This Task Group Instruction (TGI) details a deck covering replacement project for the USS BLUE RIDGE at Emergency Switchgear Room No. 2 (6-109-1-E). The project involves removing and replacing 430 square feet of electrical grade sheet deck covering, with a blue mableized color, conforming to MIL-DTL-15562, Type One specification. The work includes deck plating replacement up to one inch from the deck covering system level, with potential lead and asbestos hazards identified.
The project is scheduled for contractor work from January 12, 2026, to June 12, 2027, with SRF-JRMC providing government-furnished material and additional services including crane and rigging, utility services (electrical, air, water, steam), and safety/quality assurance inspections. The task involves carpentry, painting, and quality assurance work, with material requirements including floor matting ordered by the original contractor. The job is part of a naval ship repair and maintenance package for the USS BLUE RIDGE at Commander, Fleet Activities Yokosuka Naval Base in Japan.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
23-AUG-2024 0831
20.14.15.0.8993 (August 2024) ICN: 3819P14121 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 6-109-1-E DC A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 63411
CU PHASE TITLE: *F/O - REPLACE COVERING IN 6-109-1-E
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 4
EE010194
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
MAEDA, MITSUO 231B 3152436101 17-JUN-2024
APPROVED BY: CODE: PHONE: DATE:
NAKANO, SEIICHI 231B 3152434519 17-JUN-2024
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
EE01-0194
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA, TAKEHIDE 6-109-1-E 6 S
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
141A0021
1 SCOPE/PURPOSE:
1.1 Title: Deck Covering in 6-109-1-E; replace
1.2 Location of Work:
1.2.1 Emergency Switchgear Room No. 2 (6-109-1-E)
1.3 Identification:
1.3.1 Quantity (385 SF), Electrical Grade Sheet Deck Covering System [Existing]
1.3.2 Quantity (45 SF), Electrical Grade Sheet on False Floor [Existing]
1.3.3 Quantity (430 SF in Total), Electrical Grade Sheet
Specification: MIL-DTL-15562, Type One
TGI Short Form
23-AUG-2024 0831
20.14.15.0.8993 (August 2024) (Continued) ICN: 3819P14121 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 6-109-1-E DC A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 63411
CU PHASE TITLE: *F/O - REPLACE COVERING IN 6-109-1-E
FOUO Pg 2 of 4
CU PHASE DESCRIPTION (Cont.)
Color: Blue Mableized
1.3.4 Quantity (390 SF in Total), Deck Plating, including vertical structural surface up to height of One inch from complete electrical grade sheet deck covering system level
Remarks: The area excepts inside of false floor and foundation
1.4 Security Classification: None.
1.5 Initial Condition:
1.5.1 Potential Lead Hazard.
1.5.2 Potential Asbestos Hazard.
1.6 Contractor work start date: 1/12/2026
1.7 Contractor work completion date: 6/12/2027
2 PROCEDURE:
2.1 Accomplish the requirements of 009-26 of Ref No. One, including Attachment D, for removal of each existing equipment listed in 1.3.1 and 1.3.2, and installation of each new equipment listed in 1.3.3.
2.1.1 Accomplish the requirements of 009-32 of Ref. No. One, including Table 3, Line(s) 9, Column(s) A, B, and D, for each area listed in 1.3.4.
2.2 Notes:
2.2.1 Planner: Code 231B M. Maeda, 243-6101
2.2.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
2.2.3 JCN EE01-0194 is related to this TGI.
2.3 Government Furnished Material (GFM):
2.3.1 SRF-JRMC will provide GFM listed in the Material List.
2.4 SRF-JRMC will provide the following service work: (TGI No. 3819P14121S02)
2.4.1 [C740] Crane and crane rigging service.
2.4.2 [X99E] Utility service, electrical.
2.4.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.
2.4.4 [C106.1] Safety inspection for SRF-JRMC employees.
23-AUG-2024 0831
20.14.15.0.8993 (August 2024) (Continued) ICN: 3819P14121 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 6-109-1-E DC A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 63411
CU PHASE TITLE: *F/O - REPLACE COVERING IN 6-109-1-E
FOUO Pg 3 of 4
CU PHASE DESCRIPTION (Cont.)
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
2.4.5 [C106.2] Gas free inspection for SRF-JRMC employees.
2.4.6 [C133] QA inspection for (G) symbols.
23-AUG-2024 0831
20.14.15.0.8993 (August 2024) (Continued) ICN: 3819P14121 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 6-109-1-E DC A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 63411
CU PHASE TITLE: *F/O - REPLACE COVERING IN 6-109-1-E
FOUO Pg 4 of 4
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
2.1 CARP: HRs, PNTR: HRs, QA: HRs 22/KE PC N
CFM: $ for all deck covering, paints, thinners, nonslip tape, sampler/ analyze asbestos and lead, and MISC such as covering material and other consumable
22/MQ CS N
Process Funding Document 10/CT OM N
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
500 M MATTING,FLOOR, ORDER FOR
KTR
ORIG: C231B M. MAEDA 243-
9Q 7220 010249040 NA 4 N 40305001 1/RO
501 M MATTING,FLOOR, ORDER FOR
KTR
ORIG: C231B M. MAEDA 243-
9Q 7220 010249040 NA 4 N 40905068 1/RO
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 3819P14121 KEY OP: A01
File details come from the government source that posted it. Updated .