ATTACHMENT 28 - Montrose.EHRM.Addendum.01.B26.20260330.pdf

PDF 29 MB Posted

Attached to
Z2DA--620-22-700 Electronic Health Record Modernization Infrastructure Upgrades - Franklin Delano Roosevelt VA Hospital, Montrose, NY
Solicitation number
RFP-36C77626R0033
Issued by

About this file

This is a set of construction and electrical design documents (Addendum #1, issued 03/30/2026) for infrastructure upgrades at the Franklin Delano Roosevelt VA Hospital in Montrose, NY. The documents include drawing indexes, interim life safety and infection control plans, electrical plans, telecommunications details, and related specifications for Project 620-22-700. The project involves renovation and modernization work on a 22,255 square foot existing assembly occupancy building classified as Type II (222) construction with Category D large-scale construction activities. The work is designated as a Category III infection control risk level, requiring Class III/IV infection prevention and control measures, including the installation of temporary construction barriers with one-hour fire ratings, maintenance of negative air pressure at 0.03 inches water gauge 24/7 using HEPA filtration, anteroom construction with proper staging areas, and daily debris removal in sealed containers.

The electrical scope includes new panelboard renovations, circuit breaker installations, access control systems (Johnson Controls iSTAR Edge G2 IP-based panel), life safety power (LSP) PSX unified enclosure with minimum 4-hour backup batteries, FIPS/FICAM/HSPD-12 compliant Avigilon access control with PIV-ready card readers, telecommunications infrastructure upgrades with new enclosure cabinets, fiber optic conduit installation, and extensive grounding and bonding work. The project mandates compliance with 2024 NFPA 101 Life Safety Code, 2025 NFPA 72 National Fire Alarm Code, 2025 NFPA 13 Sprinkler Standards, 2026 National Electrical Code, and applicable ASHRAE standards. All work must maintain functioning fire protection systems, exit lighting, and life safety measures for occupied areas, with coordination required between the contractor, Contracting Officer Representative, VA safety personnel, and infection control staff. A 30-day panelboard load measurement report must be provided to the COR and Architect prior to renovation commencement.

View the file

Other files

File Type Posted
Amend 5 - B04.20260330.pdf PDF
Amend 5 - B14.20260330.pdf PDF
Amend 5 - B15.20260330.pdf PDF
Amend 5 - B17.20260330.pdf PDF
Amend 5 - B20.20260330.pdf PDF
Amend 5 - B28.20260330.pdf PDF
Amendment 4 - 36C77626R0033 0004.pdf PDF
Clause 52.222-90 ADDRESSING DEI DISCRIMINATION BY FEDERAL CONTRACTORS - APR 2026.pdf PDF
RFI TRACKING SHEET - SOLICITATION 36C77626R0033.pdf PDF
ATTACHMENT 1 - SPECS - 620-22-700.Montrose.EHRM.Spec.IFC.20260410.pdf PDF
ATTACHMENT 5 - 01 00 00.D - Appendix D - SOP 138-06HV OCCUPATIONAL SAFETY AND HEALTH PROGRAM.pdf PDF
ATTACHMENT 11 - 01 00 00.I - Appendix I - K9245005 VAMC EHRM Montrose NY GeoReport 4.12.2024.pdf PDF
ATTACHMENT 12A - Summary.Log.Add01_20260410.pdf PDF
ATTACHMENT 13 - Montrose.EHRM.Addendum.01.B01.20260330.pdf PDF
ATTACHMENT 14 - Montrose.EHRM.Addendum.01.B02.20260330.pdf PDF
ATTACHMENT 22 - Montrose.EHRM.Addendum.01.B14.20260330.pdf PDF
ATTACHMENT 25 - Montrose.EHRM.Addendum.01.B17.20260330.pdf PDF
ATTACHMENT 26A - Montrose.EHRM.Addendum.01.B19.20260330.pdf PDF
ATTACHMENT 30 - Montrose.EHRM.Addendum.01.B29.20260330.pdf PDF
ATTACHMENT 31 - Montrose.EHRM.Addendum.01.B31.20260330.pdf PDF
Amendment 3 - 36C77626R0033 0003.pdf PDF
ATTACHMENT 4 - 01 00 00.C - Appendix C - SOP 138-22HV CONST STD PROCEDURES QLTY ASSRNCE FOR PRJS.pdf PDF
ATTACHMENT 6 - 01 00 00.E - Appendix E - VHA ICRA-1.3 Dec 9 2024.pdf PDF
ATTACHMENT 9 - 01 00 00.H - Appendix H - J2237038 Montrose ACM and Lead Paint Inspection Report Final 8-21-2023.pdf PDF
ATTACHMENT 10 - 01 00 00.H1 - Appendix H1 - J2247041 Montrose NY VAMC_ACM Inspctn - Lead Paint Screening Rpt_Final 5-9-2024 - signed.pdf PDF
ATTACHMENT 15 - Montrose.EHRM.Addendum.01.B03.20260330.pdf PDF
ATTACHMENT 17 - Montrose.EHRM.Addendum.01.B05.20260330.pdf PDF
ATTACHMENT 19 - Montrose.EHRM.Addendum.01.B07.20260330.pdf PDF
ATTACHMENT 20 - Montrose.EHRM.Addendum.01.B12.20260330.pdf PDF
Site visit sign-in sheet 3-23-26.pdf PDF
Amendment 1 - 36C77626R0033 0001.pdf PDF
RFP - 36C77626R0033.pdf PDF
Attachment 3 - 01 00 00.B - Appendix B - Submittal Log.pdf PDF
Attachment 4 - 01 00 00.C - Appendix C1 SOP 138-22HV CONST STD PROCEDURES QA FOR PROJECTS.pdf PDF
Attachment 5 - 01 00 00.D - Appendix D1 SOP 138-06HV OCCUPATIONAL SAFETY AND HEALTH PROGRAM.pdf PDF
Attachment 16 - Drawing B04 20250627.pdf PDF
Attachment 18 - Drawing B06 20250627.pdf PDF
Attachment 22 - Drawing B14 20250627.pdf PDF
Attachment 27 - Drawing B20 20250627.pdf PDF
Attachment 29 - Drawing B28 20250627.pdf PDF
Attachment 32 - Drawing B52 20250627.pdf PDF
Attachment 36 - Division Cost Breakdown.xlsx XLSX spreadsheet
Attachment 10 - 01 00 00.H1 - Appendix H1 - J2247041 ACM Insp - Lead Paint Rpt_Final 5-9-2024.pdf PDF
Attachment 17 - Drawing B05 20250627.pdf PDF
Attachment 20 - Drawing B12 20250627.pdf PDF
Attachment 24 - Drawing B16 20250627.pdf PDF
Attachment 25 - Drawing B17 20250627.pdf PDF
Attachment 30 - Drawing B29 20250627.pdf PDF
Attachment 38 - PPQ.docx DOCX document
Attachment 40 - RFI TRACKING SHEET - SOLICITATION 36C77626R0033 - Project 620-22-700.xlsx XLSX spreadsheet
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD A/E:

CONSULTANT

321 4 5 6 7 8 9 10

TRIPLE C - The A/E Group 201 E. Jefferson Street, Suite 200 Syracuse, NY 13202

MAT PERKINS

(315) 484-5958

STAMP

Au to de sk

D oc s:

//6

-2

2-

M on tro se V

AM

C

E H

R M

IU

/6

-2

2-

0.

M on tro se .E

H R

M .M

EP

.B

.rv t 3/

/2

8:

:5

PM

26G-001

DRAWING INDEX 620-22-700

06/27/2025 M. PERKINS K.

MCDERMOTT

ISSUED FOR

CONSTRUCTION

(EHRM) INFRASTRUCTURE

UPGRADES

2094 Albany Post Road, Montrose, NY 10548

- DRAWING INDEX -

SHEET

NUMBER SHEET NAME INCLUDED IN 35% SD INCLUDED IN 65% DD INCLUDED IN 95% CD ISSUED FOR CONSTRUCTION

GENERAL

26G-000 COVER SHEET Yes Yes Yes Yes 26G-001 DRAWING INDEX Yes Yes Yes Yes 26G-010 GENERAL PROJECT NOTES Yes Yes Yes Yes 26G-012 GENERAL INDOOR AIR QUALITY NOTES Yes Yes Yes Yes

ICRA & LIFE SAFETY

26GI300 INTERIM LIFE SAFETY & INFECTION CONTROL PLAN - FIRST LEVEL No No Yes Yes

ARCHITECTURAL

26A-001 ARCHITECTURAL SYMBOLS, & GENERAL NOTES No No Yes Yes 26A-400 ARCHITECTURAL ENLARGED VIEWS - BASEMENT & FIRST LEVELS No No Yes Yes 26A-512 ARCHITECTURAL PARTITION HEAD DETAILS Yes Yes Yes Yes

ELECTRICAL

26E-001 ELECTRICAL ABBREVIATIONS AND SYMBOLS Yes Yes Yes Yes 26E-100 ELECTRICAL PLAN - BASEMENT LEVEL No Yes Yes Yes 26E-101 ELECTRICAL PLAN - FIRST LEVEL AREA-A & AREA-B No Yes Yes Yes 26E-501 ELECTRICAL DETAILS Yes Yes Yes Yes 26E-601 ELECTRICAL ONE-LINE DIAGRAMS No Yes Yes Yes 26E-701 ELECTRICAL SCHEDULES No Yes Yes Yes 26E-901 ELECTRICAL CUTSHEETS & BASIS OF DESIGN Yes Yes Yes Yes 26E-902 ELECTRICAL CUTSHEETS & BASIS OF DESIGN No No No Yes

TELECOMMUNICATION

26T-001 TELECOMMUNICATION ABBREVIATIONS AND SYMBOLS Yes Yes Yes Yes 26T-101 TELECOMMUNICATION PLAN - FIRST LEVEL AREA A & AREA B Yes Yes Yes Yes 26T-501 TELECOMMUNICATION DETAILS Yes Yes Yes Yes 26T-502 TELECOMMUNICATION ROOM OIT TEMPLATE DETAILS No Yes Yes Yes 26T-601 TELECOMMUNICATION RISER DIAGRAMS Yes Yes Yes Yes 26T-603 TELECOMMUNICATION FIBER RISER DIAGRAM - NEW No Yes Yes Yes 26T-604 TELECOMMUNICATION RACK ELEVATIONS Yes Yes Yes Yes 26T-901 TELECOMMUNICATION CUTSHEETS & BASIS OF DESIGN Yes Yes Yes Yes Grand total: 24

# Revisions: Date:

1 ADDENDUM #1 03/30/2026

26G-011 REMOVED FROM

CONSTRUCTION DOCUMENTS

INFECTION CONTROL / DUST

CONTROL PARTITION / BARRIER

INFECTION CONTROL/DUST CONTROL

EGRESS DOOR NON-TRANSFERRING

MULTI-SHEETED ADHESIVE FLOOR PADS

PATH OF DEMOLITION/TRASH

REMOVAL TRAVEL

CONSTRUCTION LIMIT LINE

NOT IN CONTRACT AREA

DEMOLITION

LASER PARTICLE COUNT LOCATION

LIFE SAFETY SYMBOLS

PATH OF TRAVEL

(FOR CUMULATIVE DISTANCES

REFER TO SCHEDULE)

EXIT LIGHTING

TM

FIRE EXTINGUISHER CABINET (FEC)

FIRE EXTINGUISHERS (FE)

FIRE HOSE CABINETS (FHC)

HEAT DETECTOR

SMOKE DETECTOR

DIRECTION OF EGRESS

APPLICABLE BUILDING CODES

2024 NFPA 101 LIFE SAFETY CODE & 2025 NFPA 72 NATIONAL

FIRE ALARM AND SIGNALING CODE & 2025 NFPA 13 STANDARD

FOR INSTALLATION OF SPRINKLER SYSTEMS. EXCEPTION OF

NFPA 5000 AND NFPA 900

2024 INTERNATIONAL MECHANICAL CODE (IPC)

OCCUPATIONAL, SAFETY AND HEALTH ADMINISTRATION

(OSHA) STANDARDS.

VA SEISMIC DESIGN REQUIREMENTS, H-18-8

2026 NATIONAL ELECTRICAL CODE (NEC)

2024 INTERNATIONAL PLUMBING CODE (IPC)

ASME BOILER AND PRESSURE VESSEL CODE

ASME CODE FOR PRESSURE PIPING

ARCHITECTURAL BARRIERS ACT ACCESSIBILITY STANDARDS

(ABAAS) INCLUDING VA SUPPLEMENT, BARRIER FREE DESIGN

GUIDE (PG-18-13)

BUILDING CODE REQUIREMENTS FOR REINFORCED

CONCRETE, AMERICAN CONCRETE INSTITUTE AND

COMMENTARY (ACI 318)

MANUAL OF STEEL CONSTRUCTION, LOAD AND RESISTANCE

FACTOR DESIGN SPECIFICATIONS FOR STRUCTURAL STEEL

BUILDINGS, AMERICAN INSTITUTE OF STEEL CONSTRUCTION

(AISC)

ENERGY POLICY ACT OF 2005 (EPACT)

DOE INTERIM FINAL RULE: ENERGY CONSERVATION

STANDARDS FOR NEW FEDERAL, COMMERCIAL AND MULTI-

FAMILY HIGH-RISE RESIDENTIAL BUILDINGS AND NEW LOW-

RISE RESIDENTIAL BUILDINGS, 10 CFR PARTS 433, 434 AND 435

FEDERAL LEADERSHIP IN HIGH PERFORMANCE AND

SUSTAINABLE BUILDINGS: MEMORANDUM OF

UNDERSTANDING (MOU)

EXECUTIVE ORDER 13423: STRENGTHENING FEDERAL

ENVIRONMENTAL, ENERGY, AND TRANSPORTATION

MANAGEMENT

THE PROVISIONS FOR CONSTRUCTION AND SAFETY SIGNS.

STATED IN THE GENERAL REQUIREMENTS SECTION 01 00 00

AND 01 35 26 OF THE VA MASTER CONSTRUCTION

SPECIFICATION.

VENTILATION FOR ACCEPTABLE INDOOR AIR QUALITY –

ASHRAE STANDARD 62.1-2025; MEDICAL SPACES - ASHRAE

170-2025, NON-MEDICAL SPACES - ASHRAE 62.1-2025

SAFETY STANDARD FOR REFRIGERATION SYSTEMS – ASHRAE

STANDARD 15–2024

2024 INTERNATIONAL BUILDING CODE (IBC) WHERE DIRECTED

BY VA STANDARDS

UNLESS NOTED OTHERWISE, CURRENT EDITION OF APPLICABLE

STANDARD OR CODE SHALL BE USED

APPLICABLE BUILDING GUIDES

VA FIRE PROTECTION DESIGN GUIDE, 9TH EDITION (2023)

BUILDING CODE:

CONSTRUCTION TYPE:

TYPE II (222) PER NFPA 220, Chapter 4

TYPE OF BUILDING REHABILITATION: MODIFICATION, CHAPTER 43.

FIRE RESISTIVE CONSTRUCTION (NFPA 220 Table 4.1.1)

FIRE RESISTANCE RATING REQUIREMENTS FOR BUILDING

ELEMENTS:

STRUCTURAL FRAME 2 HOURS

NON-BEARING WALLS 0 HOURS

BEARING WALLS 2 HOURS

FLOORS 2 HOURS

ROOFS/ CEILINGS 1 HOURS

FIRE RESISTIVE CONSTRUCTION FOR OCCUPANCY (VA & NFPA 101)

FIRE RESISTANCE RATING REQUIREMENTS FOR SPACES BY

FUNCTION:

ELECTRICAL CLOSETS (DEPENDENT ON EQUIPMENT SIZE)

SMOKE COMPARTMENTS 1/2 HOUR

SOILED UTILITY ROOMS 1 HOUR

VERTICAL SHAFTS / STAIRS 2 HOURS

MEDICAL GAS / HAZARDOUS 1 HOUR

STORAGE

CLASSIFICATION OF OCCUPANCY:

EXISTING: ASSEMBLY Occupancy per Chapter 13

13.1.1.6 Where construction, alteration, or demolition operations are conducted, the provisions of 4.6.10.2 shall apply

13.1.2 Assembly occupancies shall include all buildings and structures or parts thereof with occupancy defined in 6.1.11

BUILDING OCCUPANCY TYPE:

EXISTING - ASSEMBLY OCCUPANCY

6.1.14.1.3 Where incidental to another occupant, areas used as follows shall be permitted to be considered part of the predominant occupancy and shall be subject to the provisions of the Code that apply to the predominant occupancy:

(1) Assembly

6.2 Hazard of Contents.

6.2.1.3 For the purpose of this Code, where difference degrees of hazard of contents exist in different parts of a building or structure, the most hazardous shall govern the classification, unless hazardous areas are separated or protected as specified in Section 8.7 and the applicable sections of Chapters 11 through 43.

EXIT ACCESS TRAVEL DISTANCE:

13.2.6.2 The travel distance between any point in a room and an exit shall not exceed 200 ft.

13.2.6.2 (1) The maximum travel distance...shall not exceed 250 ft in buildings protected throughout by an approved automatic sprinkler system in accordance with Section 9.7.

ASSEMBLY OCCUPANCY; PROTECTED = 250'-0"

OCCUPANT LOAD:

13.1.7 Occupant Load. The occupant load, in number of persons for whom means of egress and other provisions are required, shall be determined on the basis of the occupant load factors of Table 7.3.1.2 that are characteristic of the use of the space, or shall be determined as the maximum probable population of the space under consideration, whichever is greater.

MEANS OF EGRESS:

13.2.3 Capacity of Means of Egress.

13.2.3.1 The capacity of any required means of egress shall be determined in accordance with the provisions Section 7.3.

13.2.3.2 The minimum clear widths shown in table 13.2.3.2 shall be modified in accordance with formula 13.2.3.3a

13.2.4 Number of Means of Egress.

13.2.4.1 The number of means of egress shall be in accordance with Section 7.4 other than fenced outdoor assembly occupancies in accordance with 13.2.4.4, unless otherwise permitted by 13.2.4.2 or 13.2.4.3

13.2.4.2 Assembly occupancies with occupant loads of 600 or fewer shall have two separate means of egress.

13.2.5.3 In building protected throughout by and approved supervised automatic sprinkler system, Dead-end corridors shall not exceed 20 ft.

PROTECTION OF VERTICAL OPENINGS:

13.3.1 Protection of Vertical Openings - Any vertical opening shall be enclosed or protected in accordance with Section 8.6, unless otherwise permitted.

PROTECTION FROM HAZARDS:

13.3.2 Protection from Hazards.

13.3.2.1. Service Equipment, Hazardous Operations, or Processes, and Storage Facilities.

13.3.2.1.1 Rooms containing high pressure boilers, refrigerating machinery of other than the domestic refrigerator type, large transformers, or other service equipment subject to explosion shall meet both of the following requirements:

(1) Such rooms shall not be located directly under or abutting required exits

(2) Such rooms shall be separated from other parts of the building by fire barriers in accordance with section 8.3 that have a minimum 1-hour fire resistance rating or shall be protected by automatic extinguishing systems in accordance with Section 8.7.

PARKING SUMMARY:

NO ADDITIONAL PARKING ADDED

WIDTH PROVIDEDP: XX"

R: XX" WIDTH REQUIRED

PARTITION RATING GRAPHICS:

4 HR FIRE BARRIER

3 HR FIRE BARRIER

2 HR FIRE & SMOKE BARRIER

2 HR FIRE BARRIER

2 HR FIRE BARRIER/SHAFT

1 HR FIRE & SMOKE BARRIER

1 HR FIRE BARRIER

1 HR FIRE BARRIER/SHAFT

SMOKE PARTITION (NON RATED)

NON RATED

PARTITION RATING GRAPHIC DESIGNATION: PRIORITY

1 HIGHEST

5 LOWEST

PARTITIONS REQUIRED TO BE SMOKE RESISTANT, FIRE

RESISTANT, OR BOTH FIRE AND SMOKE RESISTANT ARE SHOWN

GRAPHICALLY ON PLANS WITH HATCH PATTERNS.

X - XX'

# ICRA SYMBOLSKEYNOTES

TEMPORARY WALL TO EXTEND

AND BE SEALED TO DECK /

FLOOR ABOVE WHEN RATED

ENCLOSURE REQUIRED

FLOOR LINE

CEILING SYSTEM AS

SCHEDULED

EXISTING STRUCTURE

FI

NI

SH

ED

F

LO

OR

T O

UN

DE

RS

ID

E

OF

S

TR

UC

TU

RE

VE

RI

FY

F

LO

OR

T

O

FL

OO

R

HE

IG

HT

RENOVATED SPRINKLER

SYSTEM

WEEKLY CHANGED

OR MORE AS

NEEDED PRE-FILTER

FLEX DUCTMONTHLY CHANGED

HEPA FILTER

HEPA NEGATIVE AIR

UNIT

PROVIDE STICKY MATS (CHANGED END OF

EVERY SHIFT OR MORE IF NECESSARY TO

MAINTAIN CLEANLINESS).

PRESSURE INDICATOR SHALL BE AT

0.03 OR GREATER USING A DIGITAL

MANOMETER WITH DATA LOGGING. IF

NOT VERIFY ALL OPENING SUCH AS

DOOR ARE CLOSED AND/OR CHANGE

NEGATIVE AIR PRE-FILTER. DO NOT USE

A "BALL IN THE WALL" OR ANALOG

OTHER PRESSURE INDICATOR.

SUPPLY DUCTS EITHER

KEEP RUNNING OR

COVER WHEN NOT

RUNNING TO KEEP

DUST OUT.

A

V

OTAPE ALL SERVICES

TO PROTECT AGAINST

CONTAMINATION

E

FIRE EXTINGUISHER ON

PORTABLE FLOOR BRACKET

(SHALL REQUIRE MORE THAN

ONE.)

PUBLIC AREA

CONSTRUCTION AREA

ANTE ROOM

HARD BARRIER ALL THE WAY TO

DECK ABOVE

SIZE ANTE ROOM TO PROVIDE

SPACE FOR EQUIPMENT STAGING,

CART CLEANING, WORKERS' PPE

AND CLEANING, INCLUDING A HEPA

CLOTHING VACUUM

ROUTE DUCT TO EXTERIOR - SEE

PLANS FOR PROPOSED ROUTES -

CONFIRM ROUTE WITH ON-SITE

STAFF PRIOR TO INSTALLATION.

DISCHARGE AT A DISTANCE OF 25

FEET OR GREATER FROM

ENTRANCES, AIR INTAKES AND

OPERABLE WINDOWS. DO NOT

DIRECT EXHAUST INTO ANY

BUILDING SHARED EXHAUST

SYSTEM.

ANTE ROOM FAN

DOOR TO BE SELF-CLOSING AND

SELF-LATCHING - 45 MIN. FIRE

RATING PER NFPA

A5

26GI300

22255 SF

EXISTING ASSEMBLY -

STORAGE

110110

STAIRS

S1S1

OFFICE

111111

EQUIP

SUPPLY

112112

CLASS

ROOM

113113

GYMNASIUM

114114

CORRIDOR

116Z116Z

MENS

SHOWER

108E108E

WORKOUT

ROOM

107107

BLEACHER

STORAGE

109109

MAIN

ENTRY

118Z118Z

MENS TLT

101101

VISITOR

LOCKER

ROOM

103A103A

WOMENS

LOCKER

ROOM

105A105A

CORRIDOR

115Z115Z

WOMENS

TLT

105B105B

GALLERY

106A106A

SWIMMING

POOL

106106

CORRIDOR

119Z119Z

MENS

LOCKER

ROOM

108108

23 4

E1 ▬ 83.8'

MI

N

3'- 6"

C

LR

E2 ▬ 100'

1/4" = 1'-0"C5 TYPICAL CONSTRUCTION LAYOUT- CLASS IV

1/2" = 1'-0"A5 CROSS SECTION A'-A'- CLASS IV

NTSF1 TYPICAL ICRA PRODUCTS

TN

PN

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

TRIPLE C - The A/E Group 201 E. Jefferson Street, Suite 200 Syracuse, NY 13202

MAT PERKINS

(315) 484-5958

Au to de sk

D oc s:

//6

-2

2-

M on tro se V

AM

C

E H

R M

IU

/6

-2

2-

0.

M on tro se .E

H R

M .A

R C

H .B

.rv t 3/

/2

6:

:0

PM

26GI300

INTERIM LIFE SAFETY & INFECTION CONTROL

PLAN - FIRST LEVEL

620-22-700

06/27/2025 M. Perkins K. McDermott

ISSUED FOR CONSTRUCTION (EHRM) INFRASTRUCTURE

UPGRADES

2094 Albany Post Road, Montrose, NY 10548

A.

B.

C.

D.

E.

F.

G.

H.

I.

J.

K.

L.

M.

N.

O.

P.

Q.

R.

IMPLEMENT INFECTION CONTROL RISK ASSESSMENT (ICRA)

PROCEDURES AS PER THE MONTROSE VA ICRA PLAN AND AS

DIRECTED BY THE CONTRACTING OFFICER REPRESENTATIVE

(COR).

COORDINATE ALL DEMOLITION/ CONSTRUCTION DEBRIS PATH

OF TRAVEL AND INTERIM LIFE SAFETY MEASURES (ILSM) WITH

THE COR. ALL INTERIOR DOORS THAT LEAD TO THE

CONSTRUCTION SITE SHALL BE POSTED AS PER THE ISLM PLAN.

OBTAIN INFECTION CONTROL PERMIT PRIOR TO BEGINNING

WORK.

THE ONE HOUR FIRE RATED CONSTRUCTION BARRIERS SHALL

BE CONSTRUCTED PRIOR TO BEGINNING OTHER WORK.

CONSTRUCT ANTEROOM AT ENTRANCES TO CONSTRUCTION

AREAS AND REQUIRE ALL CONSTRUCTION PERSONNEL TO PASS

THROUGH THIS ROOM TO BE VACUUMED WITH HEPA VACUUM

CLEANER PRIOR TO LEAVING THE SITE.

FIRE PROTECTION SYSTEMS SHALL REMAIN FUNCTIONAL FOR

OCCUPIED AREAS ON THE FLOOR.

PROVIDE FIRE EXTINGUISHERS IN CONSTRUCTION AREAS;

REVIEW WITH COR AND VA SAFETY GROUP.

MAINTAIN EXIT LIGHTS IN CONSTRUCTION AREA.

MAINTAIN NEGATIVE AIR PRESSURE IN CONSTRUCTION AREA AT

ALL TIMES (24/7). WHETHER OCCUPIED OR NOT, THROUGHOUT

DURATION OF PROJECT USING HEPA EQUIPPED AIR FILTRATION

UNITS.

CONSTRUCTION AREA SHALL REMAIN ISOLATED FROM THE

OTHER AREAS OF THE MEDICAL CENTER; NO RETURN AIR OR

EXHAUST SHALL PASS INTO THE AREAS OUTSIDE THE

CONSTRUCTION AREA. ISOLATE HVAC SYSTEM WITHIN

CONSTRUCTION AREA TO PREVENT CONTAMINATION OF

EXISTING DUCT SYSTEM.

REDIRECT ALL MEDICAL CENTER PERSONNEL. PATIENTS AND

VISITORS SO THEY DO NOT EXIT THROUGH THE CONSTRUCTION

AREA. PROVIDE SIGNS ON DOORS INTO THE CONSTRUCTION

AREA THAT READS: "CONSTRUCTION AREA-DO NOT ENTER".

GENERAL CONTRACTOR SHALL MAINTAIN DAILY LOGS AND KEEP

A CURRENT HOT WORK PERMIT ON SITE.

TACKY MATS SHALL BE PLACED AT ALL DOORS INTO THE

CONSTRUCTION AREA AND SHALL BE MONITORED TO MAKE

SURE THEY REMAIN EFFECTIVE.

MAINTAIN A CLEAN AND ORDERLY CONSTRUCTION AREA. ALL

DEBRIS REMOVAL SHALL BE IN COVERED CARTS AND/OR

CONTAINERS.

SEAL ALL HOLES, PUNCTURES, AND PENETRATIONS FROM PIPES

AND CONDUITS APPROPRIATELY AND IMMEDIATELY TO MAINTAIN

DUST PROTECTION AND NEGATIVE AIR PRESSURE.

MAINTAIN STAFFING AND EQUIPMENT INCLUDING DUST MOPS,

WET MOPS, BROOMS, BUCKETS AND CLEAN WIPING RAGS FOR

CLEANING FINE DUST FROM FLOORS AND ADJACENT OCCUPIED

AREAS. ANY DUST TRACKED OUTSIDE OF CONSTRUCTION AREA

SHALL BE CLEANED IMMEDIATELY.

AFTER COMPLETION OF WORK: VACUUM CONSTRUCTION AREA

WITH HEPA FILTERED VACUUMS, WET MOP WITH DISINFECTANT,

REMOVE CONSTRUCTION BARRIERS (UPON APPROVAL). PATCH

OR REPAIR ANY DAMAGE FROM CONSTRUCTION BARRIER

REMOVAL AND REMOVE ISOLATION OF HVAC SYSTEM.

CONSTRUCTION BARRIERS SHALL NOT BE REMOVE UNTIL

PROJECT IS COMPLETED AND INSPECTED BY VA SAFETY

PERSONNEL, INFECTION CONTROL GROUP, AND COR.

ICRA NOTES:

INFECTION CONTROL RISK

ASSESSMENT:

TABLE 1: CONSTRUCTION, RENOVATION AND/OR MAINTENANCE

ACTIVITY CATEGORY

IDENTIFY THE CATEGORY OF CONSTRUCTION PROJECT

CATEGORY A: INSPECTION AND/OR FACILITY UPKEEP

CATEGORY B: GENERAL MAINTENANCE AND REPAIR WORK

CATEGORY C: SMALL-SCALE CONSTRUCTION, RENOVATION, AND/OR

MAINTENANCE

CATEGORY D: LARGE-SCALE CONSTRUCTION, RENOVATION, OR

MAINTENANCE

THIS PROJECT: CATEGORY D

TABLE 2: AFFECTED AREA ASSESSMENT

TABLE 3: PATIENT RISK CATEGORY

IDENTIFY THE PATIENT RISK CATEGORY FOR EACH AREA LISTED IN

TABLE 2. OF THE PATIENT RISK CATEGORIES IDENTIFIED, THE ONE WITH

THE GREATEST RISK SHALL BE SELECTED AS THE OVERALL PATIENT

RISK CATEGORY FOR THE ACTIVITY.

LOW RISK: NON-PATIENT CARE AREAS

MEDIUM RISK: PATIENT CARE SUPPORT AREAS

HIGH RISK: PATIENT CARE AREAS

HIGHEST RISK: PROCEDURAL, INVASIVE, STERILE SUPPORT AND HIGLY

COMPROMISED PATIENT CARE AREAS

THIS PROJECT: LOW RISK

CL

AS

S

II

Construction Activity Category

RISK GROUP

LOW RISK

MEDIUM RISK

HIGH RISK

HIGHEST RISK

I II II III

I II III IV

I II IV IV

II III IV IV

A

STEP 1:

IDENTIFY SPECIFIC SITE OF ACTIVITY, FOR EXAMPLE, PATIENT

ROOMS, MEDICATION ROOM, AND SO ON.

STEP 2:

IDENTIFY ISSUES RELATED TO: VENTILATION, PLUMBING, AND

ELECTRICAL IN TERMS OF THE OCCURRENCE OF PROBABLE

OUTAGES.

STEP 3:

IDENTIFY CONTAINMENT MEASURES, USING PRIOR

ASSESSMENT. WHAT TYPES OF BARRIERS (FOR EXAMPLE,

SOLIDS WALLS)? WILL HEPA FILTRATION BE REQUIRED?

STEP 4:

CONSIDER POTENTIAL RISK OF WATER DAMAGE. IS THERE A

RISK DUE TO COMPROMISING STRUCTURAL INTEGRITY (FOR

EXAMPLE, WALL, CEILING, ROOF)?

NOTE: RENOVATION/CONSTRUCTION AREA SHALL BE

ISOLATED FROM THE OCCUPIED AREAS DURING

CONSTRUCTION AND SHALL BE NEGATIVE WITH RESPECT TO

SURROUNDING AREAS.

STEP 5:

WORK HOURS: CAN OR WILL THE WORK BE DONE DURING

NON-PATIENT-CARE HOURS?

STEP 6:

DO PLANS ALLOW FOR ADEQUATE NUMBER OF

ISOLATION/NEGATIVE AIRFLOW ROOMS?

STEP 7:

DO THE PLANS ALLOW FOR THE REQUIRED NUMBER AND TYPE

OF HAND-WASHING SINKS?

STEP 8:

DOES THE INFECTION PREVENTION AND CONTROL STAFF AGREE

WITH THE MINIMUM NUMBER OF SINKS FOR THIS PROJECT?

(VERIFY AGAINST FACILITY GUIDELINES INSTITUTE (FGI) DESIGN

AND CONSTRUCTION GUIDELINES FOR TYPES AND AREA.)

STEP 9:

DOES THE INFECTION PREVENTION AND CONTROL STAFF

AGREE WITH THE PLANS RELATIVE TO CLEAN AND SOILED

UTILITY ROOMS?

STEP 10:

PLAN TO DISCUSS THE FOLLOWING CONTAINMENT ISSUES WITH

THE PROJECT TEAM, FOR EXAMPLE, TRAFFIC FLOW,

HOUSEKEEPING, DEBRIS REMOVAL (HOW AND WHEN).

Affected Area Assessment

AREA

Activity Area Area Above Area Below Adjacent Area

TR

SEE PLAN

SVC TYPE POC POC CONTACT INFO

SEE PLAN

SEE PLAN

Walter Hoffman (914) 208-6275

MATCH THE OVERALL PATIENT RISK CATEGORY WITH THE PLANNED

CONSTRUCTION PROJECT CATEGORY ON THE FOLLOWING MATRIX, TO

FIND THE CLASS OF PRECAUTIONS (I, II, III OR IV) OR LEVEL OF

INFECTION CONTROL ACTIVITIES REQUIRED.

THIS PROJECT: CATEGORY III

TABLE 4: LEVEL OF INFECTION PREVENTION AND CONTROL

PRECAUTIONS

B C D

TABLE 5: REQUIRED INFECTION PREVENTION AND CONTROL MEASURES

BY LEVEL OF PRECAUTIONS

NOTE: LIST IS CUMULATIVE FROM CLASS I THROUGH CLASS IV)

TABLE 6: MINIMUM INFECTION PREVENTION AND CONTROL MEASURES

REQUIRED UPON COMPLETION OF THE ACTIVITY

1.

2.

1.

2.

A.

B.

C.

D.

E.

1.

2.

1.

2.

3.

1.

Construction areas must be inspected by an infection preventionist and engineering representative (and others as determined by the facility) for final activity/project close out and removal of infection prevention and control measures

Work Area Cleaning:

Clean work areas including all environmental surfaces, high horizontal surfaces and flooring materials Check all supply and return air registers for dust accumulation on upper surfaces as well as air diffuser surfaces

Removal of Critical Barriers:

Critical barriers must remain in place during all work involving drywall removal, creation of dust and activities beyond simple touch-up work. The barrier may NOT be removed until a work area cleaning has been performed. Additional cleaning may be needed after removal of barrier All (plastic or hard) barrier removal activities must be completed in a manner that prevents dust release. Use the following precautions when removing hard barriers:

Carefully remove screws and painter tape.

If dust will be generated during screw removal, use hand-held HEPA vacuum.

Drywall cutting is prohibited during removal process Clean all stud tracks with HEPA vacuum before removing outer hard barrier Use a plastic barrier to enclose area if dust could be generated

Negative Air Requirements:

The use of negative air must be designated to remove contaminants from the work area Negative air devices (fans, filters, monitoring and documentation equipment) must remain operational at all times and in place for a period after completion of dust creating activities to remove contaminants from the work area and before removal of critical barriers.

HVAC Systems:

Upon removal of critical barriers, remove isolation of HVAC system in areas where work is being performed Verify that HVAC systems are clean and operational.

Verify and document through a TAB the HVAC systems meets original airflow and air exchange design specifications

Water Systems:

Until the potable water system is activated and in use, flushing shall continue at least twice per week in accordance with VHA directive 1061.

CL

AS

S

III

IV

13.

14.

15.

16.

17.

18.

Ensure availability of equipment for cleaning hands Construct and complete critical barriers meeting NFPA 241 requirements.

Barriers must extend to the ceiling or if ceiling tile is removed, to deck above All (plastic or hard) barrier construction activities must be completed in a manner that prevents dust release. Plastic barriers must be effectively affixed to floor and ceiling (or floor/roof deck above) and secure from movement or damage.

Seal all penetrations in containment barriers, including floors and ceiling, using approved materials (UL schedule firestop if applicable for barrier type) Maintain .01 inches /water gauge negative pressurization of the entire workspace by use of HEPA exhaust air systems directed outdoors, or comply with the alternative method outlined in Appendix A of this document.

These control measures must be maintained continuously 24/7 for the duration of the project. HEPA filtered exhaust if discharged directly to the outdoors must be at a istance of 25 feet or greater from entrances, air intakes and operable windows. Exhausting discharged air into shared or recirculating HVAC systems, or other shared exhaust systems (e.g., bathroom exhaust) is prohibited Install a differential pressure sensing device (e.g., magnehelic, manometer, or digital monitoring) on exterior of work containment to continually monitor and document negative pressurization. The “ball in the wall” or similar apparatus are not acceptable

4.

5.

6.

7.

8.

9.

10.

11.

12.

Provide active means to control airborne dust from dispersing into occupied areas and/or water mist surface to control dust (e.g., Mobile Dust Containment Cart or some other system)Ensure worker clothing is clean and free of visible dust before leaving the work area Remove or isolate air diffusers (supply and return) to protect the HVAC system from dust and reduce air turbulence. Rebalance system to address diffuser isolation When the work involves or impacts potable water systems including stagnation due to reduced usage, the piping shall be flushed twice a week or isolated from the main system Seal doors to prevent dust migration Contain all trash and debris in the work area. Perform daily cleaning and disposal of trash (covered) from work area using an identified exit route.

Any equipment, tools, or materials removed from the work area must be in sealed containers and/or cleaned of dust and debris prior to removal from the area Nonporous/smooth and cleanable containers (with a hard lid) must be used to transport trash and debris from the construction areas. These containers must be damp-wiped cleaned and free of visible dust/debris before leaving the contained work area Install a sticky (dust collection) mat at entrance of contained work area based on facility policy. Sticky mats just be changed routinely and when visibly soiled.

Maintain clean surroundings when area is not contained by damp mopping or HEPA vacuuming surfaces at least daily

1.

2.

3.

Perform work activity in a manner that does not create dust Immediately replace ceiling tile, close access panels, etc. upon completion.

Any materials and equipment being brought into the facility must be free of contaminants and loose material

19.

20.

21.

22.

Barriers must be hard barriers unless temporary to install final barrier.

Containment must include an anteroom to ensure pressure control.

Anteroom must be large enough for equipment staging, cart cleaning, workers’ PPE and cleaning.

Worker clothing and/or PPE must be removed or clean and free of visible dust before leaving the work area anteroom. HEPA vacuuming of clothing or use of cover suits is acceptable Workers must wear shoe covers or have a method to clean shoes in anteroom. Shoe covers must be removed prior to exiting the anteroom to the occupied space (non-work area). Damaged shoe covers must be changed immediately.

CL

AS

S I

CL

AS

S

III

CL

AS

S

IV

YES

N/A

N/A

N/A

N/A

AFTER-HOURS WORK TO BE COORDINATED WITH VA COR

COORDINATE WITH VA COR ON PATIENT CARE FLOORS

TEMPORARY WALLS TO BE 1-HR RATED - PREFABRICATED

WALLS / DOOR PREFERRED

TECHNOLOGY AND ELECTRICAL FOCUSED WORK -

MINIMAL PLUMBING OR MECHANICAL IMPACT

MINOR INTERIOR RENOVATION IN EXISTING BUSINESS

OCCUPANCY AREAS - SEE PLAN

Walter Hoffman (914) 208-6275 Walter Hoffman (914) 208-6275 Walter Hoffman (914) 208-6275

1/16" = 1'-0"F3 INTERIM LIFE SAFETY & INFECTION CONTROL PLAN - FIRST LEVEL

PATH OF TRAVEL SCHEDULE - FIRST LEVEL

Mark From Room To Room Type of Travel Path Length

LEVEL 1

(P-o-T) Distance to Exits

E1 CORRIDOR 116Z (P-o-T) Distance to Exits 83' - 10" E2 WOMENS TLT 105B (P-o-T) Distance to Exits 100' - 0"

1 TEMPORARY CONSTRUCTION BARRIER DOOR WITH

CLOSER AND LATCH AND WALK OFF MATS

2 DEBRIS REMOVAL PATH TO EXTERIOR -

COORDINATE REMOVAL OF MATERIALS ON THIS

FLOOR WITH ASBESTOS REPORT AND PLAN

3 SOLID GRAY HATCH DENOTES LIMITED WORK AREA

- SEE MEP AND TELECOM DRAWINGS FOR CABLING

SCOPE, TYP.

4 MAINTAIN EXIT PATHWAYS FOR OCCUPANTS AT ALL

TIMES

5 COORDINATE TEMPORARY HEPA EXHAUST

ROUTING OUT OF BUILDING - MAINTAIN 25 FEET

MINIMUM FROM INTAKES, OPERABLE WINDOWS,

AND ENTRANCES. PROVIDE BLOCK-OFF PANELS IN

EXISTING WINDOWS FOR DISCHARGE, TYP.

6 TEMPORARY CONSTRUCTION BARRIER

7 ANTEROOM - SEE INFECTION CONTROL & INTERIM

LIFE SAFETY DETAILS

8 ENTRY INTO GYMNASIUM THROUGH THIS OPENING

TO BE LIMITED DURING DEMOLITION AND

CONSTRUCTION

AREA OCCUPANCIES

LEVEL Name Area SF

Occupancy Requirements

OL

Occupancy

(IBC) Occupancy (NFPA) OLF Fixed Seats

FIRST LEVEL EXISTING ASSEMBLY 22255 SF A3 Assembly 15 SF 0 1484

NOTE:

DEBRIS REMOVAL:

CONFIRM WITH COR FOR FINAL PLAN AND PROCEDURE OF

MATERIAL REMOVAL WITH ANTEROOMS, HEPA FILTRATION, ICRA

PROTOCOLS, AND ROUTE THRU OCCUPIED SPACES; PRIOR TO

REMOVAL OF ANY MATERIALS.

SECURE STAIRWELLS FROM UNAUTHORIZED ENTRY DURING

CONSTRUCTION.

CONTRACTOR TO PROVIDE DUMPSTER 35' MINIMUM FROM ANY

BUILDING. DUMPSTER AND ANY LAY-DOWN AREA ARE TO BE

ENCLOSED BY 6'-0" HIGH TEMPORARY CONSTRUCTION FENCING.

PROVIDE TRASH CART FOR REMOVAL OF WASTE FROM JOB SITE

AREAS DAILY.

LIFE SAFETY:

NEW WORK DOES NOT CHANGE EXISTING SMOKE

COMPARTMENTS, EXIT PATHWAYS, OR EXITS.

# Revisions: Date:

1 ADDENDUM #1 03/30/2026

GENERAL

STORAGE

GENERAL

STORAGE

SERVICE

ROOM

TRANSFORMER

ROOM

STAIR

HALL 01

CHLORINE

ROOM

GENERAL

STORAGE

PIPE

BASEMENT

PIPE

BASEMENT

PIPE

BASEMENT

PIPE

BASEMENT

26E-100 B6

TRANSFORMER

ROOM

B2 6-

G-

TN

PN

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD A/E:

CONSULTANT

321 4 5 6 7 8 9 10

GENERAL NOTES

KEYNOTES

TRIPLE C - The A/E Group 201 E. Jefferson Street, Suite 200 Syracuse, NY 13202

MAT PERKINS

(315) 484-5958

STAMP

Au to de sk

D oc s:

//6

-2

2-

M on tro se V

AM

C

E H

R M

IU

/6

-2

2-

0.

M on tro se .E

H R

M .M

EP

.B

.rv t 3/

/2

8:

:5

PM

26E-100

ELECTRICAL PLAN - BASEMENT LEVEL 620-22-700

06/27/2025 M. Perkins J. Castenir

ISSUED FOR

CONSTRUCTION

(EHRM) INFRASTRUCTURE

UPGRADES

2094 Albany Post Road, Montrose, NY 10548

SCALE: 1/8" = 1'-0"F1

ELECTRICAL PLAN - BASEMENT

LEVEL

SCALE: 1/2" = 1'-0"B6

ELECTRICAL ENLARGED PLAN -

BASEMENT LEVEL - ROOM 0003 -

EXISTING

1.

2.

3.

4.

5.

6.

7.

PROVIDE NEW 16" x 4" BONDING BAR, SET OF INSULATORS STAND-OFF

BRACKETS, AND STAINLESS STEEL SCREWS. PROVIDE ALL GROUNDING CABLE

AND CONNECTORS AND INSTALL PER TYPICAL DETAIL ON T-500 SERIES SHEETS.

PROVIDE NEW WALL MOUNTED TELECOMMUNICATION ENCLOSURE CABINET,

WITH LOCKABLE FRONT DOOR AND SWING-OUT REAR ACCESS TO EQUIPMENT.

PROVIDE NEW ACCESS CONTROL PER SPECIFICATIONS. FIPS, FICAM AND

HSPD12 COMPLIANT AVIGILON ACM SYSTEM, CARD READER WITH PINPAD CARD,

PIV READY.

NEW NORMAL POWER RECEPTACLE, SEE PANEL SCHEDULE FOR ADDITIONAL

INFORMATION.

FIBER TO HAVE NEW DEDICATED 4” SPEED CONDUIT SLEEVE THROUGH WALL

ABOVE CEILING GRID FOR HORIZONTAL VOICE/DATA CABLING OR FIBER WITH

PLASTIC BUSHINGS ON BOTH ENDS TO PROTECT CABLES. FIRE CAULK

PENETRATION PER SPECIFICATIONS.PROVIDE WITH (3) SLEEVE GANG PLATE AT

EACH OF THE (2) LOCATIONS, EACH TR PROVIDE WITH (3) SLEEVE GANG PLATE

AT EACH OF THE (2) LOCATIONS, EACH TR, AS PER SPECIFICATIONS.

PROVIDE AND INSTALL NEW JOHNSON CONTROLS iSTAR EDGE G2 IP-BASED

ACCESS CONTROL PANEL. PROVIDE LIFESAFETY POWER (LSP) PSX UNIFIED

ENCLOSURE WITH INTEGRATED BACKUP BATTERIES PROVIDING A MINIMUM OF 4

HOURS OF STANDBY POWER. PROVIDE A DEDICATED 20A, 120VAC CIRCUIT IN

ACCORDANCE WITH NEC AND MANUFACTURER ’S RECOMMENDATIONS.

COORDINATE FINAL PROGRAMMING AND INTEGRATION WITH THE C •CURE 9000

EVENT MANAGEMENT SYSTEM.

EXISTING PANEL TO REMAIN, PROTECT IN PLACE.

20. PROVIDE NEW CIRCUIT BREAKERS AND FEEDERS SERVICING NEW TELECOM

EQUIPMENT. REFER TO SHEETS E-601 & E-701 FOR SIZING.

21. NEW A/B REDUNDANT L5-30 20A OUTLETS WITH INTEGRATED TYPE 3 SPD

DEVICES.

22. PROVIDE A 30 DAYS LOAD MEASUREMENT OF PANELBOARD INDICATED. PROVIDE

THE REPORT TO THE COR AND AR PRIOR TO COMMENCEMENT OF PANELBOARD

RENOVATION.

23. CONTRACTOR TO VALIDATE SWING PRIOR TO INSTALLATION.

A.

B.

C.

D.

E.

F.

G.

H.

I.

J.

K.

L.

M.

N.

O.

P.

CONTRACTOR SHALL COORDINATE ALL EQUIPMENT, DUCTWORK AND PIPING

WITH STRUCTURAL, MECHANICAL, AND ELECTRICAL SYSTEMS AND SHALL

PROVIDE NECESSARY OFFSETS TO AVOID CONFLICTS AND TO MAINTAIN

REQUIRED EQUIPMENT ACCESS AND SERVICEABILITY.

EXISTING CONDITIONS ARE BASED ON EXISTING PLANS AND FIELD VERIFICATION

WHERE FEASIBLE. CONSTRUCTION AREA CONDITIONS MAY DIFFER FROM

THOSE INDICATED.

MINIMUM BRANCH CIRCUIT SIZE SHALL BE 2#12, 1#12G., 3/4"C.

CONTRACTOR SHALL COORDINATE FINAL POINT OF CONNECTIONS

WITH VA COR PRIOR TO ROUGH-IN.

PROVIDE NEMA 3R ENCLOSURES FOR EQUIPMENT INSTALLED

OUTDOORS

SIZE BRANCH CIRCUITS AND FEEDERS TO EQUIPMENT PER PANEL

SCHEDULE AND FEEDER AND BRANCH CIRCUIT SIZING TABLE ON E-701.

COORDINATE FINAL EQUIPMENT CONNECTIONS AT EQUIPMENT WITH

EQUIPMENT SUPPLIER, PRIOR TO ROUGH-IN.

LABEL DEVICE PLATES WITH A PERMANENT ADHESIVE LABEL LISTING

PANEL AND CIRCUIT FEEDING THE WIRING DEVICE.

UPDATE PANEL SCHEDULES AFFECTED BY RENOVATION.

NEW CIRCUIT BREAKERS PROVIDED SHALL MATCH THE EXISTING TYPE

OF CIRCUIT BREAKERS IN PANEL BEING RENOVATED.

CONTRACTOR SHALL FIELD COORDINATE CABLE TRAY LAYOUT WITH

EXISTING UTILITIES ROUTED THROUGH THE RENOVATED SPACE.

CONTRACTOR SHALL COMPLY WITH NEC 300.22 FOR CONDUIT ROUTED IN

PLENUM SPACES.

REFER TO E-901 FOR CUTSHEETS.

COMPLY WITH NEC 220.87 FOR ALL 30-DAY LOAD MEASUREMENTS OF

PANELBOARDS.

LOCATE DISCONNECT SWITCHES TO MAINTAIN WORKING CLEARANCES

PER NEC 110.26.

CONTRACTOR SHALL LABEL ALL JUNCTION BOX COVERS WITH THE CIRCUITS

CONTAINED AND SOURCE PANEL IDENTIFIED.

NOTE: NOT ALL KEYNOTES

ARE USED ON EACH SHEET

CR

EL

DCRX

B8

E-

WOMENS

TLT

105B

MENS

TOILET

108D

RINSING

RM

108B

WORKOUT

ROOM

F.A.C.

BLEACHER

STORAGE

CLASS

ROOM

GYMNASIUM

STORAGE

VISITOR

ENTRY

VISITOR

LOCKER

ROOM

103A

CORRIDOR

119Z

STORAGE

MENS TLT

WOMENS

LOCKER

ROOM

105A

GALLERY

106A

STORAGE

45 SF

EQUIP

SUPPLY

CORRIDOR

116Z

OFFICE

STAIRS

S1

MENS

ENTRY

108F

MENS

LOCKER

ROOM

MENS

SHOWER

108E

SWIMMING

POOL

SOAPING

RM

108C

MAIN

ENTRY

118Z

CORRIDOR

115Z

ENTRY

108A

26E-101 B6

F1

E-

CORRIDOR

120Z

STORAGE

45 SF

CORRIDOR

116Z

STAIRS

S1

GYMNASIUM

TYP.

TYP.

B26-G-102- 13 B26-G-102- 15

TN

PN

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD A/E:

CONSULTANT

321 4 5 6 7 8 9 10

GENERAL NOTES

KEYNOTES

TRIPLE C - The A/E Group 201 E. Jefferson Street, Suite 200 Syracuse, NY 13202

MAT PERKINS

(315) 484-5958

STAMP

Au to de sk

D oc s:

//6

-2

2-

M on tro se V

AM

C

E H

R M

IU

/6

-2

2-

0.

M on tro se .E

H R

M .M

EP

.B

.rv t 3/

/2

8:

:0

PM

26E-101

ELECTRICAL PLAN - FIRST LEVEL AREA-A &

AREA-B

620-22-700

06/27/2025 M. Perkins J. Castenir

ISSUED FOR

CONSTRUCTION

(EHRM) INFRASTRUCTURE

UPGRADES

2094 Albany Post Road, Montrose, NY 10548

SCALE: 1/8" = 1'-0"F1

ELECTRICAL PLAN - FIRST LEVEL -

AREA A

SCALE: 1/8" = 1'-0"B8

ELECTRICAL PLAN - FIRST LEVEL -

AREA B

SCALE: 1/2" = 1'-0"B6

ELECTRICAL ENLARGED PLAN - FIRST

LEVEL - RM 110 - NEW

1.

2.

3.

4.

5.

6.

7.

PROVIDE NEW 16" x 4" BONDING BAR, SET OF INSULATORS STAND-OFF

BRACKETS, AND STAINLESS STEEL SCREWS. PROVIDE ALL GROUNDING CABLE

AND CONNECTORS AND INSTALL PER TYPICAL DETAIL ON T-500 SERIES SHEETS.

PROVIDE NEW WALL MOUNTED TELECOMMUNICATION ENCLOSURE CABINET,

WITH LOCKABLE FRONT DOOR AND SWING-OUT REAR ACCESS TO EQUIPMENT.

PROVIDE NEW ACCESS CONTROL PER SPECIFICATIONS. FIPS, FICAM AND

HSPD12 COMPLIANT AVIGILON ACM SYSTEM, CARD READER WITH PINPAD CARD,

PIV READY.

NEW NORMAL POWER RECEPTACLE, SEE PANEL SCHEDULE FOR ADDITIONAL

INFORMATION.

FIBER TO HAVE NEW DEDICATED 4” SPEED CONDUIT SLEEVE THROUGH WALL

ABOVE CEILING GRID FOR HORIZONTAL VOICE/DATA CABLING OR FIBER WITH

PLASTIC BUSHINGS ON BOTH ENDS TO PROTECT CABLES. FIRE CAULK

PENETRATION PER SPECIFICATIONS.PROVIDE WITH (3) SLEEVE GANG PLATE AT

EACH OF THE (2) LOCATIONS, EACH TR PROVIDE WITH (3) SLEEVE GANG PLATE

AT EACH OF THE (2) LOCATIONS, EACH TR, AS PER SPECIFICATIONS.

PROVIDE AND INSTALL NEW JOHNSON CONTROLS iSTAR EDGE G2 IP-BASED

ACCESS CONTROL PANEL. PROVIDE LIFESAFETY POWER (LSP) PSX UNIFIED

ENCLOSURE WITH INTEGRATED BACKUP BATTERIES PROVIDING A MINIMUM OF 4

HOURS OF STANDBY POWER. PROVIDE A DEDICATED 20A, 120VAC CIRCUIT IN

ACCORDANCE WITH NEC AND MANUFACTURER ’S RECOMMENDATIONS.

COORDINATE FINAL PROGRAMMING AND INTEGRATION WITH THE C •CURE 9000

EVENT MANAGEMENT SYSTEM.

EXISTING PANEL TO REMAIN, PROTECT IN PLACE.

20. PROVIDE NEW CIRCUIT BREAKERS AND FEEDERS SERVICING NEW TELECOM

EQUIPMENT. REFER TO SHEETS E-601 & E-701 FOR SIZING.

21. NEW A/B REDUNDANT L5-30 20A OUTLETS WITH INTEGRATED TYPE 3 SPD

DEVICES.

22. PROVIDE A 30 DAYS LOAD MEASUREMENT OF PANELBOARD INDICATED. PROVIDE

THE REPORT TO THE COR AND AR PRIOR TO COMMENCEMENT OF PANELBOARD

RENOVATION.

23. CONTRACTOR TO VALIDATE SWING PRIOR TO INSTALLATION.

A.

B.

C.

D.

E.

F.

G.

H.

I.

J.

K.

L.

M.

N.

O.

P.

CONTRACTOR SHALL COORDINATE ALL EQUIPMENT, DUCTWORK AND PIPING

WITH STRUCTURAL, MECHANICAL, AND ELECTRICAL SYSTEMS AND SHALL

PROVIDE NECESSARY OFFSETS TO AVOID CONFLICTS AND TO MAINTAIN

REQUIRED EQUIPMENT ACCESS AND SERVICEABILITY.

EXISTING CONDITIONS ARE BASED ON EXISTING PLANS AND FIELD VERIFICATION

WHERE FEASIBLE. CONSTRUCTION AREA CONDITIONS MAY DIFFER FROM

THOSE INDICATED.

MINIMUM BRANCH CIRCUIT SIZE SHALL BE 2#12, 1#12G., 3/4"C.

CONTRACTOR SHALL COORDINATE FINAL POINT OF CONNECTIONS

WITH VA COR PRIOR TO ROUGH-IN.

PROVIDE NEMA 3R ENCLOSURES FOR EQUIPMENT INSTALLED

OUTDOORS

SIZE BRANCH CIRCUITS AND FEEDERS TO EQUIPMENT PER PANEL

SCHEDULE AND FEEDER AND BRANCH CIRCUIT SIZING TABLE ON E-701.

COORDINATE FINAL EQUIPMENT CONNECTIONS AT EQUIPMENT WITH

EQUIPMENT SUPPLIER, PRIOR TO ROUGH-IN.

LABEL DEVICE PLATES WITH A PERMANENT ADHESIVE LABEL LISTING

PANEL AND CIRCUIT FEEDING THE WIRING DEVICE.

UPDATE PANEL SCHEDULES AFFECTED BY RENOVATION.

NEW CIRCUIT BREAKERS PROVIDED SHALL MATCH THE EXISTING TYPE

OF CIRCUIT BREAKERS IN PANEL BEING RENOVATED.

CONTRACTOR SHALL FIELD COORDINATE CABLE TRAY LAYOUT WITH

EXISTING UTILITIES ROUTED THROUGH THE RENOVATED SPACE.

CONTRACTOR SHALL COMPLY WITH NEC 300.22 FOR CONDUIT ROUTED IN

PLENUM SPACES.

REFER TO E-901 FOR CUTSHEETS.

COMPLY WITH NEC 220.87 FOR ALL 30-DAY LOAD MEASUREMENTS OF

PANELBOARDS.

LOCATE DISCONNECT SWITCHES TO MAINTAIN WORKING CLEARANCES

PER NEC 110.26.

CONTRACTOR SHALL LABEL ALL JUNCTION BOX COVERS WITH THE CIRCUITS

CONTAINED AND SOURCE PANEL IDENTIFIED.

NOTE: NOT ALL KEYNOTES

ARE USED ON EACH SHEET

# Revisions: Date:

CR

WALL

1"EMT CONDUIT

JUNCTION BOX

8'-6" AFF

CABLE TRAY TO

TELECOMMUNICATIONS

RACK

46"

ALL CABLES TO ACCESS CONTROL PANEL

4"Hx4"x2"D IN ACCESSIBLE CEILING

3/4"C

3/4"C

CEILING

LINE

DOOR

CONTACT

FINISHED

FLOOR

DOOR

DOOR FRAME

ELECTRIFIED

TRANSFER

HINGE

CORE DOOR FOR

SECURITY LOCK

5S SQ. BOX WITH SINGLE

GANG TRIM RING. MAINTAIN

FIRE RATING OF WALL

ASSEMBLY.

PUBLIC SIDE SHOWN

CONDUIT

ELECTRIC

DOOR

LOCKING

HARDWARE

REX MOTION DETECTOR

(SECURE SIDE)

PUBLIC

SIDE

5S

1.

2.

3.

4.

5.

6.

NOTES:

COORDINATE LOCKING HARDWARE

PROVIDED UNDER OTHER SECTIONS

WITH THE ELECTRONIC SECURITY

DEVICES AND CONTROL PROVIDED

HERE.

DETAILS ARE FOR REFERENCE ONLY.

SEE FLOOR PLANS FOR LEFT OR RIGHT

HAND PLACEMENT OF DEVICES.

FOR NEW DOORS, PREP THE FRAME AND

DOOR FOR SECURITY DEVICES AT THE

FACTORY BEFORE THE LABEL IS APPLIED.

EXISTING DOORS SHALL BE RECERTIFIED

AS REQUIRED.

SECURITY JUNCTION BOX SHALL BE

TAMPERED, HINGED AND LOCKABLE.

REX MOUNTED ON THE SECURE SIDE OF

THE DOOR.

EGRESS DOOR SHALL BE READILY

OPENABLE FROM THE EGRESS SIDE

SECTION VIEW FRONT VIEW

DOOR FRAME

VERTICAL

DOOR

DOOR

CONTACT

MAGNET

DOOR

CONTACT

SWITCH

REX SENSOR

CONDUIT TO SJB

SINGLE

GANG BOX

MOUNTED

HORIZONTAL

EXTEND

CONDUIT 6"

BELOW BOX

DOOR

CONTACT

CONCEALED

DOOR

FRAME

REX MOTION

DETECTOR

WALL STUD

REX AND DOOR CONTACT ENLARGED DETAIL

PB IC

FLOOR

DOOR

CL

12"

48"

AFF

80"

MIN

FIRE ALARM NOTIFIER

(STROBE/HORN/SPEAKER)

NOTES:

1. HEIGHTS SHOWN ARE TYPICAL TO CENTER OF BACKBOX / DEVICE UNLESS NOTED OTHERWISE.

2. DEVICES ABOVE DOORS SHALL BE CENTERED BETWEEN TOP OF DOOR TRIM AND CEILING LINE.

3. MOUNTING HEIGHTS SHOWN ON ARCHITECTURAL ELEVATIONS SHALL GOVERN OVER THOSE SHOWN ABOVE.

4. ALL ELEVATIONS ARE TO CENTER LINE OF DEVICE, UNLESS OTHERWISE NOTED.

5. REFER TO EQUIPMENT ELEVATION DRAWINGS FOR COORDINATION WITH CASEWORK.

6. MOUNT MANUAL MOTOR STARTER ADJACENT TO OR ON UNIT.

96"

MAX

6" MIN

LIGHT SWITCH (OR OCCUPANCY SENSOR/SWITCH)

PUSHBUTTON (DOOR ACTUATOR)

WALL PHONE JACK

INTERCOM

18"

AFF

VOICE/DATA OUTLET

POWER OUTLET

J

AUDIO-VISUAL INPUT JACK

J

AUDIO-VISUAL

CONTROL KEYPAD

CR

SECURITY CARD READER

4"

MAX

4"

MAX

UNDERSIDE OF

STRUCTURE

FIRE PROTECTION ZONE, BENEATH DECK

LIGHTING ZONE OR CEILING (9'-0")

CABLING ZONE TRAYS 6" ABOVE

DOOR

CABLE TRAY HVAC ZONE, LOCATION ON PLAN

T

THERMOSTAT

6" MIN

DISCONNECT

SWITCHES

M

MOTOR STARTER

PANELBOARDS &

CABINETS

INDIVIDUAL CIRCUIT BREAKERS

CK

CLOCK OUTLETS

NC

NURSE CALL

STATION

NURSE CALL DOME LIGHTS

DM

DIMMERS

FIRE ALARM - PULL STATIONS

FX

F

FIREMAN WALL PHONE JACK 90"

AFF

96"

AFF

66"

AFF

72"

AFF TO TOP

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD A/E:

CONSULTANT

321 4 5 6 7 8 9 10

TRIPLE C - The A/E Group 201 E. Jefferson Street, Suite 200 Syracuse, NY 13202

MAT PERKINS

(315) 484-5958

STAMP

Au to de sk

D oc s:

//6

-2

2-

M on tro se V

AM

C

E H

R M

IU

/6

-2

2-

0.

M on tro se .E

H R

M .M

EP

.G en er al .S he et s.

rv t

-0 3-

2:

:4

26E-501

ELECTRICAL DETAILS 620-22-700

06/27/2025 M. Perkins J. Castenir

ISSUED FOR

CONSTRUCTION

(EHRM) INFRASTRUCTURE

UPGRADES

2094 Albany Post Road, Montrose, NY 10548

NOT TO SCALE

F8 CARD READER - ELECTRIC LOCK

NOT TO SCALE

F7 CAMERA INTERIOR WALL MOUNTING

NOT TO SCALE

F3 ELECTRICAL COMPONENT MOUNTING HEIGHTS

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD A/E:

CONSULTANT

321 4 5 6 7 8 9 10

TRIPLE C - The A/E Group 201 E. Jefferson Street, Suite 200 Syracuse, NY 13202

MAT PERKINS

(315) 484-5958

STAMP

Au to de sk

D oc s:

//6

-2

2-

M on tro se V

AM

C

E H

R M

IU

/6

-2

2-

0.

M on tro se .E

H R

M .M

EP

.G en er al .S he et s.

rv t

-0 3-

2:

:0

26E-901

ELECTRICAL CUTSHEETS & BASIS OF DESIGN 620-22-700

06/27/2025 M. Perkins J. Castenir

ISSUED FOR

CONSTRUCTION

(EHRM) INFRASTRUCTURE

UPGRADES

2094 Albany Post Road, Montrose, NY 10548

4 35 ED UHL ELL14

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD A/E:

CONSULTANT

321 4 5 6 7 8 9 10

TRIPLE C - The A/E Group 201 E. Jefferson Street, Suite 200 Syracuse, NY 13202

MAT PERKINS

(315) 484-5958

STAMP

Au to de sk

D oc s:

//6

-2

2-

M on tro se V

AM

C

E H

R M

IU

/6

-2

2-

0.

M on tro se .E

H R

M .M

EP

.G en er al .S he et s.

rv t

-0 3-

2:

:1

26E-902

ELECTRICAL CUTSHEETS & BASIS OF DESIGN 620-22-700

06/27/2025 M. Perkins J. Castenir

ISSUED FOR

CONSTRUCTION

(EHRM) INFRASTRUCTURE

UPGRADES

2094 Albany Post Road, Montrose, NY 10548

GENERAL
26G-001 - DRAWING INDEX
ICRA & LIFE SAFETY
26GI300 - INTERIM LIFE SAFETY & INFECTION CONTROL PLAN - FIRST LEVEL
ELECTRICAL
26E-100 - ELECTRICAL PLAN - BASEMENT LEVEL
26E-101 - ELECTRICAL PLAN - FIRST LEVEL AREA-A & AREA-B
26E-501 - ELECTRICAL DETAILS
26E-901 - ELECTRICAL CUTSHEETS & BASIS OF DESIGN
26E-902 - ELECTRICAL CUTSHEETS & BASIS OF DESIGN

File details come from the government source that posted it. Updated .