Attach-1_JAXF35CWF-100P SPECIFICATIONS.pdf

PDF 8 MB Posted

Attached to
F-35 CONSTRUCT COMBINED WEAPONS FACILITY Federal contract opportunity
Solicitation number
W50S6Y-25-B-A004
Issued by
Department of the Army Florida Army National Guard

About this file

This file contains specifications for a B-3 design submission for constructing an F-35 Consolidated Weapons Training Facility at Jacksonville International Airport for the Florida Air National Guard. The specifications detail requirements across multiple construction divisions including general requirements, existing conditions, concrete, masonry, metals, wood/plastics/composites, thermal/moisture protection, openings, finishes, specialties, equipment, furnishings, special construction, fire suppression, plumbing, HVAC, integrated automation, electrical, communications, electronic safety/security, earthwork, exterior improvements, and utilities.

The project involves building a 22,696 square-foot facility with a hangar bay for load crew training, weapons and release systems shops, admin offices, classrooms, break room, and restrooms. Key milestones include an FMS Pre-Install Survey Coordination Meeting 150 days prior to Pre-Install Survey, FMS Pre-Final inspection 30 days before Pre-Install Survey, and FMS Final Inspection/Acceptance when the government can begin simulator installation. The specifications require coordination with Florida Air National Guard operations, adherence to airfield safety requirements, and implementation of hazardous materials procedures through a HAZMART program. Environmental remediation, demolition of existing structures (B1404, B1422, B1022), and installation of asphalt/concrete pavements are also included in the scope.

View the file

Other files for this federal contract opportunity

Other files attached to F-35 CONSTRUCT COMBINED WEAPONS FACILITY, newest first.
File Type Posted
LSGA239001_CWF IFB Abstract 1419-KO.pdf PDF
Bid Submission Day Sign-In Sheet-3APR25.pdf PDF
Q-A set 05G_W50S6Y25BA004 3.28.25 Final.pdf PDF
RFI-0028 REV01-HANGAR DOOR OPENING CLARIFICATIONS AND DETAILS.pdf PDF
RFI-0086 Set 5 Q-3 Louvers locations_Parsons response.pdf PDF
Solicitation Amendment W50S6Y25BA0040002 SF 30 CWF.pdf PDF
Q-A set 04Gp2_W50S6Y25BA004.pdf PDF
CWF Spec 08 34 16.20 Vertical Lift Fabric Hanger Door.pdf PDF
Q-A set 04G_W50S6Y25BA004 3.18.25.pdf PDF
RFI-0057 Q-A-29 set 04_Parsons response.pdf PDF
Solicitation Amendment W50S6Y25BA0040001 SF 30 CWF.pdf PDF
CWF Spec 08 36 16.20 Vertical Lift Fabric Hanger Door.pdf PDF
Q-A set 03G_W50S6Y25BA004 3.11.25.pdf PDF
CWF - RFI 0007 ATTACHMENT CU101.pdf PDF
CWF Spec Section 08 34 16 VERTICAL LIFT FABRIC HANGAR DOOR.pdf PDF
Missing Page from 25BA004 Sign In Sheet.pdf PDF
CWF B-3 DESIGN ANALYSIS - Appendix E.9.pdf PDF
Q-A set 02G_W50S6Y25BA004 3.7.25.pdf PDF
CWF B-3 DESIGN ANALYSIS - Appendix E.8.pdf PDF
CWF - RFI 0007.pdf PDF
CWF - RFI 0009.pdf PDF
25BA004 Pre-Bid Site Visit PP.pptx PPTX presentation
Q-A set 01G_W50S6Y25BA004 2.28.25.pdf PDF
GeoTech Rpt-Terracon.pdf PDF
Asbestos -Lead Paint Survey-Terracon.pdf PDF
CWF Pre-Proposal minutes.pdf PDF
CWF Sign In Sheet.pdf PDF
Attach-2_JAXF35CWF-100P GENERAL CS ARCH DRAWINGS VOLUME 1 OF 3.pdf PDF
Attach-4_JAXF35CWF-100P GENERAL MECH PLUM DRAWINGS VOLUME 3 OF 3.pdf PDF
Attach-5_BrandName (FAR 6)_BestCores-A- COR-KO_Redacted.pdf PDF
Solicitation - W50S6Y25BA004 Construct CWF.pdf PDF
Attach-3_JAXF35CWF-100P GENERAL FP ELECT TELE DRAWINGS VOLUME 2 OF 3.pdf PDF
Attach-6_BrandName (FAR 6)_Advantor-B COR-KO_Redacted.pdf PDF
Attach-7_BrandName (FAR 6)_Monaco-C-COR-KO_Redacted.pdf PDF
Attach-8_BrandName (FAR 6)_MMetasys-D-COR-KO_Redacted.pdf PDF
Attach-9_125FW Form 2 Access request (Aug 2023).pdf PDF
Show all 36

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

January 2025

FLORIDA AIR NATIONAL GUARD

JACKSONVILLE INTERNATIONAL AIRPORT

B-3 Design Submission

F-35 CONSOLIDATED WEAPONS

TRAINING FACILITY

Specifications B-3 Design Submittal

Prepared for:

The National Guard Bureau Contract: FA8903-21-D-0011, Order: W50S6Y24F0001

Florida Air National Guard

Jacksonville, Florida

This page intentionally left blank.

LSGA239001 JAXCWF-0

IFC B-3 Submission 100%

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 07 03/24 SEALS PAGES

00 01 15 02/24 LIST OF DRAWINGS

DIVISION 01 - GENERAL REQUIREMENTS

01 10 00 10/24 SUMMARY OF WORK

01 10 50.01 10/24 HAZARDOUS MATERIALS PROCEDURES

01 14 16 10/24 COORDINATION WITH FLORIDA AIR NATIONAL

GUARD

01 23 00 10/24 OPTIONAL LINE ITEMS (OLI's)

01 31 00 10/24 PROJECT MANAGEMENT AND COORDINATION

01 31 13 10/24 SPECIAL PROJECT PROCEDURES

01 32 00 10/24 CONSTRUCTION PROGRESS DOCUMENTATION

01 32 33 10/24 PHOTOGRAPHIC DOCUMENTATION

01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES

01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND

REPORTING

01 35 26 05/24 GOVERNMENTAL SAFETY REQUIREMENTS

01 35 43 10/24 SAFETY, HAZARDOUS MATERIALS AND HEALTH

REQUIREMENTS

01 40 00 10/24 QUALITY REQUIREMENTS

01 42 00 05/24 REFERENCES

01 42 00.01 10/24 ENVIRONMENTAL PROTECTION

01 45 35 11/20 SPECIAL INSPECTIONS

01 50 00 10/24 TEMPORARY FACILITIES AND CONTROLS

01 60 00 10/24 PRODUCT REQUIREMENTS

01 74 19 10/24 CONSTRUCTION WASTE MANAGEMENT AND

DISPOSAL

01 77 00 10/24 CLOSEOUT PROCEDURES

01 78 23 05/23 OPERATION AND MAINTENANCE DATA

01 78 39 10/24 PROJECT RECORD DOCUMENTS

01 79 00 10/24 DEMONSTRATION AND TRAINING

01 91 00.15 10/24 TOTAL BUILDING COMMISSIONING

DIVISION 02 - EXISTING CONDITIONS

02 41 00 08/22 DEMOLITION

02 61 13 02/10, CHG 1: 02/21 EXCAVATION AND HANDLING OF

CONTAMINATED MATERIAL

02 81 00 11/18 TRANSPORTATION AND DISPOSAL OF

HAZARDOUS MATERIALS

DIVISION 03 - CONCRETE

03 30 00 02/19 CAST-IN-PLACE CONCRETE

03 35 43 11/19 POLISHED CONCRETE FINISHING

03 45 00 05/16 PRECAST ARCHITECTURAL CONCRETE

DIVISION 04 - MASONRY

04 20 00 11/15 UNIT MASONRY

DIVISION 05 - METALS

05 05 23.16 08/18 STRUCTURAL WELDING

DOCUMENT PROJECT Page 1 Friday January 17, 2025 Version 0

05 12 00 08/18 STRUCTURAL STEEL

05 21 00 05/15 STEEL JOIST FRAMING

05 30 00 05/15 STEEL DECKS

05 40 00 05/15 COLD-FORMED METAL FRAMING

05 50 13 05/17 MISCELLANEOUS METAL FABRICATIONS

05 51 33 02/16 METAL LADDERS

05 52 00 02/18 METAL RAILINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 08/16 ROUGH CARPENTRY

06 41 16.00 10 08/10, CHG 1: 11/18 PLASTIC-LAMINATE-CLAD ARCHITECTURAL

CABINETS

06 61 16 08/20 SOLID SURFACING FABRICATIONS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 05 23 08/19 PRESSURE TESTING AN AIR BARRIER SYSTEM

FOR AIR TIGHTNESS

07 11 13 08/23 BITUMINOUS DAMPPROOFING

07 13 53 02/16, CHG 1: 08/17 ELASTOMERIC SHEET WATERPROOFING

07 14 00 08/23 FLUID-APPLIED WATERPROOFING

07 19 00 08/23 WATER REPELLENTS

07 21 13 08/23 BOARD AND BLOCK INSULATION

07 21 16 08/23 MINERAL FIBER BLANKET INSULATION

07 22 00 08/23 ROOF AND DECK INSULATION

07 27 10 08/23 BUILDING AIR BARRIER SYSTEM

07 27 19.01 08/23 SELF-ADHERING AIR BARRIERS

07 27 36 08/23 SPRAY FOAM AIR BARRIERS

07 42 13 05/11, CHG 2: 02/18 METAL WALL PANELS

07 42 63 05/11, CHG 4: 08/20 FABRICATED WALL PANEL ASSEMBLIES

07 60 00 08/23 FLASHING AND SHEET METAL

07 61 14.00 20 08/16, CHG 1: 08/18 STEEL STANDING SEAM ROOFING

07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING

07 92 00 08/23 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 08/20 STEEL DOORS AND FRAMES

08 14 00 08/16, CHG 1: 08/18 WOOD DOORS

08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS

08 33 23 08/20, CHG 1: 02/22 OVERHEAD COILING DOORS

08 34 73 11/19, CHG 1: 02/21 SOUND CONTROL DOOR ASSEMBLIES

08 41 13 08/18, CHG 1: 08/18 ALUMINUM-FRAMED ENTRANCES AND

STOREFRONTS

08 45 23 02/12 TRANSLUCENT FIBERGLASS SANDWICH PANEL

WALL SYSTEM

08 51 13 05/19 ALUMINUM WINDOWS

08 56 53 08/20 BLAST RESISTANT TEMPERED GLASS WINDOWS

08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE

08 81 00 05/19 GLAZING

08 91 00 08/20 METAL WALL LOUVERS

DIVISION 09 - FINISHES

09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD

09 30 10 08/20 CERAMIC, QUARRY, AND GLASS TILING

09 51 00 08/20 ACOUSTICAL CEILINGS

DOCUMENT PROJECT Page 2

09 65 00 08/10, CHG 3: 08/18 RESILIENT FLOORING

09 67 23.16 02/21 FUEL RESISTIVE RESINOUS FLOORING,

5-COAT SYSTEM

09 68 00 11/17, CHG 2: 08/20 CARPETING

09 72 00 08/17, CHG 1: 08/18 WALLCOVERINGS

09 84 20 08/16, CHG 1: 08/18 ACOUSTICAL WALL PANELS

09 90 00 02/21 PAINTS AND COATINGS

09 96 00 11/14 HIGH-PERFORMANCE COATINGS

DIVISION 10 - SPECIALTIES

10 11 00 08/20 VISUAL DISPLAY UNITS

10 14 00.10 08/17, CHG 1: 11/18 EXTERIOR SIGNAGE

10 14 00.20 08/20 INTERIOR SIGNAGE

10 14 53 02/15, CHG 1: 05/17 TRAFFIC SIGNAGE

10 21 13 08/20 TOILET COMPARTMENTS

10 22 39 08/20 FOLDING PANEL PARTITIONS

10 26 00 08/20 WALL AND DOOR PROTECTION

10 28 13 08/20 TOILET ACCESSORIES

10 44 16 11/19 FIRE EXTINGUISHERS

10 51 13 05/11 WOOD LOCKERS

DIVISION 11 - EQUIPMENT

11 31 13 08/17, CHG 1: 08/18 ELECTRIC KITCHEN APPLIANCES

11 46 00 01/08 FOOD DISPENSING/VENDING EQUIPMENT

DIVISION 12 - FURNISHINGS

12 21 00 08/17, CHG 2: 11/18 WINDOW BLINDS

12 48 13 08/2 ENTRANCE FLOOR MATS AND FRAMES

12 50 00.13 10 08/17, CHG 1: 11/18 FURNITURE AND FURNITURE INSTALLATION

12 59 00 08/17, CHG 1: 08/18 SYSTEMS FURNITURE

DIVISION 13 - SPECIAL CONSTRUCTION

13 48 73 05/22 SEISMIC CONTROL FOR MISCELLANEOUS

EQUIPMENT

DIVISION 21 - FIRE SUPPRESSION

21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE

PROTECTION

DIVISION 22 - PLUMBING

22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE

22 15 26.00 20 04/06 HIGH AND MEDIUM PRESSURE COMPRESSED

AIR PIPING

22 31 00 02/09 WATER SOFTENERS, CATION-EXCHANGE

(SODIUM CYCLE)

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 01 30.41 05/22 HVAC SYSTEM CLEANING

23 03 00.00 20 08/10, CHG 3: 08/18 BASIC MECHANICAL MATERIALS AND METHODS

23 05 15 05/22, CHG 1: 02/24 COMMON PIPING FOR HVAC

23 05 48.19 05/18, CHG 2: 08/20 BRACING FOR HVAC

23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR

DOCUMENT PROJECT Page 3

HVAC

23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL

SYSTEMS

23 08 00 05/23 COMMISSIONING OF MECHANICAL AND

PLUMBING SYSTEMS

23 09 00 02/19, CHG 3: 05/21 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES

FOR HVAC

23 09 23.02 02/19, CHG 1: 02/20 BACNET DIRECT DIGITAL CONTROL FOR HVAC

AND OTHER BUILDING CONTROL SYSTEMS

23 21 23 08/17 HYDRONIC PUMPS

23 23 00 08/21 REFRIGERANT PIPING

23 25 00 05/21 CHEMICAL TREATMENT OF WATER FOR

MECHANICAL SYSTEMS

23 30 00 05/20, CHG 1: 02/22 HVAC AIR DISTRIBUTION

23 64 10 11/16, CHG 2: 08/18 WATER CHILLERS, VAPOR COMPRESSION TYPE

23 64 26 08/09, CHG 7: 02/24 CHILLED WATER PIPING SYSTEMS

23 81 00 05/18, CHG 1: 02/21 DECENTRALIZED UNITARY HVAC EQUIPMENT

23 82 00.00 20 02/16, CHG 1: 08/18 TERMINAL HEATING UNITS

23 83 00.00 20 04/06 ELECTRIC SPACE HEATING EQUIPMENT

DIVISION 25 - INTEGRATED AUTOMATION

25 05 11 11/17 CYBERSECURITY FOR FACILITY-RELATED

CONTROL SYSTEMS FIRE ALARM REPORTING

SYSTEM/MASS NOTIFICATION SYSTEM

BUILDING LEVEL ONLY

25 08 10 04/06 UTILITY MONITORING AND CONTROL SYSTEM

TESTING

25 10 10 02/19 UTILITY MONITORING AND CONTROL SYSTEM

(UMCS) FRONT END AND INTEGRATION

DIVISION 26 - ELECTRICAL

26 05 19.00 10 11/22 INSULATED WIRE AND CABLE

26 05 48 11/23 SEISMIC PROTECTION FOR ELECTRICAL

EQUIPMENT

26 05 73 08/23 POWER SYSTEM STUDIES

26 08 00 11/22 APPARATUS INSPECTION AND TESTING

26 20 00 08/23 INTERIOR DISTRIBUTION SYSTEM

26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS

UNDER 600 VOLTS

26 35 44 08/21 270 VDC SOLID STATE CONVERTER

26 36 23 05/20, CHG 1: 08/21 AUTOMATIC TRANSFER SWITCHES AND

BY-PASS/ISOLATION SWITCH

26 41 00 08/23 LIGHTNING PROTECTION SYSTEM

26 42 13 05/21 GALVANIC (SACRIFICIAL) ANODE CATHODIC

PROTECTION (GACP) SYSTEM

26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING

26 56 20 02/19 AIRFIELD AND HELIPORT LIGHTING AND

VISUAL NAVIGATION AIDS

DIVISION 27 - COMMUNICATIONS

27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING

SYSTEM

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

DOCUMENT PROJECT Page 4

28 31 76 08/20 INTERIOR FIRE ALARM AND MASS

NOTIFICATION SYSTEM, ADDRESSABLE

DIVISION 31 - EARTHWORK

31 00 00 08/23 EARTHWORK

31 05 19.13 02/21 GEOTEXTILES FOR EARTHWORK

31 11 00 11/18 CLEARING AND GRUBBING

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 01 19.61 11/19 SEALING OF JOINTS IN RIGID PAVEMENT

32 11 20 05/22 BASE COURSE FOR RIGID PAVING

32 11 23 05/22 GRADED CRUSHED AGGREGATE BASE COURSE

32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS

32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING

32 13 13.06 05/20 PORTLAND CEMENT CONCRETE PAVEMENT FOR

ROADS AND SITE FACILITIES

32 13 14.13 11/22, CHG 1: 05/24 CONCRETE PAVING FOR AIRFIELDS AND

OTHER HEAVY DUTY PAVEMENTS

32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS

DIVISION 33 - UTILITIES

33 11 00 02/18, CHG 2: 11/23 WATER UTILITY DISTRIBUTION PIPING

33 30 00 05/18 SANITARY SEWERAGE

33 40 00 11/21 STORMWATER UTILITIES

33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT

41 22 13.14 11/19, CHG 1: 02/21 BRIDGE CRANES, OVERHEAD ELECTRIC, TOP

RUNNING

-- End of Project Table of Contents --

DOCUMENT PROJECT Page 5

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 01 07

SEALS PAGES

03/24

PART 1 GENERAL

1.1 DESIGN PROFESSIONALS OF RECORD

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

DOCUMENT 00 01 07 Page 1

SECTION 00 01 07

SEALS PAGES

03/24

PART 1 GENERAL

1.1 DESIGN PROFESSIONALS OF RECORD

A. Architect :

The Architect noted below is only responsible for the following specifications.

Stanley Douglas George, State of Florida, Registered Architect, License No.

AR102462.

This item has been digitally signed and sealed by Stanley Douglas George on the date adjacent to seal. Printed copies of this document are not considered signed and sealed and the signature code must be verified on any electronic copies.

01 33 29 - SUSTAINABILITY REQUIREMENTS AND REPORTING

01 35 26 - GOVERNMENTAL SAFETY REQUIREMENTS

01 40 00 - QUALITY REQUIREMENTS

01 60 00 - PRODUCT REQUIREMENTS

01 91 00.15 - TOTAL BUILDING COMMISSIONING

05 50 13 - MISCELLANEOUS METAL FABRICATIONS

05 52 00 - METAL RAILINGS

06 10 00 - ROUGH CARPENTRY

06 41 16.00 10 - PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS

06 61 16 - SOLID SURFACING FABRICATIONS

07 05 23 - PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS

07 11 13 - BITUMINOUS DAMPPROOFING

07 13 53 - ELASTOMERIC SHEET WATERPROOFING

07 14 00 - FLUID-APPLIED WATERPROOFING

07 19 00 - WATER REPELLENTS

07 21 13 - BOARD AND BLOCK INSULATION

07 21 16 - MINERAL FIBER BLANKET INSULATION

07 22 00 - ROOF AND DECK INSULATION

07 27 10 - BUILDING AIR BARRIER SYSTEM

07 27 19.01 - SELF-ADHERING AIR BARRIERS

07 27 36 - SPRAY FOAM AIR BARRIERS

07 42 13 - METAL WALL PANELS

07 42 63 - FABRICATED WALL PANEL ASSEMBLIES

07 60 00 - FLASHING AND SHEET METAL

07 61 14.00 - STEEL STANDING SEAM ROOFING

07 84 00 - FIRESTOPPING

07 92 00 - JOINT SEALANTS

08 11 13 - STEEL DOORS AND FRAMES

08 14 00 - WOOD DOORS

08 31 00 - ACCESS DOORS AND PANELS

08 33 23 - OVERHEAD COILING DOORS

08 34 73 - SOUND CONTROL DOOR ASSEMBLIES

08 41 13 - ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

08 45 23 - TRANSLUCENT FIBERGLASS SANDWICH PANEL WALL SYSTEM

DOCUMENT 00 01 07 Page 2 Friday January 17, 2025 Version 0

NOT FOR

CONSTRUCTIONT

CETIHCRADER

ET

SI

G E

R

FOETAT

S

RO

EG

SLGUOD

YEL

NAT S

A

E G

AR102462

F L OR I D

A

08 51 13 - ALUMINUM WINDOWS

08 56 53 - BLAST RESISTANT TEMPERED GLASS WINDOWS

08 71 00 - DOOR HARDWARE

08 81 00 - GLAZING

08 91 00 - METAL WALL LOUVERS

09 22 00 - SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 - GYPSUM BOARD

09 30 10 - CERAMIC, QUARRY, AND GLASS TILING

09 51 00 - ACOUSTICAL CEILINGS

09 65 00 - RESILIENT FLOORING

09 67 23.16 - FUEL RESISTIVE RESINOUS FLOORING, 5-COAT SYSTEM

09 68 00 - CARPETING

09 72 00 - WALLCOVERINGS

09 84 20 - ACOUSTICAL WALL PANELS

09 90 00 - PAINTS AND COATINGS

09 96 00 - HIGH-PERFORMANCE COATINGS

10 11 00 - VISUAL DISPLAY UNITS

10 14 00.10 - EXTERIOR SIGNAGE

10 14 00.20 - INTERIOR SIGNAGE

10 14 53 - TRAFFIC SIGNAGE

10 21 13 - TOILET COMPARTMENTS

10 22 39 - FOLDING PANEL PARTITIONS

10 26 00 - WALL AND DOOR PROTECTION

10 28 13 - TOILET ACCESSORIES

10 51 13 - WOOD LOCKERS

11 31 13 - ELECTRIC KITCHEN APPLIANCES

11 46 00 - FOOD DISPENSING/VENDING EQUIPMENT

12 21 00 - WINDOW BLINDS

12 48 13 - ENTRANCE FLOOR MATS AND FRAMES

12 50 00.13 10 - FURNITURE AND FURNITURE INSTALLATION

12 59 00 - SYSTEMS FURNITURE

13 48 73 - SEISMIC CONTROL FOR MISCELLANEOUS EQUIPMENT

B. Civil Engineer :

The Engineer noted below is only responsible for the following specifications.

Ed Hickey, State of Florida, Professional Engineer, License No. 87847.

This item has been digitally signed and sealed by Ed Hickey on the date adjacent to seal. Printed copies of this document are not considered signed and sealed and the signature code must be verified on any electronic copies.

01 10 50.01 - HAZARDOUS MATERIALS PROCEDURES

01 35 43 - SAFETY, HAZARDOUS MATERIALS AND HEALTH REQUIREMENTS

01 42 00.01 - ENVIRONMENTAL PROTECTION

01 50 00 - TEMPORARY FACILITIES AND CONTROLS

01 74 19 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

02 41 00 - DEMOLITION

02 61 13 - EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL

02 81 00 - TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS

31 00 00 - EARTHWORK

31 05 19.13 - GEOTEXTILES FOR EARTHWORK

31 11 00 - CLEARING AND GRUBBING

32 01 19.61 - SEALING OF JOINTS IN RIGID PAVEMENT

32 11 20 - BASE COURSE FOR RIGID PAVING

32 11 23 - GRADED CRUSHED AGGREGATE BASE COURSE

DOCUMENT 00 01 07 Page 3 Friday January 17, 2025 Version 0

NOT FOR

CONSTRUCTION

32 12 13 - BITUMINOUS TACK AND PRIME COATS

32 12 16.16 - ROAD-MIX ASPHALT PAVING

32 13 13.06 - PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE FACILITIES

32 13 14.131 - CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY PAVEMENTS

32 16 19 - CONCRETE CURBS, GUTTERS AND SIDEWALKS

33 11 00 - WATER UTILITY DISTRIBUTION PIPING

33 30 00 - SANITARY SEWERAGE

33 40 00 - STORMWATER UTILITIES

C. Structural Engineer :

The Engineer noted below is only responsible for the following specifications.

Richard A. Jones, State of Florida, Professional Engineer, License No. 90610.

This item has been digitally signed and sealed by Richard A. Jones on the date adjacent to seal. Printed copies of this document are not considered signed and sealed and the signature code must be verified on any electronic copies.

01 45 35 - SPECIAL INSPECTIONS

03 30 00 - CAST-IN-PLACE CONCRETE

03 35 43 - POLISHED CONCRETE FINISHING

03 45 00 - PRECAST ARCHITECTURAL CONCRETE

04 20 00 - UNIT MASONRY

05 05 23.16 - STRUCTURAL WELDING

05 12 00 - STRUCTURAL STEEL

05 21 00 - STEEL JOIST FRAMING

05 30 00 - STEEL DECKS

05 40 00 - COLD-FORMED METAL FRAMING

05 50 13 - MISCELLANEOUS METAL FABRICATIONS

05 51 33 - METAL LADDERS

41 22 13.14 - BRIDGE CRANES, OVERHEAD ELECTRIC, TOP RUNNING

D. Fire-Protection Engineer :

The Engineer noted below is only responsible for the following specifications.

Roy Medeiros, State of Florida, Professional Engineer, License No. 97793.

This item has been digitally signed and sealed by Roy Medeiros on the date adjacent to seal. Printed copies of this document are not considered signed and sealed and the signature code must be verified on any electronic copies.

10 44 16 - FIRE EXTINGUISHERS

21 13 13 - WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION

28 31 76 - INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM, ADDRESSABLE

E. Mechanical Engineer :

The Engineer noted below is only responsible for the following specifications.

Esperanza M. Adams, State of Florida, Professional Engineer, License No.

73156.

This item has been electronically signed and sealed by Esperanza M. Adams on

DOCUMENT 00 01 07 Page 4 the date adjacent to seal using SHA authentication code. Printed copies of this document are not considered signed and sealed and SHA authentication code must be verified on any electronic copies.

22 00 00 - PLUMBING, GENERAL PURPOSE

22 15 26.00 20 - HIGH AND MEDIUM PRESSURE COMPRESSED AIR PIPING

22 31 00 - WATER SOFTENERS, CATION-EXCHANGE (SODIUM CYCLE)

23 01 30.41 - HVAC SYSTEM CLEANING

23 03 00.00 20 - BASIC MECHANICAL MATERIALS AND METHODS

23 05 15 - COMMON PIPING FOR HVAC

23 05 48.19 - BRACING FOR HVAC

23 05 93 - TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 - THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 08 00 - COMMISSIONING OF MECHANICAL AND PLUMBING SYSTEMS

23 09 00 - INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 - INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

23 09 23.02 - BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING

CONTROL SYSTEMS

23 21 23 - HYDRONIC PUMPS

23 23 00 - REFRIGERANT PIPING

23 25 00 - CHEMICAL TREATMENT OF WATER FOR MECHANICAL SYSTEMS

23 30 00 - HVAC AIR DISTRIBUTION

23 64 10 - WATER CHILLERS, VAPOR COMPRESSION TYPE

23 64 26 - CHILLED WATER PIPING SYSTEMS

23 81 00 - DECENTRALIZED UNITARY HVAC EQUIPMENT

23 82 00.00 20 - TERMINAL HEATING UNITS

23 83 00.00 20 - ELECTRIC SPACE HEATING EQUIPMENT

F. Electrical Engineer :

The Engineer noted below is only responsible for the following specifications.

Truman G. Rogers, State of Florida, Professional Engineer, License No. 90744.

This item has been digitally signed and sealed by Truman G. Rogers on the date adjacent to seal. Printed copies of this document are not considered signed and sealed and the signature code must be verified on any electronic copies.

25 05 11 - CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS FIRE ALARM

REPORTING SYSTEM/MASS NOTIFICATION SYSTEM BUILDING LEVEL ONLY

25 08 10 - 6UTILITY MONITORING AND CONTROL SYSTEM TESTING

25 10 10 - UTILITY MONITORING AND CONTROL SYSTEM (UMCS) FRONT END AND

INTEGRATION

26 05 19.00 10 - INSULATED WIRE AND CABLE

26 05 48 - SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT

26 05 73 - POWER SYSTEM STUDIES

26 08 00 - APPARATUS INSPECTION AND TESTING

26 20 00 - INTERIOR DISTRIBUTION SYSTEM

26 29 23 - ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS UNDER 600 VOLTS

26 35 44 - 270 VDC SOLID STATE CONVERTER

26 36 23 - AUTOMATIC TRANSFER SWITCHES AND BY-PASS/ISOLATION SWITCH

26 41 00 - LIGHTNING PROTECTION SYSTEM

26 42 13 - GALVANIC (SACRIFICIAL) ANODE CATHODIC PROTECTION (GACP) SYSTEM

26 51 00 - INTERIOR LIGHTING

26 56 20 - AIRFIELD AND HELIPORT LIGHTING AND VISUAL NAVIGATION AIDS

27 10 00 - BUILDING TELECOMMUNICATIONS CABLING SYSTEM

33 71 02 - UNDERGROUND ELECTRICAL DISTRIBUTION

DOCUMENT 00 01 07 Page 5 Friday January 17, 2025 Version 0

NOT FOR

CONSTRUCTION

33 82 00 - TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

GENERAL CONTRACT ITEMS, NOT ASSIGNED/SORTED

01 10 00 - SUMMARY OF WORK

01 14 16 - COORDINATION WITH FLORIDA AIR NATIONAL GUARD

01 23 00 - OPTIONAL LINE ITEMS (OLI's)

01 31 00 - PROJECT MANAGEMENT AND COORDINATION

01 31 13 - SPECIAL PROJECT PROCEDURES

01 32 00 - CONSTRUCTION PROGRESS DOCUMENTATION

01 32 33 - PHOTOGRAPHIC DOCUMENTATION

01 33 00 - SUBMITTAL PROCEDURES

01 42 00 - REFERENCES

01 77 00 - CLOSEOUT PROCEDURES

01 78 23 - OPERATION AND MAINTENANCE DATA

01 78 39 - PROJECT RECORD DOCUMENTS

01 79 00 - DEMONSTRATION AND TRAINING

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

-- End of Section --

DOCUMENT 00 01 07 Page 6

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

DOCUMENT 00 01 15

LIST OF DRAWINGS

02/24

PART 1 GENERAL

1.1 SUMMARY

1.2 CONTRACT DRAWINGS

1.3 SUPPLEMENTARY INFORMATION

1.3.1 Boring Logs

1.3.2 Subsurface Data

-- End of Section Table of Contents --

DOCUMENT 00 01 15 Page 1

DOCUMENT 00 01 15

LIST OF DRAWINGS

02/24

PART 1 GENERAL

1.1 SUMMARY

This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings and Specifications."

1.2 CONTRACT DRAWINGS

Contract drawings are as follows:

JAX INDEX OF DRAWINGS -- VOLUME 1 OF 3

DRAWING # Revision # Drawing Title Date Issued

GENERAL

G-001 COVER SHEET

G-002 INDEX OF DRAWINGS (VOLUME 1 of 3)

G-003 INDEX OF DRAWINGS (VOLUME 2 of 3)

G-004 INDEX OF DRAWINGS (VOLUME 3 of 3)

CIVIL

C-001 LEGEND AND ABBREVIATIONS

C-002 GENERAL NOTES, SAFETY AND SECURITY NOTES

VF101 EXISTING CONDITIONS PLAN

CD101 DEMOLITION PLAN

CS101 SITE PLAN

CS501 CIVIL DETAILS – 1

CS502 CIVIL DETAILS – 2

CG101 GRADING PLAN

CG121 EROSION AND SEDIMENT CONTROL PLAN

CG201 STORM DRAIN PROFILES

CG501 EROSION CONTROL DETAIL - 1

CG502 EROSION CONTROL DETAIL - 2

CU101 UTILITY LAYOUT PLAN - 1

CU102 UTILITY LAYOUT PLAN -2

CU501 UTILITY DETAILS - 1

CU502 UTILITY DETAILS - 2

DOCUMENT 00 01 15 Page 2

CU503 UTILITY DETAILS - 3

CU504 UTILITY DETAILS - 4

CU505 UTILITY DETAILS - 5

STRUCTURAL

S-001 GENERAL STRUCTURAL NOTES

S-002 GENERAL STRUCTURAL NOTES

S-003 GENERAL STRUCTURAL NOTES

S-004 SPECIAL INSPECTION SHEDULE

S-005 SPECIAL INSPECTION SHEDULE

S-006 WIND LOAD DIAGRAMS - COMPONENTS & CLADDING

S-007 WIND LOAD DIAGRAMS - COMPONENTS & CLADDING

S-008 WIND LOAD DIAGRAMS - COMPONENTS & CLADDING

S-009 WIND LOAD DIAGRAMS - COMPONENTS & CLADDING

S-010 WIND LOAD DIAGRAMS - COMPONENTS & CLADDING

S-011 WIND LOAD DIAGRAMS - COMPONENTS & CLADDING

S-101 OVERALL FOUNDATION PLAN

S-102 FOUNDATION PLAN - AREA A

S-103 FOUNDATION PLAN - AREA B

S-104 FOUNDATION PLAN - AREA C

S-105 OVERALL FLOOR SLAB PLAN

S-106 FLOOR SLAB PLAN - AREA A

S-107 FLOOR SLAB PLAN - AREA B

S-108 FLOOR SLAB PLAN - AREA C

S-109 OVERALL ROOF FRAMING - PLAN

S-110 ROOF FRAMING PLAN - AREA A

S-111 ROOF BOTTOM CHORD FRAMING PLAN - AREA A

S-112 ROOF FRAMING PLAN - AREA B

S-113 ROOF FRAMING PLAN - AREA C

S-201 STEEL FRAME ELEVATIONS

S-202 STEEL FRAME ELEVATIONS

S-203 STEEL FRAME ELEVATIONS

S-204 CMU WALL ELEVATIONS

S-205 CMU WALL ELEVATIONS

S-206 CMU WALL ELEVATIONS

S-301 BUILDING SECTIONS

S-302 BUILDING SECTIONS

DOCUMENT 00 01 15 Page 3

S-303 WALL SECTIONS

S-304 WALL SECTIONS

S-305 WALL SECTIONS

S-306 WALL SECTIONS

S-307 WALL SECTIONS

S-308 WALL SECTIONS

S-309 WALL SECTIONS

S-310 WALL SECTIONS

S-501 STANDARD CONCRETE DETAILS

S-502 STANDARD CONCRETE DETAILS

S-503 STANDARD CONCRETE DETAILS

S-504 STANDARD CONCRETE DETAILS

S-505 STANDARD CONCRETE DETAILS

S-506 STANDARD MASONRY DETAILS

S-507 STANDARD MASONRY DETAILS

S-508 STANDARD MASONRY DETAILS

S-509 STANDARD MASONRY DETAILS

S-510 STANDARD ROOF DECK & JOIST DETAILS

S-511 STANDARD ROOF DECK & JOIST DETAILS

S-512 STANDARD STEEL DETAILS

S-513 STANDARD STEEL DETAILS

S-514 STANDARD STEEL DETAILS

S-515 STANDARD STEEL DETAILS

S-516 BASE PLATE DETAILS

S-517 HANGAR AND DRAG CONNECTION DETAILS

S-518 STEEL FRAMING SECTIONS AND DETAILS

S-520 TRUSS ELEVATIONS

S-521 TRUSS ELEVATIONS

S-522 TRUSS ELEVATIONS

S-601 STEEL COLUMN SCHEDULE

S-901 3D REPRESENTATION

S-902 3D REPRESENTATION

ARCHITECTURAL

A-001 ARCHITECTURAL ABBREVIATIONS AND SYMBOLS

A-002 GENERAL NOTES

A-003 ACCESSIBILITY INFORMATION

DOCUMENT 00 01 15 Page 4

A-011 AIRCRAFT CLEARANCE REQUIREMENT PLAN

A-012 AIRCRAFT CLEARANCE REQUIREMENT SECTIONS

A-021 AIR BARRIER DIAGRAM ENCLOSURE FLOOR PLAN

A-022 AIR BARRIER ENCLOSURE SECTIONS

A-024 HANGAR BAY STRIPING FLOOR PLAN

AP001 PLANTING PLAN

AS001 SITE PLAN

A-101 FLOOR PLAN - OVERALL

A-102 FLOOR PLAN - AREA A

A-103 FLOOR PLAN - AREA B

A-104 FLOOR PLAN - AREA C

A-131 ROOF PLAN - OVERALL

A-141 REFLECTED CEILING PLAN - OVERALL

A-142 REFLECTED CEILING PLAN - AREA A

A-143 REFLECTED CEILING PLAN - AREA B

A-144 REFLECTED CEILING PLAN - AREA C

A-201 ELEVATIONS - NORTH AND SOUTH OVERALL

A-202 ELEVATIONS - EAST AND WEST OVERALL

A-203 ELEVATION - SOUTH

A-204 ELEVATION - NORTH

A-205 ELEVATIONS - EAST AND WEST

A-206 EXTERIOR ELEVATIONS - ENLARGED

A-301 BUILDING CROSS SECTION - OVERALL

A-302 BUILDING LONGITUDINAL SECTIONS - OVERALL

A-303 BUILDING CROSS SECTIONS

A-304 BUILDING CROSS SECTIONS

A-305 BUILDING LONGITUDINAL SECTIONS

A-306 BUILDING LONGITUDINAL SECTIONS

A-307 BUILDING LONGITUDINAL SECTIONS

A-311 WALL SECTIONS

A-312 WALL SECTIONS

A-313 WALL SECTIONS

A-314 WALL SECTIONS

A-321 WALL SECTION DETAILS

A-322 WALL SECTION DETAILS

A-401 ENLARGED FLOOR PLANS

DOCUMENT 00 01 15 Page 5

A-402 ENLARGED FLOOR PLANS

A-403 ENLARGED ROOF PLANS

A-405 ENLARGED MECH YARD PLANS AND ELEVATIONS

A-406 ENLARGED MECH YARD DETAILS

A-411 ENLARGED REFLECTED CEILING PLANS

A-421 INTERIOR ELEVATIONS

A-422 INTERIOR ELEVATIONS

A-423 INTERIOR ELEVATIONS

A-501 PLAN DETAILS

A-502 PLAN DETAILS

A-511 ROOF DETAILS

A-512 ROOF DETAILS

A-513 ROOF DETAILS

A-514 ROOF DETAILS

A-515 ROOF DETAILS

A-521 CEILING DETAILS

A-522 CEILING DETAILS

A-523 LIGHTING FIXTURE DETAILS

A-531 MISCELLANEOUS DETAILS

A-601 PARTITION TYPES

A-603 PARTITION DETAILS

A-604 PARTITION FRAMING DETAILS

A-605 PARTITION BACKING PLATE DETAILS

A-611 DOOR SCHEDULE AND TYPES

A-612 DOOR AND FRAME TYPES

A-613 DOOR DETAILS

A-614 DOOR DETAILS

A-615 DOOR DETAILS

A-621 WINDOW SCHEDULE AND TYPES & LOUVER SCHEDULE

A-622 TRANSLUCENT WINDOW TYPES

A-623 TRANSLUCENT WINDOW TYPES

A-624 WINDOW DETAILS

A-625 LOUVER DETAILS

A-626 TRANSLUCENT PANEL DETAILS

A-627 STOREFRONT DETAILS

A-821 MILLWORK DETAILS

DOCUMENT 00 01 15 Page 6

A-901 PERSPECTIVE VIEWS

INTERIORS

I-101 FURNITURE PLAN

I-102 FURNITURE PLAN - AREA B

I-103 FINISH FLOOR PLAN - OVERALL

I-104 FINISH FLOOR PLAN - AREA A

I-105 FINISH FLOOR PLAN - AREA B

I-106 FINISH FLOOR PLAN - AREA C

I-107 SIGNAGE PLAN - OVERALL

I-108 SIGNAGE PLAN - AREA A

I-109 SIGNAGE PLAN - AREA B

I-110 SIGNAGE PLAN - AREA C

I-501 INTERIOR FINISH DETAILS

I-601 FINISH SCHEDULE AND LEGEND

I-602 SIGNAGE SCHEDULE

I-603 SIGNAGE TYPES

I-604 SIGNAGE TYPES

I-605 SIGNAGE TYPES

JAX INDEX OF DRAWINGS - 2 VOLUME OF 3

DRAWING # Revision # Drawing Title Date Issued

GENERAL

G-001 COVER SHEET

G-002 INDEX OF DRAWINGS (VOLUME 1 of 2)

G-003 INDEX OF DRAWINGS (VOLUME 2 of 2)

FIRE PROTECTION

FL001 CODE ANALYSIS

FL101 CODE COMPLIANCE SITE PLAN

FL102 LIFE SAFETY FLOOR PLAN

FL103 LIFE SAFETY EGRESS FLOOR PLAN - OVERALL

FL104 LIFE SAFETY EGRESS FLOOR PLAN - AREA A

FL105 LIFE SAFETY EGRESS FLOOR PLAN - AREA B

FL106 LIFE SAFETY EGRESS FLOOR PLAN - AREA C

FX001 FIRE SUPPRESSION GENERAL NOTES

FX101 FIRE SUPPRESSION HAZARD CLASSIFICATION FLOOR

PLAN

FX401 FIRE SUPPRESSION ENLARGED PLANS

FA001 FIRE ALARM GENERAL NOTES

DOCUMENT 00 01 15 Page 7

FA101 FIRE ALARM FLOOR PLAN - OVERALL

FA102 FIRE ALARM FLOOR PLAN - AREA A

FA103 FIRE ALARM FLOOR PLAN - AREA B

FA104 FIRE ALARM FLOOR PLAN - AREA C

FA501 FIRE ALARM DETAILS

FA502 FIRE ALARM MATRIX

FA601 FIRE ALARM RISER DIAGRAM

PLUMBING

P-001 PLUMBING GENERAL NOTES, LEGEND AND ABBREVIATIONS

P-101 DOMESTIC WATER PLAN - OVERALL

P-102 DOMESTIC WATER PLAN - AREA A

P-103 DOMESTIC WATER PLAN - AREA B

P-104 DOMESTIC WATER PLAN - AREA C

P-105 WASTE AND VENT PLAN - OVERALL

P-106 WASTE AND VENT PLAN - AREA A

P-107 WASTE AND VENT PLAN - AREA B

P-108 WASTE AND VENT ROOF PLAN - OVERALL

P-109 COMPRESSED AIR PLAN - OVERALL

P-111 COMPRESSED AIR PLAN - AREA B

P-112 COMPRESSED AIR PLAN - AREA C

P-401 ENLARGED PLANS

P-501 PLUMBING DETAILS

P-502 PLUMBING DETAILS

P-601 SCHEDULES

P-901 DOMESTIC WATER RISER DIAGRAM

P-902 WASTE AND VENT RISER DIAGRAM

P-903 COMPRESSED AIR RISER DIAGRAM

MECHANICAL

M-001 MECHANICAL GENERAL NOTES, LEGEND AND

ABBREVIATIONS

M-101 HVAC PLAN - OVERALL

M-102 HVAC PLAN - AREA A

M-103 HVAC PLAN - AREA B

M-104 HVAC PLAN - AREA C

M-105 PIPING PLAN - OVERALL

M-107 PIPING PLAN - AREA B

M-301 HVAC SECTIONS - CWF HANGAR

DOCUMENT 00 01 15 Page 8

M-302 HVAC SECTIONS - MECH RM

M-303 HVAC SECTIONS - WEAPONS LOAD STORAGE BAY

M-304 PIPING SECTIONS

M-401 ENLARGED PLAN - AREA B

M-402 ENLARGED PLAN - AREA B

M-403 ENLARGED PLANS - MECH ROOMS

M-501 HVAC DETAILS

M-502 HVAC DETAILS

M-503 PIPING DETAILS

M-504 PIPING DETAILS

M-601 SCHEDULES

M-602 SCHEDULES

M-603 SCHEDULES

M-611 AIR FLOW DIAGRAM - AHU-1

M-612 AIR FLOW DIAGRAM - AHU-2

M-613 AIR FLOW DIAGRAM - CWF HANGAR

M-614 AIR FLOW DIAGRAM - WEAPONS LOAD STORAGE BAY

M-615 PIPING DIAGRAM - CHILLED WATER

M-620 CONTROL DIAGRAM - AHU DUAL PATH AND VAV

M-621 CONTROL POINTS - AHU DUAL PATH AND VAV

M-622 CONTROL DIAGRAM - CAV

M-623 CONTROL DIAGRAM - AHU

M-624 CONTROL DIAGRAM - FAN COIL UNIT AND SPLIT SYSTEM

M-625 CONTROL DIAGRAM - EXHAUST FANS AND CIRCULATION

FAN

M-626 CONTROL DIAGRAM - UNIT HEATER AND BUILDING

GLOBAL

M-627 CONTROL DIAGRAM - CHILLED WATER

M-628 CONTROL DIAGRAM - INDIRECT HOT WATER

ELECTRICAL

E-001 ELECTRICAL SYMBOL LEGENDS

E-002 GENERAL ELECTRICAL ABBREVIATIONS AND NOTES

EG101 GROUNDING PLAN - OVERALL

EG102 GROUNDING PLAN - AREA A

EG103 GROUNDING PLAN - AREA B

EG104 GROUNDING PLAN - AREA C

EG105 LIGHTNING PROTECTION PLAN

EG106 LIGHTNING PROTECTION PLAN - AREA A

DOCUMENT 00 01 15 Page 9

EG107 LIGHTNING PROTECTION PLAN - AREA B

EG108 LIGHTNING PROTECTION PLAN - AREA C

EG501 GROUNDING DETAILS

EG502 GROUNDING DETAILS

EG503 GROUNDING DETAILS

EG504 GROUNDING RISER DIAGRAM

EG511 LIGHTNING PROTECTION DETAILS

EL101 LIGHTING PLAN - OVERALL

EL102 LIGHTING PLAN - AREA A

EL103 LIGHTING PLAN - AREA B

EL104 LIGHTING PLAN - AREA C

EL105 ROOF LIGHTING PLAN

EL501 LIGHTING DETAILS

EL502 LIGHTING DETAILS

EL503 LIGHTING DETAILS

EL504 LIGHTING DETAILS

EL505 LIGHTING DETAILS

EL601 LIGHTING FIXTURE SCHEDULE

EL602 LIGHTING CONTROLS SCHEDULE

EP101 POWER PLAN - OVERALL

EP102 POWER PLAN - AREA A

EP103 POWER PLAN - AREA B

EP104 POWER PLAN - AREA C

EP105 MECH POWER PLAN - OVERALL

EP106 MECH POWER PLAN - AREA A

EP107 MECH POWER PLAN - AREA B

EP108 MECH POWER PLAN - AREA C

EP109 HAZARD CLASSIFICATION PLAN

EP110 HAZARD CLASSIFICATION PLAN - AREA A

EP111 HAZARD CLASSIFICATION PLAN - AREA B

EP301 HAZARD CLASSIFICATION SECTION

EP302 ELEVATION PLANS

EP401 ENLARGED POWER PLANS

EP501 POWER DETAILS

EP502 POWER DETAILS

EP601 PANELBOARD SCHEDULES

DOCUMENT 00 01 15 Page 10

EP602 PANELBOARD SCHEDULES

EP603 PANELBOARD SCHEDULES

EP604 ELECTRICAL EQUIPMENT SCHEDULE

EP610 FEEDER SCHEDULE

EP701 SINGLE LINE DIAGRAM

TELECOM

T-001 GENERAL TELECOM SYMBOLS, ABBREVIATIONS AND NOTES

T-111 TELECOM PLAN - OVERALL

T-112 TELECOM PLAN - AREA A

T-113 TELECOM PLAN - AREA B

T-114 TELECOM PLAN - AREA C

T-401 TELECOM ENLARGED PLANS

T-501 TELECOM DETAILS

T-502 CABLE TRAY DETAILS

T-503 WIRING DETAILS

T-504 TELECOM DETAILS

T-505 TELECOM DETAILS

T-601 TELECOM RISER DIAGRAM

TY001 IDS AND ESS SYSTEM NOTES

TY101 SECURITY PLAN - OVERALL

TY102 SECURITY PLAN - AREA A

TY103 SECURITY PLAN - AREA B

TY104 SECURITY PLAN - AREA C

TY501 SECURITY DOOR DETAILS

TY502 SECURITY DETAILS

DOCUMENT 00 01 15 Page 11

TY503 SECURITY RISER DIAGRAM AND SCHEDULE

1.3 SUPPLEMENTARY INFORMATION

1.3.1 Boring Logs

The Government does not guarantee that borings indicate actual conditions, except for the exact locations and the time that they were made.

Subsurface data, not specified or indicated, have been obtained by the Government at this station. The data are available for examination by prospective bidders in the office of the Contracting Officer.

1.3.2 Subsurface Data

Subsurface data, not specified or indicated, have been obtained by the Government at the station. The data are available for examination by prospective bidders in the office of the Contracting Officer The soils report is included as part of the solicitation.

-- End of Document --

DOCUMENT 00 01 15 Page 12

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 10 00

SUMMARY OF WORK

10/24

PART 1 GENERAL

1.1 SUMMARY

1.2 SUBMITTALS

1.3 PROJECT INFORMATION

1.4 WORK COVERED BY CONTRACT DOCUMENTS

1.5 ACCESS TO SITE

1.6 WORK RESTRICTIONS

1.7 EXISTING WORK

1.8 LOCATION OF UNDERGROUND UTILITIES

1.8.1 Notification Prior to Excavation

1.9 SPECIFICATION AND DRAWING CONVENTIONS

1.10 SAFETY REQUIREMENTS

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 10 00 Page 1

SECTION 01 10 00

SUMMARY OF WORK

10/24

PART 1 GENERAL

1.1 SUMMARY

A. Section Includes:

1. Submittals.

2. Project information.

3. Work covered by Contract Documents.

4. Access to site.

5. Work restrictions.

6. Existing Work.

7. Location of Underground Utilities.

8. Government Furnished Material and Equipment.

9. Salvage Material and Equipment.

10. Specification and Drawing Conventions.

11. Safety Requirements.

B. Related Requirements:

1. Section 01 50 00 TEMPORARY FACILITIES AND CONTROLS for limitations and procedures governing temporary use of Government facilities.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" classification.

Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Salvage Plan; G

1.3 PROJECT INFORMATION

A. Project Identification:

1. Project Location: Jacksonville International Airport.

SECTION 01 10 00 Page 2

B. Owner: Florida Air National Guard.

1. Contracting Officer's Representative (COR):

Pending Appointment 14300 FANG Drive, Building 28 Jacksonville, Florida 32218-7933

(904) 741-7601

C. Architect/Engineer:

Parsons 6100 Bandera Road, Suite 800 San Antonio, Texas 78238 210 227 2500

1.4 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and consists of the following:

1. Site grading/preparation for new facility and paving.

2. Extension of existing utilities to serve new building.

3. Construction of new facility

4. Revisions/additions to existing perimeter fencing to accommodate new building and access/gate.

B. Type of Contract:

1. Project will be constructed under a single prime contract.

2. Contractor will be responsible for requesting proposal from Johnson Controls for Work associated Metasys controls system.

Contractor shall also be responsible for all costs and coordination required with installation/extension of Johnson Controls Metasys system. Johnson Controls, Inc. contact:

Johnson Controls, Inc.

8245 Bayberry Road Jacksonville, Florida 32256 brad.e.tepper@jci.com

(904) 732-5449

1.5 ACCESS TO SITE

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

A. General: Employees will be required to submit necessary information to obtain entry access badges. Access to building while on-site will be per Florida Air National Guard regulations and may require escort(s).

B. Use of Site: Limit use of Project site to work in areas indicated.

Do not disturb portions of Project site beyond areas in which the

SECTION 01 10 00 Page 3

Work is indicated.

1. Limits: Coordinate construction operations with Contracting Officer's Representative (COR).

C. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weather tight condition throughout construction period. Repair damage caused by construction operations.

1.6 WORK RESTRICTIONS

A. Work Restrictions, General: Comply with restrictions on construction operations.

1. Comply with Government's limitations on use of facilities and with other requirements of authorities having jurisdiction.

B. On-Site Work Hours: Limit work to normal business working hours of 7:00 a.m. to 4:15 p.m., Monday through Friday, unless otherwise indicated.

1. Weekend Hours: Only if approved by Contracting Officer's Representative (COR) 48 hours prior to the Work.

C. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise, vibration, odors, or other disruption to Government.

1. Notify Contracting Officer's Representative (COR) not less than two days in advance of proposed disruptive operations.

2. Obtain Government permission before proceeding with disruptive operations.

D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor-air intakes.

E. Employee Identification: Provide identification tags for Contractor personnel working on Project site. Require personnel to use identification tags at all times.

F. Employee Screening: Comply with Government's requirements for drug and background screening of Contractor personnel working on Project site.

1. Maintain list of approved screened personnel with Contracting Officer's Representative (COR).

1.7 EXISTING WORK

Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed

SECTION 01 10 00 Page 4 before new work started.

1.8 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.

Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.

Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities or utilities encased in pier structures are discovered. Verify the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.8.1 Notification Prior to Excavation

Notify the Contracting Officer at least 15 days prior to starting excavation work.

1.9 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations published as part of the U.S. National AUTOCAD 2020 2020 Standard and scheduled on Drawings.

SECTION 01 10 00 Page 5

3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.

1.10 SAFETY REQUIREMENTS

A. The Contractor shall provide and maintain all necessary fences, barriers and other reasonable safeguards required to ensure the safety of all personnel.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 10 00 Page 6

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 10 50.01

HAZARDOUS MATERIALS PROCEDURES

10/24

PART 1 GENERAL

1.1 SUMMARY OF WORK

1.2 SUPPLEMENTS

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

-- End of Section Table of Contents --

SECTION 01 10 50.01 Page 1

SECTION 01 10 50.01

HAZARDOUS MATERIALS PROCEDURES

10/24

PART 1 GENERAL

1.1 SUMMARY OF WORK

A. A key element to the Pollution Prevention program at the 125th Fighter Wing is the control of Hazardous Material (HM). To control HM use, a Hazardous Materials Pharmacy (HAZMART) program has been fully implemented within the installation. The HAZMART focuses on source reduction as the preferred method of pollution prevention.

Control of HM includes reducing the number of types and amounts of HM used, and controlling its proper distribution, storage, use, and disposal. The Contractor shall comply with all Federal, state and local Environmental Management System (EMS) environmental standards.

B. Contractor shall establish Hazardous Material (HM) storage and distribution system when HM is to be used.

1. All HM required to support the contract shall be reported to the Hazardous Material Pharmacy (HMP) using the Construction Hazardous Materials Submittal Form in attachment 1 of this specification section.

2. Contractor Construction Hazardous Materials Submittal Form will be provided to the Contractor at or prior to the Pre-Construction meeting.

3. All hazardous materials must be approved by the Installation Hazardous Materials Management Team prior to being brought on base.

4. Additional HM needed by the Contractor shall be identified to the Contracting Officer's Representative (COR) for approval by the

HMP.

C. Contractor shall register the installation HMP prior to start of work using Construction Hazardous Materials Submittal Form in order to support the installation's compliance with Executive Order 12856, Federal Compliance with Right-to-Know Laws and Pollution Prevention Requirements.

D. Contractor shall maintain a Construction Hazardous Materials Submittal Form for all HM on the job site for inspection/verification.

E. Contracting Officer's Representative (COR) will verify that the HM identified to the HMP is the only HM in use on the job site.

F. Contractor shall provide the following to the HMP:

1. A list of each material and quantity of material for all proposed HM. Hazardous Material (HM) shall be construed to mean any item that is:

SECTION 01 10 50.01 Page 2

a. A health hazard or physical hazard as defined in 29 CFR, 1910.1200(c).

b. Regulated in its disposal by federal Environmental Protection Agency (EPA) under 40 CFR.

c. Hazardous as defined by federal Department of Transportation (DOT) regulations under 49 CFR.

d. Hazardous as defined by the Dangerous Goods Regulations of the International Air Transport Association.

2. All material safety data sheet (MSDS) for each item on the HM list. This listing shall also be provided electronically by individual MSDS for processing prior to work beginning. These MSDS shall also be maintained in a Binder within the Job Trailer or wherever the construction project is headquartered out of.

3. Examples of hazardous materials used on the job site include, but are not limited to:

a. Petroleum based liquids/gases (gasoline, kerosene, diesel, propane, butane, acetylene, etc.).

b. Adhesives and glues.

c. Shot charges for anchor systems.

d. Volatile solvents (such as PVC cleaner and glues, paint thinners).

e. Non-water-based paints.

f. Liquid sealants.

g. Epoxies and coating systems.

h. Acidic or alkali cleaners.

G. Contractor shall establish a construction-specific HM storage and issue location that fully complies with federal, state and local environmental regulations.

1. Materials issued shall be tracked for quantities used.

2. Unused materials shall be inventoried and removed from Base property prior to close-out of the contract or expiration date of the HM.

3. Reports of materials delivered, used and removed from the installation shall be submitted to the Contracting Officer's Representative (COR) monthly and prior to contract close- out.

H. Contractor shall accompany the Contracting Officer's Representative (COR) and the installation Environmental Manager (EM) on project close-out inspection to ensure all used and unused HM has been removed from the installation. This requirement shall not be a punch list item and must be accomplished prior to the

SECTION 01 10 50.01 Page 3 government accepting Full Mission Simulator (FMS) Occupancy of the facility or construction item. (See Attachment 2.)

1.2 SUPPLEMENTS

A. The supplements listed below, following "End of Section," are part of this specification.

1. Contractor Hazardous Material Identification Form.

2. Contractor Hazardous Material Identification Form Close-Out Procedures.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

-- End of Section --

SECTION 01 10 50.01 Page 4

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 14 16

COORDINATION WITH FLORIDA AIR NATIONAL GUARD

10/24

PART 1 GENERAL

1.1 SUMMARY

1.2 SECURITY

1.3 SAFETY AND PROTECTION OF WORK AND EXISTING PROPERTY

1.4 USE OF PREMISES

1.5 SECURITY PLAN

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 14 16 Page 1

SECTION 01 14 16

COORDINATION WITH FLORIDA AIR NATIONAL GUARD

10/24

PART 1 GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Security.

2. Safety and Protection of Work and Existing Property.

3. Use of Premises.

4. Government Occupancy.

5. Security Plan.

1.2 SECURITY

A. The Contractor is responsible for all construction permit and fees that are required. Additional requirements will be discussed at the Pre-Construction Conference. The secure entrance to the site shall be the main entry on FANG Drive.

The Contractor shall comply with all components of the Construction Security Plan (CSP) available upon request.

All construction materials will be purchased from US companies.

All materials will be secured at the construction site and will be under surveillance of SFS roving patrols. APO security personnel will conduct periodic inspections of the construction site and construction materials.

All construction workers will be checked and vetted through the 125FW SFS prior to being allowed entry onto the installation. No security clearances will be issued.

The construction site will be secured with fencing and gates locked with cipher or medium/high security lock, only allowing authorized contractors to enter the construction area. During normal duty hours, contractors and 125FW CE personnel are responsible for maintaining security of the construction site.

After duty hours, the 125FW SFS will maintain security of the construction site.

The 125FW SFS will maintain a list of construction workers' names and visitors names and will ensure they are registered and tracked upon entry to the base. The 125FW SFS will document security incidents at the construction site and will report such incidents for mitigation.

1.3 SAFETY AND PROTECTION OF WORK AND EXISTING PROPERTY

A. General:

1. The Contractor shall take all reasonable steps to prevent injury to persons (including employees) and property in

SECTION 01 14 16 Page 2 performance of this Contract, including all steps and actions required under safety provisions of applicable laws and construction codes.

B. Work Performance:

1. Contractor shall provide for the safety and protection of the Work at all times. Contractor shall provide protection at all times against rain, wind, storms, and condensation or heat so as to maintain all work, equipment and materials free from injury or damage. At the end of each day, all new work likely to be damaged shall be protected and covered.

2. Contracting Officer's Representative (COR) shall be notified immediately at any time operations are stopped due to conditions which make it impracticable to continue operations safely or to obtain proper results.

C. Existing Property:

1. Contractor shall provide for the safety and protection of existing property at all times. Any damage to existing facilities resulting from construction operations shall be reported immediately to the Contracting Officer's Representative (COR) and promptly repaired, subject to the approval of the Contracting Officer's Representative (COR), by the Contractor at no additional cost to the Government.

2. The applicable requirements specified for protection of the Work shall also apply to the protection of existing property.

3. Before acceptance of the Work by the Contracting Officer's Representative (COR), Contractor shall restore all property affected by its operation to the original or better conditions.

1.4 USE OF PREMISES

A. Coordinate the use of premises under direction of Contracting Officer's Representative (COR) and his duly authorized representative. The Contractor shall provide security information on all on-site workers (as directed by the Contracting Officer's Representative (COR)) in advance of any workers being allowed to enter the site.

1.5 SECURITY PLAN

A. Contractor shall ensure that all rules and regulations that pertain to safety and security are strictly adhered to at all time that Work is conducted.

B. Identification requirements pertaining to the site will be discussed at the Pre-Construction Conference. Construction workers will be subject to lunchbox/tool box inspections. Access gate will be the main entry to the site for entry and exit for all construction personnel.

C. Vehicle passes, if allowed, will be issued by the Government on an as-needed basis only. Vehicles found to be violating safety procedures (speed limits, etc.) may not be allowed re-entry from

SECTION 01 14 16 Page 3 date of violation.

D. Contractor shall provide Contracting Officer's Representative (COR) and the Florida Air National Guard Security Representatives 24 hour notice for overtime work during regular workdays.

Contractor shall request permission from the Contracting Officer's Representative (COR) 48 hours in advance of any work on Saturdays, Sundays or holidays.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

SECTION 01 14 16 Page 4

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 23 00

OPTIONAL LINE ITEMS (OLI's)

10/24

PART 1 GENERAL

1.1 SUMMARY

1.2 DEFINITIONS

1.3 PROCEDURES

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 SCHEDULE OF OPTIONAL LINE ITEMS (OLI's)

-- End of Section Table of Contents --

SECTION 01 23 00 Page 1

SECTION 01 23 00

OPTIONAL LINE ITEMS (OLI's) 10/24

PART 1 GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for bid options (Optional Line Items or OLIs).

1.2 DEFINITIONS

A. Bid Options (OLI): An amount proposed by bidders and stated on the Bid Form for certain work defined in the bidding requirements that may be added to or deducted from the base bid amount if Government decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents.

1. Bid Options (OLI) described in this Section are part of the Work only if enumerated in the Agreement.

2. The cost or credit for each bid option (OLI) is the net addition to or deduction from the Contract Sum to incorporate bid option (OLI) into the Work. No other adjustments are made to the Contract Sum.

1.3 PROCEDURES

A. Coordination: Revise or adjust affected…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .