This is a Task Group Instruction (TGI) for naval maintenance work on the USS SHOUP (DDG-86). The document provides detailed specifications for cleaning, assessing, inspecting, repairing, and preserving portable water tank 4-150-2-W, a 3,921-gallon steel tank located in the Forward Power Supply/Conversion Room. The work encompasses approximately 1,100 square feet of interior surface area, including the tank's manhole cover (15" x 23") and Air Vent Hose Connection cover (10" diameter).
The contractor must accomplish general cleaning at Level II; perform structural assessment documenting deterioration, pitting, cracks, and damage; conduct commercial blast cleaning to SSPC-SP 6 standards; execute visual inspection; and complete repairs including base metal weld buildup (36 square inches maximum per defect, one-quarter inch thick for bidding purposes). Additional requirements include installing new gaskets, washers, and brass nuts (MIL-DTL-1222, 5/8-11 UNC-2B specification) on cover plates; applying interior preservation coating per specification 009-032; performing completion air testing at 2 PSIG with zero allowable pressure drop; and conducting chlorination and bacteriological testing through an ISO 17025-accredited laboratory. The document identifies specific references, material requirements (synthetic rubber gaskets and brass fasteners), and government-furnished materials. Supporting SRF-JRMC services include crane rigging, utility provision, safety and gas-free inspections, and quality assurance reviews. The work is scheduled per TGI Period of Performance list, with the planner identified as Code 231A T. Tsutsui and Work Integration Manager as Code 333 T. Yaginuma.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
FOUO: Public availability to be determined under 5 USC 552
TASK GROUP INSTRUCTION
AIM REV 20.11.4.0 (OCTOBER 2020)
TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:
NO.: POT WTR 4-150-2-W TK A 1 0
SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:
DDG-86 USS SHOUP 12314 KC3
CU PHASE TITLE:
F/O - CLN, ASSESS, INSP, RPR, AND PSV PORTABLE WATER TANK 4-150-2-W
PREPARING ACTIVITY:
PREPARED BY: CODE PHONE DATE
TOSHIHIRO TSUTSUI 231A. 315-243-0097 08-MAY-2026
APPROVED BY: CODE PHONE DATE
RYOUSUKE NANBA 231A. 315-243-6141 08-MAY-2026
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
REASON FOR WORK/NEED FOR CHANGE:
CHANGE INSTRUCTIONS:
SPECIAL REQUIREMENTS:
SURFMEPP
CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL II
WORK CERTIFICATION SIGNATURES
COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
ACCEPTANCE OF COMPLETED WORK
PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:
REQUIRED:☐YES ☒NO
RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
TGI NO.: POT WTR 4-150-2-W TK A 1
FOUO
SHIP: DDG-86 CHG/VER: 0/0
LIST OF EFFECTIVE PAGES
SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.
1-5 J1-2 M1-2
1. SCOPE/PURPOSE
1.1 Title: Portable Water Tank 4-150-2-W; clean, assess, inspect, repair and preserve
1.2 Location of Work:
1.2.1 Portable Water Tank (4-150-2-W)
1.2.2 Forward Power Supply/Conversion Room (3-126-2-Q)
1.3 Identification:
1.3.1 Quantity (One EA), Portable Water Tank
Tank No.: 4-150-2-W Capacity: 3,921 Gallons
1.3.2 Quantity (One EA), Manhole Cover plate(s) for 4-150-2-W
Manhole No(s).: 3-160-2 Size: 15 Inches x 23 Inches Material: Steel
1.3.3 Quantity (One EA), Air Vent Hose Connection (AVHC) Cover Plate(s) for 4-150-2-W
AVHC No(s).: 3-151-2 Size: 10 Inches Diameter Material: Steel
1.3.4 Quantity (1,100 SF), Entire Interior Surface of Portable Water Tank (4-150-2-W)
Remarks: The area includes tank side of manhole cover plate(s) and bolting ring
1.4 Security Classification: None.
1.5 Initial Condition:
1.5.1 Critical Coated Area: CCNY-DDG86-012-27 for each area listed in 1.3.4.
1.6 Contractor work start date: See TGI POP List
1.7 Contractor work completion date: See TGI POP List
2. REFERENCES:
FOUO
SHIP: DDG-86 CHG/VER: 0/0
REF.
NO.
DOCUMENT
/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV CHG
NO.
COPY
REQ’D
(Y/N)
SOURCE
DOC
(Y/N)
PARA SEC PG CHP
1 NSI FY-27 NAVSEA Standard Items - 2 N 2 LI FY-27 Local Standard Items - ORG N
3 NSI T-9630-
AB-MMD-
Corrosion Control Assessment and Maintenance Manual (CCAMM)
3 N
4 TM NAVSEA
4790/14
Tank and Void Structural and Coating Condition Survey (MRC G1N5)
- N
5 TM S9086-
CJ-STM-
010/CH-075
Fasteners 7 N
6 DWG 8100-
1254-0085
FLUSH DK. W.T. & OIL TIGHT
BOLTED PLATE MANHOLE 15" x 36", 15" x 18" & 15" x 23"
AE Y 2,
7 DWG 8100-
1254-0239
10" DIA AIR VENT HOSE
CONNECTIONS
P Y 5, 8, 8 TM
SYSTEMS &
SPECIFICAT
IONS
SSPC Painting Manual Volume 2 - N
9 DWG 100-
7060385
UNIT STRL ARR DWG ASSY UNIT
D Y SE
E N
OT
E
10 DWG 100-
7060390
UNIT STRL ARR DWG ASSY UNIT
C Y SE
E N
OT
E
3. APPENDICES:
3.1 Appendix “J” TGI Job Summary Information Sheet
3.2 Appendix "M" TGI Material List
3.3 Appendix “D” Deficiency Form
4. GENERAL REQUIREMENTS:
4.1 Not Applicable
5. PROCEDURE:
5.1 Accomplish the requirements of 099-902YO of 2.2 for each tank listed in 1.3.1.
5.1.1 Ensure General Cleaning must be Level II.
5.1.2 Accomplish an assessment of each tank listed in 1.3.1 for existing preservation coating, structural integrity, deterioration, pitting, cracks, and areas of damage or distortion, including sounding tubes, tank/void vents, overflows, piping and associated material, structural members, ladders, anodes, desiccant, tank level indicator (TLI), radar TLI, and their electric cables, stud, and tank top cable penetration, and manhole covers in accordance with 2.3 and 2.4.
Document the assessment on 2.4.
(I) “CCIMS ASSESSMENT”
5.1.2.1 Submit one legible copy, in hard copy or approved transferrable media, of completed assessment form 2.4 and a report with a sketch listing results of the requirements of 5.1.2.1 to the SUPERVISOR
FOUO
SHIP: DDG-86 CHG/VER: 0/0
5.1.3 Install each manhole cover, including AVHC cover, using new gasket(s), new washer(s), and new nut(s) in accordance with Figure 075-4-1 of 2.5, and 2.6 and 2.7.
5.1.3.1 Brass nuts confirming to MIL-DTL-1222, Type One, Grade 464, 5/8-11 UNC-2B for each AVHC cover.
5.2 Commercial blast clean each tank listed in 1.3.1. Accomplish each requirement of Surface Preparation Specification SSPC-SP 6 of 2.8.
5.3 Accomplish a visual inspection of each tank listed in 1.3.1 for existing preservation coating, structural integrity, deterioration, pitting, cracks, and areas of damage or distortion, including sounding tubes, tank vents, overflows, piping, structural members, and manhole covers, using 2.9 and 2.10.
5.3.1 Submit one legible copy, in hard copy or approved transferrable media, of a report listing results of the requirements of 5.3 to the SUPERVISOR.
5.4 Repair each tank listed in 1.3.1, based on the results of 5.1.2 and 5.3 as designated by the SUPERVISOR, using
2.9 and 2.10 for guidance. See 5.10.6 and 5.10.7.
5.4.1 Base metal weld buildup a total of 36 square inches of each plate defect in the tank.
5.4.1.1 For bidding purposes the base metal weld buildup must be one quarter inch thick.
5.4.1.2 Surface must be ground to sound metal prior to base metal weld buildup.
5.4.1.3 Fill each local pit and groove with weld material prior to application of each principal buildup layer.
5.4.1.4 Grind each surface of completed base weld metal buildup smooth if greater than 1/8 inch above plate surface.
5.4.2 Accomplish the requirements of 009-012 of 2.1, including Table 2, Columns A, Lines One through 7.
5.4.2.1 Accomplish nondestructive testing in accordance with Line 11.
5.4.3 Accomplish the requirements of 009-025 of 2.1 for an air hose, water hose, or vacuum box test of each new insert weld seam. Allowable leakage: None.
5.5 Accomplish the requirements of 009-032 of 2.1, including Table 3, Line(s) 25, for interior compartment side surfaces of each cover plate listed in 1.3.2 and 1.3.3.
5.6 Accomplish the requirements of 009-032 of 2.1, including Table 4, Line(s) 5, for each area listed in 1.3.4.
5.6.1 Submit new coating data applied to the SUPERVISOR in accordance with 2.3 and 2.4.
5.7 Accomplish the requirements of 009-025 of 2.1 for a completion air test of each tank listed in 1.3.1. Test pressure must be 2 PSIG. Allowable drop in pressure: None.
5.8 Accomplish the requirements of 009-087 of 2.1 for each tank listed in 1.3.1.
5.8.1 Accomplish the requirements of 009-009 of 2.1 for chlorination and bacteriological tests. Analysis and testing conducted by a qualified Japanese laboratory (accredited by ISO 17025 or equal) are authorized by the
SUPERVISOR.
5.8.2 Record results of chlorination and bacteriological tests on a Laboratory Analysis Record(s) and DD Form 686, and submit one legible copy, in hard copy or approved transferrable media, of completed record(s) and form(s) to the
SUPERVISOR.
FOUO
SHIP: DDG-86 CHG/VER: 0/0
5.9 Accomplish the requirements of 009-032 of 2.1 for each new and disturbed surface.
5.10 Notes:
5.10.1 Planner: Code 231A T. Tsutsui, 243-0097
5.10.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-6522-9560
5.10.3 2.4 is available on P:\C200\C225\Enclosures\C231\Tank and Void Structural and Coating Condition Survey
(MRC G1N5).
5.10.4 This TGI meets the intent of DDG CSWT File Nos. 123-096, 123-102, and 123-133.
5.10.5 JCNs EA01-ZBI5, EA01-ZBH9, EA01-ZBI3, and EA01-ZBH3 are related to this TGI.
5.10.6 Removal and installation of interferences, and gas free operation, preservation of boundary spaces relating to front loading structure repair are not included in this TGI. They will be covered by a DL in the future based on Contractor submitted condition report.
5.10.7 Materials for structure members relating to front loading repair will be provided in the future as a DL based on Contractor submitted condition report.
5.10.8 SRF-JRMC Code 134 will provide laboratory analysis and test service for disinfectant solution used for portable water tank when requested by the WIM Code 333.
5.10.9 WPC will copy the following pages in reference.
REF. 2.9: Pages 3, 4A, 4B, 6, 5A-2, 5B-2, 5, and 9.
REF. 2.10: Pages 3, 3A, 4, 4A, 5, 6, and 9.
5.11 Government Furnished Material (GFM):
5.11.1 SRF-JRMC will provide GFM listed in Appendix “M”.
5.12 SRF-JRMC will provide the following service work: (TGI No. 38KC312304S02)
5.12.1 [C740] Crane and crane rigging service.
5.12.2 [X99E] Utility service, electrical.
5.12.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.
5.12.4 [C106.1] Safety inspection for SRF-JRMC employees.
5.12.5 [C106.2] Gas free inspection for SRF-JRMC employees.
5.12.6 [C133] QA inspection for (G) symbol(s), review of coating application data, and Surface Corrosion Control Information Management System (CCIMS) entry.
5.12.7 [C135] QA inspection for (G) Symbol(s).
5.12.8 [C250] Technical support and process of the tank/void assessment results.
FOUO
J-1
SHIP: DDG-86 CHG/VER: 0/0
APPENDIX "J"
TGI JOB SUMMARY INFORMATION SHEET
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
12314 POT WTR 4-150-2-W TK A 1 0
CU PHASE TITLE:
F/O - CLN, ASSESS, INSP, RPR, AND PSV PORTABLE WATER TANK 4-150-2-W
PRIMARY COMPONENT:
COMPONENT UNIT LIST (FOR ASSEMBLIES):
ATTACHMENT LIST:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA ,TAKEHIDE 4-150-2-W 4 U
JO: KO: TOTAL MAN HRS: PLANNING ACCEPTANCE:
38KC312304 A01
TOTAL MAT’L COST TOTAL DURATION:
CU PHASE DESCRIPTION:
The purpose of this TGI is to accomplish cleaning, assessment, inspection, repair and preservation portable water tank 4-150-2-W.
Location of Work:
Portable Water Tank (4-150-2-W) Forward Power Supply/Conversion Room (3-126-2-Q)
FOUO
J-2
SHIP: DDG-86 CHG/VER: 0/0
TASK NAME
SHOP TSD/WC TS CREW# MHRS
HIGH RAD
HOURS
RC
GRID#
Process Funding Document. 10 CT OM 1 1 0
FOUO
M-1
SHIP: DDG-86 CHG/VER: 0/0
APPENDIX “M”
TGI MATERIAL LIST
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
12314 POT WTR 4-150-2-W TK A 1 0
CU PHASE TITLE:
F/O - CLN, ASSESS, INSP, RPR, AND PSV PORTABLE WATER TANK 4-150-2-W
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV
JOB ORDER: KEY OP:
38KC312304 A01
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
001 M RUBBER S, ORDER FOR KTR
ORIG, C231A T. TSUTSUI 243-
GASKET SHEET, SYNTHETIC
RUBBER, SPEC: MIL-PRF-1149
(FORMERLY MIL-G-1149)
TYPE-I CLASS-1, THK: 3/16",
SIZE: 3 FT X 3 FT, MATL:
SYNTHETIC RUBBER, 50
DUROMETER, OIL RESISTANT,
*TYPE 1
9G 9320 LL4820283 NA 4 N 61147425 9/SF
002 M NUT, HEX, ORDER FOR KTR
ORIG, C231A T. TSUTSUI 243-
NUT, HEX, SPEC: MIL-DTL-1222
TYPE I, SIZE: 5/8"-11UNC-3B,
BEARING SURFACE:
CHAMFERED, MATL: BRASS
GRADE 464, BIW CATALOG
NO. 53094-210,
9Z 5310 LL7033306 NA 4 N 61147426 28/EA
NOTES:
FOUO
M-2
SHIP: DDG-86 CHG/VER: 0/0
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
003 M WASHER,, ORDER FOR KTR
ORIG, C231A T. TSUTSUI 243-
WASHER, FLAT, BOLT 5/8" DIA
BOLT,
SPEC: FF-W-92 TY A GR I CL B,
SIZE: 1-3/8" OD (1.375") X
21/32" ID (0.656") X 1/16" THK
(0.062"), MATL: CRES 316,
BIW CATALOG NO. 53239-161,
9Z 5310 LL6991322 NA 4 N 61147427 40/EA
004 M NUT,HEX, ORDER FOR KTR
ORIG, C231A T. TSUTSUI 243-
9Z 5310 LL9001079 NA 4 N 61147428 12/EA
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR APPENDIX "D"
DEFICIENCY FORM
☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One)
2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
DDG-86 POT WTR 4-150-2-W TK A 1
4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:
38KC312304 A01
7. DESCRIPTION:
8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
9. CORRECTIVE ACTION:
10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
FOR NON-NUCLEAR USE ONLY
11. RFD/RFW REQ’D ☐ LAR REQ'D ☐
ILS MOD REQ’D ☐
SRD/PLAN REV REQ'D ☐
DWG NO.: _____________________ S/A NO.: ___________________
12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:
SATISFACTORY:
13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
YES ☐ NO ☐
14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE:
15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
_________:YES ☐ NO ☐
16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE (DR ONLY)
DL’s ISSUED
(DR ONLY)
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
DDG-86 POT WTR 4-150-2-W TK A 1