SOW_B-2_CLN-1_38KC3123CQ_A01_NEW TGI_c0v0.pdf

PDF 301 KB Posted

Attached to
USS SHOUP (DDG-86) 7C1 SRA BUNDLE-2
Solicitation number
N6264926RA060
Issued by

About this file

This is a WebAIM Short Form Task Group Instruction (TGI) for U.S. Navy maintenance work on the USS SHOUP (DDG-86). The document provides detailed specifications for replacing exterior insulation and lagging on the 2B Gas Turbine Module (GTM) exhaust duct located in Uptake Engine Room No. 2, compartments 01-248-0-Q and 02-242-0-Q. The work scope includes removing 150 square feet of existing insulation (MIL-PRF-2818) and lagging (MIL-C-20079, Type I, Class 9) and installing new materials to the same specifications. The initial condition notes a potential asbestos hazard, requiring appropriate handling procedures. Work procedures reference MIL-STD-769 for insulation requirements and drawing 259-7060867 for fabrication and installation guidance. Contractor start and completion dates are referenced to a separate TGI Period of Performance (POP) List.

The Government Furnished Material (GFM) includes ten distinct items specified in the Material List: thermal insulation blankets (Rockwool SEAROX SL 620), wire mesh, finish cement, strapping, seals, glass cloth, felt, wire fabric, cork and rubber sheet, and adhesive. Supporting services to be provided by SRF-JRMC include crane and rigging, utility services (low pressure air, water, and steam supply), safety and gas-free inspections for employees, and QA inspection for specified quality assurance symbols. The TGI was prepared by M. Hosoda (Code 234) and approved by N. Izumi (Code 234) on 06-MAY-2026, with Work Integration Manager T. Yaginuma assigned as the zone manager. A sketch (Enclosure-01) provides visual reference for work location and scope.

View the file

Other files

File Type Posted
Solicitation Amendment N6264926RA0600006 SF 30.pdf PDF
Solicitation Amendment N6264926RA0600005 SF 30.pdf PDF
Solicitation Amendment N6264926RA0600004 SF 30.pdf PDF
SOW_B-2_CLN-1_38KC3123CC_A01_NEW TGI_c1v1.pdf PDF
Solicitation Amendment N6264926RA0600003 SF 30.pdf PDF
Solicitation Amendment N6264926RA0600002 SF 30.pdf PDF
SOW_B-2_CLN-1_38KC3123CH_A01_NEW TGI_c1v1.pdf PDF
Solicitation Amendment N6264926RA0600001 SF 30.pdf PDF
SOW_B-2_CLN-1_38KC3123CC_A01_NEW TGI_c0v0.pdf PDF
SOW_B-2_CLN-1_38KC312366_A01_NEW TGI_c2v1.pdf PDF
SOW_B-2_CLN-1_38KC312303_A01_NEW TGI_c0v0.pdf PDF
Attachment IV Request for Information Form.docx DOCX document
Attachment VI Warranty Tracking Information.pdf PDF
SOW_B-2_CLN-1_38KC312301_A01_NEW TGI_c0v0.pdf PDF
Attachment IV Request for Information Sheet (Fillable).pdf PDF
Exhibit A Contract Data Requirements List (CDRL) IPS.pdf PDF
SOW_B-2_CLN-1_38KC3123CH_A01_NEW TGI_c0v0.pdf PDF
Attachment I POP list BUNDLE-2_Rev2.pdf PDF
SOW_B-2_CLN-1_38KC331104_A01_NEW TGI_c0v0.pdf PDF
Attachment VIII Contract data.pdf PDF
Exhibit B Contract Data Requirements List (CDRL) GFP.pdf PDF
Attachment III DDG-115_BUNDLE1_GFP_List.xlsx XLSX spreadsheet
SOW_B-2_CLN-1_38KC312318_A01_NEW TGI_c0v0.pdf PDF
SOW_B-2_CLN-1_38KC312302_A01_NEW TGI_c0v0.pdf PDF
SOW_B-2_CLN-1_38KC3123CK_A01_NEW TGI_c0v0.pdf PDF
SOW_B-2_CLN-1_38KC313905_A03_NEW TGI_c0v0.pdf PDF
SOW_B-2_CLN-1_38KC3123BT_A01_NEW TGI_c0v0.pdf PDF
Attachment VII QSAP.pdf PDF
SOW_B-2_CLN-1_38KC3123AY_A01_NEW TGI_c0v0.pdf PDF
Solicitation - N6264926RA060.pdf PDF
Attachment V Source of Repair Instruction.pdf PDF
SOW_B-2_CLN-1_38KC3123CT_A01_NEW TGI_c0v0.pdf PDF
SOW_B-2_CLN-1_38KC312304_A01_NEW TGI_c0v0.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

12-MAY-2026 1007

20.15.6.0.9333 (July 2025) ICN: 38KC3123CQ KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: #2B GTM UPTAKE IN A 2 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-86 USS SHOUP KC3 25914

CU PHASE TITLE: *F/O – REPLACE INSULATION AND LAGGING ON 2B GTM EXHAUST DUCT IN 01-248-0-Q

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 6

EM02WA08

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

HOSODA, MASATO 234 3152434572 06-MAY-2026

APPROVED BY: CODE: PHONE: DATE:

IZUMI, NORIAKI 234 3152432243 06-MAY-2026

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

EM02-WA08

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE STACK U

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

123A21CQ

1. SCOPE/PURPOSE:

1.1 Title: Exterior Insulation and Lagging on 2B Gas Turbine Module (GTM) Exhaust Duct; replace

1.2 Location of Work:

1.2.1 Uptake Engine Room No. 2 (01-248-0-Q)

1.2.2 Uptake Engine Room No. 2 (02-242-0-Q)

1.3 Identification:

1.3.1 Quantity (150 SF), Exterior Insulation and Lagging, 2B GTM Exhaust Duct Interior Insulation: MIL-PRF-2818 Lagging: MIL-C-20079, Type I, Class 9 Piece Number: DMEX2/UP015 Remarks: See Sketch Enclosure-01 for details.

TGI Short Form

12-MAY-2026 1007

20.15.6.0.9333 (July 2025) (Continued) ICN: 38KC3123CQ KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: #2B GTM UPTAKE IN A 2 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-86 USS SHOUP KC3 25914

CU PHASE TITLE: *F/O – REPLACE INSULATION AND LAGGING ON 2B GTM EXHAUST DUCT IN 01-248-0-Q

FOUO Pg 2 of 6

CU PHASE DESCRIPTION (Cont.)

1.4 Security Classification: None.

1.5 Initial Condition:

1.5.1 Potential Asbestos Hazard

1.6 Contractor Start Date: See TGI POP List

1.7 Contractor Work Completion Date: See TGI POP List

2. PROCEDURE:

2.1 Remove each existing insulation and lagging listed in 1.3.1 from exhaust duct, using Ref. No. 3 for guidance.

2.2 Accomplish the requirements of 009-011 of Ref. No. One for installation each new insulation and lagging listed in 1.3.1 to exhaust duct, using Ref. No. 4 for guidance.

2.2.1 Accomplish the requirements of 009-032 of Ref. No. One for top surface where new insulation and lagging are installed.

2.3 Accomplish the requirements of 009-032 of Ref. No. One for each new and disturbed surface.

2.4 Notes:

2.4.1 Planner: Code 234 M. Hosoda, 243-4572

2.4.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598

2.4.3 JCN EM02-WA08 is related to this TGI.

2.5 Government Furnished Material (GFM):

2.5.1 SRF-JRMC will provide GFM listed in the Material List.

2.6 SRF-JRMC will provide the following service work: (TGI No: 38KC3123CQS02)

2.6.1 [C740] Crane and crane rigging service.

2.6.2 [X99E] Provide utility service.

2.6.3 [X99M] Provide utility service, including low pressure air supply, water supply, and steam supply.

2.6.4 [C106.1] Safety inspection for SRF-JRMC employees.

2.6.5 [C106.2] Gas free inspection for SRF-JRMC employees.

2.6.6 [C133] QA inspection for (G) symbol(s).

12-MAY-2026 1007

20.15.6.0.9333 (July 2025) (Continued) ICN: 38KC3123CQ KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: #2B GTM UPTAKE IN A 2 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-86 USS SHOUP KC3 25914

CU PHASE TITLE: *F/O – REPLACE INSULATION AND LAGGING ON 2B GTM EXHAUST DUCT IN 01-248-0-Q

FOUO Pg 3 of 6

CU PHASE DESCRIPTION (Cont.)

12-MAY-2026 1007

20.15.6.0.9333 (July 2025) (Continued) ICN: 38KC3123CQ KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: #2B GTM UPTAKE IN A 2 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-86 USS SHOUP KC3 25914

CU PHASE TITLE: *F/O – REPLACE INSULATION AND LAGGING ON 2B GTM EXHAUST DUCT IN 01-248-0-Q

FOUO Pg 4 of 6

OTHER SPECIAL REQUIREMENTS:

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY-27 NAVSEA Standard Items - 2 N 2 LI LI FY-27 Local Standard Items - N 3 MIL MIL-STD-769 Insulation Requirements for

U.S. Naval Vessels K 1 N

4 DWG 259-7060867 FAB & INSTL OF GTRB

UPTAKE ENG RM NO.2 &

ABOVE

B N

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

001 M INSULATION, INSULATION

BLANKET,

THERMAL,MINERAL

WOOL,SPEC: MIL-PRF-

2818,SIZE: 24" X 48" X 2" THK,

DENSITY: 8 LBS/CU FT,BIW

CATALOG NO. 47111-

030,ROCKWOOL P/N: SEAROX

SL 620(128),

REMARKS: OMIT METALLIC

SUPPORT MEMBERS FROM

BOTH SIDES,

ORDERED FOR KTR

ORIG: C234 M. HOSODA, 243-

9B 5640 LL9606678 NA 4 N 61277470 50/SH

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 38KC3123CQ KEY OP: A01

12-MAY-2026 1007

20.15.6.0.9333 (July 2025) (Continued) ICN: 38KC3123CQ KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: #2B GTM UPTAKE IN A 2 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-86 USS SHOUP KC3 25914

CU PHASE TITLE: *F/O – REPLACE INSULATION AND LAGGING ON 2B GTM EXHAUST DUCT IN 01-248-0-Q

FOUO Pg 5 of 6

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

002 M WIRE MESH,

WIRE,MESH,CHICKEN NET,#20

X 16 MESH

NO.20G,HEXAGONAL WIRE

NETTING,

GALVANIZED

STEEL,1RLL=30METER

ORDERED FOR KTR

ORIG: C234 M. HOSODA, 243-

9Z 5340 LL4651079 NA 4 N 61277810 1/RL

003 M CEMENT,I, CEMENT, FINISH

ORDERED FOR KTR

ORIG: C234 M. HOSODA, 243-

9Q 5640 002264540 NA 4 Y 61275111 7/BG

004 M STRAPPIN, HAYATA TOUGH

BAND, MATL: CRES 316,

5/8"(15.88MM)W X

0.015"(0.38MM)THK X 100FT

LG.

ORDERED FOR KTR

ORIG: C234 M. HOSODA, 243-

9Z 5340 LL6978272 NA 4 N 61277471 2/RO

005 M SEAL,STR, SEAL, STRAPPING

ORDERED FOR KTR

ORIG: C234 M. HOSODA, 243-

9B 5340 006643249 NA 4 N 61275113 10/EA

006 M CLOTH,PL, H/W GLASS CLOTH

COLOR IS NATURAL

ORDERED FOR KTR

ORIG: C234 M. HOSODA, 243-

9B 8305 001487364 NA 4 N 61275115 1/RO

007 M INSULATI, FELT,

ORDERED FOR KTR

ORIG: C234 M. HOSODA, 243-

9B 5640 001736591 NA 4 Y 61275120 1/RO

008 M WIRE FAB, WIRE MESH

ORDERED FOR KTR

ORIG: C234 M. HOSODA, 243-

9B 5335 005989404 NA 4 N 61275125 1/EA

009 M CORK AND RUBBER SH, CORK

AND RUBBER SHEET,

SPEC: AMS-C-6183

(FORMERLY: MIL-C-6183), TY-I

(MOLDED), CL-1 (AROMATIC

FUEL), GR-B (MEDIUM),

SIZE: 36"W X 36"L X 3/16"THK,

ORDERED FOR KTR

ORIG: C234 M. HOSODA, 243-

9Z 5330 LL4823084 NA 4 N 61277472 1/SH

12-MAY-2026 1007

20.15.6.0.9333 (July 2025) (Continued) ICN: 38KC3123CQ KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: #2B GTM UPTAKE IN A 2 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-86 USS SHOUP KC3 25914

CU PHASE TITLE: *F/O – REPLACE INSULATION AND LAGGING ON 2B GTM EXHAUST DUCT IN 01-248-0-Q

FOUO Pg 6 of 6

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

010 M ADHESIVE, ADHESIVE FOR

CLOTH

ORDERED FOR KTR

ORIG: C234 M. HOSODA, 243-

9B 8040 002738708 NA 4 Y 61275127 7/GL

ATTACHMENT LIST

TITLE FILE NAME SAVED DATE

ENCLOSURE-01 38KC3123CQA01-Sketch.pdf 06-MAY-2026 0000

SKETCH

ENCLOSURE-01 Sheet 1 of 138KC3123CQA01

Uptake Engine Room No. 2 (01-248-0-Q)

Remove existing and install new insulation and lagging listed in 1.3.1