This document is a Task Group Instruction (TGI) for the USS Blue Ridge (LCC-19) detailing a specific maintenance task for the Main Circulation Pump Suction Valve MSW-E1. The work involves installing an indicator and collar for a 28-inch gate valve manufactured by Anchor/Darling Valve Co., located in the ship's Engine Room (Zone 8-86-0-E). Key technical specifications include a carbon steel collar (ASTM A108), an indicator to be engraved with "OPEN" and "CLOSED", and a stem extension, with specific fabrication requirements such as thread inspections per ASTM F788/F812 and using a Monel set screw.
The task is scheduled for execution between January 12, 2026, and May 15, 2027, at Commander, Fleet Activities Yokosuka (CFAY) Naval Base in Japan. The SRF-JRMC (Shore Repair Facility - Japan Regional Maintenance Center) will provide government-furnished materials and support services including crane rigging, utility services (electrical, water, steam, air), and quality assurance inspections. The work is part of a larger maintenance package for the USS Blue Ridge, with the TGI serving as a detailed technical instruction for precise valve component installation.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
30-SEP-2024 1447
20.14.15.2.9020 (September 2024) ICN: 3819P25604 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: MSW-E1 V- A 0 1/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 25611
CU PHASE TITLE: F/O INSTALL INDICATOR AND COLLAR FOR MN CIRC PUMP SUCTION VALVE MSW-E1, 8-86-0-E
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 5
EM01L190
PREPARING ACTIVITY: STATUS: APP WORKING STATUS: PKG
PREPARED BY: CODE: PHONE: DATE:
FUNAKI, TAKASHI 232 3152432494 19-SEP-2024
APPROVED BY: CODE: PHONE: DATE:
OIKAWA, KAZUYUKI 232 3152435615 30-SEP-2024
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
EM01-L190
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA, TAKEHIDE 8-86-0-E U
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
256A1104
1. SCOPE/PURPOSE:
1.1 Title: Indicator and Collar for Main Circ Pump Suction Valve MSW-E1; install
1.2 Location of Work:
1.2.1 Engine Room (8-86-0-E)
1.2.2 Contactor Shop
1.3 Identification:
1.3.1 Quantity (One EA), Main Circ Pump Suction Valve MSW-E1
Mfr: Anchor/ Darling Valve Co.
Mfr Id: 1S473-5D Size: 28 Inch IPS Type: Gate, Flanged
TGI Short Form
30-SEP-2024 1447
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P25604 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: MSW-E1 V- A 0 1/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 25611
CU PHASE TITLE: F/O INSTALL INDICATOR AND COLLAR FOR MN CIRC PUMP SUCTION VALVE MSW-E1, 8-86-0-E
FOUO Pg 2 of 5
CU PHASE DESCRIPTION (Cont.)
Pressure: 30 PSI
1.3.1.1 Quantity (One EA), Collar
Material: Carbon Steel, ASTM A108 Remarks: See Engineering Instruction Enclosure-01 for detail, Item No. 25 of Ref. No.4
1.3.1.2 Quantity (One EA), Indicator
Remarks: See Item No.20 of Ref. No. 4 for detail
1.3.1.3 Quantity (One EA), Indicator Nut
Remarks: See Item No.21 of Ref. No. 4 for detail
1.3.1.4 Quantity (One EA), Stem, Extension
Remarks: See Item No.33 of Ref. No. 4 for detail
1.4 Security Classification: None.
1.5 Initial Condition: None.
1.6 Contractor work start date:
1.7 Contractor work completion date:
2. PROCEDURE:
2.1 Accomplish the requirements for fabrication and installation of the equipment listed in 1.3.1.1 through 1.3.1.4 in accordance with Enclosure-01, Ref. No. 3 and Ref. No. 4.
2.1.1 Engrave letters “OPEN” and “CLOSED” on the indicator listed in 1.3.1.2, using Item No. 20 of Ref. No. 4 for guidance.
2.1.2 Accomplish the following inspection and check for fabricated threaded area.
2.1.2.1 Accomplish a visual inspection of thread in accordance with ASTM F788 or F812.
2.1.2.2 Accomplish a thread dimensional check, using System 21 gage of ASME B1.3-2007 and Paragraph 075-2.3.2.5.3 of Ref. No. 5 for guidance.
2.1.3 Drill and thread on tip of valve stem in accordance with Item No. 5 of Ref. No. 4.
2.1.4 Fix indicator assembly with Monel set screw instead of brass screw.
2.2 Notes:
2.2.1 Planner: Code 232 T. Funaki, 243-2494
Engineer: Code 260 T. Ito, 243-4173
2.2.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
2.2.3 JCN EM02-L190 is related to this TGI.
1/12/2026
5/15/2027
30-SEP-2024 1447
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P25604 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: MSW-E1 V- A 0 1/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 25611
CU PHASE TITLE: F/O INSTALL INDICATOR AND COLLAR FOR MN CIRC PUMP SUCTION VALVE MSW-E1, 8-86-0-E
FOUO Pg 3 of 5
CU PHASE DESCRIPTION (Cont.)
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
2.3 Government Furnished Material (GFM):
2.3.1 SRF-JRMC will provide GFM listed in the material list.
2.4 SRF-JRMC will provide the following service work: (TGI No. 3819P25604S02).
2.4.1 [C740] Crane and crane rigging service.
2.4.2 [X99E] Utility service, electrical.
2.4.3 [X99M] Utility service, including water supply steam supply and low-pressure air supply.
2.4.4 [C106.1] Safety inspection for SRF-JRMC employees.
2.4.5 [C106.2] Gas free inspection for SRF-JRMC employees.
2.4.6 [C133] QA inspection for (G) Symbol (s).
30-SEP-2024 1447
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P25604 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: MSW-E1 V- A 0 1/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 25611
CU PHASE TITLE: F/O INSTALL INDICATOR AND COLLAR FOR MN CIRC PUMP SUCTION VALVE MSW-E1, 8-86-0-E
FOUO Pg 4 of 5
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N
3 DWG 209-2492117 MAIN CIRC SYSTEM ARRGT F - Y ALL
4 DWG 1S-473-5 28" - 30# GATE VALVE NRS
CAST BRONZE FLANGED
BEVEL GEAR OPERATED MN
CIRC PMP
G - Y ALL
5 TM S9086-CJ-STM-
010/CH-075
Fasteners 7 - N
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
2.1 OMCH HRs, IMCH HRs 22/KE PC N
Machinery Work CFM for consumable, tape, abrasion, lubricant, degreaser and MISC.
22/MQ CS N
Process Funding Document 10/CT OM N
Version-1: Admin change C232 K. Oikawa, 9/30/2024 Y/Y/N / V-01 N
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
001 M BAR,METAL, FOR KTR
DWG: 1S-473-5, PC#25
C232 T.FUNAKI
243-2494
9B 9510 008135341 NA 4 N 1/FT
002 M SETSCREW, FOR KTR
DWG: 1S-473-5, FOR COLLAR
PC NO.25
C232 T.FUNAKI
243-2494
9B 5305 008176139 NA 4 N 4/EA
003 M BAR,METAL, FOR KTR
DWG: 1S-473-5, PC#20 & 21
CONTINUOUS LENGTH IS
REQUIRED.
C232 T.FUNAKI
243-2494
9B 9530 001671938 NA 4 N 2/FT
004 M BAR,METAL, FOR KTR
DWG: 1S-473-5, PC#33
C232 T.FUNAKI
243-2494
9B 9530 002394460 NA 4 N 1/FT
ATTACHMENT LIST
TITLE FILE NAME SAVED DATE
ENCLOSURE-01 3819P25604A01 Engrg Inst.pdf 20-SEP-2024 0000
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 3819P25604 KEY OP: A01
30-SEP-2024 1447
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P25604 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: MSW-E1 V- A 0 1/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 25611
CU PHASE TITLE: F/O INSTALL INDICATOR AND COLLAR FOR MN CIRC PUMP SUCTION VALVE MSW-E1, 8-86-0-E
FOUO Pg 5 of 5
3819P25604A01
4--}-20UNF-38
DETAIL 1-A, COLLAR
SCALE: 12" = 1'-0"
FINISH: 12'1 ALL OVER
BREAK ALL SHARP EDGES & CORNERS
Sheet _1_ OF _1_
ENGRG INST
Enclosure-01
Takashi.Funaki.ja Pencil
File details come from the government source that posted it. Updated .