About this file
The file is a Base Offer Price Breakdown Excel template for a VA construction project (Solicitation Number: 36C24125R0008) involving the upgrade of a Laundry Building 45 at VISN 1. The spreadsheet provides a comprehensive cost breakdown template across 34 construction divisions, including sections for labor costs, material costs, overhead, profit, and bonding. While the current template is populated with sample data (e.g., a plumber at $35/hour and pipe materials), it is designed for contractors to input specific labor and material costs for each division of the construction project, with calculations for subtotals, overhead, profit, and total base offer cost.
View the file
Other files for this federal contract opportunity
Show all 43
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Base Offer
Base Offer Cost Breakdown
Project Number:
Edward L Roy: VA assigned project #
| Date: | |
| Project Title |
| Edward L Roy: VA assigned Project Title | Project Location | ||
| Offeror Name | |||
| Offeror Street | |||
| Offeror City | State | Zip |
Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division
| Material Cost | |
| Edward L Roy: Enter all Material Costs by Division | Total Cost |
Edward L Roy: This Column is the sum of the Division's Labor and Material Costs
| Division 1 | General Requirements | $ - 0 | $ - 0 | $ - 0 |
| Division 2 | Existing Conditions | - 0 | - 0 | - 0 |
| Division 3 | Concrete | - 0 | - 0 | - 0 |
| Division 4 | Masonry | - 0 | - 0 | - 0 |
| Division 5 | Metals | - 0 | - 0 | - 0 |
| Division 6 | Wood and Plastic | - 0 | - 0 | - 0 |
| Division 7 | Thermal & Moisture Protect | - 0 | - 0 | - 0 |
| Division 8 | Doors and Windows | - 0 | - 0 | - 0 |
| Division 9 | Finishes | - 0 | - 0 | - 0 |
| Division 10 | Specialties | - 0 | - 0 | - 0 |
| Division 11 | Equipment | - 0 | - 0 | - 0 |
| Division 12 | Furnishings | - 0 | - 0 | - 0 |
| Division 13 | Special Construction | - 0 | - 0 | - 0 |
| Division 14 | Conveying Equipment | - 0 | - 0 | - 0 |
| Division 21 | Fire Suppression | - 0 | - 0 | - 0 |
| Division 22 | Plumbing | - 0 | - 0 | - 0 |
| Division 23 | HVAC | - 0 | - 0 | - 0 |
| Division 26 | Electrical | - 0 | - 0 | - 0 |
| Division 27 | Communications | - 0 | - 0 | - 0 |
| Division 28 | Electronic Safety & Security | - 0 | - 0 | - 0 |
| Division 31 | Earthwork | - 0 | - 0 | - 0 |
| Division 32 | Exterior Improvements | - 0 | - 0 | - 0 |
| Division 33 | Utilities | - 0 | - 0 | - 0 |
| Division 34 | Transportation Subtotal | - 0 | - 0 | - 0 |
| Division Subtotals : | $ - 0 | $ - 0 | $ - 0 |
Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).
Edward L Roy: Date Offer Prepared/Submitted
| - 0 | |||
| Profit % | 0.00% | ||
| Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38). | - 0 | ||
| Bond % | 0.00% |
Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).
Edward L Roy: Enter all Labor Costs by Division
| - 0 | ||
| Overhead/Profit Subtotals : | $ - 0 |
Edward L Roy: Sum of Overhead, Profit and Bond %.
Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Base Offer Cost $ - 0 $ - 0 $ - 0
Labor Detail
| Sample Example | ||||
| Division | Labor Category | Labor Rate | Hours | Total |
| 1 | Plumber | $35.00 | 123 | $4,305.00 |
| 1 | Laborer | 14.75 | 70 | $1,032.50 |
| $5,337.50 |
Materials and Equipment Details
| Sample Example | ||||
| Division | Item | Rate | Units | Total |
| 1 | Pipe - 150' | $1.50 | 150 | $225.00 |
| 1 | 90 Degree Coupling | $1.10 | 5 | $5.50 |
| 1 | Pump Rental - Hour | $200.00 | 6 | $1,200.00 |
| $1,430.50 |