TGI_3819P12360A01_c0v0.pdf
PDF 143 KB Posted
- Solicitation number
- N6264925RA024
About this file
This document is a Task Group Instruction (TGI) for the USS BLUE RIDGE (LCC-19) detailing a maintenance and repair project for the ship's Cofferdam (9-86-3-V) space. The specific work involves cleaning, inspecting, repairing, and preserving the Cofferdam, which includes commercial blast cleaning, visual inspection, structural repairs, and preservation coating. The project covers multiple spaces including the Cofferdam (9-86-3-V), Fresh Water Ballast (9-86-5-W), and Self Service Storeroom (6-86-1-A).
Key technical requirements include vee-out and welding one linear foot of deteriorated welds, base metal weld buildup of 60 square inches, removal and replacement of 10 square feet of deteriorated plate and 4 linear feet of defective stiffener, and completing nondestructive testing. The work is scheduled to start on 1/12/2026 and complete by 5/15/2027, with special requirements including addressing a fire zone boundary and potential lead hazards. The instruction includes detailed procedural steps, material references, and quality assurance requirements for executing the ship maintenance work.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
FOUO: Public availability to be determined under 5 USC 552
TASK GROUP INSTRUCTION
AIM REV 20.11.4.0 (OCTOBER 2020)
TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:
NO.: COFFERDAM 9-86-3-V AY A 0 0
SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE:
F/O - CLEAN, INSPECT, REPAIR, AND PRESERVE COFFERDAM (9-86-3-V)
PREPARING ACTIVITY:
PREPARED BY: CODE PHONE DATE
KOUKI YOSHIDA 231B. 315-243-0163 04-MAR-2024
APPROVED BY: CODE PHONE DATE
RYOUTA TAKAGI 231B. 315-243-4502 04-MAR-2024
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
REASON FOR WORK/NEED FOR CHANGE:
CHANGE INSTRUCTIONS:
SPECIAL REQUIREMENTS:
SURFMEPP
This work affects a fire zone boundary. Fabrication and/or staging of a non-flammable closure is required
CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL III
WORK CERTIFICATION SIGNATURES
COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
ACCEPTANCE OF COMPLETED WORK
PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:
REQUIRED:☐YES ☒NO
RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
TGI NO.: COFFERDAM 9-86-3-V AY A 0
FOUO
SHIP: LCC-19 CHG/VER: 0/0
LIST OF EFFECTIVE PAGES
SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.
1-5 J1-2 M-1
1. SCOPE/PURPOSE
1.1 Title: Cofferdam (9-86-3-V); clean, inspect, repair, and preserve
1.2 Location of Work:
1.2.1 Cofferdam (9-86-3-V)
1.2.2 Fresh Water Ballast (9-86-5-W)
1.2.3 Self Service Storeroom (6-86-1-A)
1.3 Identification:
1.3.1 Quantity (One EA), Cofferdam
Void No.: 9-86-3-V
1.3.2 Quantity (One EA), Manhole Cover Plate(s) for 9-86-3-V
Manhole No(s).: 7-86-1 Size: 15 Inches x 23 Inches Material: Steel
1.3.3 Quantity (One EA), Bolting Ring for Manhole Cover Plate(s) for 9-86-3-V Manhole No(s).: 7-86-1 Material: Steel
REF.
NO.
DOCUMENT
/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV CHG
NO.
COPY
REQ’D
(Y/N)
SOURCE
DOC
(Y/N)
PARA SEC PG CHP
1.3.4 Quantity (460 SF), Entire Interior Surface of 9-86-3-V
Remarks: The area includes cofferdam side of manhole cover plate(s) and bolting ring.
1.4 Security Classification: None.
1.5 Initial Condition: None.
1.5.1 Critical Coated Area: CCNY-LCC19-020-25 for area listed in 1.3.4.
1.5.2 Potential Lead Hazard.
1.6 Contractor work start date: 1/12/2026
1.7 Contractor work completion date: 5/15/2027
2. REFERENCES:
FOUO
SHIP: LCC-19 CHG/VER: 0/0
REF.
NO.
DOCUMENT
/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV CHG
NO.
COPY
REQ’D
(Y/N)
SOURCE
DOC
(Y/N)
PARA SEC PG CHP
1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N
3 TM S9086-
CJ-STM-
010/CH-075
Fasteners 7 N
4 TM
SYSTEMS &
SPECIFICAT
IONS
SSPC Painting Manual Volume 2 - N
5 DWG 100-
2491003
SHELL PLTG & STGR FRAME 51
1/2 -102 1/4 CL TO 4 TH DECK
G Y AL
L
6 DWG 103-
2491033
2 PLATF FR 52-98 J Y AL
7 DWG 114-
2491157
TRANSV BHD FR 76 & 86 N Y AL
8 DWG 114-
2491162
Wing Tank BHD FR76-98 D Y AL
9 DWG 114-
2491176
STRUCTURAL DETAILS AE Y 11,
B, 10 TM T-9630-
AB-MMD-
Corrosion Control Assessment and Maintenance Manual (CCAMM)
3 N
11 TM NAVSEA
4790/14
Tank and Void Structural and Coating Condition Survey (MRC G1N5)
- N
3. APPENDICES:
3.1. Appendix “J” TGI Job Summary Information Sheet
3.2. Appendix "M" TGI Material List
3.3. Appendix “D” Deficiency Form
4. GENERAL REQUIREMENTS:
4.1 Not Applicable.
5. PROCEDURE:
5.1 Accomplish the requirements of 099-902YO of 2.2 for each space listed in 1.3.1.
5.1.1 Accomplish installation of each manhole cover for each space listed in 1.3.1 in accordance with Figure 075-4-1 of 2.3.
5.2 Commercial blast clean each space listed in 1.3.1. Accomplish each requirement of Surface Preparation Specification SSPC-SP 6 of 2.4.
5.3 Accomplish a visual inspection of each space listed in 1.3.1 for existing preservation coating, structural integrity, deterioration, pitting, each crack, and area of damage or distortion, including each sounding tube, tank vent, overflow, piping, each structural member, and manhole cover, using 2.5 through 2.9 for guidance.
5.3.1 Submit one legible copy, in hard copy or approved transferrable media, of a report listing results of the requirements of 5.3 to the SUPERVISOR.
FOUO
SHIP: LCC-19 CHG/VER: 0/0
5.4 Repair each space listed in 1.3.1, based on the report 5.3.1 and CCIMS assessment report as designated by the SUPERVISOR, using 2.5 through 2.9 for guidance. See 5.9.6 through 5.9.8.
5.4.1 Vee-out and weld a total of one linear foot of each deteriorated and damaged weld. Each area of repair must include deck, bulkhead, shell plating, and overhead.
5.4.2 Chip and grind each surface flush in way of each repair.
5.4.3 Base metal weld buildup a total of 60 square inches of each plate defect in the space.
5.4.3.1 For bidding purposes the base metal weld buildup must be one quarter inch thick.
5.4.3.2 Surface must be ground to sound metal prior to base metal weld buildup.
5.4.3.3 Fill each local pit and groove with weld material prior to application of each principal build up layer.
5.4.3.4 Grind each surface of completed base weld metal buildup smooth if greater than 1/8 inch above plate surface.
5.4.4 Remove existing, fabricate and install new a total of 10 square feet of deteriorated plate.
5.4.5 Remove existing, fabricate and install new a total of 4 linear feet of defective stiffener.
5.4.6 Accomplish the requirements of 009-12 of 2.1, including Table 2, Columns A, Lines One through 7.
5.4.6.1 Accomplish nondestructive testing in accordance with Line 11.
5.4.7 Accomplish the requirements of 009-25 of 2.1 for an air hose, water hose, or vacuum box test of each new insert weld seam. Allowable leakage: None.
5.5 Accomplish the requirements of 009-32 of 2.1, including Table 4, Line(s) 17, for fresh water ballast side surface of each cover plate listed in 1.3.2.
5.6 Accomplish the requirements of 009-32 of 2.1 for fresh water ballast side surface of each bolting ring listed in 1.3.3.
5.7 Accomplish the requirements of 009-32 of 2.1, including Table 4, Line(s) 17, for each area listed in 1.3.4.
5.7.1 Submit new coating data applied to the SUPERVISOR in accordance with 2.10 and 2.11.
5.8 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
5.9 Notes:
5.9.1 Planner: Code 231B K. Yoshida, 243-0163
5.9.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
5.9.3 Opening, initial cleaning, and closing of each tank listed in 1.2.2 will be covered by TGI No. 3819P12343A01
(KTR TGI).
5.9.4 2.11 is available on P:\C200\C225\Enclosures\C231\Tank and Void Structural and Coating Condition Survey
(MRC G1N5).
5.9.5 This TGI meets the intent of DDG CSWT File Nos. 123-111, 123-133, and 123-142.
FOUO
SHIP: LCC-19 CHG/VER: 0/0
5.9.6 CCIMS assessment of each space listed in 1.3.1 will be accomplished by SRF-JRMC (TGI No.
3819P12360I01), and the Project team will provide the assessment report with engineering evaluation under DL process for front loading structure repair.
5.9.7 Removal and installation of interferences, and gas free operation, preservation of boundary spaces relating to front loading structure repair are not included in this TGI. They will be covered by a DL in the future based on Contractor submitted condition report.
5.9.8 Materials for structure members relating to front loading repair will be provided in the future as a DL based on Contractor submitted condition report.
5.9.9 Work per this instruction involves cutting an access (or removal of a door) through a fire zone bulkhead, through the hull of the ship above the turn of the bilge, through ventilation components (ducting, plenums, etc.), or through any air-tight, fume-tight or watertight bulkheads normally used to control air flow in the event of a shipboard fire. A nonflammable closure is required in accordance with COMNAVSEASYSCOM MSG R 261400Z JUL 12. The closure, if not continuously in use, shall be staged near the access, readily visible and accessible, so that any emergency responder can install the closure to affect proper air flow onboard the ship.
5.9.10 JCNs ER04-ZA72, ER01-ZAQ3, and ER01-ZAT7 are related to this TGI.
5.10 Government Furnished Material (GFM): None.
5.11 SRF-JRMC will provide the following service work: (TGI No. 3819P12360S02).
5.11.1 [C740] Crane and crane rigging service.
5.11.2 [X99E] Utility service, electrical.
5.11.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.
5.11.4 [C106.1] Safety inspection for SRF-JRMC employees.
5.11.5 [C106.2] Gas free inspection for SRF-JRMC employees.
5.11.6 [C133] QA inspection for (G) symbol(s) and review of coating application data.
5.11.7 [C135] QA inspection for (G) symbol(s).
5.11.8 [C250] Technical support.
FOUO
J-1
SHIP: LCC-19 CHG/VER: 0/0
APPENDIX "J"
TGI JOB SUMMARY INFORMATION SHEET
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
COFFERDAM 9-86-3-V AY A 0 0
CU PHASE TITLE:
F/O - CLEAN, INSPECT, REPAIR, AND PRESERVE COFFERDAM (9-86-3-V)
PRIMARY COMPONENT:
COMPONENT UNIT LIST (FOR ASSEMBLIES):
MANHOLE 7-86-1 HA VOID 9-86-3-V VD
ATTACHMENT LIST:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA ,TAKEHIDE
JO: KO: TOTAL MAN HRS: PLANNING ACCEPTANCE:
3819P12360 A01
TOTAL MAT’L COST TOTAL DURATION:
CU PHASE DESCRIPTION:
The purpose of this TGI is to clean, inspect, repair, and preserve Cofferdam (9-86-3-V).
Location of Work:
Cofferdam (9-86-3-V) Fresh Water Ballast (9-86-5-W) Self Service Storeroom (6-86-1-A)
TASK NAME
SHOP TSD/WC TS CREW# MHRS
HIGH RAD
HOURS
RC
GRID#
5.1 LBR HRs 22 KE PC
5.2 PNTR HRs, RGRS HRs, QA HRs 22 KE PC
5.3 PNTR HRs, SFTR HRs 22 KE PC
5.4 SFTR HRs, WELD HRs, CARP HRs, QA HRs 22 KE PC
5.5 PNTR HRs, QA HRs 22 KE PC
5.6 PNTR HRs, QA HRs 22 KE PC
5.7 PNTR HRs, RGRS HRs, QA HRs 22 KE PC
5.8 PNTR HRs, QA HRs 22 KE PC
Dewatering and Cleaning Work CFM marine chemist, gaskets, fasteners, tank watch cost, and MISC.
22 MQ CS
Structural Work CFM for fire watch and tank watch cost, marine chemist cost, MT inspection cost, lead sampling/analysis cost, air compressor rental cost and fuel oil cost for air hose test, and MISC such as electrode, gases, temporary closure and covering material, and other consumable.
22 MQ CS
Preservation Work CFM for all paints, thinner, grits, disposal cost, tank watch cost, air compressor, dryer, fuel oil, air conditioning, and MISC such as covering material and other consumable.
22 MQ CS
FOUO
J-2
SHIP: LCC-19 CHG/VER: 0/0
TASK NAME
SHOP TSD/WC TS CREW# MHRS
HIGH RAD
HOURS
RC
GRID#
Process Funding Document 10 CT OM 1 1 0
FOUO
M-1
SHIP: LCC-19 CHG/VER: 0/0
APPENDIX “M”
TGI MATERIAL LIST
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
COFFERDAM 9-86-3-V AY A 0 0
CU PHASE TITLE:
F/O - CLEAN, INSPECT, REPAIR, AND PRESERVE COFFERDAM (9-86-3-V)
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV
JOB ORDER: KEY OP:
3819P12360 A01
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
NOTES:
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR APPENDIX "D"
DEFICIENCY FORM
☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One)
2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
LCC-19 COFFERDAM 9-86-3-V AY A 0
4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:
3819P12360 A01
7. DESCRIPTION:
8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
9. CORRECTIVE ACTION:
10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
FOR NON-NUCLEAR USE ONLY
11. RFD/RFW REQ’D ☐ LAR REQ'D ☐
ILS MOD REQ’D ☐
SRD/PLAN REV REQ'D ☐
DWG NO.: _____________________ S/A NO.: ___________________
12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:
SATISFACTORY:
13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
YES ☐ NO ☐
14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE:
15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
_________:YES ☐ NO ☐
16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE (DR ONLY)
DL’s ISSUED
(DR ONLY)
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
LCC-19 COFFERDAM 9-86-3-V AY A 0