This document is a Task Group Instruction (TGI) for a tightness and operational test of the 1A Boiler Air Casing on the USS Blue Ridge (LCC-19), with a specific focus on contractor work. The instruction is dated 27-SEP-2024 and includes detailed task specifications for contractor (22/KE), Quality Assurance (33/G1), and Ship/Force (EM01) personnel to accomplish and document the test in accordance with technical procedure TP 22111-3-300KTR.

Key administrative details include preparation by Nagano, Takumi on 10-AUG-2024 and approval by Higa, Riley on 27-AUG-2024. The document is marked FOUO (For Official Use Only) and is part of a naval maintenance package for the USS Blue Ridge, which is located in Yokosuka, Japan. The task group instruction provides a structured approach for executing a specific technical test on the ship's boiler air casing, with clear delineation of responsibilities and reference materials.

View the file

Other files

File Type Posted
TGI_3819P51403A01_c0v0_FY26.pdf PDF
TGI_3819P26202_A01_c0v0_FY26.pdf PDF
TGI_3819P25604A01_c1v1_FY26.pdf PDF
TGI_3819P22103A01_c0v0_FY26.pdf PDF
TGI_3819P14121A01_c0v0_FY26.pdf PDF
TGI_3819P13507A01_c0v0_FY26.pdf PDF
TGI_3819P12351A01_c0v0_FY26.pdf PDF
TGI_3819P12333A01_c0v0_FY26.pdf PDF
TGI_3819P12331A01_c1v1_FY26.pdf PDF
TGI_3819P12315A01_c0v0_FY26.pdf PDF
TGI_3819P12314A01_0c0v0_FY26.pdf PDF
TGI_3819P12309A01_c1v0_FY26.pdf PDF
TGI_3819P12303A01_c1v0_FY26.pdf PDF
TGI_3819P12302A01_c2v2_FY26.pdf PDF
EXHIBIT - Contract Data Requirements List (CDRL)_R1.pdf PDF
Attachment VIII Source of Repair Instruction.pdf PDF
Attachment II Price Proposal Form N6264925RA024.xlsx XLSX spreadsheet
TGI_3819P25502_A01_c0v0.pdf PDF
TGI_3819P14208T02_c0v0.pdf PDF
TGI_3819P14204A01_c0v0.pdf PDF
TGI_3819P13507A01_c0v0.pdf PDF
TGI_3819P13505A01_c0v0.pdf PDF
TGI_3819P12389A01_c0v0.pdf PDF
TGI_3819P12360A01_c0v0.pdf PDF
TGI_3819P12359_A01_c0v0.pdf PDF
TGI_3819P12358_A01_c0v0.pdf PDF
TGI_3819P12353_A01_c1v0.pdf PDF
TGI_3819P12343A01_c1v1.pdf PDF
TGI_3819P12334T01_c0v0.pdf PDF
TGI_3819P12333A01_c0v0.pdf PDF
TGI_3819P12329A01_c1v1.pdf PDF
TGI_3819P12322_A01_c2v1.pdf PDF
TGI_3819P12319A01_c0v0.pdf PDF
TGI_3819P12308A01_c0v0.pdf PDF
TGI_3819P12303A01_c1v0.pdf PDF
Attachment V Contract Data Sheet.pdf PDF
TGI_3819P23103_A03_c0v0.pdf PDF
TGI_3819P22102_T01_c0v0.pdf PDF
TGI_3819P14208T01_c0v0.pdf PDF
TGI_3819P14208A01_c1v1.pdf PDF
TGI_3819P14122A01_c0v0.pdf PDF
TGI_3819P14121A01_c0v0.pdf PDF
TGI_3819P13422A01_c0v0.pdf PDF
TGI_3819P13411A01_c1v1.pdf PDF
TGI_3819P12351A01_c0v0.pdf PDF
TGI_3819P12350A01_c0v0.pdf PDF
TGI_3819P12347_A01_c0v0.pdf PDF
TGI_3819P12345_A01_c1v3.pdf PDF
TGI_3819P12332A01_c1v1.pdf PDF
TGI_3819P12327_A01_c1v1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

27-SEP-2024 0907

20.14.15.2.9020 (September 2024) ICN: 3819P22101 KeyOp: T09

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 22111-3-300KTR TT T 1 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 22111

CU PHASE TITLE: 1A BOILER, AIR CASING (T & OP) - KTR

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 2

EM01ZAG0 * EM01ZAG2 * EM01ZAG5 * EM01ZAK4 * EM01ZAG8 * EM01ZAH1 * EM01ZAH2 * EM01ZAH4 * EM01ZAH5 *

EM01ZAH7 * EM01ZAH9 * EM01ZAI2 * EM01ZAI6

PREPARING ACTIVITY: STATUS: APP WORKING STATUS: PKG

PREPARED BY: CODE: PHONE: DATE:

NAGANO, TAKUMI 246.2 3152438406 10-AUG-2024

APPROVED BY: CODE: PHONE: DATE:

HIGA, RILEY 246.2 3152432291 27-AUG-2024

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

EM01-ZAG0 * EM01-ZAG2 * EM01-ZAG5 * EM01-ZAG8 * EM01-ZAH1 * EM01-ZAH2 * EM01-ZAH4 * EM01-ZAH5 * EM01-ZAH7 *

EM01-ZAH9 * EM01-ZAI2 * EM01-ZAI6 * EM01-ZAK4

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE U

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

221A1101

Tightness & operational test for 1A BOILER, AIR CASING - KTR.

TGI Short Form

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

27-SEP-2024 0907

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22101 KeyOp: T09

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 22111-3-300KTR TT T 1 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 22111

CU PHASE TITLE: 1A BOILER, AIR CASING (T & OP) - KTR

FOUO Pg 2 of 2

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 TP 22111-3-300KTR BOILER (T & OP) - KTR LAT Y

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

(V) Contractor work:

Accomplish/document the tightness & operational test in accordance with reference, TP 22111-3-300KTR.

22/KE PC N

(G) QA work:

Accomplish/document the tightness & operational test in accordance with reference, TP 22111-3-300KTR.

33/G1 QA N

(S) S/F work:

Accomplish/document the tightness & operational test in accordance with reference, TP 22111-3-300KTR.

/ EM01 N

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 3819P22101 KEY OP: T09