CWF Pre-Proposal minutes.pdf

PDF 131 KB Posted

Attached to
F-35 CONSTRUCT COMBINED WEAPONS FACILITY Federal contract opportunity
Solicitation number
W50S6Y-25-B-A004
Issued by
Department of the Army Florida Army National Guard

About this file

This is a memorandum documenting the pre-proposal conference and site visit held on February 26, 2025 for solicitation W50S6Y25BA004, to construct a Combined Weapons Facility (CWF) for the Florida National Guard. The meeting was attended by government representatives including the Contracting Officer, Contract Specialists, CORs, and Project Officer.

Key details discussed include: a 720-day contract period with anticipated award in late May/June 2025; work hours of 0600-1800 M-F for F-35 projects; base access processing times of 10 days for US citizens and 30 days for foreign nationals; required double hearing protection during flight operations; prohibition on aircraft photography; utility connections to be provided but contractor responsible for final connections; and onsite supervision requirements including Superintendent, SSHO, QCM, and Project Manager with minimum 2 onsite at all times (QCM cannot serve as Superintendent). All technical questions must be submitted in writing to the Contracting Office, with responses to be posted on SAM.gov. The site visit portion allowed attendees to view all operational areas and take photos of the work areas, concluding at approximately 1100 hours.

View the file

Other files for this federal contract opportunity

Other files attached to F-35 CONSTRUCT COMBINED WEAPONS FACILITY, newest first.
File Type Posted
LSGA239001_CWF IFB Abstract 1419-KO.pdf PDF
Bid Submission Day Sign-In Sheet-3APR25.pdf PDF
Q-A set 05G_W50S6Y25BA004 3.28.25 Final.pdf PDF
RFI-0028 REV01-HANGAR DOOR OPENING CLARIFICATIONS AND DETAILS.pdf PDF
RFI-0086 Set 5 Q-3 Louvers locations_Parsons response.pdf PDF
Solicitation Amendment W50S6Y25BA0040002 SF 30 CWF.pdf PDF
Q-A set 04Gp2_W50S6Y25BA004.pdf PDF
CWF Spec 08 34 16.20 Vertical Lift Fabric Hanger Door.pdf PDF
Q-A set 04G_W50S6Y25BA004 3.18.25.pdf PDF
RFI-0057 Q-A-29 set 04_Parsons response.pdf PDF
Solicitation Amendment W50S6Y25BA0040001 SF 30 CWF.pdf PDF
CWF Spec 08 36 16.20 Vertical Lift Fabric Hanger Door.pdf PDF
Q-A set 03G_W50S6Y25BA004 3.11.25.pdf PDF
CWF - RFI 0007 ATTACHMENT CU101.pdf PDF
CWF Spec Section 08 34 16 VERTICAL LIFT FABRIC HANGAR DOOR.pdf PDF
Missing Page from 25BA004 Sign In Sheet.pdf PDF
CWF B-3 DESIGN ANALYSIS - Appendix E.9.pdf PDF
Q-A set 02G_W50S6Y25BA004 3.7.25.pdf PDF
CWF B-3 DESIGN ANALYSIS - Appendix E.8.pdf PDF
CWF - RFI 0007.pdf PDF
CWF - RFI 0009.pdf PDF
25BA004 Pre-Bid Site Visit PP.pptx PPTX presentation
Q-A set 01G_W50S6Y25BA004 2.28.25.pdf PDF
GeoTech Rpt-Terracon.pdf PDF
Asbestos -Lead Paint Survey-Terracon.pdf PDF
CWF Sign In Sheet.pdf PDF
Attach-1_JAXF35CWF-100P SPECIFICATIONS.pdf PDF
Attach-2_JAXF35CWF-100P GENERAL CS ARCH DRAWINGS VOLUME 1 OF 3.pdf PDF
Attach-4_JAXF35CWF-100P GENERAL MECH PLUM DRAWINGS VOLUME 3 OF 3.pdf PDF
Attach-5_BrandName (FAR 6)_BestCores-A- COR-KO_Redacted.pdf PDF
Solicitation - W50S6Y25BA004 Construct CWF.pdf PDF
Attach-3_JAXF35CWF-100P GENERAL FP ELECT TELE DRAWINGS VOLUME 2 OF 3.pdf PDF
Attach-6_BrandName (FAR 6)_Advantor-B COR-KO_Redacted.pdf PDF
Attach-7_BrandName (FAR 6)_Monaco-C-COR-KO_Redacted.pdf PDF
Attach-8_BrandName (FAR 6)_MMetasys-D-COR-KO_Redacted.pdf PDF
Attach-9_125FW Form 2 Access request (Aug 2023).pdf PDF
Show all 36

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NATIONAL GUARD BUREAU

OFFICE OF THE UNITED STATES PROPERTY & FISCAL OFFICER, FLORIDA

POST OFFICE BOX 1008

ST. AUGUSTINE, FL 32085-1008

MEMORANDUM FOR RECORD

SUBJECT: MINUTES OF PRE-PROPOSAL CONFERENCE AND SITE VISIT, SOLICITATION

W50S6Y25BA004, Construct Combined Weapons Facility (CWF)

26 Feb 2025, 0900AM EST

1. The list of contractors attending the meeting is shown on the attached sign-in sheet. The following

Government representatives attended the subject meeting:

Name Position Matt Michael KO Mark Penwell CS Katie Perna CS Jason Davis COR Mike Rivera COR Jonathan Kassebaum Project Officer

2. The following items were discussed during the Pre-proposal Conference:

a. The Contract period is 720 days. This includes all work to include cleanup and punch list.

We anticipate award of the contract in late May early June. Following receipt and approval of bonds we will hold a pre-construction conference and issue NTP.

b. Interested offerors must be registered in SAM. To register go to:

https://www.sam.gov/portal/public/SAM/. You will need your CAGE/UEI number register.

c. Work hours for the F-35 Projects are 0600 to 1800hrs M-F

d. Base access is a priority and processing time to get approval are 10days US citizen, 30days for Foreign Nationals.

e. Government will handle all crane permits with FAA.

f. Double hearing protection will be required during flight operations due to proximity of project to airfield.

g. Reminder that NO pictures of aircraft will be allowed, phones/cameras will be confiscated.

h. It’s ok to drill holes for jobsite perimeter fence posts. The holes must be repaired when the fence is removed.

i. Along flightline apron, Fence and Plastic water field jersey barriers are required.

j. Electric and water connection locations will be provided, the “connection” is responsibility of the GC, no change for utilities.

k. Air Guard does not have a recycling center, the GC will be responsible for proper recycling and reporting weights/amounts to government.

3. A power point slide presentation on the project specifics and the selection process will be provided to all attendees via SAM.

4. Questions must be submitted in writing via email, especially technical questions POC in Sec 000100 Item 4. DO NOT CONTACT the Design Engineers or the Government Engineers. All questions must be routed through the Contracting Office. All Contractor questions when answered will be posted to the website. If a question arises that will result in a change to the plans or specifications, an official amendment will be issued. All correspondence, questions and answers, amendments etc. will be issued or posted at SAM.gov.

5. No technical question were address at the Conference, all were directed to email the POCs in the solicitation written Questions to be responded to on SAM IAW item 4.

6. During the meeting it was asked to clarify onsite supervisions requirements, Government responded with Superintendent, SSHO, QCM, Project Manager. Minimum 2 onsite at all times and the QCM cannot dual role as Superintendent.

7. All attendees were escorted thru the worksite showing each phase area as described in the Plans and Specs. All were afforded opportunities to take pictures and show all operational area in the Scope of Work.

8. Any amendments that are issued will be posted to SAM.GOV site. Contractors were advised to check the website frequently.

9. The pre-proposal conference and site visit concluded at approximately 1100 hours.

MATTHEW MICHAEL

CONTRACTING OFFICER

2025-02-27T11:34:04-0500
MICHAEL.MATTHEW.JOHN.1077434387