This Task Group Instruction (TGI) details the installation, modification, and removal of a temporary cleanliness enclosure in the Engine Room (8-86-0-E) of the USS Blue Ridge at Naval Base Yokosuka, Japan. The work is scheduled from January 12, 2026, to May 15, 2027, and involves fabricating, installing, modifying, and removing scaffolding and enclosure structures in accordance with specified references, including NAVSEA Standard Items and scaffolding regulations.

The TGI outlines specific procedural requirements for the contractor, including precise installation and modification guidelines. SRF-JRMC will provide supporting services such as crane and rigger services, utility services (electrical, air, water, steam), safety inspections, gas-free inspections, and quality assurance inspections. The work will be performed by RGRS and CARP hours, with tasks tracked through various shop/TSD codes and will require processing of funding documents and covering materials.

View the file

Other files

File Type Posted
TGI_3819P51403A01_c0v0_FY26.pdf PDF
TGI_3819P26202_A01_c0v0_FY26.pdf PDF
TGI_3819P25604A01_c1v1_FY26.pdf PDF
TGI_3819P22103A01_c0v0_FY26.pdf PDF
TGI_3819P14121A01_c0v0_FY26.pdf PDF
TGI_3819P13507A01_c0v0_FY26.pdf PDF
TGI_3819P12351A01_c0v0_FY26.pdf PDF
TGI_3819P12333A01_c0v0_FY26.pdf PDF
TGI_3819P12331A01_c1v1_FY26.pdf PDF
TGI_3819P12315A01_c0v0_FY26.pdf PDF
TGI_3819P12314A01_0c0v0_FY26.pdf PDF
TGI_3819P12309A01_c1v0_FY26.pdf PDF
TGI_3819P12303A01_c1v0_FY26.pdf PDF
TGI_3819P12302A01_c2v2_FY26.pdf PDF
EXHIBIT - Contract Data Requirements List (CDRL)_R1.pdf PDF
Attachment VIII Source of Repair Instruction.pdf PDF
Attachment II Price Proposal Form N6264925RA024.xlsx XLSX spreadsheet
TGI_3819P25502_A01_c0v0.pdf PDF
TGI_3819P22101_T09_c0v0.pdf PDF
TGI_3819P14208T02_c0v0.pdf PDF
TGI_3819P14204A01_c0v0.pdf PDF
TGI_3819P13507A01_c0v0.pdf PDF
TGI_3819P13505A01_c0v0.pdf PDF
TGI_3819P12389A01_c0v0.pdf PDF
TGI_3819P12360A01_c0v0.pdf PDF
TGI_3819P12359_A01_c0v0.pdf PDF
TGI_3819P12358_A01_c0v0.pdf PDF
TGI_3819P12353_A01_c1v0.pdf PDF
TGI_3819P12343A01_c1v1.pdf PDF
TGI_3819P12334T01_c0v0.pdf PDF
TGI_3819P12333A01_c0v0.pdf PDF
TGI_3819P12329A01_c1v1.pdf PDF
TGI_3819P12322_A01_c2v1.pdf PDF
TGI_3819P12319A01_c0v0.pdf PDF
TGI_3819P12308A01_c0v0.pdf PDF
TGI_3819P12303A01_c1v0.pdf PDF
2.01 N6264925RA024.pdf PDF
EXHIBIT - Contract Data Requirements List (CDRL).pdf PDF
Attachment VII Warranty Tracking Information.pdf PDF
TGI_3819P26201A01_c0v0.pdf PDF
TGI_3819P25604A01_c1v1.pdf PDF
TGI_3819P22102_T08_c0v0.pdf PDF
TGI_3819P22102_T06_c0v0.pdf PDF
TGI_3819P22102_T02_c0v0.pdf PDF
TGI_3819P22101_T08_c0v0.pdf PDF
TGI_3819P22101A01_c2v2.pdf PDF
TGI_3819P14207_T01_c0v0.pdf PDF
TGI_3819P14117A01_c0v0.pdf PDF
TGI_3819P14115A01_c0v0.pdf PDF
TGI_3819P13339A01_c0v0.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

30-AUG-2024 1550

20.14.15.0.8998 (August 2024) ICN: 3819P23103 KeyOp: A03

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 8-86-0-E MS A 5 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 13500

CU PHASE TITLE: F/O - ACCOMP INSTL, MOD, AND REM OF TEMP CLEANLINESS ENCL IN 8-86-0-E

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 3

EM01ZAN6 * EM01ZAN5

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

KUROKAWA, NAOKI 231B 3152430108 10-AUG-2024

APPROVED BY: CODE: PHONE: DATE:

TAKAGI, RYOUTA 231B 3152434502 10-AUG-2024

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

EM01-ZAN5 * EM01-ZAN6

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE 8-86-0-E 8 U

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

231A1103

1. SCOPE/PURPOSE:

1.1 Title: Installation, Modification, and Removal of Temporary Cleanliness Enclosure in 8-86-0-E; accomplish

1.2 Location of Work:

1.2.1 Engine Room (8-86-0-E)

1.3 Identification:

1.3.1 Quantity (One Lot), Temporary Cleanliness Enclosure, including Scaffolding Assembly in 8-86-0-E

Remarks: See Sketch Enclosure-01 for location detail Modification of Enclosure, including Scaffolding Assembly up to One Time/Day

1.4 Security Classification: None.

TGI Short Form

30-AUG-2024 1550

20.14.15.0.8998 (August 2024) (Continued) ICN: 3819P23103 KeyOp: A03

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 8-86-0-E MS A 5 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 13500

CU PHASE TITLE: F/O - ACCOMP INSTL, MOD, AND REM OF TEMP CLEANLINESS ENCL IN 8-86-0-E

FOUO Pg 2 of 3

CU PHASE DESCRIPTION (Cont.)

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1.5 Initial Condition: None.

1.6 Contractor Work start date: 1/12/2026

1.7 Contractor Work completion date: 5/15/2027

2. PROCEDURE:

2.1 Fabricate and install each temporary cleanliness enclosure listed in 1.3.1 in accordance with Ref. No. 3, using Enclosure-01 for guidance.

2.2 Modify each temporary cleanliness enclosure listed in 1.3.1 in accordance with Ref. No. 3, when requested by Project Team.

2.3 Remove each temporary cleanliness enclosure listed in 1.3.1 in accordance with Ref. No. 3, when requested by Project Team.

2.4 Notes:

2.4.1 Planner: Code 231B N. Kurokawa, 243-0108

2.4.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598

2.4.3 Exact installation, modification, and removal date, area, and detail of temporary cleanliness enclosure listed 1.3.1 will be notified by the Project Team.

2.4.4 JCNs EM01-ZAN5 and EM01-ZAN6 are related to this TGI.

2.5 Government Furnished Material (GFM): None.

2.6 SRF-JRMC will provide the following service work: (TGI No. 3819P23103S02)

2.6.1 [C740] Crane and crane rigger service.

2.6.2 [X99E] Utility service, electrical.

2.6.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.

2.6.4 [C106.1] Safety inspection for SRF-JRMC employees.

2.6.5 [C106.2] Gas free inspection for SRF-JRMC employees.

2.6.6 [C133] QA inspection for (G) symbol(s).

30-AUG-2024 1550

20.14.15.0.8998 (August 2024) (Continued) ICN: 3819P23103 KeyOp: A03

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 8-86-0-E MS A 5 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 13500

CU PHASE TITLE: F/O - ACCOMP INSTL, MOD, AND REM OF TEMP CLEANLINESS ENCL IN 8-86-0-E

FOUO Pg 3 of 3

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N

3 TM 29 CFR PART

1915.71 Scaffolding or Staging - N

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

2.1 RGRS HRs, CARP HRs 22/KE PC N

2.2 RGRS HRs, CARP HRs 22/KE PC N

2.3 RGRS HRs, CARP HRs 22/KE PC N

CFM for covering material and MISC such as and other consumable.

22/MQ CS N

Process Funding Document. 10/CT OM N

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

ATTACHMENT LIST

TITLE FILE NAME SAVED DATE

ENCLOSURE-01 3819P23103A03-Sketch.pdf 10-AUG-2024 0000

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 3819P23103 KEY OP: A03

Sheet 1 of 1

SKETCH

ENCLOSURE-013819P23103A03

PLAN VIEW

8-86-0-E

Naoki.Kurokawa.ja Line

Naoki.Kurokawa.ja_1 Line