TGI_3819P12303A01_c1v0.pdf

PDF 246 KB Posted

Attached to
USS BLUE RIDGE 5C1 DSRA TYCOM 3 (YOKOSUKA, JAPAN)
Solicitation number
N6264925RA024
Issued by

About this file

This Task Group Instruction (TGI) details maintenance and repair work for the USS Blue Ridge's Distillate Fuel Service tank (7-82-2-F). The scope of work includes comprehensive cleaning, inspection, repair, and preservation of the fuel service tank, with specific requirements including visual inspection of existing preservation coating, marking corroded or damaged areas, general cleaning at Level II, and multiple repair tasks such as welding, grinding, and plate replacements.

Key technical requirements involve repairing a total of one linear foot of deteriorated welds, base metal weld buildup of 60 square inches, removal and installation of 10 square feet of deteriorated plate, and 4 linear feet of defective stiffener. The work also includes power tool cleaning of interior and exterior surfaces, partial coating removal, and surface preparation. The project is scheduled for contractor work from January 12, 2026, to May 15, 2027, and will be performed at Commander, Fleet Activities Yokosuka Naval Base in Japan, with specific safety and fire zone boundary considerations noted in the instruction.

View the file

Other files

File Type Posted
EXHIBIT - Contract Data Requirements List (CDRL)_R2.pdf PDF
TGI_3819P25502_A01_c0v0_FY26.pdf PDF
TGI_3819P22102_A01_c0v0_FY26.pdf PDF
TGI_3819P22101_A01_c0v0_FY26.pdf PDF
TGI_3819P14207_A01_c1v2_FY26.pdf PDF
TGI_3819P14205A01_c2v2_FY26.pdf PDF
TGI_3819P14116A01_c0v0_FY26.pdf PDF
TGI_3819P14114A01_c0v0_FY26.pdf PDF
TGI_3819P14113A01_c0v0_FY26.pdf PDF
TGI_3819P13505A01_c0v0_FY26.pdf PDF
TGI_3819P13411A01_c1v1_FY26.pdf PDF
TGI_3819P13339A01_c0v0_FY26.pdf PDF
TGI_3819P12352A01_c1v0_FY26.pdf PDF
TGI_3819P12350A01_c0v0_FY26.pdf PDF
TGI_3819P12347_A01_c0v0_FY26.pdf PDF
TGI_3819P12346_A01_c0v0_FY26.pdf PDF
TGI_3819P12343A01_c1v1_FY26.pdf PDF
TGI_3819P12329A01_c1v1_FY26.pdf PDF
TGI_3819P12326_A01_c1v0_FY26.pdf PDF
TGI_3819P12325_A01_c0v01_FY26.pdf PDF
TGI_3819P12308A01_c0v0_FY26.pdf PDF
TGI_3819P12307A01_c0v0_FY26.pdf PDF
Attachment V Contract Data Sheet.pdf PDF
TGI_3819P23103_A03_c0v0.pdf PDF
TGI_3819P22102_T01_c0v0.pdf PDF
TGI_3819P14208T01_c0v0.pdf PDF
TGI_3819P14208A01_c1v1.pdf PDF
TGI_3819P14122A01_c0v0.pdf PDF
TGI_3819P14121A01_c0v0.pdf PDF
TGI_3819P13422A01_c0v0.pdf PDF
TGI_3819P13411A01_c1v1.pdf PDF
TGI_3819P12351A01_c0v0.pdf PDF
TGI_3819P12350A01_c0v0.pdf PDF
TGI_3819P12347_A01_c0v0.pdf PDF
TGI_3819P12345_A01_c1v3.pdf PDF
TGI_3819P12332A01_c1v1.pdf PDF
TGI_3819P12327_A01_c1v1.pdf PDF
TGI_3819P12324_A01_c2v1.pdf PDF
TGI_3819P12313A01_c0v0.pdf PDF
Attachment VIII Source of Repair Instruction.pdf PDF
Attachment II Price Proposal Form N6264925RA024.xlsx XLSX spreadsheet
TGI_3819P25502_A01_c0v0.pdf PDF
TGI_3819P22101_T09_c0v0.pdf PDF
TGI_3819P14208T02_c0v0.pdf PDF
TGI_3819P14204A01_c0v0.pdf PDF
TGI_3819P13507A01_c0v0.pdf PDF
TGI_3819P13505A01_c0v0.pdf PDF
TGI_3819P12389A01_c0v0.pdf PDF
TGI_3819P12360A01_c0v0.pdf PDF
TGI_3819P12359_A01_c0v0.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

FOUO: Public availability to be determined under 5 USC 552

TASK GROUP INSTRUCTION

AIM REV 20.11.4.0 (OCTOBER 2020)

TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:

NO.: DFS TK 7-82-2-F AY A 0 1

SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE:

F/O - CLEAN, INSPECT, REPAIR, AND PRESERVE DISTILLATE FUEL SERVICE (7-82-2-F)

PREPARING ACTIVITY:

PREPARED BY: CODE PHONE DATE

KENICHIRO ISHIKAWA 231B. 315-243-2479 21-FEB-2024

APPROVED BY: CODE PHONE DATE

RYOUTA TAKAGI 231B. 315-243-4502 21-FEB-2024

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

REASON FOR WORK/NEED FOR CHANGE:

(V)(I) symbols of paragraph 5.7 are not required.

CHANGE INSTRUCTIONS:

CH1: delete unnecessary (V)(I) symbols in paragraph 5.7. (8/28/2024)

SPECIAL REQUIREMENTS:

CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL II

SURFMEPP

This work Affects a fire zone boundary. Fabrication and/or staging of a non-flammable closure is required.

WORK CERTIFICATION SIGNATURES

COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:

ACCEPTANCE OF COMPLETED WORK

PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:

REQUIRED:☐YES ☒NO

RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:

TGI NO.: DFS TK 7-82-2-F AY A 0

FOUO

SHIP: LCC-19 CHG/VER: 1/0

LIST OF EFFECTIVE PAGES

SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.

1-5 J1-2 M-1

1. SCOPE/PURPOSE

1.1 Title: Distillate Fuel Service (7-82-2-F); clean, inspect, repair, and preserve

1.2 Location of Work:

1.2.1 Distillate Fuel Service (7-82-2-F)

1.2.2 B Division Storeroom (6-76-2-A)

1.3 Identification:

1.3.1 Quantity (One EA), Distillate Fuel Service

Tank No.: 7-82-2-F Capacity: 8,890 Gallons

1.3.2 Quantity (2 EA), Manhole Cover Plate(s) for 7-82-2-F

Manhole No(s).: 6-82-2 and 6-85-2 Size: 15 Inches x 23 Inches Material: Steel

1.3.3 Quantity (2 EA), Bolting Ring for Manhole Cover Plate(s) for 7-82-2-F Manhole No(s).: 6-82-2 and 6-85-2 Material: Steel

1.4 Security Classification: None.

1.5 Initial Condition:

1.5.1 Potential Lead Hazard

1.6 Contractor work start date:

1.7 Contractor work completion date:

2. REFERENCES:

REF.

NO.

DOCUMENT

/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV CHG

NO.

COPY

REQ’D

(Y/N)

SOURCE

DOC

(Y/N)

PARA SEC PG CHP

1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N

3 TM S9086-

CJ-STM-

010/CH-075

Fasteners 7 N

1/12/2026

5/15/2027

FOUO

SHIP: LCC-19 CHG/VER: 1/0

REF.

NO.

DOCUMENT

/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV CHG

NO.

COPY

REQ’D

(Y/N)

SOURCE

DOC

(Y/N)

PARA SEC PG CHP

4 DWG 100-

2491003

SHELL PLTG & STGR FRAME 51

1/2 -102 1/4 CL TO 4 TH DECK

G Y AL

L

5 DWG 101-

2491023

WEBS FR 77 1/2,79,81,83&84 1/2 H Y AL

L

6 DWG 114-

2491162

Wing Tank BHD FR76-98 D Y AL L

7 DWG 103-

2491033

2 PLATF FR 52-98 J Y AL

L

8 DWG 103-

2491036

1ST PLATF PLTG FR 52-98 G Y AL

L

9 DWG 114-

2491157

TRANSV BHD FR 76 & 86 N Y AL

L

10 NSI 220-

018B

Fuel Oil Tank Coating Condition Conversion to P10 After Partial Coating

02 Y AL

L

3. APPENDICES:

3.1 Appendix “J” TGI Job Summary Information Sheet

3.2 Appendix "M" TGI Material List

3.3 Appendix “D” Deficiency Form

4. GENERAL REQUIREMENTS:

4.1 Not Applicable.

5. PROCEDURE:

5.1 Accomplish the requirements of 099-902YO of 2.2 for each tank listed in 1.3.1.

5.1.1 Accomplish a visual inspection of each tank listed in 1.3.1 for existing preservation coating.

5.1.1.1 Mark each corroded, damaged and/or deteriorated coating area in each tank.

5.1.1.2 Submit one legible copy, in hard copy or approved transferrable media, of a report with a sketch listing results of the requirements of 5.1.1.1 to the SUPERVISOR.

5.1.2 Accomplish the requirements of 009-107 of 2.1.

5.1.2.1 Accomplish the requirements of 009-09 of 2.1.

5.1.2.2 Ensure General Cleaning must be Level II.

5.1.3 Accomplish installation of each manhole cover for each tank listed in 1.3.1 in accordance with Figure 075-4-1 of 2.3.

5.2 Weld fill, drill, and tap a total of 10 each stripped manhole cover bolting ring holes for each tank listed in 1.3.1 as designated by the SUPERVISOR. See 5.9.5.

5.2.1 Accomplish the requirements of 009-12 of 2.1, including Table 2, Column A, Lines One through 7.

5.3 Repair each tank listed in 1.3.1, based on the CCIMS assessment report as designated by the SUPERVISOR, using 2.4 through 2.9 for guidance. See 5.9.4 through 5.9.6.

FOUO

SHIP: LCC-19 CHG/VER: 1/0

5.3.1 Vee-out and weld a total of one linear foot of each deteriorated and damaged weld. Each area of repair must include deck, bulkhead, shell plating, and overhead.

5.3.2 Chip and grind each surface flush in way of each repair.

5.3.3 Base metal weld buildup a total of 60 square inches of each plate defect in the tank.

5.3.3.1 For bidding purposes the base metal weld buildup must be one quarter inch thick.

5.3.3.2 Surface must be ground to sound metal prior to base metal weld buildup.

5.3.3.3 Fill each local pit and groove with weld material prior to application of each principal build up layer.

5.3.3.4 Grind each surface of completed base weld metal buildup smooth if greater than 1/8 inch above plate surface.

5.3.4 Remove existing, fabricate, and install new a total of 10 square feet of deteriorated plate.

5.3.5 Remove existing, fabricate, and install new a total of 4 linear feet of defective stiffener.

5.3.6 Accomplish the requirements of 009-12 of 2.1, including Table 2, Columns A, Lines One through 7.

5.3.6.1 Accomplish nondestructive testing in accordance with Line 11.

5.3.7 Accomplish the requirements of 009-25 of 2.1 for an air hose, water hose, or vacuum box test of each new insert weld seam. Allowable leakage: None.

5.4 Accomplish the requirements of 009-32 of 2.1 for interior surface of each tank listed in 1.3.1 where new material is installed and disturbed by hot work repaired in 5.2 and 5.3.

5.4.1 Power tool clean for interior surface of each tank to remove all rust and corrosion.

5.4.1.1 Light coat of system fluid must be wiped over the surface prior to closing. See 5.9.7.

5.5 Accomplish the requirements of 009-32 of 2.1, including Table 3, Line(s) 25, for storeroom side surface of each cover plate listed in 1.3.2.

5.5.1 Power tool clean for tank side surface of each cover plate to remove all existing coating, rust, and corrosion.

5.5.1.1 Light coat of system fluid must be wiped over the surface prior to closing. See 5.9.7.

5.6 Accomplish the requirements of 009-32 of 2.1 for each bolting ring listed in 1.3.3.

5.6.1 Power tool clean to remove all existing coating, rust, and corrosion.

5.6.1.1 Light coat of system fluid must be wiped over the surface prior to closing. See 5.9.7.

5.7 Accomplish the requirements of general notes 2 and 6 and surface preparation process one through 4 of 2.10 for a total 145 square feet of partial coating removal area of each tank listed in 1.3.1 as determined by the visual inspection in 5.1.1 as designated by the SUPERVISOR. See 5.9.7.

5.8 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.

5.9 Notes:

FOUO

SHIP: LCC-19 CHG/VER: 1/0

5.9.1 Planner: Code 231B K. Ishikawa, 243-2479

Engineer: Code 250 S. Fujita, 243-4307

5.9.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598

5.9.3 This TGI meets the intent of DDG CSWT File Nos. 123-094, 123-133, and 123-142.

5.9.4 CCIMS assessment of each tank listed in 1.3.1 will be accomplished by SRF-JRMC (TGI No. 3819P12303I01), and the Project team will provide the assessment report with engineering evaluation under DL process for front loading structure repair.

5.9.5 Removal and installation of interferences, and gas free operation, preservation of boundary spaces relating to front loading structure repair are not included in this TGI. They will be covered by a DL in the future based on Contractor submitted condition report.

5.9.6 Materials for structure members relating to front loading repair will be provided in the future as a DL based on Contractor submitted condition report.

5.9.7 Ship’s Force will provide system fluid for contractor when requested by Code 333 Work Integration Manager

(WIM).

5.9.8 Work per this instruction involves cutting an access (or removal of a door) through a fire zone bulkhead, through the hull of the ship above the turn of the bilge, through ventilation components (ducting, plenums, etc.), or through any air-tight, fume-tight or watertight bulkheads normally used to control air flow in the event of a shipboard fire. A nonflammable closure is required in accordance with COMNAVSEASYSCOM MSG R 261400Z JUL 12. The closure, if not continuously in use, shall be staged near the access, readily visible and accessible, so that any emergency responder can install the closure to affect proper air flow onboard the ship.

5.9.9 JCNs EM04-ZAC1, EM04-ZAE3, and ER01-ZAL9 are related to this TGI.

5.10 Government Furnished Material (GFM): None.

5.11 SRF-JRMC will provide the following service work: (TGI No. 3819P12303S02).

5.11.1 [C740] Crane and crane rigging service.

5.11.2 [X99E] Utility service, electrical.

5.11.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.

5.11.4 [C106.1] Safety inspection for SRF-JRMC employees.

5.11.5 [C106.2] Gas free inspection for SRF-JRMC employees.

5.11.6 [C133] QA inspection for (G) symbol(s).

5.11.7 [C135] QA inspection for (G) symbol(s).

5.11.8 [C250] Technical support.

FOUO

J-1

SHIP: LCC-19 CHG/VER: 1/0

APPENDIX "J"

TGI JOB SUMMARY INFORMATION SHEET

SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH

VERSION:

CASREP

CAT:

DFS TK 7-82-2-F AY A 0 0

CU PHASE TITLE:

F/O - CLEAN, INSPECT, REPAIR, AND PRESERVE DISTILLATE FUEL SERVICE (7-82-2-F)

PRIMARY COMPONENT:

COMPONENT UNIT LIST (FOR ASSEMBLIES):

MANHOLE 6-82-2 HA MANHOLE 6-85-2 HA FOST 7-82-2-F TK

ATTACHMENT LIST:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA ,TAKEHIDE

JO: KO: TOTAL MAN HRS: PLANNING ACCEPTANCE:

3819P12303 A01

TOTAL MAT’L COST TOTAL DURATION:

CU PHASE DESCRIPTION:

The purpose of this TGI is to clean, inspect, repair, and preserve distillate fuel service (7-82-2-F).

Location of Work:

Distillate Fuel Service (7-82-2-F) B Division Storeroom (6-76-2-A)

TASK NAME

SHOP TSD/WC TS CREW# MHRS

HIGH RAD

HOURS

RC

GRID#

5.1 LBR HRs, QA HRs, PNTR HRs 22 KE PC

5.2 SFTR HRs, WELD HRs, PNTR HRs, QA HRs 22 KE PC

5.3 SFTR HRs, WELD HRs, PNTR HRs, CARP HRs, QA HRs 22 KE PC

5.4 PNTR HRs 22 KE PC

5.5 PNTR HRs, QA HRs 22 KE PC

5.6 PNTR HRs, RGRS HRs 22 KE PC

5.7 PNTR HRs 22 KE PC

5.8 PNTR HRs, QA HRs 22 KE PC

Dewatering and Cleaning Work CFM: $ for marine chemist, gaskets, fasteners, tank watch cost, and misc.

22 MQ CS

Structural Work CFM: $ for fire watch cost, tank watch cost, MT inspection cost, air compressor rental cost and fuel oil cost for air hose test, lead sampling/analysis cost, and misc such as electrode, gases, temporary closure, covering materials, and other consumable.

22 MQ CS

Preservation Work CFM: $ for all paints, grits, disposal cost, thinners, tank watch cost, and MISC such as consumable parts and covering material.

22 MQ CS

Process Funding Document. 10 CT OM

FOUO

J-2

SHIP: LCC-19 CHG/VER: 1/0

FOUO

M-1

SHIP: LCC-19 CHG/VER: 1/0

APPENDIX “M”

TGI MATERIAL LIST

SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH

VERSION:

CASREP

CAT:

DFS TK 7-82-2-F AY A 0 0

CU PHASE TITLE:

F/O - CLEAN, INSPECT, REPAIR, AND PRESERVE DISTILLATE FUEL SERVICE (7-82-2-F)

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV

JOB ORDER: KEY OP:

3819P12303 A01

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

NOTES:

FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____

☐ NUCLEAR APPENDIX "D"

DEFICIENCY FORM

☐ NON-NUCLEAR

1. SHIP/HULL NO.: 2a. DL or DR No.

(Circle One)

2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:

LCC-19 DFS TK 7-82-2-F AY A 0

4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:

3819P12303 A01

7. DESCRIPTION:

8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:

9. CORRECTIVE ACTION:

10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:

FOR NON-NUCLEAR USE ONLY

11. RFD/RFW REQ’D ☐ LAR REQ'D ☐

ILS MOD REQ’D ☐

SRD/PLAN REV REQ'D ☐

DWG NO.: _____________________ S/A NO.: ___________________

12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:

SATISFACTORY:

13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

YES ☐ NO ☐

14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

COMPLETE:

15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

_________:YES ☐ NO ☐

16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

COMPLETE (DR ONLY)

DL’s ISSUED

(DR ONLY)

FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____

☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR

1. SHIP/HULL NO.: 2a. DL or DR No.

(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:

LCC-19 DFS TK 7-82-2-F AY A 0

File details come from the government source that posted it. Updated .