S02 F2-1 Structural Design Criteria 523A5-10-316 Laundry Building 45.pdf

PDF 49 KB Posted

Attached to
Z2EZ 523A5-10-316 Upgrade VISN 1 Laundry Building 45 Federal contract opportunity
Solicitation number
36C24125R0008
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 1

About this file

This document is a Structural Design Criteria appendix for the Upgrade B45 Laundry project at the Brockton VA Medical Center. The criteria outline specific engineering and design standards for the renovation, including detailed specifications for structural loads, seismic considerations, and serviceability requirements. Key technical details include adherence to the 2021 International Building Code, ANSI/ASCE 7-16 standards, and specific load calculations such as a ground snow load of 35 psf, ultimate wind speed of 123 mph, and seismic design parameters with a Seismic Design Category of B. The document provides comprehensive deflection and drift criteria for existing and new roof and floor members, specifying precise load and deflection limits to ensure structural integrity and compatibility with building finish materials.

View the file

Other files for this federal contract opportunity

Other files attached to Z2EZ 523A5-10-316 Upgrade VISN 1 Laundry Building 45, newest first.
File Type Posted
36C24125R0008 0007.docx DOCX document
S06 RFI Questions and Answers 8.11.2025 523A5-10-316 Upgrade VISN 1 Laundry Building 45.docx DOCX document
S06 Site Visit Sheet 7.28.2025.pdf PDF
S06 Updated Drawings 2025-07-18 VA Brockton B45 Laundry Structural Rev 2.pdf PDF
S06 Updated Drawings 10438_ELEC_REV2.pdf PDF
S06 WD MA20250012 07.18.2025.pdf PDF
S06 Updated Drawings Mechanical Rev2.pdf PDF
S06 Updated Specifications 87100 R2.pdf PDF
S06 Updated Drawings 2224 VA Brockton REV 2 architectural.pdf PDF
S06 Updated Specifications 085113.pdf PDF
S06 2025-07-18 Addendum No. 2.pdf PDF
S06 Updated Drawings 250716 FP REV 2.pdf PDF
S06 Updated Drawings Plumbing Rev2 7-14-25.pdf PDF
S06 Updated Specifications 000110.pdf PDF
S06 RFI Questions and Answers 523A5-10-316 Upgrade VISN 1 Laundry Building 45.docx DOCX document
36C24125R0008 0006.docx DOCX document
S06 36C24125R0008 0005.docx DOCX document
S06 36C24125R00008 0004.pdf PDF
36C24125R0008 0003.docx DOCX document
36C24125R0008 0002.docx DOCX document
36C24125R0008 0001.docx DOCX document
S06 Site Visit Sign In Sheet 4.24.2025.pdf PDF
S02 Brockton Campus Map.pdf PDF
S02 Base Offer Price Breakdown.xlsx XLSX spreadsheet
S02 SSJ 523A-10-316 Laundry Building 45.pdf PDF
S02 F3-1 Code Search 523A5-10-316 Laundry Building 45.pdf PDF
S02 Submittal Register 523A5-10-316 Laundry Building 45.xlsx XLSX spreadsheet
S02 Final Design Analysis Consolidated 523A5-10-316 Laundry Building 45.pdf PDF
36C24125R0008_2.docx DOCX document
S02 Attachment A Technical Project Information Sheet for 36C24125R0008.docx DOCX document
S02 WD MA20250012 04.04.2025.pdf PDF
S02 Primavera P6 Schedule Review Checklist 523A5-10-316 Laundry Building 45.xlsx XLSX spreadsheet
S02 Equipment List - Existing vs New Equipment 523A5-10-316 Laundry Building 45.pdf PDF
S02 Attachment B Past Performance Project Information Sheet for 36C24125R0008.docx DOCX document
S02 SOW 523A5-10-316 Laundry Building 45.pdf PDF
S02 PCRA 523A5-10-316 Laundry Building 45.pdf PDF
S02 Final Specifications 523A5-10-316 Laundry Building 45.pdf PDF
S02 Final Drawings Revision 01 523A5-10-316 Laundry Building 45.pdf PDF
S02 Final Drawing Set 523A5-10-316 Laundry Building 45 08.21.2024.pdf PDF
S02 F8-1 Laundry Equipment Storage 523A5-10-316 Laundry Building 45.pdf PDF
S02 F3-3 HLAC Accreditation Standards 09.21.2023 523A5-10-316 Laundry Building 45.pdf PDF
S02 F2-2 Attachment 2 Structural Calculations 523A5-10-316 Laundry Building 45.pdf PDF
S02 6500 Appendix B and C Security Language 523A-10-316 Laundry Building 45.pdf PDF
Show all 43

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Upgrade B45 Laundry

Brockton VA Medical Center

Page IV-1

Appendix F2.1

Structural Design Criteria

1. Codes & Standards:

a. International Building Code (IBC) 2021 Edition as modified by:

i. Seismic Design Requirements, H-18-8, Department of Veterans

Affairs.

b. ANSI/ASCE 7-16, Minimum Design Loads for Buildings and Other

Structures

c. ACI 318-19 Building Code Requirements for Structural Concrete

d. AISC 360-16, Specification for Steel Buildings

2. Design Loads

a. Dead Loads

i. Existing Roof and Existing Floor: Self weight of building materials

ii. Equipment loads as shown on the drawings.

b. Collateral Loads

i. Existing Roof and Existing Floor: 10 psf

c. Live Loads

i. Roof: 20 psf unreducible

ii. Walls: 5 psf minimum

d. Snow Loads: 35 psf Ground Snow Load

e. Wind loads:

i. Ultimate Wind Speed: V=123 mph

ii. Risk Category: II

iii. Wind Importance Factor: IW=1.0

iv. Wind Exposure: B

v. Internal Pressure Coefficient:

a) + 0.18 “Enclosed”

f. Seismic Loads

i. Risk Category: II

ii. Seismic Importance Factor: IE=1.0

Upgrade B45 Laundry

Brockton VA Medical Center

Page IV-2

iii. Mapped Spectral Response Accelerations:

a) SS=0.22

b) S1=0.059

iv. Site Class: D

v. Spectral Response Coefficients:

a) SDS=0.234

b) SD1=0.094

vi. Seismic Design Category: B

vii. Analysis Procedure Used: Equivalent Lateral Force Procedure

3. Serviceability

a. Drift & Deflection Criteria: The criteria used shall be compatible with finish materials for the building that are connected to the building structure.

i. Lateral Drift: 0.1xHsx

ii. Horizontal Deflection: L/240

iii. Vertical Deflection

a) Existing floor members:

1) Live Load: L/360

2) Dead + Live Load: L/240

b) Existing roof members:

1) Live Load: L/240

2) Dead + Live Load: L/180

c) New Roof Members

1) Live Load L/240

2) Dead + Live Load: L/180

d) New Floor Members

1) Live Load: L/360

2) Dead + Live Load: L/240