WebAIM Short Form Task Group Instruction for USS SHOUP (DDG-86) Corrosion Pit Repair
This document is a Task Group Instruction (TGI) that provides detailed repair specifications for the USS SHOUP (DDG-86). The instruction authorizes repair work on a corrosion pit located on Oil Tight Longitudinal Girder No. 4(S) in compartment 5-300-01-E, between Frames 300 and 308 on the starboard side. The base material is high-strength steel (MIL-S-22698, Grade DH-36), weighing 20.4 pounds. The work is classified as a Field Order (F/O) and is prepared under Project KC3 with TGI No. 38KC3123CH, issued July 29, 2026. Prepared by Tsubasa Kosuge (Code 231A) and approved by Yuuji Nakamura (Code 231A), with zone manager Takehide Yaginuma overseeing execution.
The repair procedure requires pumping out, cleaning, and drying the bilge area in the Air Conditioning Machinery and Pump Room (5-300-01-E) and Fuel Tank Group-3 (5-300-1-F) to remove oil, debris, and foreign matter. Weld repair of the corrosion pit must comply with NAVSEA Standard Items (NSI FY-27) requirements, specifically sections 009-012 and 009-032, with reference to Drawing 100-7060403. SRF-JRMC will provide supporting services including crane and rigging, electrical and utility services (air, water, steam), safety inspections, gas-free inspections, and QA inspection for "G" symbol work. The instruction clears DFS DDG-86-1000-2026 in its entirety and cross-references related work covered under separate TGIs including dewatering of fuel tanks and space opening/closing procedures.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
29-JUL-2026 0733
20.16.6.0.9631 (May 2026) ICN: 38KC3123CH KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CRSNPIT IN5-300-01-E AY A 0 1/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-86 USS SHOUP KC3
CU PHASE TITLE: *F/O - REPAIR CRSN PIT ON OIL TIGHT LONGITUDINAL GIRDER NO. 4(S) IN 5-300-01-E
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 4
ES01NPAV
PREPARING ACTIVITY: STATUS: APP WORKING STATUS: PKG
PREPARED BY: CODE: PHONE: DATE:
KOSUGE, TSUBASA 231A 3152434371 19-MAR-2026
APPROVED BY: CODE: PHONE: DATE:
NAKAMURA, YUUJI 231A 3152436041 28-JUL-2026
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
ES01-NPAV
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA, TAKEHIDE
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
123A41CH
1. SCOPE/PURPOSE:
1.1 Title: Corrosion Pit on Oil Tight Longitudinal Girder No. 4(S) in 5-300-01-E; repair
1.2 Location of Work:
1.2.1 Air Conditioning Machinery and Pump Room (5-300-01-E)
1.2.2 Fuel Tank Group-3 (5-300-1-F)
1.3 Identification:
1.3.1 Quantity (One Lot), Oil Tight Longitudinal Girder No. 4(S) in 5-300-01-E, between Frames 300 and 308, Starboard
Base Material: HS, MIL-S-22698, GR DH-36, 20.4 LBs, Plate Remarks: See Sketch Enclosure-01 for location detail
TGI Short Form
29-JUL-2026 0733
20.16.6.0.9631 (May 2026) (Continued) ICN: 38KC3123CH KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CRSNPIT IN5-300-01-E AY A 0 1/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-86 USS SHOUP KC3
CU PHASE TITLE: *F/O - REPAIR CRSN PIT ON OIL TIGHT LONGITUDINAL GIRDER NO. 4(S) IN 5-300-01-E
FOUO Pg 2 of 4
CU PHASE DESCRIPTION (Cont.)
1.4 Security Classification: None.
1.5 Initial Condition: None.
1.6 Contractor work start date: See TGI POP List
1.7 Contractor work completion date: See TGI POP List
2. PROCEDURE:
2.1 Pump out, clean and dry the bilge area located in 1.2.1 free of oil, debris, and other foreign matter.
2.2 Accomplish weld repair of corrosion pit on each existing oil tight longitudinal girder no. 4(s) listed in 1.3.1, using Ref. No. 3 for guidance.
2.2.1 Accomplish the requirements of 009-012 of Ref. No. One, including Table 2, Column(s) A, Lines One through 7.
2.3 Accomplish the requirements of 009-032 of Ref. No. One for each new and disturbed surface.
2.4 Notes:
2.4.1 Planner: Code 231A T. Kosuge, 243-4371
Engineer: Code 250 K. Nogi, 243-5294
2.4.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-6522-9560
2.4.3 Provision of oily/chemical water barge will be coordinated by Project Team.
2.4.4 This TGI is in response to CCIMS report No. CCIMS-G1N6-DDG86-041-26 from TGI No. 38KC111007I04.
2.4.5 Opening, initial cleaning, and closing of each space listed in 1.2.2 will be covered by TGI No. 38KC312337A01 (KTR TGI).
2.4.6 Dewatering of Fuel Tank GP-3 and GP-4 to open the tank and to adjust ship’s trim and ship’s list will be covered by TGI No. 38KC312305D01 (SRF-JRMC TGI).
2.4.7 This TGI clears DFS DDG-86-1000-2026 in its entirety.
2.4.8 JCN ES01-NPAV is related to this TGI.
2.5 Government Furnished Material (GFM): None.
2.6 SRF-JRMC will provide the following service work: (TGI No. 38KC3123CHS02).
2.6.1 [C740] Crane and crane rigging service.
2.6.2 [X99E] Utility service, electrical.
2.6.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.
29-JUL-2026 0733
20.16.6.0.9631 (May 2026) (Continued) ICN: 38KC3123CH KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CRSNPIT IN5-300-01-E AY A 0 1/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-86 USS SHOUP KC3
CU PHASE TITLE: *F/O - REPAIR CRSN PIT ON OIL TIGHT LONGITUDINAL GIRDER NO. 4(S) IN 5-300-01-E
FOUO Pg 3 of 4
CU PHASE DESCRIPTION (Cont.)
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
2.6.4 [C106.1] Safety inspection for SRF-JRMC employees.
2.6.5 [C106.2] Gas free inspection for SRF-JRMC employees.
2.6.6 [C133] QA inspection for (G) symbol(s).
29-JUL-2026 0733
20.16.6.0.9631 (May 2026) (Continued) ICN: 38KC3123CH KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CRSNPIT IN5-300-01-E AY A 0 1/1
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-86 USS SHOUP KC3
CU PHASE TITLE: *F/O - REPAIR CRSN PIT ON OIL TIGHT LONGITUDINAL GIRDER NO. 4(S) IN 5-300-01-E
FOUO Pg 4 of 4
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 NSI FY-27 NAVSEA Standard Items - 2 N 2 LI FY-27 Local Standard Items - N
3 DWG 100-7060403 UNIT STRL ARR DWG ASSY
UNIT 3110
D Y 4B
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
ATTACHMENT LIST
TITLE FILE NAME SAVED DATE
ENCLOSURE-01 38KC3123CH-Sketch.pdf 28-JUL-2026 0000
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 38KC3123CH KEY OP: A01
Tsubasa.Kosuge.ja Text Box Location of Corrosion Pit in 5-300-01-E
Tsubasa.Kosuge.ja_1 Text Box Enclosure-01
Tsubasa.Kosuge.ja_2 Text Box Sketch
Tsubasa.Kosuge.ja_3 Text Box
38KC3123CHA01
Tsubasa.Kosuge.ja_4 Text Box Sheet 1 of 3
Tsubasa.Kosuge.ja_5 Line
Tsubasa.Kosuge.ja_6 Line
Tsubasa.Kosuge.ja_7 Text Box
DET 1-B
Tsubasa.Kosuge.ja_8 Text Box
DET 1-A
Tsubasa.Kosuge.ja_9 Line
Tsubasa.Kosuge.ja_10
Location of Corrosion Pit in 5-300-01-E
Tsubasa.Kosuge.ja_11 Text Box Sheet 2 of 3
Tsubasa.Kosuge.ja_12 Text Box Enclosure-01
Tsubasa.Kosuge.ja_13 Text Box Sketch
Tsubasa.Kosuge.ja_14 Text Box
38KC3123CHA01
Tsubasa.Kosuge.ja_15 Text Box See DET A, B, and C
Tsubasa.Kosuge.ja_16 Text Box
DET 1-A
Tsubasa.Kosuge.ja_17 Text Box
DET 1-B
Tsubasa.Kosuge.ja_18 Text Box See DET D
Tsubasa.Kosuge.ja_19 Line
Tsubasa.Kosuge.ja_20
Location of Corrosion Pit in 5-300-01-E
Tsubasa.Kosuge.ja_21 Text Box Sheet 3 of 3
Tsubasa.Kosuge.ja_22 Text Box Enclosure-01
Tsubasa.Kosuge.ja_23 Text Box Sketch
Tsubasa.Kosuge.ja_24 Text Box
38KC3123CHA01
Tsubasa.Kosuge.ja_25 Text Box DET A, B, and C
Tsubasa.Kosuge.ja_26 Text Box
DET D
Tsubasa.Kosuge.ja_27 Text Box A
Tsubasa.Kosuge.ja_28 Text Box B
Tsubasa.Kosuge.ja_29 Text Box C
Tsubasa.Kosuge.ja_30 Text Box D
Tsubasa.Kosuge.ja_31 Text Box
DET A
Tsubasa.Kosuge.ja_32 Text Box
DET B
Tsubasa.Kosuge.ja_33 Text Box
DET C
Tsubasa.Kosuge.ja_34 Text Box
DET D
Tsubasa.Kosuge.ja_35 Line
Tsubasa.Kosuge.ja_36