This document is a construction drawing set for infrastructure upgrades at a residential board and care facility, issued for construction. The project encompasses renovation and telecommunications infrastructure improvements across multiple levels of an existing building, with work areas designated on ground, first, and second levels. Key project requirements include strict infection control and interim life safety measures (ICRA Category D - Large-Scale Construction), with maintenance of negative air pressure, HEPA filtration, temporary barriers, and specialized cleaning protocols throughout construction. The facility must remain operational during renovation with stairs and elevators remaining functional for emergency egress and occupant access.
The scope includes installation of new telecom rooms (Room 12A on Ground Level and Room 142 on First Level, each 119 SF) with associated electrical infrastructure, access control systems, and fire extinguisher cabinets. Electrical work encompasses new circuits, receptacles, UPS systems, and panel modifications across service levels. Telecommunications requirements include new 4-post racks, Category 6A cabling, cable tray systems, wireless access points (WAPs), IP-addressable security cameras with Avigilon NVR integration, and fiber optic cabling coordinated through building interiors. Construction must comply with 2024 NFPA 101 Life Safety Code, 2026 NEC, 2024 IBC, ASHRAE 62.1-2025 and 170-2025 standards, VA seismic requirements, and federal accessibility standards. All work requires coordination with the Contracting Officer Representative (COR), asbestos abatement protocols, and maintenance of clear exit pathways with signage requirements throughout the project duration.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
CONSULTANT
321 4 5 6 7 8 9 10
TRIPLE C - The A/E Group 201 E. Jefferson Street, Suite 200 Syracuse, NY 13202
MAT PERKINS
(315) 484-5958
STAMP
Au to de sk
D oc s:
//6
-2
2-
M on tro se V
AM
C
E H
R M
IU
/6
-2
2-
0.
M on tro se .E
H R
M .M
EP
.B
.rv t 3/
/2
:0
1:
P M
15G-001
DRAWING INDEX 620-22-700
06/27/2025 M. PERKINS K.
HUTCHINSON
ISSUED FOR
CONSTRUCTION
(EHRM) INFRASTRUCTURE
UPGRADES
2094 Albany Post Road, Montrose, NY 10548
- DRAWING INDEX -
SHEET
NUMBER SHEET NAME INCLUDED IN 35% SD INCLUDED IN 65% DD INCLUDED IN 95% CD ISSUED FOR CONSTRUCTION
ARCHITECTURAL
15A-402 ARCHITECTURAL EXTERIOR ELEVATIONS No Yes Yes
GENERAL
15G-000 COVER SHEET Yes Yes Yes Yes 15G-001 DRAWING INDEX Yes Yes Yes Yes 15G-010 GENERAL PROJECT NOTES Yes Yes Yes Yes 15G-012 GENERAL INDOOR AIR QUALITY NOTES Yes Yes Yes Yes
ICRA & LIFE SAFETY
15GI300 INTERIM LIFE SAFETY & INFECTION CONTROL PLAN - GROUND LEVEL No Yes Yes Yes 15GI301 INTERIM LIFE SAFETY & INFECTION CONTROL PLAN - FIRST LEVEL No Yes Yes Yes 15GI302 INTERIM LIFE SAFETY & INFECTION CONTROL PLAN - SECOND LEVEL No Yes Yes Yes 15GI303 INTERIM LIFE SAFETY & INFECTION CONTROL DETAILS No Yes Yes Yes
ARCHITECTURAL
15A-001 ARCHITECTURAL SYMBOLS, & GENERAL NOTES No Yes Yes Yes 15A-400 ARCHITECTURAL ENLARGED VIEWS - GROUND & FIRST LEVELS No Yes Yes Yes 15A-401 ARCHITECTURAL ENLARGED VIEWS - SECOND LEVEL No Yes Yes Yes 15A-501 ARCHITECTURAL ROOF PLAN & DETAILS No Yes Yes Yes 15A-511 ARCHITECTURAL PARTITION AND FRAMING DETAILS No Yes Yes Yes 15A-512 ARCHITECTURAL PARTITION HEAD DETAILS No Yes Yes Yes 15A-531 ARCHITECTURAL CEILING DETAILS No Yes Yes Yes
INTERIORS
15IN101 INTERIOR FINISH PLAN, SIGNAGE & SCHEDULES No Yes Yes Yes
FIRE PROTECTION
15FX001 FIRE PROTECTION ABBREVIATIONS, SYMBOLS, AND DETAILS No Yes Yes Yes 15FX101 FIRE PROTECTION PLAN - GROUND LEVEL No Yes Yes Yes 15FX102 FIRE PROTECTION PLAN - FIRST LEVEL No Yes Yes Yes 15FX103 FIRE PROTECTION PLAN - SECOND LEVEL No Yes Yes Yes 15FX901 FIRE PROTECTION CUTSHEETS & BASIS OF DESIGN No Yes Yes Yes
MECHANICAL
15M-001 MECHANICAL ABBREVIATIONS AND SYMBOLS No Yes Yes Yes 15M-101 MECHANICAL PLAN - GROUND LEVEL No Yes Yes Yes 15M-102 MECHANICAL PLAN - FIRST LEVEL No Yes Yes Yes 15M-103 MECHANICAL PLAN - SECOND LEVEL No Yes Yes Yes 15M-401 MECHANICAL ENLARGED PLANS No Yes Yes Yes 15M-501 MECHANICAL DETAILS No Yes Yes Yes 15M-701 MECHANICAL SCHEDULES No Yes Yes Yes 15M-801 MECHANICAL CONTROL SYMBOL LEGEND AND ABBREVIATIONS No Yes Yes Yes 15M-802 MECHANICAL CONTROL DIAGRAMS No Yes Yes Yes 15M-901 MECHANICAL CUTSHEETS & BASIS OF DESIGN No Yes Yes Yes 15M-902 MECHANICAL CUTSHEETS & BASIS OF DESIGN No Yes Yes Yes
ELECTRICAL
15E-001 ELECTRICAL ABBREVIATIONS AND SYMBOLS Yes Yes Yes Yes 15E-100 ELECTRICAL PLAN - SERVICE LEVEL No Yes Yes Yes 15E-101 ELECTRICAL PLAN - GROUND LEVEL No Yes Yes Yes 15E-102 ELECTRICAL PLAN - FIRST LEVEL No Yes Yes Yes 15E-103 ELECTRICAL PLAN - SECOND LEVEL No Yes Yes Yes 15E-401 ELECTRICAL ENLARGED PLANS No Yes Yes Yes 15E-402 ELECTRICAL ENLARGED PLANS No Yes Yes Yes 15E-501 ELECTRICAL DETAILS Yes Yes Yes Yes 15E-601 ELECTRICAL ONE-LINE DIAGRAMS Yes Yes Yes Yes 15E-701 ELECTRICAL SCHEDULES No Yes Yes Yes 15E-702 ELECTRICAL SCHEDULES No Yes Yes Yes 15E-703 ELECTRICAL SCHEDULES No Yes Yes Yes 15E-901 ELECTRICAL CUTSHEETS & BASIS OF DESIGN Yes Yes Yes Yes 15E-902 ELECTRICAL CUTSHEETS & BASIS OF DESIGN No No No Yes
TELECOMMUNICATION
15T-001 TELECOMMUNICATION ABBREVIATIONS AND SYMBOLS Yes Yes Yes Yes 15T-101 TELECOMMUNICATION PLAN - GROUND LEVEL Yes Yes Yes Yes 15T-102 TELECOMMUNICATION PLAN - FIRST LEVEL Yes Yes Yes Yes 15T-103 TELECOMMUNICATION PLAN - SECOND LEVEL Yes Yes Yes Yes 15T-401 TELECOMMUNICATION ENLARGED PLANS No Yes Yes Yes 15T-501 TELECOMMUNICATION DETAILS Yes Yes Yes Yes 15T-502 TELECOMMUNICATION ROOM OIT TEMPLATE DETAILS Yes Yes Yes Yes 15T-503 TELECOMMUNICATION ROOM OIT TEMPLATE DETAILS Yes Yes Yes Yes 15T-504 TELECOMMUNICATION ROOM OIT TEMPLATE DETAILS No Yes Yes Yes 15T-601 TELECOMMUNICATION RISER DIAGRAMS Yes Yes Yes Yes 15T-603 TELECOMMUNICATION FIBER RISER DIAGRAM - NEW No Yes Yes Yes 15T-604 TELECOMMUNICATION RACK ELEVATIONS Yes Yes Yes Yes 15T-700 TELECOMMUNICATION SCHEDULES No Yes Yes Yes 15T-701 TELECOMMUNICATION SCHEDULES No Yes Yes Yes 15T-901 TELECOMMUNICATION CUTSHEETS & BASIS OF DESIGN Yes Yes Yes Yes 15T-902 TELECOMMUNICATION CUTSHEETS & BASIS OF DESIGN No No Yes Yes 15T-903 TELECOMMUNICATION CUTSHEETS & BASIS OF DESIGN No No Yes Yes
REFERENCE
15R-900 PHOTO REFERENCE No Yes Yes Yes 15R-901 PHOTO REFERENCE No Yes Yes Yes 15R-902 PHOTO REFERENCE No Yes Yes Yes 15R-903 PHOTO REFERENCE No Yes Yes Yes Grand total: 68
# Revisions: Date:
1 ADDENDUM #1 03/30/2026
15G-011 REMOVED FROM
CONSTRUCTION DOCUMENTS
Ranjan Text Box
FEC
E1 ▬ 70.6'
TELECOM
ROOM
12A12A
CORRIDOR
23Z23Z
ELEV
ELEV
MECH
ROOM
20A20A
ELEV
LOBBY
CORRIDOR
22Z22Z
STAIR
HALL B
STAIR
HALL A
OFFICE
1212CLOSET
11K11K
CLOSET
11J11J
RECEPTION
HOPTEL
NURSING
STORAGE
AGENT
CASHIER
LOBBY
AGENT
CASHIER
2A2A
6 7
3 3A
101 MI
N
4'- 0"
C
LR
18059 SF
EXISTING BUSINESS -
CORRIDOR
TLT
EMS
CORRIDOR
PATIENT
FUNDS
2B2B
TLT
5A5A
TLT
5B5B
OFFICE
5C5C
OFFICE
5D5D
OFFICE
5E5E
OFFICE
5F5F
MENS
LOCKERS
5G5G
PIV ROOM
5H5H
OFFICE
5I5I
STAFF
LOUNGE
5J5J
OPERATIONS
5K5K
WEAPONS
ROOM
5L5L
EVIDENCE
ROOM
5M5M
WOMENS
LOCKERS
5H15H1
SOILED
LINEN
SOCIAL
HALL
OFFICE
OFFICE
PATIENT
CLOTHING
ENTRANCE
1616EMS
1717HOPTEL
LOBBY
TLT
7A7A INVESTIGATIONS
11A11A
FILE
ROOM
11B11B
GENERAL
STORAGE
11C11C
OFFICE
11D11D
CONFERENCE
ROOM
11E11E
OFFICE
11F11F
OFFICE
11G11G
OFFICE
11H11H
CORRIDOR
11I11I
TRANSFORMER
ROOM
15A15A
PATIENT
CLOTHING
15B15B
PATIENT
CLOTHING
15C15C
FOYER
16A16A
MULTI-PURPOSE
ROOM
16B16B
STORAGE
16C16C
TLT
16D16D
ELEC
CLOSET
16G16G
BATHROOM
18A18ABATHROOM
19A19A
CORRIDOR
21Z21Z
DRESSING
ROOM
15C15C
CLOSET
HOLDING
CELL
5D15D1
INFECTION CONTROL / DUST
CONTROL PARTITION / BARRIER
INFECTION CONTROL/DUST CONTROL
EGRESS DOOR NON-TRANSFERRING
MULTI-SHEETED ADHESIVE FLOOR PADS
PATH OF DEMOLITION/TRASH
REMOVAL TRAVEL
CONSTRUCTION LIMIT LINE
NOT IN CONTRACT AREA
DEMOLITION
LASER PARTICLE COUNT LOCATION
LIFE SAFETY SYMBOLS
PATH OF TRAVEL
(FOR CUMULATIVE DISTANCES
REFER TO SCHEDULE)
EXIT LIGHTING
TM
FIRE EXTINGUISHER CABINET (FEC)
FIRE EXTINGUISHERS (FE)
FIRE HOSE CABINETS (FHC)
HEAT DETECTOR
SMOKE DETECTOR
DIRECTION OF EGRESS
APPLICABLE BUILDING CODES
2024 NFPA 101 LIFE SAFETY CODE & 2025 NFPA 72 NATIONAL
FIRE ALARM AND SIGNALING CODE & 2025 NFPA 13 STANDARD
FOR INSTALLATION OF SPRINKLER SYSTEMS. EXCEPTION OF
NFPA 5000 AND NFPA 900
2024 INTERNATIONAL MECHANICAL CODE (IPC)
OCCUPATIONAL, SAFETY AND HEALTH ADMINISTRATION
(OSHA) STANDARDS.
VA SEISMIC DESIGN REQUIREMENTS, H-18-8
2026 NATIONAL ELECTRICAL CODE (NEC)
2024 INTERNATIONAL PLUMBING CODE (IPC)
ASME BOILER AND PRESSURE VESSEL CODE
ASME CODE FOR PRESSURE PIPING
ARCHITECTURAL BARRIERS ACT ACCESSIBILITY STANDARDS
(ABAAS) INCLUDING VA SUPPLEMENT, BARRIER FREE DESIGN
GUIDE (PG-18-13)
BUILDING CODE REQUIREMENTS FOR REINFORCED
CONCRETE, AMERICAN CONCRETE INSTITUTE AND
COMMENTARY (ACI 318)
MANUAL OF STEEL CONSTRUCTION, LOAD AND RESISTANCE
FACTOR DESIGN SPECIFICATIONS FOR STRUCTURAL STEEL
BUILDINGS, AMERICAN INSTITUTE OF STEEL CONSTRUCTION
(AISC)
ENERGY POLICY ACT OF 2005 (EPACT)
DOE INTERIM FINAL RULE: ENERGY CONSERVATION
STANDARDS FOR NEW FEDERAL, COMMERCIAL AND MULTI-
FAMILY HIGH-RISE RESIDENTIAL BUILDINGS AND NEW LOW-
RISE RESIDENTIAL BUILDINGS, 10 CFR PARTS 433, 434 AND 435
FEDERAL LEADERSHIP IN HIGH PERFORMANCE AND
SUSTAINABLE BUILDINGS: MEMORANDUM OF
UNDERSTANDING (MOU)
EXECUTIVE ORDER 13423: STRENGTHENING FEDERAL
ENVIRONMENTAL, ENERGY, AND TRANSPORTATION
MANAGEMENT
THE PROVISIONS FOR CONSTRUCTION AND SAFETY SIGNS.
STATED IN THE GENERAL REQUIREMENTS SECTION 01 00 00
AND 01 35 26 OF THE VA MASTER CONSTRUCTION
SPECIFICATION.
VENTILATION FOR ACCEPTABLE INDOOR AIR QUALITY –
ASHRAE STANDARD 62.1-2025; MEDICAL SPACES - ASHRAE
170-2025, NON-MEDICAL SPACES - ASHRAE 62.1-2025
SAFETY STANDARD FOR REFRIGERATION SYSTEMS – ASHRAE
STANDARD 15–2024
2024 INTERNATIONAL BUILDING CODE (IBC) WHERE DIRECTED
BY VA STANDARDS
UNLESS NOTED OTHERWISE, CURRENT EDITION OF APPLICABLE
STANDARD OR CODE SHALL BE USED
APPLICABLE BUILDING GUIDES
VA FIRE PROTECTION DESIGN GUIDE, 9TH EDITION (2023)
BUILDING CODE:
CONSTRUCTION TYPE:
TYPE II (222) PER NFPA 220, Chapter 4
TYPE OF BUILDING REHABILITATION: MODIFICATION, CHAPTER 43.
FIRE RESISTIVE CONSTRUCTION (NFPA 220 Table 4.1.1)
FIRE RESISTANCE RATING REQUIREMENTS FOR BUILDING
ELEMENTS:
STRUCTURAL FRAME 2 HOURS
NON-BEARING WALLS 0 HOURS
BEARING WALLS 2 HOURS
FLOORS 2 HOURS
ROOFS/ CEILINGS 1 HOURS
FIRE RESISTIVE CONSTRUCTION FOR OCCUPANCY (VA & NFPA 101)
FIRE RESISTANCE RATING REQUIREMENTS FOR SPACES BY
FUNCTION:
ELECTRICAL CLOSETS (DEPENDENT ON EQUIPMENT SIZE)
SMOKE COMPARTMENTS 1 HOUR
SOILED UTILITY ROOMS 1 HOUR
VERTICAL SHAFTS / STAIRS 2 HOURS (4 FLOORS)
(INCL. MECHANICAL SHAFTS) 1 HOUR (1 - 3 FLOORS)
MEDICAL GAS / HAZARDOUS 1 HOUR
STORAGE
CLASSIFICATION OF OCCUPANCY:
EXISTING: RESIDENTIAL BOARD AND CARE Occupancy per Chapter 33 and BUSINESS Occupancy per Chapter 39
BUILDING OCCUPANCY TYPE:
PRIMARY - EXISTING RESIDENTIAL BOARD AND CARE, LARGE
SECONDARY - EXISTING BUSINESS OCCUPANCY
6.1.14.1.3 Where incidental to another occupant, areas used as follows shall be permitted to be considered part of the predominant occupancy and shall be subject to the provisions of the Code that apply to the predominant occupancy:
(1) Mercantile, BUSINESS, industrial, or storage use
6.1.14.3 Mixed Occupancies
6.1.14.3.2 The building shall comply with the most restrictive requirements of the occupancies involved, unless separate safeguards are approved.
Table 6.1.14.4.1 (a) - separation of occupancies - 2 Hr between Board and Care and Business
6.2 Hazard of Contents.
6.2.1.3 For the purpose of this Code, where difference degrees of hazard of contents exist in different parts of a building or structure, the most hazardous shall govern the classification, unless hazardous areas are separated or protected as specified in Section 8.7 and the applicable sections of Chapters 11 through 43.
EXIT ACCESS TRAVEL DISTANCE:
33.3.2.5.2 COMMON PATH OF TRAVEL 75 FT
33.3.2.5.4 DEAD END 30 FT
33.3.2.6 TRAVEL DISTANCE FROM ANY 250 FT
POINT IN ROOM TO EXIT
OCCUPANT LOAD:
33.1.4 Occupant Load. The occupant load, in number of persons for whom means of egress and other provisions are required, shall be determined on the basis of the occupant load factors of Table 7.3.1.2 that are characteristic of the use of the space, or shall be determined as the maximum probable population of the space under consideration, whichever is greater.
MEANS OF EGRESS:
33.3.2 Capacity of Means of Egress.
33.3.2.3.3 The clear width of any corridor or passageway required for exit access shall not be less than 60 in. (1525 mm).
PROTECTION OF VERTICAL OPENINGS:
33.3.3.1 Protection of Vertical Openings.
33.3.3.1.1 Any vertical opening shall be enclosed or protected in accordance with Section 8.6, unless otherwise permitted.
PROTECTION FROM HAZARDS:
33.3.3.2 Protection from Hazards.
33.3.3.2.1 Hazardous Areas - Any hazardous areas shall be protected in accordance with Section 9.7.1.1(1)
33.3.3.2.2 The following areas shall be considered hazardous areas and shall be protected by fire barriers having a minimum 1-hour fire resistance rating in accordance with Section 8.7:
(1) Boilder and fuel-fired heater rooms
(2) Laundries
(3) Repair Shops
(4) Rooms or spaces used for storage of combustible supplies and equipment in quantities deemed hazardous by the AHJ.
33.3.3.5.7 Portable fire extinguishers shall be provided in all health care occupancies facilities in accordance with Section 9.9.
PARKING SUMMARY:
NO ADDITIONAL PARKING ADDED
SUBDIVISION OF BUILDING SPACES:
33.3.3.7 SUBDIVISION OF BUILDING SPACES
33.3.3.7.1 EVERY STORY SHALL BE DIVIDED INTO NOT LESS THAN
TWO SMOKE COMPARTMENTS.
33.3.3.7.3 THE TRAVEL DISTANCE FROM ANY POINT TO REACH A
DOOR IN THE REQUIRED SMOKE BARRIER SHALL NOT EXCEED
200 FT.
33.3.3.7.9 SMOKE BARRIERS IN ACCORDANCE WITH SECTION 8.5
SHALL HAVE A MINIMUM 1-HOUR FIRE RESISTANCE RATING.
WIDTH PROVIDEDP: XX"
R: XX" WIDTH REQUIRED
PARTITION RATING GRAPHICS:
4 HR FIRE BARRIER
3 HR FIRE BARRIER
2 HR FIRE & SMOKE BARRIER
2 HR FIRE BARRIER
2 HR FIRE BARRIER/SHAFT
1 HR FIRE & SMOKE BARRIER
1 HR FIRE BARRIER
1 HR FIRE BARRIER/SHAFT
SMOKE PARTITION (NON RATED)
NON RATED
PARTITION RATING GRAPHIC DESIGNATION: PRIORITY
1 HIGHEST
5 LOWEST
PARTITIONS REQUIRED TO BE SMOKE RESISTANT, FIRE
RESISTANT, OR BOTH FIRE AND SMOKE RESISTANT ARE SHOWN
GRAPHICALLY ON PLANS WITH HATCH PATTERNS.
X - XX'
# ICRA SYMBOLSKEYNOTES
TN
PN
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
TRIPLE C - The A/E Group 201 E. Jefferson Street, Suite 200 Syracuse, NY 13202
MAT PERKINS
(315) 484-5958
Au to de sk
D oc s:
//6
-2
2-
M on tro se V
AM
C
E H
R M
IU
/6
-2
2-
0.
M on tro se .E
H R
M .A
R C
H .B
.rv t 3/
/2
4:
:4
PM
15GI300
INTERIM LIFE SAFETY & INFECTION CONTROL
PLAN - GROUND LEVEL
620-22-700
06/27/2025 M. Perkins K. McDermott
ISSUED FOR
CONSTRUCTION
(EHRM) INFRASTRUCTURE
UPGRADES
2094 Albany Post Road, Montrose, NY 10548
1/8" = 1'-0"F1 INTERIM LIFE SAFETY & INFECTION CONTROL PLAN - GROUND LEVEL
PATH OF TRAVEL SCHEDULE - GROUND LEVEL
Mark From Room To Room Type of Travel Path Length
GROUND LEVEL
(P-o-T) Distance to Exits
E1 TELECOM ROOM 12A (P-o-T) Distance to Exits 70' - 7"
1 TEMPORARY CONSTRUCTION BARRIER DOOR WITH
CLOSER AND LATCH AND WALK OFF MATS
2 STAIRS ARE TO REMAIN OPERATIONAL AT ALL TIMES
FOR EMERGENCY EGRESS ONLY. THEY ARE NOT TO BE
USED FOR ANY CONSTRUCTION ACTIVITY.
3 ELEVATORS ARE TO REMAIN OPERATIONAL AT ALL
TIMES
3A ONE ELEVATOR TO BE DESIGNATED FOR CONTRACTOR
USE. CONTRACTOR TO PROTECT / REPAIR ALL
FINISHES AND FOLLOW PROPER ICRA REMOVAL
PROTOCOLS FOR ANY MATERIALS REMOVED FROM
SITE THROUGH ELEVATOR
4 DEBRIS REMOVAL PATH TO EXTERIOR - COORDINATE
REMOVAL OF MATERIALS ON THIS FLOOR WITH
ASBESTOS REPORT AND PLAN
5 CORRIDOR MAY BE REDUCED TO 3'-4" FOR MAX 48 HRS
OR ALTERNATE ENTRY PROVIDED FOR TIME REQUIRED
TO DEMO OPENING IN CORRIDOR WALL. COORDINATE
WITH COR
6 SOLID GRAY HATCH DENOTES LIMITED WORK AREA -
SEE MEP AND TELECOM DRAWINGS FOR CABLING
SCOPE, TYP.
7 MAINTAIN EXIT PATHWAYS FOR OCCUPANTS AT ALL
TIMES
8 COORDINATE TEMPORARY HEPA EXHAUST ROUTING
OUT OF BUILDING - MAINTAIN 25 FEET MINIMUM FROM
INTAKES, OPERABLE WINDOWS, AND ENTRANCES.
PROVIDE BLOCK-OFF PANELS IN EXISTING WINDOWS
FOR DISCHARGE, TYP.
9 TEMPORARY CONSTRUCTION BARRIER
10 ANTEROOM - SEE INFECTION CONTROL & INTERIM LIFE
SAFETY DETAILS
AREA OCCUPANCIES
LEVEL Name Area SF
Occupancy Requirements
OL
Occupancy
(IBC) Occupancy (NFPA) OLF Fixed Seats
GROUND LEVEL EXISTING BUSINESS 18059 SF B Business 150 SF 0 120
NOTE:
DEBRIS REMOVAL:
CONFIRM WITH COR FOR FINAL PLAN AND PROCEDURE OF
MATERIAL REMOVAL WITH ANTEROOMS, HEPA FILTRATION, ICRA
PROTOCOLS, AND ROUTE THRU OCCUPIED SPACES; PRIOR TO
REMOVAL OF ANY MATERIALS.
SECURE STAIRWELLS FROM UNAUTHORIZED ENTRY DURING
CONSTRUCTION.
LIFE SAFETY:
NEW WORK DOES NOT CHANGE EXISTING SMOKE
COMPARTMENTS, EXIT PATHWAYS, OR EXITS.
# Revisions: Date:
1 ADDENDUM #1 03/30/2026
E1 ▬ 66.6'
TELECOM
ROOM
142142
CLEAN
LINEN
143143
DATA
CLOSET
141141
ELEC.
CLOSET
139139
RECEPTION
136136
CORRIDOR
137Z137Z
LOBBY
101Z101Z
RECREATION
ROOM
103103
ELEVATOR
E1E1
ELEVATOR
E2E2
ENTRY
171171
BATHROOM
171B171B
STAIR
HALL 2
1S21S2
RESIDENT
VISITORS
ROOM
101Z2101Z2
FEC
MI
N.
4'- 0"
C
LR
18080 SF
EXISTING RESIDENTIAL -
4 6 7
3 3A
NOURISHMENT
104104
TLT
105105
TLT
106106
UTILITY
STORAGE
107107
LINEN
ROOM
108108
ONE
BEDROOM
109109
ONE
BEDROOM
110110
BATHROOM
111A111A
ONE
BEDROOM
112112
ENTRY
113113
ONE
BEDROOM
114114
ONE
BEDROOM
115115
ONE
BEDROOM
116116
SHOWER
ROOM
117117
COMM.
CTR.
117A117A
ELECTRIC
119119
ENTRY
120120
TLT
121A121A
OFFICE
122122
EXAM
ROOM
123123
OFFICE
124124
OFFICE
125125
OFFICE
126126 OFFICE
127127
OFFICE
128128
OFFICE
129129
CORRIDOR
132Z132Z
SPA
131131
STAIR
HALL 1
1S11S1
CLEAN
UTILITY
133A133A
134134
PYXIS
135135
DAYROOM
138138
MECH
ROOM
138A138A
SOILED
LINEN
144144
ONE
BEDROOM
146146
TWO
BEDROOM
149149
BATHROOM
149A149A
TWO
BEDROOM
151151
TWO
BEDROOM
152152
TWO
BEDROOM
153153
BEDROOM
154154
BATHROOM
154A154A
WELLNESS
CENTER
156156
ELEC. CL.
157157
TWO
BEDROOM
158158
BEDROOM
159159
BATHROOM
159A159A
BEDROOM
161161
LOUNGE
162162
BEDROOM
163163
BEDROOM
164164
TWO
BEDROOM
165165
COMM.
CTR.
166166
BATHROOM
165A165A
BEDROOM
168168
LAUNDRY
ROOM
169169
ONE
BEDROOM
171A171A
BATHROOM
163A163A
BEDROOM
162A162A
BATHROOM
162B162BBEDROOM
162C162C
BATHROOM
162A1162A1
CORRIDOR
167Z167Z
CORRIDOR
155Z155Z
BATHROOM
158A158A
BATHROOM
152A152A
BATHROOM
146A146A
CONFERENCE
ROOM
133B133B
FEMALE
LOCKERS
121B121B
STAFF
LOUNGE
121C121C
TLT
121D121D
MALE
LOCKERS
121E121E
ANTE
117B117B
ONE
BEDROOM
113A113A
BATHROOM
113B113B
ONE
BEDROOM
113C113C
BATHROOM
114A114A
BATHROOM
109A109A
BATHROOM
116A116A
CORRIDOR
118Z118Z
CORRIDOR
148Z148Z
INFECTION CONTROL / DUST
CONTROL PARTITION / BARRIER
INFECTION CONTROL/DUST CONTROL
EGRESS DOOR NON-TRANSFERRING
MULTI-SHEETED ADHESIVE FLOOR PADS
PATH OF DEMOLITION/TRASH
REMOVAL TRAVEL
CONSTRUCTION LIMIT LINE
NOT IN CONTRACT AREA
DEMOLITION
LASER PARTICLE COUNT LOCATION
LIFE SAFETY SYMBOLS
PATH OF TRAVEL
(FOR CUMULATIVE DISTANCES
REFER TO SCHEDULE)
EXIT LIGHTING
TM
FIRE EXTINGUISHER CABINET (FEC)
FIRE EXTINGUISHERS (FE)
FIRE HOSE CABINETS (FHC)
HEAT DETECTOR
SMOKE DETECTOR
DIRECTION OF EGRESS
APPLICABLE BUILDING CODES
2024 NFPA 101 LIFE SAFETY CODE & 2025 NFPA 72 NATIONAL
FIRE ALARM AND SIGNALING CODE & 2025 NFPA 13 STANDARD
FOR INSTALLATION OF SPRINKLER SYSTEMS. EXCEPTION OF
NFPA 5000 AND NFPA 900
2024 INTERNATIONAL MECHANICAL CODE (IPC)
OCCUPATIONAL, SAFETY AND HEALTH ADMINISTRATION
(OSHA) STANDARDS.
VA SEISMIC DESIGN REQUIREMENTS, H-18-8
2026 NATIONAL ELECTRICAL CODE (NEC)
2024 INTERNATIONAL PLUMBING CODE (IPC)
ASME BOILER AND PRESSURE VESSEL CODE
ASME CODE FOR PRESSURE PIPING
ARCHITECTURAL BARRIERS ACT ACCESSIBILITY STANDARDS
(ABAAS) INCLUDING VA SUPPLEMENT, BARRIER FREE DESIGN
GUIDE (PG-18-13)
BUILDING CODE REQUIREMENTS FOR REINFORCED
CONCRETE, AMERICAN CONCRETE INSTITUTE AND
COMMENTARY (ACI 318)
MANUAL OF STEEL CONSTRUCTION, LOAD AND RESISTANCE
FACTOR DESIGN SPECIFICATIONS FOR STRUCTURAL STEEL
BUILDINGS, AMERICAN INSTITUTE OF STEEL CONSTRUCTION
(AISC)
ENERGY POLICY ACT OF 2005 (EPACT)
DOE INTERIM FINAL RULE: ENERGY CONSERVATION
STANDARDS FOR NEW FEDERAL, COMMERCIAL AND MULTI-
FAMILY HIGH-RISE RESIDENTIAL BUILDINGS AND NEW LOW-
RISE RESIDENTIAL BUILDINGS, 10 CFR PARTS 433, 434 AND 435
FEDERAL LEADERSHIP IN HIGH PERFORMANCE AND
SUSTAINABLE BUILDINGS: MEMORANDUM OF
UNDERSTANDING (MOU)
EXECUTIVE ORDER 13423: STRENGTHENING FEDERAL
ENVIRONMENTAL, ENERGY, AND TRANSPORTATION
MANAGEMENT
THE PROVISIONS FOR CONSTRUCTION AND SAFETY SIGNS.
STATED IN THE GENERAL REQUIREMENTS SECTION 01 00 00
AND 01 35 26 OF THE VA MASTER CONSTRUCTION
SPECIFICATION.
VENTILATION FOR ACCEPTABLE INDOOR AIR QUALITY –
ASHRAE STANDARD 62.1-2025; MEDICAL SPACES - ASHRAE
170-2025, NON-MEDICAL SPACES - ASHRAE 62.1-2025
SAFETY STANDARD FOR REFRIGERATION SYSTEMS – ASHRAE
STANDARD 15–2024
2024 INTERNATIONAL BUILDING CODE (IBC) WHERE DIRECTED
BY VA STANDARDS
UNLESS NOTED OTHERWISE, CURRENT EDITION OF APPLICABLE
STANDARD OR CODE SHALL BE USED
APPLICABLE BUILDING GUIDES
VA FIRE PROTECTION DESIGN GUIDE, 9TH EDITION (2023)
BUILDING CODE:
CONSTRUCTION TYPE:
TYPE II (222) PER NFPA 220, Chapter 4
TYPE OF BUILDING REHABILITATION: MODIFICATION, CHAPTER 43.
FIRE RESISTIVE CONSTRUCTION (NFPA 220 Table 4.1.1)
FIRE RESISTANCE RATING REQUIREMENTS FOR BUILDING
ELEMENTS:
STRUCTURAL FRAME 2 HOURS
NON-BEARING WALLS 0 HOURS
BEARING WALLS 2 HOURS
FLOORS 2 HOURS
ROOFS/ CEILINGS 1 HOURS
FIRE RESISTIVE CONSTRUCTION FOR OCCUPANCY (VA & NFPA 101)
FIRE RESISTANCE RATING REQUIREMENTS FOR SPACES BY
FUNCTION:
ELECTRICAL CLOSETS (DEPENDENT ON EQUIPMENT SIZE)
SMOKE COMPARTMENTS 1 HOUR
SOILED UTILITY ROOMS 1 HOUR
VERTICAL SHAFTS / STAIRS 2 HOURS (4 FLOORS)
(INCL. MECHANICAL SHAFTS) 1 HOUR (1 - 3 FLOORS)
MEDICAL GAS / HAZARDOUS 1 HOUR
STORAGE
CLASSIFICATION OF OCCUPANCY:
EXISTING: RESIDENTIAL BOARD AND CARE Occupancy per Chapter 33 and BUSINESS Occupancy per Chapter 39
BUILDING OCCUPANCY TYPE:
PRIMARY - EXISTING RESIDENTIAL BOARD AND CARE, LARGE
SECONDARY - EXISTING BUSINESS OCCUPANCY
6.1.14.1.3 Where incidental to another occupant, areas used as follows shall be permitted to be considered part of the predominant occupancy and shall be subject to the provisions of the Code that apply to the predominant occupancy:
(1) Mercantile, BUSINESS, industrial, or storage use
6.1.14.3 Mixed Occupancies
6.1.14.3.2 The building shall comply with the most restrictive requirements of the occupancies involved, unless separate safeguards are approved.
Table 6.1.14.4.1 (a) - separation of occupancies - 2 Hr between Board and Care and Business
6.2 Hazard of Contents.
6.2.1.3 For the purpose of this Code, where difference degrees of hazard of contents exist in different parts of a building or structure, the most hazardous shall govern the classification, unless hazardous areas are separated or protected as specified in Section 8.7 and the applicable sections of Chapters 11 through 43.
EXIT ACCESS TRAVEL DISTANCE:
33.3.2.5.2 COMMON PATH OF TRAVEL 75 FT
33.3.2.5.4 DEAD END 30 FT
33.3.2.6 TRAVEL DISTANCE FROM ANY 250 FT
POINT IN ROOM TO EXIT
OCCUPANT LOAD:
33.1.4 Occupant Load. The occupant load, in number of persons for whom means of egress and other provisions are required, shall be determined on the basis of the occupant load factors of Table 7.3.1.2 that are characteristic of the use of the space, or shall be determined as the maximum probable population of the space under consideration, whichever is greater.
MEANS OF EGRESS:
33.3.2 Capacity of Means of Egress.
33.3.2.3.3 The clear width of any corridor or passageway required for exit access shall not be less than 60 in. (1525 mm).
PROTECTION OF VERTICAL OPENINGS:
33.3.3.1 Protection of Vertical Openings.
33.3.3.1.1 Any vertical opening shall be enclosed or protected in accordance with Section 8.6, unless otherwise permitted.
PROTECTION FROM HAZARDS:
33.3.3.2 Protection from Hazards.
33.3.3.2.1 Hazardous Areas - Any hazardous areas shall be protected in accordance with Section 9.7.1.1(1)
33.3.3.2.2 The following areas shall be considered hazardous areas and shall be protected by fire barriers having a minimum 1-hour fire resistance rating in accordance with Section 8.7:
(1) Boilder and fuel-fired heater rooms
(2) Laundries
(3) Repair Shops
(4) Rooms or spaces used for storage of combustible supplies and equipment in quantities deemed hazardous by the AHJ.
33.3.3.5.7 Portable fire extinguishers shall be provided in all health care occupancies facilities in accordance with Section 9.9.
PARKING SUMMARY:
NO ADDITIONAL PARKING ADDED
SUBDIVISION OF BUILDING SPACES:
33.3.3.7 SUBDIVISION OF BUILDING SPACES
33.3.3.7.1 EVERY STORY SHALL BE DIVIDED INTO NOT LESS THAN
TWO SMOKE COMPARTMENTS.
33.3.3.7.3 THE TRAVEL DISTANCE FROM ANY POINT TO REACH A
DOOR IN THE REQUIRED SMOKE BARRIER SHALL NOT EXCEED
200 FT.
33.3.3.7.9 SMOKE BARRIERS IN ACCORDANCE WITH SECTION 8.5
SHALL HAVE A MINIMUM 1-HOUR FIRE RESISTANCE RATING.
WIDTH PROVIDEDP: XX"
R: XX" WIDTH REQUIRED
PARTITION RATING GRAPHICS:
4 HR FIRE BARRIER
3 HR FIRE BARRIER
2 HR FIRE & SMOKE BARRIER
2 HR FIRE BARRIER
2 HR FIRE BARRIER/SHAFT
1 HR FIRE & SMOKE BARRIER
1 HR FIRE BARRIER
1 HR FIRE BARRIER/SHAFT
SMOKE PARTITION (NON RATED)
NON RATED
PARTITION RATING GRAPHIC DESIGNATION: PRIORITY
1 HIGHEST
5 LOWEST
PARTITIONS REQUIRED TO BE SMOKE RESISTANT, FIRE
RESISTANT, OR BOTH FIRE AND SMOKE RESISTANT ARE SHOWN
GRAPHICALLY ON PLANS WITH HATCH PATTERNS.
X - XX'
# ICRA SYMBOLSKEYNOTES
TN
PN
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
TRIPLE C - The A/E Group 201 E. Jefferson Street, Suite 200 Syracuse, NY 13202
MAT PERKINS
(315) 484-5958
Au to de sk
D oc s:
//6
-2
2-
M on tro se V
AM
C
E H
R M
IU
/6
-2
2-
0.
M on tro se .E
H R
M .A
R C
H .B
.rv t 3/
/2
4:
:5
PM
15GI301
INTERIM LIFE SAFETY & INFECTION CONTROL
PLAN - FIRST LEVEL
620-22-700
06/27/2025 M. Perkins K. McDermott
ISSUED FOR
CONSTRUCTION
(EHRM) INFRASTRUCTURE
UPGRADES
2094 Albany Post Road, Montrose, NY 10548
1/8" = 1'-0"F1 INTERIM LIFE SAFETY & INFECTION CONTROL PLAN - FIRST LEVEL
PATH OF TRAVEL SCHEDULE - FIRST LEVEL
Mark From Room To Room Type of Travel Path Length
LEVEL 1
(P-o-T) Distance to Exits
E1 TELECOM ROOM 142 STAIR HALL 2 1S2 (P-o-T) Distance to Exits 66' - 7"
1 TEMPORARY CONSTRUCTION BARRIER DOOR WITH
CLOSER AND LATCH AND WALK OFF MATS
2 STAIRS ARE TO REMAIN OPERATIONAL AT ALL TIMES
FOR EMERGENCY EGRESS ONLY. THEY ARE NOT TO
BE USED FOR ANY CONSTRUCTION ACTIVITY.
3 ELEVATORS ARE TO REMAIN OPERATIONAL AT ALL
TIMES
3A ONE ELEVATOR TO BE DESIGNATED FOR
CONTRACTOR USE. CONTRACTOR TO PROTECT /
REPAIR ALL FINISHES AND FOLLOW PROPER ICRA
REMOVAL PROTOCOLS FOR ANY MATERIALS
REMOVED FROM SITE THROUGH ELEVATOR
4 DEBRIS REMOVAL PATH TO EXTERIOR - COORDINATE
REMOVAL OF MATERIALS ON THIS FLOOR WITH
ASBESTOS REPORT AND PLAN
5 REMOVE EXISTING WINDOW, AC UNIT AND METAL
SUPPORT FRAME. PROVIDE TEMPORARY INFILL.
6 SOLID GRAY HATCH DENOTES LIMITED WORK AREA -
SEE MEP AND TELECOM DRAWINGS FOR CABLING
SCOPE, TYP.
7 MAINTAIN EXIT PATHWAYS FOR OCCUPANTS AT ALL
TIMES
8 COORDINATE TEMPORARY HEPA EXHAUST ROUTING
OUT OF BUILDING - MAINTAIN 25 FEET MINIMUM FROM
INTAKES, OPERABLE WINDOWS, AND ENTRANCES.
PROVIDE BLOCK-OFF PANELS IN EXISTING WINDOWS
FOR DISCHARGE, TYP.
9 TEMPORARY CONSTRUCTION BARRIER
10 ANTEROOM - SEE INFECTION CONTROL & INTERIM LIFE
SAFETY DETAILS
11 LOCK DOOR IN CLOSED POSITION. PROVIDE SIGNAGE
"DOOR INOPERABLE - USE OTHER DOOR".
COORDINATE WITH COR TO LIMIT TIME THAT CROSS
CORRIDOR DOORS ARE OUT OF USE.
12 FOR NEW WORK AT TELECOM ROOM 142 AND NEW
RECESSED FIRE EXTINGUISHER CABINET, PHASE NEW
WORK AND INSTALL ONLY 1 COMPLETE ICRA
ENCLOSURE AT A TIME. REMOVE ICRA ENCLOSURE
ONLY AFTER ALL NEW WORK IS COMPLETE AND SPACE
IS FULLY CLEANED. ENSURE 1 SIDE OF THE DOUBLE
DOORS IN THE CORRIDOR ARE OPERABLE AND CLEAR
AT ANY GIVEN TIME.
AREA OCCUPANCIES
LEVEL Name Area SF
Occupancy Requirements
OL
Occupancy
(IBC) Occupancy (NFPA) OLF Fixed Seats
FIRST LEVEL EXISTING RESIDENTIAL 18080 SF R4 Residential Board & Care
200 SF 0 90
NOTE:
DEBRIS REMOVAL:
CONFIRM WITH COR FOR FINAL PLAN AND PROCEDURE OF
MATERIAL REMOVAL WITH ANTEROOMS, HEPA FILTRATION, ICRA
PROTOCOLS, AND ROUTE THRU OCCUPIED SPACES; PRIOR TO
REMOVAL OF ANY MATERIALS.
SECURE STAIRWELLS FROM UNAUTHORIZED ENTRY DURING
CONSTRUCTION.
LIFE SAFETY:
NEW WORK DOES NOT CHANGE EXISTING SMOKE
COMPARTMENTS, EXIT PATHWAYS, OR EXITS.
1 ADDENDUM #1 03/27/202603/30/2026
INFECTION CONTROL / DUST
CONTROL PARTITION / BARRIER
INFECTION CONTROL/DUST CONTROL
EGRESS DOOR NON-TRANSFERRING
MULTI-SHEETED ADHESIVE FLOOR PADS
PATH OF DEMOLITION/TRASH
REMOVAL TRAVEL
CONSTRUCTION LIMIT LINE
NOT IN CONTRACT AREA
DEMOLITION
LASER PARTICLE COUNT LOCATION
LIFE SAFETY SYMBOLS
PATH OF TRAVEL
(FOR CUMULATIVE DISTANCES
REFER TO SCHEDULE)
EXIT LIGHTING
TM
FIRE EXTINGUISHER CABINET (FEC)
FIRE EXTINGUISHERS (FE)
FIRE HOSE CABINETS (FHC)
HEAT DETECTOR
SMOKE DETECTOR
DIRECTION OF EGRESS
APPLICABLE BUILDING CODES
2024 NFPA 101 LIFE SAFETY CODE & 2025 NFPA 72 NATIONAL
FIRE ALARM AND SIGNALING CODE & 2025 NFPA 13 STANDARD
FOR INSTALLATION OF SPRINKLER SYSTEMS. EXCEPTION OF
NFPA 5000 AND NFPA 900
2024 INTERNATIONAL MECHANICAL CODE (IPC)
OCCUPATIONAL, SAFETY AND HEALTH ADMINISTRATION
(OSHA) STANDARDS.
VA SEISMIC DESIGN REQUIREMENTS, H-18-8
2026 NATIONAL ELECTRICAL CODE (NEC)
2024 INTERNATIONAL PLUMBING CODE (IPC)
ASME BOILER AND PRESSURE VESSEL CODE
ASME CODE FOR PRESSURE PIPING
ARCHITECTURAL BARRIERS ACT ACCESSIBILITY STANDARDS
(ABAAS) INCLUDING VA SUPPLEMENT, BARRIER FREE DESIGN
GUIDE (PG-18-13)
BUILDING CODE REQUIREMENTS FOR REINFORCED
CONCRETE, AMERICAN CONCRETE INSTITUTE AND
COMMENTARY (ACI 318)
MANUAL OF STEEL CONSTRUCTION, LOAD AND RESISTANCE
FACTOR DESIGN SPECIFICATIONS FOR STRUCTURAL STEEL
BUILDINGS, AMERICAN INSTITUTE OF STEEL CONSTRUCTION
(AISC)
ENERGY POLICY ACT OF 2005 (EPACT)
DOE INTERIM FINAL RULE: ENERGY CONSERVATION
STANDARDS FOR NEW FEDERAL, COMMERCIAL AND MULTI-
FAMILY HIGH-RISE RESIDENTIAL BUILDINGS AND NEW LOW-
RISE RESIDENTIAL BUILDINGS, 10 CFR PARTS 433, 434 AND 435
FEDERAL LEADERSHIP IN HIGH PERFORMANCE AND
SUSTAINABLE BUILDINGS: MEMORANDUM OF
UNDERSTANDING (MOU)
EXECUTIVE ORDER 13423: STRENGTHENING FEDERAL
ENVIRONMENTAL, ENERGY, AND TRANSPORTATION
MANAGEMENT
THE PROVISIONS FOR CONSTRUCTION AND SAFETY SIGNS.
STATED IN THE GENERAL REQUIREMENTS SECTION 01 00 00
AND 01 35 26 OF THE VA MASTER CONSTRUCTION
SPECIFICATION.
VENTILATION FOR ACCEPTABLE INDOOR AIR QUALITY –
ASHRAE STANDARD 62.1-2025; MEDICAL SPACES - ASHRAE
170-2025, NON-MEDICAL SPACES - ASHRAE 62.1-2025
SAFETY STANDARD FOR REFRIGERATION SYSTEMS – ASHRAE
STANDARD 15–2024
2024 INTERNATIONAL BUILDING CODE (IBC) WHERE DIRECTED
BY VA STANDARDS
UNLESS NOTED OTHERWISE, CURRENT EDITION OF APPLICABLE
STANDARD OR CODE SHALL BE USED
APPLICABLE BUILDING GUIDES
VA FIRE PROTECTION DESIGN GUIDE, 9TH EDITION (2023)
BUILDING CODE:
CONSTRUCTION TYPE:
TYPE II (222) PER NFPA 220, Chapter 4
TYPE OF BUILDING REHABILITATION: MODIFICATION, CHAPTER 43.
FIRE RESISTIVE CONSTRUCTION (NFPA 220 Table 4.1.1)
FIRE RESISTANCE RATING REQUIREMENTS FOR BUILDING
ELEMENTS:
STRUCTURAL FRAME 2 HOURS
NON-BEARING WALLS 0 HOURS
BEARING WALLS 2 HOURS
FLOORS 2 HOURS
ROOFS/ CEILINGS 1 HOURS
FIRE RESISTIVE CONSTRUCTION FOR OCCUPANCY (VA & NFPA 101)
FIRE RESISTANCE RATING REQUIREMENTS FOR SPACES BY
FUNCTION:
ELECTRICAL CLOSETS (DEPENDENT ON EQUIPMENT SIZE)
SMOKE COMPARTMENTS 1 HOUR
SOILED UTILITY ROOMS 1 HOUR
VERTICAL SHAFTS / STAIRS 2 HOURS (4 FLOORS)
(INCL. MECHANICAL SHAFTS) 1 HOUR (1 - 3 FLOORS)
MEDICAL GAS / HAZARDOUS 1 HOUR
STORAGE
CLASSIFICATION OF OCCUPANCY:
EXISTING: RESIDENTIAL BOARD AND CARE Occupancy per Chapter 33 and BUSINESS Occupancy per Chapter 39
BUILDING OCCUPANCY TYPE:
PRIMARY - EXISTING RESIDENTIAL BOARD AND CARE, LARGE
SECONDARY - EXISTING BUSINESS OCCUPANCY
6.1.14.1.3 Where incidental to another occupant, areas used as follows shall be permitted to be considered part of the predominant occupancy and shall be subject to the provisions of the Code that apply to the predominant occupancy:
(1) Mercantile, BUSINESS, industrial, or storage use
6.1.14.3 Mixed Occupancies
6.1.14.3.2 The building shall comply with the most restrictive requirements of the occupancies involved, unless separate safeguards are approved.
Table 6.1.14.4.1 (a) - separation of occupancies - 2 Hr between Board and Care and Business
6.2 Hazard of Contents.
6.2.1.3 For the purpose of this Code, where difference degrees of hazard of contents exist in different parts of a building or structure, the most hazardous shall govern the classification, unless hazardous areas are separated or protected as specified in Section 8.7 and the applicable sections of Chapters 11 through 43.
EXIT ACCESS TRAVEL DISTANCE:
33.3.2.5.2 COMMON PATH OF TRAVEL 75 FT
33.3.2.5.4 DEAD END 30 FT
33.3.2.6 TRAVEL DISTANCE FROM ANY 250 FT
POINT IN ROOM TO EXIT
OCCUPANT LOAD:
33.1.4 Occupant Load. The occupant load, in number of persons for whom means of egress and other provisions are required, shall be determined on the basis of the occupant load factors of Table 7.3.1.2 that are characteristic of the use of the space, or shall be determined as the maximum probable population of the space under consideration, whichever is greater.
MEANS OF EGRESS:
33.3.2 Capacity of Means of Egress.
33.3.2.3.3 The clear width of any corridor or passageway required for exit access shall not be less than 60 in. (1525 mm).
PROTECTION OF VERTICAL OPENINGS:
33.3.3.1 Protection of Vertical Openings.
33.3.3.1.1 Any vertical opening shall be enclosed or protected in accordance with Section 8.6, unless otherwise permitted.
PROTECTION FROM HAZARDS:
33.3.3.2 Protection from Hazards.
33.3.3.2.1 Hazardous Areas - Any hazardous areas shall be protected in accordance with Section 9.7.1.1(1)
33.3.3.2.2 The following areas shall be considered hazardous areas and shall be protected by fire barriers having a minimum 1-hour fire resistance rating in accordance with Section 8.7:
(1) Boilder and fuel-fired heater rooms
(2) Laundries
(3) Repair Shops
(4) Rooms or spaces used for storage of combustible supplies and equipment in quantities deemed hazardous by the AHJ.
33.3.3.5.7 Portable fire extinguishers shall be provided in all health care occupancies facilities in accordance with Section 9.9.
PARKING SUMMARY:
NO ADDITIONAL PARKING ADDED
SUBDIVISION OF BUILDING SPACES:
33.3.3.7 SUBDIVISION OF BUILDING SPACES
33.3.3.7.1 EVERY STORY SHALL BE DIVIDED INTO NOT LESS THAN
TWO SMOKE COMPARTMENTS.
33.3.3.7.3 THE TRAVEL DISTANCE FROM ANY POINT TO REACH A
DOOR IN THE REQUIRED SMOKE BARRIER SHALL NOT EXCEED
200 FT.
33.3.3.7.9 SMOKE BARRIERS IN ACCORDANCE WITH SECTION 8.5
SHALL HAVE A MINIMUM 1-HOUR FIRE RESISTANCE RATING.
WIDTH PROVIDEDP: XX"
R: XX" WIDTH REQUIRED
PARTITION RATING GRAPHICS:
4 HR FIRE BARRIER
3 HR FIRE BARRIER
2 HR FIRE & SMOKE BARRIER
2 HR FIRE BARRIER
2 HR FIRE BARRIER/SHAFT
1 HR FIRE & SMOKE BARRIER
1 HR FIRE BARRIER
1 HR FIRE BARRIER/SHAFT
SMOKE PARTITION (NON RATED)
NON RATED
PARTITION RATING GRAPHIC DESIGNATION: PRIORITY
1 HIGHEST
5 LOWEST
PARTITIONS REQUIRED TO BE SMOKE RESISTANT, FIRE
RESISTANT, OR BOTH FIRE AND SMOKE RESISTANT ARE SHOWN
GRAPHICALLY ON PLANS WITH HATCH PATTERNS.
X - XX'
# ICRA SYMBOLSKEYNOTES
18079 SF
EXISTING RESIDENTIAL -
FEC
4 6 7
3 3A
E1 ▬ 67'
TELECOM
ROOM
242242
CLEAN
LINEN
243243
STORAGE
244244
DATA
CLOSET
241241
ELEC.
CLOSET
239239
CORRIDOR
237Z237Z
ELEVATOR
ELEVATOR
LOBBY
201Z201Z ONE
BEDROOM
271A271A
ENTRY
271271
BATHROOM
271B271B
NURSING
STATION
236236
BATHROOM
246A246A
ONE
BEDROOM
246246
STAIR
HALL 2
2S22S2
LAUNDRY
ROOM
269269
BILLIARD
ROOM
268268
EMS
CLOSET
266266
BATHROOM
265A265A
TWO
BEDROOM
249249
CORRIDOR
255Z255Z
TWO
BEDROOM
253253
BATHROOM
252A252A
TWO
BEDROOM
252252
TWO
BEDROOM
251251
BATHROOM
249A249A
TWO
BEDROOM
254254
TWO
BEDROOM
256256
BATHROOM
254A254A
ELEC. CL.
257257
BATHROOM
258A258A
TWO
BEDROOM
258258
TWO
BEDROOM
265265
BEDROOM
264264
BEDROOM
259259
BATHROOM
259A259A
BATHROOM
263A263A
BEDROOM
263263
TWO
BEDROOM
262C262C
TWO
BEDROOM
262A262A
BEDROOM
261261
BATHROOM
262B262B
ENTRY
262262
DAYROOM
238238
MECH
ROOM
238A238A
MEDICATION
ROOM
235235
GROUP
ROOM
233B233B
WAITING
ROOM
202202
GROUP
ROOM
203203
NOURISHMENT
204204
BATHROOM
209A209A
CONFERENCE
ROOM
209209
OFFICE
211211
BATHROOM
211A211A
OFFICE
212212
GROUP
ROOM
213A213A
BATHROOM
213B213B
GROUP
ROOM
213C213C
ENTRY
213213
OFFICE
214214
BATHROOM
214A214A
OFFICE
215215
GROUP
ROOM
216216
CORRIDOR
218Z218Z
BATHROOM
216A216A
LOCKER
ROOM
217217
FEMALE
LOCKERS
221B221B
STAFF
LOUNGE
221C221C
TLT
221E221E
OFFICE
222222
EXAM
ROOM
223223
OFFICE
224224
OFFICE
225225
OFFICE
226226 OFFICE
227227
OFFICE
228228
OFFICE
229229
EQUIPMENT
STORAGE
231231
CORRIDOR
232Z232Z
STAIR
HALL 1
2S12S1
OFFICE
233A233A
MALE
LOCKERS
221D221D
TLT
221A221A
EMS
207207
STORAGE
208208
TLT
206206
TLT
205205
OFFICE
201ZA201ZA
TN
PN
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
TRIPLE C - The A/E Group 201 E. Jefferson Street, Suite 200 Syracuse, NY 13202
MAT PERKINS
(315) 484-5958
Au to de sk
D oc s:
//6
-2
2-
M on tro se V
AM
C
E H
R M
IU
/6
-2
2-
0.
M on tro se .E
H R
M .A
R C
H .B
.rv t
-0 3-
6:
:5
15GI302
INTERIM LIFE SAFETY & INFECTION CONTROL
PLAN - SECOND LEVEL
620-22-700
06/27/2025 M. Perkins K. McDermott
ISSUED FOR
CONSTRUCTION
(EHRM) INFRASTRUCTURE
UPGRADES
2094 Albany Post Road, Montrose, NY 10548
1/8" = 1'-0"F1 INFECTION CONTROL & INTERIM LIFE SAFETY PLAN - SECOND LEVEL
PATH OF TRAVEL SCHEDULE - SECOND LEVEL
Mark From Room To Room Type of Travel Path Length
LEVEL 2
(P-o-T) Distance to Exits
E1 TELECOM ROOM 242 STAIR HALL 2 2S2 (P-o-T) Distance to Exits 67' - 1"
1 TEMPORARY CONSTRUCTION BARRIER DOOR WITH
CLOSER AND LATCH AND WALK OFF MATS
2 STAIRS ARE TO REMAIN OPERATIONAL AT ALL TIMES
FOR EMERGENCY EGRESS ONLY. THEY ARE NOT TO
BE USED FOR ANY CONSTRUCTION ACTIVITY.
3 ELEVATORS ARE TO REMAIN OPERATIONAL AT ALL
TIMES
3A ONE ELEVATOR TO BE DESIGNATED FOR
CONTRACTOR USE. CONTRACTOR TO PROTECT /
REPAIR ALL FINISHES AND FOLLOW PROPER ICRA
REMOVAL PROTOCOLS FOR ANY MATERIALS REMOVED
FROM SITE THROUGH ELEVATOR
4 DEBRIS REMOVAL PATH TO EXTERIOR - COORDINATE
REMOVAL OF MATERIALS ON THIS FLOOR WITH
ASBESTOS REPORT AND PLAN
5 REMOVE EXISTING WINDOW, AC UNIT AND METAL
SUPPORT FRAME. PROVIDE TEMPORARY INFILL.
6 SOLID GRAY HATCH DENOTES LIMITED WORK AREA -
SEE MEP AND TELECOM DRAWINGS FOR CABLING
SCOPE, TYP.
7 MAINTAIN EXIT PATHWAYS FOR OCCUPANTS AT ALL
TIMES
8 COORDINATE TEMPORARY HEPA EXHAUST ROUTING
OUT OF BUILDING - MAINTAIN 25 FEET MINIMUM FROM
INTAKES, OPERABLE WINDOWS, AND ENTRANCES.
PROVIDE BLOCK-OFF PANELS IN EXISTING WINDOWS
FOR DISCHARGE, TYP.
9 TEMPORARY CONSTRUCTION BARRIER
10 ANTEROOM - SEE INFECTION CONTROL & INTERIM LIFE
SAFETY DETAILS
11 LOCK DOOR IN CLOSED POSITION. PROVIDE SIGNAGE
"DOOR INOPERABLE - USE OTHER DOOR".
COORDINATE WITH COR TO LIMIT TIME THAT CROSS
CORRIDOR DOORS ARE OUT OF USE.
AREA OCCUPANCIES
LEVEL Name Area SF
Occupancy Requirements
OL
Occupancy
(IBC) Occupancy (NFPA) OLF Fixed Seats
SECOND LEVEL EXISTING RESIDENTIAL 18079 SF R4 Residential Board & Care
200 SF 0 90
NOTE:
DEBRIS REMOVAL:
CONFIRM WITH COR FOR FINAL PLAN AND PROCEDURE OF
MATERIAL REMOVAL WITH ANTEROOMS, HEPA FILTRATION, ICRA
PROTOCOLS, AND ROUTE THRU OCCUPIED SPACES; PRIOR TO
REMOVAL OF ANY MATERIALS.
SECURE STAIRWELLS FROM UNAUTHORIZED ENTRY DURING
CONSTRUCTION.
LIFE SAFETY:
NEW WORK DOES NOT CHANGE EXISTING SMOKE
COMPARTMENTS, EXIT PATHWAYS, OR EXITS.
INFECTION CONTROL / DUST
CONTROL PARTITION / BARRIER
INFECTION CONTROL/DUST CONTROL
EGRESS DOOR NON-TRANSFERRING
MULTI-SHEETED ADHESIVE FLOOR PADS
PATH OF DEMOLITION/TRASH
REMOVAL TRAVEL
CONSTRUCTION LIMIT LINE
NOT IN CONTRACT AREA
DEMOLITION
LASER PARTICLE COUNT LOCATION
TEMPORARY WALL TO EXTEND
AND BE SEALED TO DECK /
FLOOR ABOVE WHEN RATED
ENCLOSURE REQUIRED
FLOOR LINE
CEILING SYSTEM AS
SCHEDULED
EXISTING STRUCTURE
FI
NI
SH
ED
F
LO
OR
T O
UN
DE
RS
ID
E
OF
S
TR
UC
TU
RE
VE
RI
FY
F
LO
OR
T
O
FL
OO
R
HE
IG
HT
RENOVATED SPRINKLER
SYSTEM
WEEKLY CHANGED
OR MORE AS
NEEDED PRE-FILTER
FLEX DUCTMONTHLY CHANGED
HEPA FILTER
HEPA NEGATIVE AIR
UNIT
PROVIDE STICKY MATS (CHANGED END OF
EVERY SHIFT OR MORE IF NECESSARY TO
MAINTAIN CLEANLINESS).
PRESSURE INDICATOR SHALL BE AT
0.03 OR GREATER USING A DIGITAL
MANOMETER WITH DATA LOGGING. IF
NOT VERIFY ALL OPENING SUCH AS
DOOR ARE CLOSED AND/OR CHANGE
NEGATIVE AIR PRE-FILTER. DO NOT USE
A "BALL IN THE WALL" OR ANALOG
OTHER PRESSURE INDICATOR.
SUPPLY DUCTS EITHER
KEEP RUNNING OR
COVER WHEN NOT
RUNNING TO KEEP
DUST OUT.
A
V
OTAPE ALL SERVICES
TO PROTECT AGAINST
CONTAMINATION
E
FIRE EXTINGUISHER ON
PORTABLE FLOOR BRACKET
(SHALL REQUIRE MORE THAN
ONE.)
PUBLIC AREA
CONSTRUCTION AREA
ANTE ROOM
HARD BARRIER ALL THE WAY TO
DECK ABOVE
SIZE ANTE ROOM TO PROVIDE
SPACE FOR EQUIPMENT STAGING,
CART CLEANING, WORKERS' PPE
AND CLEANING, INCLUDING A HEPA
CLOTHING VACUUM
ROUTE DUCT TO EXTERIOR - SEE
PLANS FOR PROPOSED ROUTES -
CONFIRM ROUTE WITH ON-SITE
STAFF PRIOR TO INSTALLATION.
DISCHARGE AT A DISTANCE OF 25
FEET OR GREATER FROM
ENTRANCES, AIR INTAKES AND
OPERABLE WINDOWS. DO NOT
DIRECT EXHAUST INTO ANY
BUILDING SHARED EXHAUST
SYSTEM.
ANTE ROOM FAN
DOOR TO BE SELF-CLOSING AND
SELF-LATCHING - 45 MIN. FIRE
RATING PER NFPA
D7
15GI303
1/4" = 1'-0"F7 TYPICAL CONSTRUCTION LAYOUT- CLASS IV
1/2" = 1'-0"D7 CROSS SECTION A'-A'- CLASS IV
NTSF2 TYPICAL ICRA PRODUCTS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
TRIPLE C - The A/E Group 201 E. Jefferson Street, Suite 200 Syracuse, NY 13202
MAT PERKINS
(315) 484-5958
Au to de sk
D oc s:
//6
-2
2-
M on tro se V
AM
C
E H
R M
IU
/6
-2
2-
0.
M on tro se .E
H R
M .A
R C
H .B
.rv t 3/
/2
4:
:5
PM
15GI303
INTERIM LIFE SAFETY & INFECTION CONTROL
DETAILS
620-22-700
06/27/2025 M. Perkins K. McDermott
ISSUED FOR
CONSTRUCTION
(EHRM) INFRASTRUCTURE
UPGRADES
2094 Albany Post Road, Montrose, NY 10548
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.
K.
L.
M.
N.
O.
P.
Q.
R.
IMPLEMENT INFECTION CONTROL RISK ASSESSMENT (ICRA)
PROCEDURES AS PER THE MONTROSE VA ICRA PLAN AND AS
DIRECTED BY THE CONTRACTING OFFICER REPRESENTATIVE
(COR).
COORDINATE ALL DEMOLITION/ CONSTRUCTION DEBRIS PATH
OF TRAVEL AND INTERIM LIFE SAFETY MEASURES (ILSM) WITH
THE COR. ALL INTERIOR DOORS THAT LEAD TO THE
CONSTRUCTION SITE SHALL BE POSTED AS PER THE ISLM PLAN.
OBTAIN INFECTION CONTROL PERMIT PRIOR TO BEGINNING
WORK.
THE ONE HOUR FIRE RATED CONSTRUCTION BARRIERS SHALL
BE CONSTRUCTED PRIOR TO BEGINNING OTHER WORK.
CONSTRUCT ANTEROOM AT ENTRANCES TO CONSTRUCTION
AREAS AND REQUIRE ALL CONSTRUCTION PERSONNEL TO PASS
THROUGH THIS ROOM TO BE VACUUMED WITH HEPA VACUUM
CLEANER PRIOR TO LEAVING THE SITE.
FIRE PROTECTION SYSTEMS SHALL REMAIN FUNCTIONAL FOR
OCCUPIED AREAS ON THE FLOOR.
PROVIDE FIRE EXTINGUISHERS IN CONSTRUCTION AREAS;
REVIEW WITH COR AND VA SAFETY GROUP.
MAINTAIN EXIT LIGHTS IN CONSTRUCTION AREA.
MAINTAIN NEGATIVE AIR PRESSURE IN CONSTRUCTION AREA AT
ALL TIMES (24/7). WHETHER OCCUPIED OR NOT, THROUGHOUT
DURATION OF PROJECT USING HEPA EQUIPPED AIR FILTRATION
UNITS.
CONSTRUCTION AREA SHALL REMAIN ISOLATED FROM THE
OTHER AREAS OF THE MEDICAL CENTER; NO RETURN AIR OR
EXHAUST SHALL PASS INTO THE AREAS OUTSIDE THE
CONSTRUCTION AREA. ISOLATE HVAC SYSTEM WITHIN
CONSTRUCTION AREA TO PREVENT CONTAMINATION OF
EXISTING DUCT SYSTEM.
REDIRECT ALL MEDICAL CENTER PERSONNEL. PATIENTS AND
VISITORS SO THEY DO NOT EXIT THROUGH THE CONSTRUCTION
AREA. PROVIDE SIGNS ON DOORS INTO THE CONSTRUCTION
AREA THAT READS: "CONSTRUCTION AREA-DO NOT ENTER".
GENERAL CONTRACTOR SHALL MAINTAIN DAILY LOGS AND KEEP
A CURRENT HOT WORK PERMIT ON SITE.
TACKY MATS SHALL BE PLACED AT ALL DOORS INTO THE
CONSTRUCTION AREA AND SHALL BE MONITORED TO MAKE
SURE THEY REMAIN EFFECTIVE.
MAINTAIN A CLEAN AND ORDERLY CONSTRUCTION AREA. ALL
DEBRIS REMOVAL SHALL BE IN COVERED CARTS AND/OR
CONTAINERS.
SEAL ALL HOLES, PUNCTURES, AND PENETRATIONS FROM PIPES
AND CONDUITS APPROPRIATELY AND IMMEDIATELY TO MAINTAIN
DUST PROTECTION AND NEGATIVE AIR PRESSURE.
MAINTAIN STAFFING AND EQUIPMENT INCLUDING DUST MOPS,
WET MOPS, BROOMS, BUCKETS AND CLEAN WIPING RAGS FOR
CLEANING FINE DUST FROM FLOORS AND ADJACENT OCCUPIED
AREAS. ANY DUST TRACKED OUTSIDE OF CONSTRUCTION AREA
SHALL BE CLEANED IMMEDIATELY.
AFTER COMPLETION OF WORK: VACUUM CONSTRUCTION AREA
WITH HEPA FILTERED VACUUMS, WET MOP WITH DISINFECTANT,
REMOVE CONSTRUCTION BARRIERS (UPON APPROVAL). PATCH
OR REPAIR ANY DAMAGE FROM CONSTRUCTION BARRIER
REMOVAL AND REMOVE ISOLATION OF HVAC SYSTEM.
CONSTRUCTION BARRIERS SHALL NOT BE REMOVE UNTIL
PROJECT IS COMPLETED AND INSPECTED BY VA SAFETY
PERSONNEL, INFECTION CONTROL GROUP, AND COR.
ICRA NOTES:
ICRA SYMBOL LEGENDINFECTION CONTROL RISK
ASSESSMENT:
TABLE 1: CONSTRUCTION, RENOVATION AND/OR MAINTENANCE
ACTIVITY CATEGORY
IDENTIFY THE CATEGORY OF CONSTRUCTION PROJECT
CATEGORY A: INSPECTION AND/OR FACILITY UPKEEP
CATEGORY B: GENERAL MAINTENANCE AND REPAIR WORK
CATEGORY C: SMALL-SCALE CONSTRUCTION, RENOVATION, AND/OR
MAINTENANCE
CATEGORY D: LARGE-SCALE CONSTRUCTION, RENOVATION, OR
MAINTENANCE
THIS PROJECT: CATEGORY D
TABLE 2: AFFECTED AREA ASSESSMENT
TABLE 3: PATIENT RISK CATEGORY
IDENTIFY THE PATIENT RISK CATEGORY FOR EACH AREA LISTED IN
TABLE 2. OF THE PATIENT RISK CATEGORIES IDENTIFIED, THE ONE WITH
THE GREATEST RISK SHALL BE SELECTED AS THE OVERALL PATIENT
RISK CATEGORY FOR THE ACTIVITY.
LOW RISK: NON-PATIENT CARE AREAS
MEDIUM RISK: PATIENT CARE SUPPORT AREAS
HIGH RISK: PATIENT CARE AREAS
HIGHEST RISK: PROCEDURAL, INVASIVE, STERILE SUPPORT AND HIGLY
COMPROMISED PATIENT CARE AREAS
THIS PROJECT: HIGH RISK
CL
AS
S
II
Construction Activity Category
RISK GROUP
LOW RISK
MEDIUM RISK
HIGH RISK
HIGHEST RISK
I II II III
I II III IV
I II IV IV
II III IV IV
A
STEP 1:
IDENTIFY SPECIFIC SITE OF ACTIVITY, FOR EXAMPLE, PATIENT
ROOMS, MEDICATION ROOM, AND SO ON.
STEP 2:
IDENTIFY ISSUES RELATED TO: VENTILATION, PLUMBING, AND
ELECTRICAL IN TERMS OF THE OCCURRENCE OF PROBABLE
OUTAGES.
STEP 3:
IDENTIFY CONTAINMENT MEASURES, USING PRIOR
ASSESSMENT. WHAT TYPES OF BARRIERS (FOR EXAMPLE,
SOLIDS WALLS)? WILL HEPA FILTRATION BE REQUIRED?
STEP 4:
CONSIDER POTENTIAL RISK OF WATER DAMAGE. IS THERE A
RISK DUE TO COMPROMISING STRUCTURAL INTEGRITY (FOR
EXAMPLE, WALL, CEILING, ROOF)?
NOTE: RENOVATION/CONSTRUCTION AREA SHALL BE
ISOLATED FROM THE OCCUPIED AREAS DURING
CONSTRUCTION AND SHALL BE NEGATIVE WITH RESPECT TO
SURROUNDING AREAS.
STEP 5:
WORK HOURS: CAN OR WILL THE WORK BE DONE DURING
NON-PATIENT-CARE HOURS?
STEP 6:
DO PLANS ALLOW FOR ADEQUATE NUMBER OF
ISOLATION/NEGATIVE AIRFLOW ROOMS?
STEP 7:
DO THE PLANS ALLOW FOR THE REQUIRED NUMBER AND TYPE
OF HAND-WASHING SINKS?
STEP 8:
DOES THE INFECTION PREVENTION AND CONTROL STAFF AGREE
WITH THE MINIMUM NUMBER OF SINKS FOR THIS PROJECT?
(VERIFY AGAINST FACILITY GUIDELINES INSTITUTE (FGI) DESIGN
AND CONSTRUCTION GUIDELINES FOR TYPES AND AREA.)
STEP 9:
DOES THE INFECTION PREVENTION AND CONTROL STAFF
AGREE WITH THE PLANS RELATIVE TO CLEAN AND SOILED
UTILITY ROOMS?
STEP 10:
PLAN TO DISCUSS THE FOLLOWING CONTAINMENT ISSUES WITH
THE PROJECT TEAM, FOR EXAMPLE, TRAFFIC FLOW,
HOUSEKEEPING, DEBRIS REMOVAL (HOW AND WHEN).
Affected Area Assessment
AREA
Activity Area Area Above Area Below Adjacent Area
TR
SEE PLAN
SVC TYPE POC POC CONTACT INFO
SEE PLAN
SEE PLAN
Walter Hoffman (914) 208-6275
MATCH THE OVERALL PATIENT RISK CATEGORY WITH THE PLANNED
CONSTRUCTION PROJECT CATEGORY ON THE FOLLOWING MATRIX, TO
FIND THE CLASS OF PRECAUTIONS (I, II, III OR IV) OR LEVEL OF
INFECTION CONTROL ACTIVITIES REQUIRED.
THIS PROJECT: CATEGORY IV
TABLE 4: LEVEL OF INFECTION PREVENTION AND CONTROL
PRECAUTIONS
B C D
TABLE 5: REQUIRED INFECTION PREVENTION AND CONTROL MEASURES
BY LEVEL OF PRECAUTIONS
NOTE: LIST IS CUMULATIVE FROM CLASS I THROUGH CLASS IV)
TABLE 6: MINIMUM INFECTION PREVENTION AND CONTROL MEASURES
REQUIRED UPON COMPLETION OF THE ACTIVITY
1.
2.
1.
2.
A.
B.
C.
D.
E.
1.
2.
1.
2.
3.
1.
Construction areas must be inspected by an infection preventionist and engineering representative (and others as determined by the facility) for final activity/project close out and removal of infection prevention and control measures
Work Area Cleaning:
Clean work areas including all environmental surfaces, high horizontal surfaces and flooring materials Check all supply and return air registers for dust accumulation on upper surfaces as well as air diffuser surfaces
Removal of Critical Barriers:
Critical barriers must remain in place during all work involving drywall removal, creation of dust and activities beyond simple touch-up work. The barrier may NOT be removed until a work area cleaning has been performed. Additional cleaning may be needed after removal of barrier All (plastic or hard) barrier removal activities must be completed in a manner that prevents dust release. Use the following precautions when removing hard barriers:
Carefully remove screws and painter tape.
If dust will be generated during screw removal, use hand-held HEPA vacuum.
Drywall cutting is prohibited during removal process Clean all stud tracks with HEPA vacuum before removing outer hard barrier Use a plastic barrier to enclose area if dust could be generated
Negative Air Requirements:
The use of negative air must be designated to remove contaminants from the work area Negative air devices (fans, filters, monitoring and documentation equipment) must remain operational at all times and in place for a period after completion of dust creating activities to remove contaminants from the work area and before removal of critical barriers.
HVAC Systems:
Upon removal of critical barriers, remove isolation of HVAC system in areas where work is being performed Verify that HVAC systems are clean and operational.
Verify and document through a TAB the HVAC systems meets original airflow and air exchange design specifications
Water Systems:
Until the potable water system is activated and in use, flushing shall continue at least twice per week in accordance with VHA directive 1061.
CL
AS
S
III
IV
13.
14.
15.
16.
17.
18.
Ensure availability of equipment for cleaning hands Construct and complete critical barriers meeting NFPA 241 requirements.
Barriers must extend to the ceiling or if ceiling tile is removed, to deck above All (plastic or hard) barrier construction activities must be completed in a manner that prevents dust release. Plastic barriers must be effectively affixed to floor and ceiling (or floor/roof deck above) and secure from movement or damage.
Seal all penetrations in containment barriers, including floors and ceiling, using approved materials (UL schedule firestop if applicable for barrier type) Maintain .01 inches /water gauge negative pressurization of the entire workspace by use of HEPA exhaust air systems directed outdoors, or comply with the alternative method outlined in Appendix A of this document.
These control measures must be maintained continuously 24/7 for the duration of the project. HEPA filtered exhaust if discharged directly to the outdoors must be at a istance of 25 feet or greater from entrances, air intakes and operable windows. Exhausting discharged air into shared or recirculating HVAC systems, or other shared exhaust systems (e.g., bathroom exhaust) is prohibited Install a differential pressure sensing device (e.g., magnehelic, manometer, or digital monitoring) on exterior of work containment to continually monitor and document negative pressurization. The “ball in the wall” or similar apparatus are not acceptable
4.
5.
6.
7.
8.
9.
10.
11.
12.
Provide active means to control airborne dust from dispersing into occupied areas and/or water mist surface to control dust (e.g., Mobile Dust Containment Cart or some other system)Ensure worker clothing is clean and free of visible dust before leaving the work area Remove or isolate air diffusers (supply and return) to protect the HVAC system from dust and reduce air turbulence. Rebalance system to address diffuser isolation When the work involves or impacts potable water systems including stagnation due to reduced usage, the piping shall be flushed twice a week or isolated from the main system Seal doors to prevent dust migration Contain all trash and debris in the work area. Perform daily cleaning and disposal of trash (covered) from work area using an identified exit route.
Any equipment, tools, or materials removed from the work area must be in sealed containers and/or cleaned of dust and…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .