This Task Group Instruction (TGI) details maintenance and repair work for the USS BLUE RIDGE's Lube Oil Storage Tank (7-117-3-F) at Commander, Fleet Activities Yokosuka. The comprehensive work scope includes cleaning and repairing the 691-gallon tank, involving specific technical requirements such as vee-out and welding one linear foot of deteriorated welds, base metal weld buildup of 60 square inches, removing and installing 10 square feet of deteriorated plate, and removing/installing 4 linear feet of defective stiffener.

The work is scheduled from January 12, 2026 through June 12, 2027, with multiple procedural steps including Level II general cleaning, manhole cover installation, nondestructive testing, surface preparation, and application of system fluid. Special requirements include working near a fire zone boundary and potential lead hazard. The project will be executed at multiple locations including the Lube Oil Storage Tank, Auxiliary Fuel Service Tank, and Emergency Diesel Generator Room, with various quality assurance and technical support services to be provided by SRF-JRMC (Shore Repair Facility - Japan Regional Maintenance Center).

View the file

Other files

File Type Posted
TGI_3819P51403A01_c0v0_FY26.pdf PDF
TGI_3819P26202_A01_c0v0_FY26.pdf PDF
TGI_3819P25604A01_c1v1_FY26.pdf PDF
TGI_3819P22103A01_c0v0_FY26.pdf PDF
TGI_3819P14121A01_c0v0_FY26.pdf PDF
TGI_3819P13507A01_c0v0_FY26.pdf PDF
TGI_3819P12351A01_c0v0_FY26.pdf PDF
TGI_3819P12333A01_c0v0_FY26.pdf PDF
TGI_3819P12331A01_c1v1_FY26.pdf PDF
TGI_3819P12315A01_c0v0_FY26.pdf PDF
TGI_3819P12314A01_0c0v0_FY26.pdf PDF
TGI_3819P12309A01_c1v0_FY26.pdf PDF
TGI_3819P12303A01_c1v0_FY26.pdf PDF
TGI_3819P12302A01_c2v2_FY26.pdf PDF
EXHIBIT - Contract Data Requirements List (CDRL)_R1.pdf PDF
Attachment VIII Source of Repair Instruction.pdf PDF
Attachment II Price Proposal Form N6264925RA024.xlsx XLSX spreadsheet
TGI_3819P25502_A01_c0v0.pdf PDF
TGI_3819P22101_T09_c0v0.pdf PDF
TGI_3819P14208T02_c0v0.pdf PDF
TGI_3819P14204A01_c0v0.pdf PDF
TGI_3819P13507A01_c0v0.pdf PDF
TGI_3819P13505A01_c0v0.pdf PDF
TGI_3819P12389A01_c0v0.pdf PDF
TGI_3819P12360A01_c0v0.pdf PDF
TGI_3819P12359_A01_c0v0.pdf PDF
TGI_3819P12358_A01_c0v0.pdf PDF
TGI_3819P12353_A01_c1v0.pdf PDF
TGI_3819P12343A01_c1v1.pdf PDF
TGI_3819P12334T01_c0v0.pdf PDF
TGI_3819P12329A01_c1v1.pdf PDF
TGI_3819P12322_A01_c2v1.pdf PDF
TGI_3819P12319A01_c0v0.pdf PDF
TGI_3819P12308A01_c0v0.pdf PDF
TGI_3819P12303A01_c1v0.pdf PDF
2.01 N6264925RA024.pdf PDF
EXHIBIT - Contract Data Requirements List (CDRL).pdf PDF
Attachment VII Warranty Tracking Information.pdf PDF
TGI_3819P26201A01_c0v0.pdf PDF
TGI_3819P25604A01_c1v1.pdf PDF
TGI_3819P22102_T08_c0v0.pdf PDF
TGI_3819P22102_T06_c0v0.pdf PDF
TGI_3819P22102_T02_c0v0.pdf PDF
TGI_3819P22101_T08_c0v0.pdf PDF
TGI_3819P22101A01_c2v2.pdf PDF
TGI_3819P14207_T01_c0v0.pdf PDF
TGI_3819P14117A01_c0v0.pdf PDF
TGI_3819P14115A01_c0v0.pdf PDF
TGI_3819P13339A01_c0v0.pdf PDF
TGI_3819P13327A01_c0v1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

FOUO: Public availability to be determined under 5 USC 552

TASK GROUP INSTRUCTION

AIM REV 20.11.4.0 (OCTOBER 2020)

TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:

NO.: LO TK 7-117-3-F AY A 0 0

SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P

CU PHASE TITLE:

F/O - CLEAN AND REPAIR LUBE OIL STORAGE TANK (7-117-3-F)

PREPARING ACTIVITY:

PREPARED BY: CODE PHONE DATE

TAKAAKI ASHINA 231B 315-243-4370 22-DEC-2023

APPROVED BY: CODE PHONE DATE

RYOUTA TAKAGI 231B 315-243-4502 22-DEC-2023

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

REASON FOR WORK/NEED FOR CHANGE:

CHANGE INSTRUCTIONS:

SPECIAL REQUIREMENTS:

SURFMEPP

This work affects a fire zone boundary. Fabrication and/or staging of a non-flammable closure is required.

CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL II

WORK CERTIFICATION SIGNATURES

COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:

ACCEPTANCE OF COMPLETED WORK

PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:

REQUIRED:☐YES ☒NO

RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:

TGI NO.: LO TK 7-117-3-F AY A 0

FOUO

SHIP: LCC-19 CHG/VER: 0/0

LIST OF EFFECTIVE PAGES

SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.

1-5 J-1 M-1

1. SCOPE/PURPOSE

1.1 Title: Lube Oil Storage Tank (7-117-3-F); clean and repair

1.2 Location of Work:

1.2.1 Lube Oil Storage Tank (7-117-3-F)

1.2.2 Auxiliary Fuel Service Tank (7-116-1-F)

1.2.3 Emergency Diesel Generator Room No. 2 (7-109-1-E)

1.3 Identification:

1.3.1 Quantity (One EA), Lube Oil Storage Tank

Tank No.: 7-117-3-F Capacity: 691 Gallons

1.3.2 Quantity (One EA), Auxiliary Fuel Service Tank

Tank No.: 7-116-1-F Capacity: 561 Gallons

1.3.3 Quantity (One EA), Manhole Cover Plate for 7-117-3-F

Manhole No(s).: 6-117-1 Size: 15 Inches x 18 Inches Material: Steel

1.3.4 Quantity (One EA), Bolting Ring for Manhole Cover Plate for 7-117-3-F

Manhole No(s).: 6-117-1 Material: Steel

1.3.5 Quantity (One EA), Manhole Cover Plate for 7-116-1-F

Manhole No(s).: 6-116-1 Size: 15 Inches x 18 Inches Material: Steel

1.3.6 Quantity (One EA), Bolting Ring for Manhole Cover Plate for 7-116-1-F

Manhole No(s).: 6-116-1 Material: Steel

1.4 Security Classification: None.

FOUO

SHIP: LCC-19 CHG/VER: 0/0

1.5 Initial Condition:

1.5.1 Potential Lead Hazard.

1.6 Contractor work start date:

1.7 Contractor work completion date:

2. REFERENCES:

REF.

NO.

DOCUMENT

/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV CHG

NO.

COPY

REQ’D

(Y/N)

SOURCE

DOC

(Y/N)

PARA SEC PG CHP

1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N

3 TM S9086-

CJ-STM-

010/CH-075

Fasteners 7 N

4 DWG 114-

2491167

MISC STRUCT BHD BELOW 1ST

PLATF FR 98-121

J Y 5,1 4,1

5 DWG 114-

2491163

SHAFT ALLEY BHD F Y AL

L

6 DWG 103-

2491034

1ST & 2ND PLATF PLTG AFT

FR98

H Y AL

L

3. APPENDICES:

3.1 Appendix “J” TGI Job Summary Information Sheet

3.2 Appendix "M" TGI Material List

3.3 Appendix “D” Deficiency Form

4. GENERAL REQUIREMENTS:

4.1 Not Applicable.

5. PROCEDURE:

5.1 Accomplish the requirements of 099-902YO of 2.2 for each tank listed in 1.3.1 and 1.3.2.

5.1.1 Accomplish the requirements of 009-107 of 2.1.

5.1.1.1 Accomplish the requirements of 009-09 of 2.1.

5.1.1.2 Ensure General Cleaning must be Level II.

5.1.2 Accomplish installation of each manhole cover for each tank listed in 1.3.1 and 1.3.2 in accordance with Figure 075-4-1 of 2.3.

5.2 Repair each tank listed in 1.3.1, based on the CCIMS assessment report as designated by the SUPERVISOR, using 2.4 through 2.6 for guidance. See 5.9.4 through 5.9.6.

5.2.1 Vee-out and weld a total of one linear feet of each deteriorated and damaged weld. Each area of repair must include deck, bulkhead, and overhead.

5.2.2 Chip and grind each surface flush in way of each repair.

1/12/2026

6/12/2027

FOUO

SHIP: LCC-19 CHG/VER: 0/0

5.2.3 Base metal weld buildup a total of 60 square inches of each plate defect in the tank.

5.2.3.1 For bidding purposes the base metal weld buildup must be one quarter inch thick.

5.2.3.2 Surface must be ground to sound metal prior to base metal weld buildup.

5.2.3.3 Fill each local pit and groove with weld material prior to application of each principal build up layer.

5.2.3.4 Grind each surface of completed base weld metal buildup smooth if greater than 1/8 inch above plate surface.

5.2.4 Remove existing, fabricate and install new a total of 10 square feet of deteriorated plate.

5.2.5 Remove existing, fabricate and install new a total of 4 linear feet of defective stiffener.

5.2.6 Accomplish the requirements of 009-12 of 2.1, including Table 2, Column(s) A, Lines One through 7.

5.2.6.1 Accomplish nondestructive testing in accordance with Line 11.

5.2.7 Accomplish the requirements of 009-25 of 2.1 for an air hose, water hose, or vacuum box test of each new insert weld seam. Allowable leakage: None.

5.3 Accomplish the requirements of 009-32 of 2.1 for interior surface of each tank listed in 1.3.1 where new material is installed and disturbed by hot work repaired in 5.2.

5.3.1 Power tool clean for interior surface of each tank to remove all rust and corrosion.

5.3.1.1 Apply system fluid conforming to MIL-PRF-3150 to interior surface of each tank.

5.4 Accomplish the requirements of 009-32 of 2.1, including Table 3, Line(s) 12, for machinery space side surfaces of each manhole cover plate listed in 1.3.3.

5.4.1 Power tool clean for tank side surface of each manhole cover plate to remove all rust and corrosion.

5.4.1.1 Apply system fluid conforming to MIL-PRF-3150 to tank side surface of manhole cover plate.

5.5 Accomplish the requirements of 009-32 of 2.1 for machinery space side surface of each bolting ring listed in 1.3.4.

5.5.1 Power tool clean for tank side surface of each bolting ring to remove all rust and corrosion.

5.5.1.1 Apply system fluid conforming to MIL-PRF-3150 to tank side surface of bolting ring.

5.6 Accomplish the requirements of 009-32 of 2.1, including Table 3, Line(s) 12, for machinery space side surfaces of each manhole cover plate listed in 1.3.5.

5.6.1 Power tool clean for tank side surface of each manhole cover plate to remove all rust and corrosion.

5.6.1.1 Light coat of system fluid must be wiped over the surface prior to closing. See 5.9.7.

5.7 Accomplish the requirements of 009-32 of 2.1 for machinery space side surface of each bolting ring listed in 1.3.6.

5.7.1 Power tool clean for tank side surface of each bolting ring to remove all rust and corrosion.

5.7.1.1 Light coat of system fluid must be wiped over the surface prior to closing. See 5.9.7.

FOUO

SHIP: LCC-19 CHG/VER: 0/0

5.8 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.

5.9 Notes:

5.9.1 Planner: Code 231B T. Ashina, 243-4370

Engineer: Code 250 J. Igarashi, 243-4230

5.9.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598

5.9.3 This TGI meets the intent of DDG CSWT File Nos. 123-133 and 123-142.

5.9.4 CCIMS assessment of each tank listed in 1.3.1 will be accomplished by SRF-JRMC (TGI No. 3819P12333I01), and the Project team will provide the assessment report with engineering evaluation under DL process for front loading structure repair.

5.9.5 Removal and installation of interferences, and gas free operation, preservation of boundary spaces relating to front loading structure repair are not included in this TGI. They will be covered by a DL in the future based on Contractor submitted condition report.

5.9.6 Materials for structure members relating to front loading repair will be provided in the future as a DL based on Contractor submitted condition report.

5.9.7 Ship's Force will provide system fluid for contractor when requested by Code 333 Work Integration Manager

(WIM).

5.9.8 Work per this instruction involves cutting an access (or removal of a door) through a fire zone bulkhead, through the hull of the ship above the turn of the bilge, through ventilation components (ducting, plenums, etc.), or through any air-tight, fume-tight or watertight bulkheads normally used to control air flow in the event of a shipboard fire. A nonflammable closure is required in accordance with COMNAVSEASYSCOM MSG R 261400Z JUL 12. The closure, if not continuously in use, shall be staged near the access, readily visible and accessible, so that any emergency responder can install the closure to affect proper air flow onboard the ship.

5.9.9 JCNs EA02-ZAB0, ER01-ZAO4, and ER01-ZAK3 are related to this TGI.

5.10 Government Furnished Material (GFM): None.

5.11 SRF-JRMC will provide the following service work: (TGI No. 3819P12333S02)

5.11.1 [C740] Crane and crane rigging service.

5.11.2 [X99E] Utility service, electrical.

5.11.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.

5.11.4 [C106.1] Safety inspection for SRF-JRMC employees.

5.11.5 [C106.2] Gas free inspection for SRF-JRMC employees.

5.11.6 [C133] QA inspection for (G) symbol(s).

5.11.7 [C135] QA inspection for (G) symbol(s).

5.11.8 [C250] Technical support.

FOUO

J-1

SHIP: LCC-19 CHG/VER: 0/0

APPENDIX "J"

TGI JOB SUMMARY INFORMATION SHEET

SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH

VERSION:

CASREP

CAT:

LO TK 7-117-3-F AY A 0 0

CU PHASE TITLE:

F/O - CLEAN AND REPAIR LUBE OIL STORAGE TANK (7-117-3-F)

PRIMARY COMPONENT:

COMPONENT UNIT LIST (FOR ASSEMBLIES):

MANHOLE 6-117-1 HA MANHOLE 6-116-1 HA AUX FO SVC 7-116-1-F TK LO STWG 7-117-3-F

TK

ATTACHMENT LIST:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA ,TAKEHIDE

JO: KO: TOTAL MAN HRS: PLANNING ACCEPTANCE:

3819P12333 A01

TOTAL MAT’L COST TOTAL DURATION:

CU PHASE DESCRIPTION:

The purpose of this TGI is to clean and repair lube oil storage tank (7-117-3-F).

Location of Work:

Lube Oil Storage Tank (7-117-3-F) Auxiliary Fuel Service Tank (7-116-1-F) Emergency Diesel Generator Room No. 2 (7-109-1-E)

TASK NAME

SHOP TSD/WC TS CREW# MHRS

HIGH RAD

HOURS

RC

GRID#

5.1 LBR HRs, QA HRs 22 KE PC

5.2 SFTR HRs, WELD HRs, CARP HRs, QA HRs 22 KE PC

5.3 PNTR HRs 22 KE PC

5.4 PNTR HRs, QA HRs 22 KE PC

5.5 PNTR HRs, QA HRs 22 KE PC

5.6 PNTR HRs, QA HRs 22 KE PC

5.7 PNTR HRs, QA HRs 22 KE PC

5.8 PNTR HRs, QA HRs 22 KE PC

Dewatering and Cleaning Work CFM: $ for marine chemist, gaskets, fasteners, tank watch cost, and MISC.

22 MQ CS

Structural Work CFM: $ for all paints, thinner, fire watch cost, tank watch cost, MT inspection cost, grits including disposal cost, air compressor rental cost and fuel oil cost for air hose test, lead sampling/analysis cost, and misc such as electrode, gases, temporary closure, covering materials, and other consumable.

22 MQ CS

Process Funding Document. 10 CT OM

FOUO

M-1

SHIP: LCC-19 CHG/VER: 0/0

APPENDIX “M”

TGI MATERIAL LIST

SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH

VERSION:

CASREP

CAT:

LO TK 7-117-3-F AY A 0 0

CU PHASE TITLE:

F/O - CLEAN AND REPAIR LUBE OIL STORAGE TANK (7-117-3-F)

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV

JOB ORDER: KEY OP:

3819P12333 A01

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

NOTES:

FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____

☐ NUCLEAR APPENDIX "D"

DEFICIENCY FORM

☐ NON-NUCLEAR

1. SHIP/HULL NO.: 2a. DL or DR No.

(Circle One)

2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:

LCC-19 LO TK 7-117-3-F AY A 0

4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:

3819P12333 A01

7. DESCRIPTION:

8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:

9. CORRECTIVE ACTION:

10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:

FOR NON-NUCLEAR USE ONLY

11. RFD/RFW REQ’D ☐ LAR REQ'D ☐

ILS MOD REQ’D ☐

SRD/PLAN REV REQ'D ☐

DWG NO.: _____________________ S/A NO.: ___________________

12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:

SATISFACTORY:

13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

YES ☐ NO ☐

14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

COMPLETE:

15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

_________:YES ☐ NO ☐

16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

COMPLETE (DR ONLY)

DL’s ISSUED

(DR ONLY)

FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____

☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR

1. SHIP/HULL NO.: 2a. DL or DR No.

(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:

LCC-19 LO TK 7-117-3-F AY A 0