf PDF
A07 TE 4.11 Oil Water Separator List.xlsx XLSX spreadsheet
A07 TE 8.2 Food Handling Establishments.xlsx XLSX spreadsheet
A07 TE 7.10 Water Distribution Valves.pdf PDF
A07 TE 1.4 RIA Spill Prevention Contingency and Countermeasure Plan 2017.pdf PDF
A07 TE 7.6 Major Components of Sanitary Sewer System.pdf PDF
A07 TE 7.21 RIA Flood Emergency Plan 2018.pdf PDF
A07 TE 6.5 Electrical Distribution.pdf PDF
A07 TE 4.14 Lightning Protection System Maintenance.pdf PDF
Show 40 more

Latest 50 of 94 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TE 3.1 Snow and Ice Removal Standard Operating

TE 3.1 Snow and Ice Removal Standard Operating 1

Snow Removal and Ice Control Requirements

1. Snow Removal and Ice Control Plan:

a. The Contractor shall develop a Snow Removal and Ice Control Plan which covers tasks included below. The plan shall be established IAW priorities for clearance of designated critical areas such as, but not limited to, handicapped parking, handicap building entrance ramps, fire/police station, medical, and family housing and shall assign equipment to accomplish the task.

Contractor's plan shall specify the following locations of markers and materials to be used for snow removal and ice control and areas from which snow must be hauled when accumulation reaches an established level.

b. The plan shall establish procedures for adding additional crew and equipment when a Winter Storm Warning has been issued by the National Weather Service or additional manpower is required. The Contractor shall notify the KO/COR in writing of any proposed changes to this plan. No such changes shall be implemented prior to approval in writing from the KO/COR.

Contractor's plan shall be furnished to the Government as part of the Contractor's technical proposal. Reference TM 5-624, Chapter 11, for guidance on snow and ice control.

2. Snow Removal and Ice Control Common Level of Service Requirements:

The Contractor shall provide snow removal and ice control services IAW contractor-developed, Government-approved Snow and Ice Removal Plan. The

Contractor shall collect and report all costs associated. The service requirements include, as a minimum, the following:

a. The Contractor shall remove snow and ice down to clean pavement from docks, steps, sidewalks, ramps, building entrances, doorways, bike/jogging paths, recreational trails.

Contractor shall remove snow and provide access from the buildings to five trash compactors.

The Contractor shall remove snow/ice and provide a clear walk path to the flagpoles at structures 361 and 301, when snow depth reaches one inch (1”) or more.

b. The Contractor shall remove snow and ice to a maximum residual depth of one- quarter (1/4") from primary roads.

TE 3.1 Snow and Ice Removal Standard Operating 2

c. The Contractor shall remove snow from railroad tracks as required to maintain use. The Contractor shall remove snow and ice to a maximum residual depth of one- quarter (1/4") from primary parking lots. The contractor shall remove snow and ice in front and on of refuse compactors at buildings 350 south east, 108 south court, 104 south court, 62 north court, and 68 north court. The contractor shall remove snow and ice in front of refuse dumpsters at buildings 102 south court. Contractor shall provide snow shovels, deicer containers, hand scoops and supply deicer approved by KO/COR throughout winter weather at up to 60 building entrances designated by the KO/COR.

d. The Contractor shall not remove any snow and ice from secondary roads if the snow event is expected to be 1” of accumulation or less. In the event of a variable forecast (1” – 3” accumulation expected) the KO/COR shall determine the whether the Contractor conducts snow removal operations on secondary roads. If accumulation is expected to exceed 1” or as directed by the KO/COR for variable forecasts the Contractor shall clear secondary roads as prioritized above to the primary standard (a maximum residual depth of one- quarter (1/4")).

Analysis of historical weather shows that on average of 8 snow events of the average 16 total snow events per year will be less than 1” accumulation.

e. The Contractor shall not remove any snow and ice from secondary parking lots if the snow event is expected to be 1” of accumulation or less. In the event of a variable forecast (1”

– 3” accumulation expected) the KO/COR shall determine the whether the Contractor conducts snow removal operations on secondary parking lots. If accumulation is expected to exceed 1” or as directed by the KO/COR for variable forecasts the Contractor shall clear secondary parking lots as prioritized above to the primary standard (a maximum residual depth of one- quarter (1/4")) from secondary parking lots. Analysis of historical weather shows that on average of 8 snow events of the average 16 total snow events per year will be less than 1” accumulation.

f. The contractor shall haul snow away as required to maintain traffic flow, visibility, parking availability fire hydrant access, safety for motorists and pedestrians and as directed by the KO/COR . The Contractor shall remove snow within three (3) feet radius around all fire hydrants when snow depths reach four (4) inches. This guidance shall apply to the entire installation.

g. The Contractor shall inspect the roofs of buildings 210 and 220 anytime there is an accumulation of 2” or more of snow/ice or, every two weeks if there is a continuing accumulation of snow/ice. Contractor shall immediately provide the results of the inspection to the Government. Should snow/ice removal be required, contractor will be issued a DMO or a PWO.

TE 3.1 Snow and Ice Removal Standard Operating 3

h. The Contractor shall remove icicles and accumulated ice from exterior down spouts and gutters. This guidance shall apply to the entire installation.

3. Snow and Ice Removal Methods and Requirements

a. The Contractor shall apply abrasives and/or chemicals for ice control to ensure that all sidewalks, ramps, stairs, roads, and parking areas are safe for pedestrian or vehicle travel. The contractor shall prewett with liquid calcium chloride all rock salt used on streets. Prewetting shall be accomplished at the trucks immediately after loading of the salt. Contractor shall be required to calibrate spreaders on trucks. Since the prewetted salt is more effective, the quantity of wetted salt to be used for a particular application shall be determined prior to placement.

Contractor shall be required to calibrate deicer spreaders to ensure that the proper quantity of deicer is placed as the use of too much deicer damages vegetation, vehicles, pavements, and structures. Pelletized potassium chloride shall be used at building entrances, sidewalks, steps, and ramps (within 20 feet). Pelletized calcium chloride shall be used on the three vehicular bridge decks and approaches to the bridges. Sodium chloride and other highly corrosive chemicals shall not be used on bridge surfaces. Use of urea, calcium magnesium acetate, and other non-approved deicers is not allowed. Sand is not a deicer, but can be used to improve traction on paved surfaces that are icy or covered with compacted snow. The Contractor shall not use salt or any other corrosive de-icing agents on the Rock Island Arsenal structure 345, all agents and application shall meet U.S. DOT Federal Aviation Administration Advisory Circular (AC 150/5200- 30A). The contractor shall reapply abrasives and chemicals to roadways, sidewalks, parking lots and other areas, where water has refrozen and poses a traffic or safety hazard. All costs for abrasives, deicing chemicals and their application shall be tracked and reported.

b. The contractor shall respond within forty five minutes of initial notification snow or ice work requirement. Response is defined as being physically on the premises at the work site, with appropriate tools, equipment, materials and labor, ready to perform the work required.

Response should also be appropriate to the type of snow or ice requirement. Contractor shall notify the KO/COR prior to initiating each snow removal and/or ice control action.

c. Snow removal and/or ice control work may be required during or outside normal duty hours and be required continuously for many days as dictated by weather. The Contractor shall have a sufficient amount of qualified personnel available on call, 24 hours per day, and seven days per week, to perform this work.

TE 3.1 Snow and Ice Removal Standard Operating 4

d. The contractor shall provide snow and ice removal services to allow the Government to conduct normal mission requirements. Should snow and ice requirements be implemented during normal RIA business hours the contractor will coordinate priority requirements with the KO/COR to concentrate removal efforts to allow employees passable and safe conditions while walking and driving. The Contractor shall initiate work during non-duty hours in time to have the roads, sidewalks, and parking lots clear for traffic by 0600 hours, and continue to work throughout the day as necessary to maintain normal work day operations. The Contractor shall also perform snow removal and ice control work specified in priorities to keep roads clear and safe for access to the family housing areas and for security patrols and other emergency vehicles, 24 hours per day, seven days per week.

e. The Contractor shall notify the KO/COR immediately of any snow removal and/or ice control work which cannot be accomplished IAW the above.

f. The Contractor shall follow the order of priorities for snow removal and ice control primary roads, bridges, primary parking lots, secondary roads, secondary parking lots, sidewalks etc. as listed below and on the snow/ice removal plan drawing. The contractor shall clear primary roads and primary parking lots concurrently as well as associated sidewalks, steps, building entrances etc. These priorities may be adjusted by the KO/COR as conditions or mission requirements dictate.

1. Primary Roads.

a. Fire Department driveway; Moline bridge; Government bridge; Rock Island Viaduct Bridge (structure 275); and all bridge approaches. Hand shoveling and use of snow blowers will be required around sentry and vehicle inspection stations.

b. Rodman Avenue from Government Bridge to Moline Bridge.

c. Fort Armstrong Avenue; East and West Pershing Streets and around building 390;

and North Avenue, Rock Island Avenue.

d. Gillespie Avenue; Ramsey Road Hedge Lane; and Quarters' (1-4,6,7) drives.

TE 3.1 Snow and Ice Removal Standard Operating 5

e. Beck Avenue from Rock Island Avenue east to Gillespie Avenue.

f. East Street, East Circle and South Avenue.

g. Prospect Drive to Visitor’s Center.

h. New Quarter's access roads- Baker Avenue, Durnin Avenue, Howard Street, Chamberlain Drive and Walker Drive.

i. Sylvan Drive from south corner of Building 299 west and north.

j. Flagler Street from building 229 north to Rodman Avenue.

k. Baumbeck Ave., Kingsbury Ave. and roadway between Buildings 208 and 212.

l. Buffington Street from Rodman Avenue north and North Avenue in the V-Area.

m. Beck Avenue from Gillespie Street east to East Street and East Street from Beck Avenue to Rodman.

n. Building 334 North side loading dock and roadway

2. Secondary Roads.

a. Blunt Road and King Drive.

b. Terrace Drive

c. Prospect Drive to Building 32 and testing area

TE 3.1 Snow and Ice Removal Standard Operating 6

d. Building 204 access roads

e. Building 244 access road and fuel dispensing areas

f. Chestnut Ave

g. North Ave adjacent to Buildings 339, 340, 341

h. Davenport Drive and Davenport Drive North

i. Benet Ave.

j. Sylvan Drive South of Beck Ave

k. Building 301 access roads

l. Dyke Road

m. Cemetery Drive

n. Building 25 access road

o. Road to pump station North of Building 25

p. Burr Drive

q. Other roads/areas as required by mission and prioritized by the KO/COR.

TE 3.1 Snow and Ice Removal Standard Operating 7

3. Primary Parking Lots:

a. Command Interest Parking Lots:

OM, OR, 2Q, 3D, 3E, 3G.

b. Reserved and Employee Parking Lots:

OA, OB, OC, OD, OE, OF, OG, OH, OI, OJ, OK, OL, ON, OP, OQ, OS, 1A, 1B,

1C, 1D, 1E, 1F, 1G, 1I, 1J, 1N, 1O, 1P, 1Q, 1R, 1S, 1V, 2A, 2B,2D, 2E, 2F, 2G, 2H, 2P, 2R, 2T, 2U, 2V, 3A, 3B, 3C, 3H, 3I, 3J, 3K, 3L, 3M, 3N, 3O, 3T, 3X, OT, 0U, 1U, 1X, 0X, 0W, 3RR, 3QQ, 3PP, 300, 2FF, 1LL, 100.

4. Secondary Parking Lots:

1H, 1M, 1T, 1U, 1W, 1X, 2C, 2S, 2W, 2X, 2Y, 2Z, 2ZZ 3F, 3P, 3Q, 3R, 3S, 3U, 3V.

5. Sidewalks, steps and building entrances:

a. Sidewalks, steps and entrances from primary parking lots to building entrances.

b. Sidewalks, steps and entrances serving childcare facilities, administration, manufacturing and warehouse buildings.

c. Sidewalks and crosswalks to Pershing Streets East and West

d. Sidewalks and crosswalks to Rodman Avenue, North Avenue and adjacent housing areas.

e. Sidewalks and crosswalks to Gillespie and East streets and adjacent housing areas.

TE 3.1 Snow and Ice Removal Standard Operating 8

f. Sidewalks and crosswalks (except sidewalks in front of residences) to Walker Drive, Chamberlain Drive, Howard Street, Baker Avenue, Durnin Avenue and Structure 364.

g. Sidewalks and crosswalks to Fort Armstrong and Rock Island Drive

h. Sidewalks and crosswalks to Terrace Lane

i. All other sidewalks, Recreation trails, steps, building entrances, ramps, compactors etc. as required by mission and prioritized by KO/COR.