Specifications.pdf

PDF 14 MB Posted

Attached to
ELECTRICAL SWITCHING STATION NORTH, WATERVLIET ARSENAL, NEW YORK
Solicitation number
W912DS26RA015
Issued by

About this file

This is a comprehensive Specifications document for the construction of an Electrical Switching Station (North Switch Station) at Watervliet Arsenal in New York. The project involves constructing a backup power facility capable of delivering 4000 kW of power to support the Arsenal during extended outages from the Main Substation. The primary scope includes procurement and installation of four 2MW generators, construction of a generator facility building, installation of electric manholes, duct bank, grounding cable, high-security fencing, switchgear, automatic transfer switches, medium-voltage cables with splices and connections, and associated site work including paving, walks, curbs, and utilities infrastructure. Supporting work encompasses fuel system interconnections, stormwater management, testing, and commissioning of all mechanical, electrical, and control systems. The contract is a firm fixed price construction contract with an estimated performance period of 1081 calendar days from Notice to Proceed, with contract value estimated between $25,000,000 and $100,000,000.

The specifications establish comprehensive requirements for quality control, safety, environmental protection, and project administration. The Contractor must establish a three-phase quality control system (Preparatory, Initial, and Follow-up), maintain a dedicated Quality Control Manager with specific engineering qualifications, and perform extensive testing and inspections coordinated with an independent Special Inspector. Safety requirements mandate compliance with EM 385-1-1, including development of an Accident Prevention Plan, Activity Hazard Analyses, and appointment of a qualified Site Safety and Health Officer. Environmental compliance requires preparation of an Environmental Protection Plan addressing stormwater management per NPDES requirements, hazardous waste management, air quality controls, and erosion/sediment control. The project schedule must be developed in Primavera P6 format with detailed activity-level planning, submitted within 15 days of Notice to Proceed for preliminary approval and within 42 days for the baseline schedule. The Contractor must utilize the Resident Management System (RMS) for contract administration, daily quality control reporting, submittal tracking, and schedule management. Extensive sustainability documentation is required to demonstrate compliance with High Performance and Sustainable Building Guiding Principles, including energy efficiency, water conservation, indoor air quality, recycled content materials, and waste diversion targets. The work is subject to all applicable federal, state, and local regulations, with particular attention to military installation security protocols, force protection conditions, and coordination with ongoing Arsenal operations.

View the file

Other files

File Type Posted
Amendment 0016.pdf PDF
Amendment 0015.pdf PDF
Amendment 0015_23 09 00 and 23 09 23.02.pdf PDF
Amendment 0015_JA for Johnson Controls Inc Metasys.pdf PDF
Amendment 0015_Submittal REGISTER.pdf PDF
Amendment 0014.pdf PDF
Amendment 0013.pdf PDF
Amendment 0012.pdf PDF
Amendment 0011_33 57 55.pdf PDF
Amendment 0011.pdf PDF
Amendment 0011_RFI Photos.pdf PDF
Amendment 0010.pdf PDF
Amendment 0010_Pictures_Switches Nameplates.pdf PDF
Amendment 0009.pdf PDF
Amendment 0009_Photos.pdf PDF
Amendment 0008.pdf PDF
Amendment 0007.pdf PDF
Amendment 0007_Pictures.pdf PDF
Amendment 0007_Site Visit Photos Compressed.pdf PDF
Amendment 0006.pdf PDF
Amendment 0005.pdf PDF
Amendment 0004.pdf PDF
Amendment 0004_C-001.pdf PDF
Amendment 0004_01 14 00.pdf PDF
Amendment 0003_Site Visit Sign In Sheet_06MAY2026.pdf PDF
Amendment 0003.pdf PDF
Amendment 0003_ Site Visit Photos.pdf PDF
Amendment 0002.pdf PDF
Amendment 0002_G-101.pdf PDF
Amendment 0002_01 14 00.pdf PDF
Amendment 0002_01 50 00.pdf PDF
Amendment 0001_JA - ESS North - North - Square D.pdf PDF
Amendment 0001.pdf PDF
Amendment 0001_ JA - ESS North - Fire Alarm.pdf PDF
Amendment 0001_ Spec 33 57 55.pdf PDF
Amendment 0001_ JA - ESS North - CAC-IDS.pdf PDF
Amendment 0001_ Dwg MS101.pdf PDF
Evaluation Factors.pdf PDF
Drawings.pdf PDF
Solicitation - W912DS26RA015.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Department of the Army

New York District

Corps of Engineers

26 Federal Plaza, RM 16-300

New York, NY 10278-0090

FY26 PN 096278 Electrical Switch Station Watervliet, New York

U.S. Army Corps of Engineers, New York District

Specifications 100% RTA Submission

September 2025

North Switch Station 100% RTA Submission Watervliet Arsenal September 2025

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 02/24 SUMMARY OF WORK

01 14 00 11/22, CHG 3: 08/24 WORK RESTRICTIONS

01 20 00 11/20, CHG 4: 08/24 PRICE AND PAYMENT PROCEDURES

01 30 00 11/20, CHG 4: 08/24 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 08/23, CHG 1: 08/24 PROJECT SCHEDULE

01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES

01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND

REPORTING

01 35 26 05/24 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 05/24 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 08/23, CHG 1: 05/24 QUALITY CONTROL

01 45 00.15 10 11/23 RESIDENT MANAGEMENT SYSTEM CONTRACTOR

MODE (RMS CM)

01 45 35 05/24 SPECIAL INSPECTIONS

01 50 00 11/20, CHG 3: 08/24 TEMPORARY CONSTRUCTION FACILITIES AND

CONTROLS

01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS

01 58 00 08/19, CHG 5: 08/22 PROJECT IDENTIFICATION

01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND

DISPOSAL

01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS

01 78 23 05/23 OPERATION AND MAINTENANCE DATA

01 78 24.00 10 05/23 FACILITY DATA REQUIREMENTS

01 91 00.15 05/23, CHG 3: 08/24 BUILDING COMMISSIONING

DIVISION 02 - EXISTING CONDITIONS

02 41 00 08/22 DEMOLITION

DIVISION 03 - CONCRETE

03 30 00 02/19, CHG 7: 02/24 CAST-IN-PLACE CONCRETE

DIVISION 04 - MASONRY

04 20 00 11/15, CHG 2: 05/19 UNIT MASONRY

DIVISION 05 - METALS

05 05 20 05/22, CHG 1: 08/24 POST-INSTALLED CONCRETE AND MASONRY

ANCHORS

05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL

05 21 00 05/15, CHG 1: 08/18 STEEL JOIST FRAMING

05 30 00 05/15, CHG 2: 08/18 STEEL DECKS

05 50 13 05/17, CHG 1: 08/18 MISCELLANEOUS METAL FABRICATIONS

05 51 33 02/16, CHG 2: 02/18 METAL LADDERS

05 52 00 08/23 METAL RAILINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 08/23 BOARD AND BLOCK INSULATION

PROJECT TABLE OF CONTENTS Page 1

07 22 00 08/23 ROOF AND DECK INSULATION

07 27 19.01 08/23 SELF-ADHERING AIR BARRIERS

07 42 63 05/11, CHG 4: 08/20 FABRICATED WALL PANEL ASSEMBLIES

07 53 23 05/12, CHG 2: 08/18 ETHYLENE-PROPYLENE-DIENE-MONOMER

ROOFING

07 60 00 08/23 FLASHING AND SHEET METAL

07 80 00 05/10 ROOF SAFETY RAILINGS

07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING

07 92 00 08/23 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 08/20 STEEL DOORS AND FRAMES

08 33 23 08/20, CHG 1: 02/22 OVERHEAD COILING DOORS

08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE

08 81 00 05/19 GLAZING

08 91 00 08/20 METAL WALL LOUVERS

DIVISION 09 - FINISHES

09 90 00 02/21 PAINTS AND COATINGS

09 96 00 11/14 HIGH-PERFORMANCE COATINGS

DIVISION 10 - SPECIALTIES

10 14 00.20 08/20 INTERIOR SIGNAGE

10 44 16 11/19 FIRE EXTINGUISHERS

DIVISION 12 - FURNISHINGS

12 50 00.13 10 08/17, CHG 1: 11/18 FURNITURE AND FURNITURE INSTALLATION

DIVISION 21 - FIRE SUPPRESSION

21 13 16 08/20 DRY PIPE SPRINKLER SYSTEMS, FIRE

PROTECTION

DIVISION 22 - PLUMBING

22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE

22 05 48.00 20 04/06, CHG 1: 05/15 MECHANICAL SOUND AND VIBRATION CONTROL

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 03 00.00 20 08/10, CHG 3: 08/18 BASIC MECHANICAL MATERIALS AND METHODS

23 05 15 05/22 COMMON PIPING FOR HVAC

23 05 48.19 05/18, CHG 2: 08/20 BRACING FOR HVAC

23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR

HVAC

23 07 00 08/24 THERMAL INSULATION FOR MECHANICAL

SYSTEMS

23 08 00 05/23, CHG 1: 08/24 COMMISSIONING OF MECHANICAL AND

PLUMBING SYSTEMS

23 09 00 08/24 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES

FOR HVAC

23 09 23.02 08/24 BACNET DIRECT DIGITAL CONTROL FOR HVAC

AND OTHER BUILDING CONTROL SYSTEMS

23 23 00 08/21 REFRIGERANT PIPING

PROJECT TABLE OF CONTENTS Page 2

23 30 00 05/20, CHG 1: 02/22 HVAC AIR DISTRIBUTION

23 81 00 05/18, CHG 1: 02/21 DECENTRALIZED UNITARY HVAC EQUIPMENT

DIVISION 25 - INTEGRATED AUTOMATION

25 05 11.01 08/24 CYBERSECURITY FOR UTILITY MONITORING

AND CONTROL SYSTEM

25 05 11.02 08/24 CYBERSECURITY FOR ELECTRICAL SYSTEMS

25 05 11.03 08/24 CYBERSECURITY FOR FIRE PROTECTION

SYSTEMS

25 08 10 05/21 UTILITY MONITORING AND CONTROL SYSTEM

TESTING

25 10 10 02/19, CHG 1: 05/21 UTILITY MONITORING AND CONTROL SYSTEM

(UMCS) FRONT END AND INTEGRATION

DIVISION 26 - ELECTRICAL

26 05 13.00 10 11/23 MEDIUM-VOLTAGE CABLES

26 05 73 08/23 POWER SYSTEM STUDIES

26 08 00 11/22 APPARATUS INSPECTION AND TESTING

26 08 00.00 20 02/21, CHG 1: 05/21 COMMISSIONING OF ELECTRICAL SYSTEMS

26 13 00 05/21, CHG 1: 05/22 SF6/HIGH-FIREPOINT FLUIDS INSULATED

PAD-MOUNTED SWITCHGEAR

26 13 13 11/21 METAL-CLAD SWITCHGEAR

26 13 16 MEDIUM VOLTAGE OUTDOOR LOAD BANK

26 20 00 08/23 INTERIOR DISTRIBUTION SYSTEM

26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS

UNDER 600 VOLTS

26 32 15.00 05/20 ENGINE-GENERATOR SET STATIONARY

15-2500 KW, WITH AUXILIARIES

26 36 23 05/20, CHG 1: 08/21 AUTOMATIC TRANSFER SWITCHES

26 41 00 08/23 LIGHTNING PROTECTION SYSTEM

26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING

SYSTEM

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 10 05 05/24 ELECTRONIC SECURITY SYSTEMS (ESS)

28 31 70 08/20 INTERIOR FIRE ALARM SYSTEM, ADDRESSABLE

DIVISION 31 - EARTHWORK

31 00 00 08/08 EARTHWORK

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 11 20 08/17 BASE COURSE AND SUBBASES FOR FLEXIBLE

PAVING

32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS

32 12 16 08/09 HOT-MIX ASPHALT (HMA) FOR ROADS

32 31 13.53 11/21 HIGH-SECURITY FENCES (CHAIN LINK AND

ORNAMENTAL) AND GATES

32 92 19 08/17 SEEDING

DIVISION 33 - UTILITIES

PROJECT TABLE OF CONTENTS Page 3

33 01 50.31 02/20 LEAK DETECTION FOR FUELING SYSTEMS

33 11 00 02/18 WATER UTILITY DISTRIBUTION PIPING

33 40 00 02/10 STORM DRAINAGE UTILITIES

33 52 40 11/18, CHG 2: 11/20 FUEL SYSTEMS PIPING (NON-HYDRANT)

33 57 55 11/18, CHG 1: 11/20 FUEL SYSTEM COMPONENTS (NON-HYDRANT)

33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 4

SECTION 01 11 00

SUMMARY OF WORK

02/24

PART 1 GENERAL

1.1 FAR 52.211-10, COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK

a. The Contractor is required to (i) commence work under this contract within five (5) calendar days after the date the Contractor receives the Notice to Proceed, (ii) prosecute the work diligently, and (iii) complete the entire work ready for use, not later than 1081 calendar days after the date the Contractor receives the notice to proceed. The time stated for completion must include final cleanup of the premises.

b. The Contractor must furnish all labor, materials, equipment, and services for the following work: shown in the plans and specifications.

c. All work must be in accordance with the drawings and specifications or instructions attached hereto and made a part thereof, or to be furnished hereafter by the Contracting Officer and subject, in every detail, to his supervision, direction, and instructions.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The purpose of the project is to construct a generator connection terminal to provide backup power to the Arsenal in the event of a long-term power outage from the facility’s Main Substation. The primary scope includes electric manholes, duct bank, grounding cable, fencing, switchgear, transfer switches, cables, splices and connections. Supporting facilities include paving, walks, curbs, gutters, and utilities testing and commissioning.

1.2.2 Location

The work is located at the Watervliet Arsenal, New York,, approximately as indicated. The site of the work is on a military reservation and all rules and regulations issued by the Commanding Officer covering general safety, security, and sanitary requirements, etc., must be observed by the Contractor. The exact location will be shown by the Contracting Officer.

1.3 DFARS 236.204, DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECTS

This project is estimated between $25,000,000.00 and $100,000,000.00

1.4 OCCUPANCY OF PREMISES

Building(s) will be occupied during performance of work under this Contract. Occupancy notifications must be posted in a prominent location in the work area.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

SECTION 01 11 00 Page 1

1.5 EXISTING WORK

Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

At Contractor's own expense, immediately restore to service and repair any damage caused by Contractor's workmen to the existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone). Provide immediate notification of the Contracting Officer and verbal procedures to restore.

Immediately assemble personnel, equipment and material necessary to restore. Compliance with Contract Documents for quality installation must be included. The work must proceed at 24-hours per day until satisfactorily restored service is achieved. Fixing loose ends requires Contracting Officer approval to perform during normal working hours. The request to perform repairs during normal working hours requires Contractor's written approval. The write up of procedures to repair must be submitted to Contracting Officer.

Repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

1.6 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.

No excavation whether minor or major including trenching, sidewalk replacement, etc. will be permitted without an approved digging permit.

Contractor shall apply for renewal of work permits as required if the work continues beyond the original permit expiration date. Contact local utility locating service a minimum of 14 days prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.

Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

SECTION 01 11 00 Page 2

1.6.1 Notification Prior to Excavation

Notify the Contracting Officer at least 15 days prior to starting excavation work.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 3

SECTION 01 14 00

WORK RESTRICTIONS

11/22, CHG 3: 08/24

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 13 (2022; TIA 23-4) Standard for the Installation of Sprinkler Systems

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2024) Safety -- Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section

01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel ; G

Digging Permit ; G

SD-07 Certificates

3Rs Explosive Safety Education Training Certificate (annual submission required)

1.3 SPECIAL SCHEDULING REQUIREMENTS

a. Contractor must be ready for operation as approved by Contracting Officer before work is started which would interfere with normal operation.

b. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.

c. The building will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.

d. Permission to interrupt any Activity roads, railroads, or utility

SECTION 01 14 00 Page 1 service must be requested in writing a minimum of 28 calendar days prior to the desired date of interruption.

e. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations.

f. The work to be performed within Building 130 will require escorts to accompany the Contractor. The Contractor must submit adavanced notice within 30 calendar days when work is proposed to begin in Building 130 for escorts to be arranged. All work in Building 130 must be completed in a single mobilization within Building 130, multiple advance notfifications will not be allowed.

1.4 CONTRACTOR ACCESS AND USE OF PREMISES

Notify the Contracting Officer in writing 30 calendar days in advance for any DOT Classified wide loads. The Contractor shall contact the Contracting Officer to determine if there are other access limitations at NUWC Div Newport.

Notify the Explosive Safety Officer (ESO), Frequency Manager, and Test Directors in writing 21 calendar days in advance of bring equipment into the Hazards Of Electromagnetic Radiation to Ordnance emission Control (HERO EMCON) area. Include Make and Model number of equipment in the notification.

Contractor personnel must obey restrictions imposed by operating in a Hazards of Electromagnetic Radiation to Ordnance Emission Control area (HERO EMCON) as outlined in NAVSEA OP 2365 Volume 2.

1.4.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, include delivery vehicles, are clearly identified with their company name.

1.4.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.4.1.2 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

SECTION 01 14 00 Page 2

1.4.2 Working Hours

Regular working hours will consist of an 8 hour period, between 7 a.m. and 3:30 p.m., Monday through Friday, excluding Government holidays. Night and weekend work may be necessary as required by the Contracting Officer's Representative so as to not impact ongoing operations of the facility.

When requested, the contractor will amend their working hours as needed to accomodate ongoing Watervliet Arsenal operations. The contractor may submit a request for equitable adjustment for costs solely due to the change in working hours directed by the U.S. Government. Scheduling of major demolition activities that are particularly noisy or involve excessive vibration must be coordinated with the Contracting Officer and may be outside regular working hours. Excessive noise is defined as exceeding 85-dBA when the equipment is in use or activity is ongoing (measure by a sound level meter set for A scale, slow response). The vicinity of measure is defined as a distance not to exceed 1 meter from the equipment or activity. Techniques such as sound level averaging or exposure time weighting shall not be used to meet this requirement.

Excessive vibration shall adhere to the requirements within EM 385-1-1, chapter 29, for maximum total energy loads (ER) and maximum total peak particle velocities (PV), whichever is more stringent.

1.4.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 28 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.

1.4.4 Exclusionary Period

No work may be performed during the period during the Govt holidays inclusive, without prior written approval of the Contracting Officer. This period has not been considered in computing the time allowed for the performance of this contract.

1.4.5 Occupied Building

The Contractor shall be working around existing buildings which are occupied.

The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.

Provide dust covers or protective enclosures to protect existing work that remains, and Government material located in the work area during the construction period.

1.4.6 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or

SECTION 01 14 00 Page 3 on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS. Such interruptions are further limited to 4 hours or as directed by Contracting offier. This time limit includes time for deactivation and reactivation.

d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.

1.5 DIGGING PERMIT

The Contractor is responsible for obtaining a digging permit prior to commencing excavations. No excavation whether minor or major including trenching, side-walk replacement, etc. will be permitted without an approved digging permit. Contractor must carefully avoid contact or damage with known or identified underground utilities. Work on or near roadways must be flagged in accordance with EM 385-1-1 , which forms a part of these specifications. Work located along the alert force route cannot cause blockage, and the Contractor must maintain un-obstructed access for alert force traffic at all times.

Contractor is required to locate and verify all underground utilities and thereafter maintain those locations on the ground and/or on the contract drawings for use through out the project by all interested.

Dig safe permit must be submitted to the contracting officer's representative a minimum of 30 days prior to the commencement of any work requiring.

A UXO survey will be required to be performed prior to any ground disturbing activities as part of the digging permit approval process.

1.6 CONTRACTOR'S PROJECT WORK ATTENDANCE

Inform the COR and/or Project Inspector of their presence on post at all times. At the beginning and end of each workday, notify the COR and/or Project Inspector of location(s) on post where work is being performed or has been completed for the day.

1.7 SUBCONTRACTORS

It is the responsibility of the Contractor to inform all their subcontractors of all the instructions contained in this information sheet. Subcontractors are responsible to report project work attendance through the Prime Contractor to the COR whenever they are on post.

SECTION 01 14 00 Page 4

1.8 ELEVATED THREAT LEVEL FORCE PROTECTION CONDITION (FPCON) AT WATERVLIET

ARSENAL

Impact on Contractor performance during increased FPCON during periods of increased threat. During FPCONs Charlie and Delta, services may be discontinued/postponed due to higher threat. Services will resume when FPCON level is reduced to level Bravo or lower.

1.9 RANDOM ANTITERRORISM MEASURES PROGRAM (RAMP) AT THE WATERVLIET ARSENAL

In accordance with AR 525-13, Contractor personnel working on an installation are subject to participation in installation RAMP security program (e.g., vehicles, wearing of ID badges) and installation security program.

1.9.1 Badges

All personnel will report to the Visitors Center daily to be issued a pass. They must return the pass when they leave for the day by dropping it off in the drop box by the Visitors Center attached to the barrier to the left prior to entering the exit lane of the south gate. All personnel must show a driver's license or state identification card (picture ID) to the security guard in order to get the pass. If the personnel will be working on the arsenal for over 90 days, they may be authorized a WVA picture badge, which will allow them access during normal work hours without getting a daily pass. All state identification must be REAL ID compliant.

1.9.2 Picture Badges

The Contractor may request through the Contracting Officer a picture badge if the term of the contract warrants. Requests must be made in writing on company letterhead to the Contracting Officer listing the following:

a. Contract Number.

b. Indicate that the individual(s) work for said company.

c. Project name and location of work site (e.g., Bldg. #).

d. Duration of performance (start and stop dates).

e. All personnel being issued a picture badge shall present a passport or original birth certificate (with a raised seal) and driver's license.

(A social security card is not an acceptable form of identification).

f. During performance of the contract, the Contractor is responsible for prompt return of badges for any employee who no longer requires access to the work site.

g. Upon completion or termination of the contract or expiration of badge(s), the Contractor shall ensure that they are returned to the issuing office.

h. Final payment on the contract will be held until all badges are properly returned.

i. Possession of a picture badge does not relieve the badge holder from the responsibility to notify the COR of project work attendance.

SECTION 01 14 00 Page 5

1.10 ACCESS POLICY

a. All Contractor personnel entering the installation and requiring unescorted access must have a valid purpose to enter and be sponsored by a U.S. Government organization or a Contractor providing support on the installation. They must have their identity proofed and vetted through the National Crime Information Center (NCIC) database, and be issued, or in possession of an authorized and valid access credential from the Watervliet Arsenal installation.

b. At the discretion of the Commander, US Army Watervliet Arsenal, any individual known to have a criminal background involving violence or meets the disqualifying standards in the Final Credentialing Standards for Issuing Personal Identity Verification Cards under HSPD-12 (31 JUL 2008) and local command guidance, may be denied access to the Watervliet Arsenal. Fingerprinting of employees and any other security procedures deemed necessary for the security of Watervliet Arsenal (vehicle searches or x-raying packages, bags, briefcases) may be required based on the Force Protection Condition level at the time of access and whether the installation or building location is identified as a restricted area or Mission Essential Vulnerable Area

(MEVA).

1.11 NON-CITIZENS

Non-citizens of the U.S. may not be approved for access.

1.12 CAMERAS

a. The Security Office and Public Affairs Officer must approve all cameras use prior to any pictures being taken, to include using a photographic-capable cell phone as a photographic device. Requests must be submitted to the WVA COR then routed to Security and then to the Public Affairs Officer. Violations may result in the camera and film being confiscated and a citation being issued for an appearance before the U.S. Magistrate in Albany, NY.

b. For any photos that have been approved by the Security Office and Public Affairs Officer be advised that the photos contain military imagery that is owned by the US Government: US Army Watervliet Arsenal. It is not to be used for any purpose other than the purpose for which it is furnished nor distributed or reproduced for any purpose to persons other than the individuals specified to receive it, or their employees, without written consent of the US Army Watervliet Arsenal.

c. All photos must be reviewed by the security office before the photo capture system (e.g., camera, cell phone) has left the arsenal.

1.13 TRAFFIC CONTROL

Post Speed Limit is 15 mph. Parking is allowed in valid spaces only. All valid spaces are clearly marked with white lines on both sides of the space. Vehicles parked in other than valid spaces are subject to being issued traffic citations requiring a monetary fine and/or an appearance before the U.S. Magistrate in Albany, N.Y. Motorists within the confines of WVA are subject to all New York State Vehicle and Traffic Laws. Any moving or nonmoving violation may result in a traffic citation being

SECTION 01 14 00 Page 6 issued. Loading and unloading of vehicles will be allowed only for the amount of time required to perform the function. Vehicles cannot be left unattended in other than valid parking spaces. If a patrol officer can approach a vehicle, write a traffic citation, affix that citation to the vehicle, and depart the area with no one present at the vehicle, that vehicle is considered to be unattended. Both the Fire Department and Security Department must be notified prior to blocking of streets. The Contractor must coordinate through the COR for approval to block or close streets.

1.14 DELIVERIES

Deliveries to Contractors must enter the post through the South Gate.

Contractors expecting deliveries should notify the South Gate (266-5821) prior to the arrival of the delivery. The Contractor's representative must accept deliveries. Materials, which are delivered to the site, are the responsibility of the Contractor. Storage and special conditions must be coordinated with the COR for approval to block or close streets.

1.15 CONTRABAND

Alcohol, illegal drugs, and any firearms are prohibited. Violations may result in the items being confiscated and a citation being issued for an appearance before the U.S. Magistrate in Albany, NY.

1.16 RESTRICTION OF WVA PROVIDED DOCUMENTS

Documents provided by WVA contain proprietary information and are to be used only in support of their current authorized release. Other requests for documents must be referred to the Contracting Officer, Army Contracting Command - Warren (ACC-WRN) (WVA), 1 Buffington Street, Watervliet, NY 12189. Documents shall be destroyed to prevent disclosure and reconstruction of the contents upon completion of contracted work.

1.17 SECURITY OF EQUIPMENT

Contractors are responsible for securing all of their equipment. WVA is not responsible for stolen or lost items.

1.18 VEHICLES IN BUILDINGS

Contractors' vehicles and equipment using fuel shall receive clearance from the Fire Chief before entering the building. Refueling of vehicles in a building requires Fire Department standby.

1.19 STORAGE SHED/TRAILERS/TEMPORARY OFFICES

The placement of all storage shed/trailers/temporary offices are subject to the approval of the Public Works Division, the Watervliet Arsenal Fire department, and the Watervliet Arsenal Security Department. The Contractor shall submit their placement request in writing 10 business days in advance to the project COR or technical POC for request evaluation and approval. (Note: Request approval is not guaranteed.) All temporary sheds, trailers or offices within thirty feet of any Arsenal structure must be equipped with a temporary sprinkler system as required by NFPA 13 .

The Fire Inspection Staff will assist Contractors in determining sprinkler requirements on site, upon request. Call extension 5990 for fire inspector assistance.

SECTION 01 14 00 Page 7

1.20 EQUIPMENT, DUMPSTER, STORAGE CONTAINER/SHED, TRAILER, and OFFICE

IDENTIFICATION

Contractor shall prominently display the following information on all Contractor and subcontractor, owned, leased or rented motorized and wheeled equipment, dumpsters, storage containers/sheds, trailers, and offices:

a. Contractor Company Name.

b. Project Number/Contract Number or Equivalent (information will be provided to Contractor by the Watervliet Arsenal, the Arsenal Partnership (AP), or the AP's Construction Manager).

c. Contractor Project Point of Contact (POC) with phone number or Arsenal/AP Project POC with phone number (information will be provided to Contractor by the Watervliet Arsenal, the AP, or the AP's Construction Manager).

1.21 GASOLINE CONTAINERS AND FLAMMABLES

Gasoline will be stored in safety containers equipped with self closing lids and other features as certified by the Underwriters' Laboratories.

Flammable liquids will be kept in National Fire Protection Association or UL approved containers; Fire Department (extension 5990) will be called in event of a question. If gasoline or any other type fuel is kept in a portable tank it must have secondary containment or the tank be double walled and the product labeled on the side of the tank (e.g., flammable).

1.22 FIRE HYDRANTS

Fire hydrants shall not be used without the permission of Facilities Engineering and notification of the Fire Department (extension 5990). If permission is granted to use hydrants, the Contractor will provide adapters, valves and hoses. A backflow preventer will also be required of the Contractor. It is the responsibility of the Contractor to ensure the hydrants are shut off and have drained properly. The Fire Department must be notified when finished.

1.23 DISCHARGES

Unless granted prior written approval, there shall be no discharge to the sanitary sewer, the storm sewer, the industrial sewer system, or the Industrial Waste Treatment Plant (IWTP). Except when WVA has established with the Contractor a prior written agreement regarding discharge of "purge water" originating from groundwater monitoring wells and/or "decontamination water" originating from activities associated with groundwater monitoring wells, there shall be no dumping of oil or chemicals or fluids to the ground.

1.24 DOCUMENTATION OF DISPOSITION OF MATERIALS AND ITEMS REMOVED FROM

WATERVLIET ARSENAL

The Contractor shall furnish documentation of the final disposition of all materials and items leaving Watervliet Arsenal. If an item is resold intact, indicate such action for the item and the name and address of purchaser. If oil is drained from an item, provide documentation for both the oil and the item by identifying final disposition location and management method for each (e.g., recycled, incinerated, land filled).

SECTION 01 14 00 Page 8

All materials and items leaving Watervliet Arsenal shall be managed strictly in accordance with all applicable environmental regulations. The Contractor shall indicate intentions for all such materials and items at the pre-construction meeting, for approval by Watervliet Arsenal.

1.25 WASTE DISPOSAL

All hazardous waste shall be disposed of by the Contractor. The Contractor is responsible for management and disposal of all hazardous waste in accordance with applicable regulations, WVA's Hazardous Waste Management Plan, Section 01 57 19 and the Contractor's Approved Environmental Protection Plan. Hazardous waste shall be moved to Building 145 for 90 day storage in accordance with the RCRA "three day" rule.

Drums of hazardous waste shall not remain outdoors overnight. Other wastes include any spent material such as garbage, packaging, residues, construction and demolition debris, excavated soils and earthen materials not designated for immediate reuse, etc., which is known by WVA and/or demonstrated by the Contractor via appropriate sampling and analysis to not be hazardous waste (such demonstration shall be to the satisfaction of WVA). The Contractor is responsible for disposal of other wastes, unless noted otherwise. Disposal of wastes at private sites such as sites advertising clean fill wanted, etc., is prohibited. The Contractor shall comply with 6 NYCRR Part 364 for all waste hauling activities. The Contractor shall furnish copies of documents for each waste shipment, such as Bills of Lading, etc., (Including "light weight" upon entering WVA, and "heavy weight" upon exiting WVA) through the COR to Facilities Engineering. Contractor shall furnish and properly label new, unused, appropriate drums and/or containers (including, but not limited to, compliance with DOT's Performance Oriented Packaging Standards (POPS)) for containerizing waste. Contractor supplied dumpsters shall be covered with water proof covers to prevent precipitation from entering the dumpster.

Covers shall be secured in place whenever the Contractor leaves the job site, and whenever precipitation is possible or occurring. Scrap metals that are recycled at an approved scrap metal facility do not required testing and waste characterization. Proper cleaning (triple rinse) is still required.

1.26 INDUSTRIAL WASTE TREATMENT PLANT (IWTP)

Due to OSHA Process Safety Management rule requirements, the Contractor shall coordinate with the IWTP Leader regarding IWTP-specific requirements when work is to be performed in and/or around the IWTP.

Requirements will include:

a. Hazard awareness of chemicals used at the facility to include sulfur dioxide (so2), chromic acid, and sulfuric acid.

b. Hazmin system-access by IWTP leader for all chemicals/sds upon request.

c. Proper PPE to be used when working with chemicals. This shall include protective suites (Tyvek), hardhats, chemical resistant gloves, respiratory protection, and hearing protection.

d. Building evacuation procedures when so2 alarm activates.

e. Must sign in/out of IWTP roster as acknowledgment this procedure.

SECTION 01 14 00 Page 9

1.27 UTILITY CLEARANCE PERMIT (UCP)

All contracted work is subject to the WVA Regulation on utility clearance permits, WVAR 420-02. The Contractor will assist the COR in preparing the UCP. The Contractor shall review the project site, project documents and utility record plans to determine the presence of concealed utilities within the area(s) of the project work. The Contractor is required to sign the UCP and concur / non-concur with the project UCP.

1.28 MARKING UNDER GROUND UTILITIES

All contract work, which involves the installation or unearthing of underground utilities, shall include the marking of these utilities as part of the required project work. The tape shall be detectable by a metal detector when buried up to 3 feet deep. The tape shall be of a type specifically manufactured for marking and locating underground utilities.

The metallic core of the tape shall be encased in a protective jacket or provided with other means to protect it from corrosion. Tape color shall be as specified below and shall bear a continuous printed inscription describing the specific utility.

RED: ELECTRIC

BLUE: WATER SYSTEM

GREEN: SEWER SYSTEM

YELLOW: GAS LINE OR PIPELINE (FOR NATURAL GAS, OIL,

STEAM/CONDENSATE OR OTHER DANGEROUS MATERIALS)

ORANGE: FIBER OPTIC (TELEPHONE, TELEVISION, SECURITY OR FIRE ALARM)

SULFUR DIOXIDE (SO2) AWARENESS

Due to the presence of highly hazardous chemicals located in the Industrial Waste Treatment Plant, always follow the instructions of WVA officials quickly and completely in the event of any emergency. This is especially important when working in or near the Industrial Waste Treatment Plant (IWTP).

Because of the requirements of OSHA's Process Safety Management (PSM) standard (For specific requirements see Title 29 of the Code of Federal Regulations, Part 1910.119 on the OSHA website) safe work practices have been developed that provide for the control of hazards during operations such as lockout/tag out; confined space entry; line breaking of process associated piping; control over IWTP facility entry. These safe work practices apply to all employees and Contractors equally. Contractors must follow all safe work practices while working on the installation and provide training to employees on PSM before working within the IWTP.

For Contractors performing maintenance or repair, turnaround, major renovation, or specialty work on or adjacent to a covered process, contact the Contracting Officer's Representative (COR) for more instructions on special provisions of the PSM standard that applies to this work.

1.29 ARMY AND ARMY NATIONAL GUARD REQUIREMENTS AND RESTRICTIONS

1.29.1 3Rs Explosive Safety Education Training Certificate

All Contractor and subcontractor employees requiring access to Army or Army National Guard installations, facilities, and areas for the performance of a contract or subcontract must complete the 3Rs (Recognize, Retreat, Report) Explosives Safety Education Program training. Complete

SECTION 01 14 00 Page 10 the training within 30 calendar days after the date of receipt of a written notice of award. The Contractor is responsible for ensuring that all subcontractor employees complete the training before access to the installation is required for performance of the subcontract. The Contractor is also responsible for ensuring that all contractor and subcontractor employees renew the training annually for the duration of the performance period of the contract or subcontract. The Contractor must submit certificates of completion for each Contractor and subcontractor employee subject to this requirement to the Contracting Officer’s Representative (COR) or to the Contracting Officer, if a COR is not assigned, within 5 calendar days after completion of training. 3Rs Explosives Safety Education Program training is available at the following website: https://www.denix.osd.mil/uxo/3rs-training/ .

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

SECTION 01 14 00 Page 11

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

11/20, CHG 4: 08/24

PART 1 GENERAL

1.1 CONTRACT COST BREAKDOWN

The Contractor must furnish within 30 days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items. This Contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.

1.2 SINGLE JOB PAYMENT ITEMS

Payment items for the work of this Contract for which Contract job payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

SECTION 01 20 00 Page 1

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

11/20, CHG 4: 08/24

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

View Location Map

Progress and Completion Pictures

1.3 VIEW LOCATION MAP

Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

1.4 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice a set of digital photographs, electronically, cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch electronically as a digital file. Include a date designator in file names. Photographs provided are for unrestricted use by the Government.

Refer to section 01 33 00 SUBMITTAL PROCEDURES, Electronic File Format paragraph for information on electronic file format for submission.

SECTION 01 30 00 Page 1

1.5 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by the New York State law and 52.228-5 - Insurance - Work on a Government Installation.

a. Before commencing work under this contract, the Contractor must notify the Contracting Officer in writing that the required insurance has been obtained. The policies evidencing required insurance must contain an endorsement to the effect that cancellation or material change adversely affecting the Government's interest cannot be effective for such a period as may be prescribed by the laws of the State in which this contract is to be performed and in no event less than 30 days after written notice thereof to the Contracting Officer.

b. The Contractor must insert the substance of this clause, including this paragraph (b), in subcontracts under this contract that require work on a Government installation and must require subcontractors to provide and maintain the insurance required in the Schedule or elsewhere in the contract. The Contractor must maintain a copy of all subcontractors' proofs of required insurance, and must make copies available to the Contracting Officer upon request.

c. This insurance will be included at no additional cost to the government.

1.6 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS

In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS

222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) Contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE Contractors are encouraged to seek out highly qualified veterans to perform services under this contract.

The following resources are available to assist USACE Contractors in their outreach efforts:

Federal Veteran employment information at http://www.fedshirevets.gov/index.aspx Department of Labor Veterans Employment Assistance https://www.dol.gov/vets/ Department of Veterans Affairs-VOW to Hire Heroes Act http://benefits.va.gov/vow/ Army Wounded Warrior Program-http://wtc.army.mil/modules/employers/index.html U.S. Chamber of Commerce Foundation-Hiring Our Heroes http://www.hiringourheroes.org /

1.7 SUPERVISION

1.7.1 Superintendent Qualifications

Provide project superintendent with a minimum of 10 years experience in

SECTION 01 30 00 Page 2 construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

1.7.2 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work. In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.

1.7.3 Duties

The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.7.4 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.8 SUPERINTENDENCE OF SUBCONTRACTORS

a. The Contractor shall be required to furnish the following, in addition to the superintendence required by the Contract Clause titled, "SUPERINTENDENCE BY THE CONTRACTOR".

(1) If more than 50% and less than 70% of the value of the contract work is subcontracted, one superintendent shall be provided at the site and on the Contractor's payroll to be responsible for coordinating, directing, inspecting and expediting the subcontract work.

(2) If 70% or more of the value of the work is subcontracted, the Contractor shall be required to furnish two such superintendents to be responsible for coordinating, directing, inspecting and expediting the subcontract work.

b. If the Contracting Officer, at any time after 50% of the subcontracted work has been completed, finds that satisfactory progress is being made, SECTION 01 30 00 Page 3 he may waive all or part of the above requirement for additional superintendence subject to the right of the Contracting Officer to reinstate such requirement if at any time during the progress of the remaining work he finds that satisfactory progress is not being made.

1.9 PRECONSTRUCTION CONFERENCE

Immediately after award, prior to commencing any work at the site, coordinate with the Contracting Officer a time…

This is the start of the file's text. The full file is on GovTribe.