This document is an amendment to a federal solicitation for construction services. The solicitation is for the construction of a multi-story Bachelor Officers Quarters building with attached common area wing and detached utility building at Marine Corps Base Guam. The amendment revises the submission requirements and dates for price proposals, technical proposals, and subcontracting plans to March 10th and 11th, 2021. It also updates wage determinations, project descriptions, drawings, and notes. Relevant agencies include the Department of the Navy and Naval Facilities Engineering Command. Offerors must acknowledge any revisions in responses to remain eligible for award.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
972483
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
N62472-21-R-1334, Amendment 0002
See Next Page
1. CONTRACT ID CODE PAGE OF PAGES
1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 21-Jan-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6274221R1334
X 9B. DATED (SEE ITEM 11)
17-Dec-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
21-Jan-2021
CODE
HAND DELIVER
NAVFAC PACIFIC
CONSTRUCTION CONTRACTS BR (ACQ33)
4256 RADFORD DR, BLDG 62
HONOLULU HI 96818-3296
N62742 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6274221R1334
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
This amendment is issued to revise the following:
1. Document 00100, paragraph 1.1.a., b., and c., are revised to read as follows. Subparagraphs under paragraphs a., b., and c. remain unchanged.
a. PRICE PROPOSAL (PAPER): An original paper and one (1) paper copy of the price proposal shall be submitted on 10 March 2021, 2:00 p.m., H.S.T. in a sealed envelope and marked in the bottom right corner
"PRICE PROPOSAL SUBMITTED UNDER RFP N62742-21-R-1334 - DO NOT OPEN IN MAILROOM."
The PRICE PROPOSAL shall include the following:
b. TECHNICAL: (FACTORS 1, 2, AND 3)(PAPER): An original paper and three (3) paper copies of the technical proposals shall be submitted on 10 March 2021, 2:00 p.m., H.S.T. in a sealed envelope/package/box and marked in the bottom right corner "TECHNICAL PROPOSAL SUBMITTED UNDER RFP N62742-21-R- 1334 - DO NOT OPEN IN MAILROOM." Identify the original proposal as "Original" on the cover of the proposal. The TECHNICAL PROPOSAL shall be submitted in a three-ring binder with table of contents and tabbed. The TECHNICAL PROPOSAL shall include the following:
c. SUBCONTRACTING PLAN (PAPER): An original paper and one (1) paper copy of the subcontracting plan shall be submitted by 11 March 2021, 2:00 p.m., H.S.T. in a sealed envelope/package/box and marked in the bottom right corner "SUBCONTRACTING PLAN SUBMITTED UNDER RFP N62742-21-R-1334 - DO NOT OPEN IN MAILROOM." Identify the original proposal as "Original" on the cover of the proposal.
2. Document 00800, Special Contract Requirements is revised as follows:
a. Paragraph 1.5, Notice Concerning Labor Rates, first paragraph is revised to read as follows:
The Construction Wage Requirements statute (formerly known as the Davis-Bacon Act) will apply. The attached Guam General Decision Number: GU20200002, Modification No. 1, Publication Date 12/25/2020 will remain in effect for the duration of the project, unless modified.
b. Delete General Decision Number GU20200002, Publication Date 08/07/2020 and replace it with the attached General Decision Number GU20200002, Modification No. 1, Publication Date 12/25/2020.
3. Section 01 11 00, Summary of Work, paragraph 1.1.1, Project Description is revised as follows:
a. Line 1: delete “two” and replace it with “one”
b. Line 1: delete “s” after “structures”
c. Line 5: delete “Each”
d. Line 10: delete “Each” and replace it with “BOQ”
4. Section 01 14 00, Work Restrictions is revised as follows:
a. Delete Section 01 14 00 in its entirety and replace it with the attached Section 01 14 00.
b. Delete Title Page located after Section 01 14 00 in its entirety.
5. Section 01 57 19.03, Paragraph 3.8, bedrock Determinations for Low Likelihood Consideration is revised as follows:
a. Insert the following as the first two paragraphs:
“See Bedrock Determination Maps attached at the end of this Section. This information was obtained from
Project J-001B and indicates that most of the project site appears within the bedrock area.
The remainder of the project site was cleared of MEC/UXO/MPPEH to a depth of 4 feet during Project J-001B.
Bedrock may be encountered in excavations deeper than 4 feet in the remainder of the project. If bedrock is encountered, the following shall be followed. ”
b. Insert the attached two bedrock determination maps at the end of Section 01 57 19.03.
6. Delete DWGS CD101 through CU605 and replace them with the attached DWGS CD101 through CU605.
Drawings are reissued for clarity purposes only.
7. Revised Drawings: The following previously issued drawings are revised. These revised drawings supersede the previously issued drawings:
NO.
SHEET
NO.
NAVFAC
NO.
DESCRIPTION
1 GI011 17255211
INDEX REVISED TO MATCH TOPOGRAPHIC SURVEY
DRAWING NUMBERS
2 CG201 17255247 UPDATED FOR UTILITY BLDG MOVE
3 CG401 17255249 UPDATED FOR UTILITY BLDG MOVE
4 CS101 17255256 UPDATED NOTE, PAVILIONS AND BENCHES
5 CS102 17255257 UPDATE TRAFFIC SIGNAGE
6 CS401 17255259
UPDATED FOR UTILITY BLDG MOVE AND TRAFFIC
SIGNAGE
7 CS402 17255260 UPDATED TRAFFIC SIGNAGE
8 CS506 17255267 UPDATE TRAFFIC SIGNAGE
9 CS508 17255269 UPDATED TRANSFORMER FOUNDATION AND NOTE
10 CS601 17255271 UPDATED FOR UTILITY BLDG MOVE
11 CU101 17255272 UPDATED FOR UTILITY BLDG MOVE
12 CU201 17255274 UPDATED FOR UTILITY BLDG MOVE
13 CU202 17255275 UPDATED FOR UTILITY BLDG MOVE
14 CU203 17255276 UPDATED FOR UTILITY BLDG MOVE
15 CU601 17255282 UPDATED FOR UTILITY BLDG MOVE
16 CU602 17255283 UPDATED FOR UTILITY BLDG MOVE
17 CU603 17255284 UPDATED FOR UTILITY BLDG MOVE
18 CU604 17255285 UPDATED FOR UTILITY BLDG MOVE
19 CU605 17255286 UPDATED FOR UTILITY BLDG MOVE
20 LP101 17255288 ADDED BIKE RACK DETAIL CALLOUT.
21 LP102 17255289 DELETED TREE AND ROOT BARRIER.
22 LP103 17255290 ADJUSTED SHRUB AND SYNTHETIC TURF LAYOUT.
23 LP105 17255292 ADJUSTED SHRUB, GRASS, SYNTHETIC TURF LAYOUT.
24 LP503 17255295 ADDED BIKE RACK DETAIL.
25 LP601 17255296 REMOVED TREE.
26 S-116 17255309 REVISED UTILITY YARD DESIGN
27 S-205 17255332 REVISED UTILITY YARD DESIGN
28 A-102 17255352 MECH YARD/TRANSFORMER 'BA'/B.O. NOTES
29 A-116 17255358 MECHANICAL YARD SHIFT/GATE ADDED
30 A-118 17255360 TRANSFORMER 'BA'
31 A-124 17255364 ELEVATOR LOBBY CORNER GUARDS
32 A-141 17255371 MGR ROOM CEILING
33 A-203 17255378 MECHANICAL YARD SHIFT/GATE ADDED
34 A-401 17255391 SD CHANGED TO SH
35 A-402 17255392 SD CHANGED TO SH
36 A-403 17255393 SD CHANGED TO SH
37 A-601 17255418 GATES ADDED/REMARKS EDIT
38 A-602 17255419 MACHINE ROOM DOOR & REMARKS EDITS
39 A-605 17255420 REMARKS EDIT
40 IN401 17255455 LVT-5 NOTE REMOVED
41 M-102 17255485 REVISED UTILITY YARD DESIGN
42 M-114 17255489 REVISED UTILITY YARD DESIGN
43 M-404 17255499 REVISED UTILITY YARD DESIGN
44 M-501 17255500 REVISED UTILITY YARD DESIGN
45 P-114 17255521 REVISED UTILITY YARD DESIGN
46 P-501 17255537 REVISED RADON DETAILS
47 ES101 17255556
REVISED TRANSFORMER ENCLOSURE DIMENSIONS AND
ADDED WATER CONNECTION
48 E-104 17255562 REVISED LIGHT FIXTURE LAYOUT
49 E-122 17255568 RELOCATED RECEPTACLES
50 E-124 17255570 RELOCATED EQUIPMENT AND RECEPTACLES
51 E-143 17255576 REVISED LIGHTNING PROTECTION LAYOUT
52 E-402 17255578
REVISED EQUIPMENT DIMENSIONS AND ADDED
RECEPTACLES
53 E-502 17255583
REVISED WORKING CLEARANCE AND TRANSFORMER
DIMENSION
54 E-601 17255588 REVISED TRANSFORMER SIZE
55 E-602 17255589 REVISED WIRE CONDUIT, WIRE AND BREAKER SIZE
56 E-603 17255590 REVISED WIRE CONDUIT, WIRE AND BREAKER SIZE
57 E-608 17255595 REVISED KVA LOAD AND ADDED BRANCH CIRCUIT
58 E-609 17255596 REVISED KVA LOAD AND ADDED BRANCH CIRCUIT
59 E-610 17255597 REVISED KVA LOAD
8. All other terms and conditions remain unchanged.
End of Amendment
12/31/2020 beta.SAM.gov | Search https://beta.sam.gov/wage-determination/GU20200002/1?index=wd&is_active=true&date_filter_index=0&date_rad_selection=date&wdType=dbra&sta… 1/4
"General Decision Number: GU20200002 12/25/2020
State: Guam
Construction Type: Building Building Construction (Applies only to projects funded under the National Defense Authorization Act of 2010 - Guam Realignment Fund - Defense Policy Review Initiative) BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories)
County: Guam Statewide.
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.80 for calendar year 2020 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.80 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2020. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 08/07/2020 1 12/25/2020
SUGU2019-001 03/20/2020
Rates Fringes
CARPENTER, Includes Form Work....$ 15.78 0.00
CEMENT MASON/CONCRETE FINISHER...$ 14.34 0.00
ELECTRICIAN......................$ 18.11 0.00
HVAC TECHNICIAN (HVAC Unit Installation)....................$ 14.74 4.69
IRONWORKER, REINFORCING..........$ 15.45 0.00
LABORER: Common or General......$ 10.72 0.00
OPERATOR:
Backhoe/Excavator/Trackhoe.......$ 17.12 0.00 https://beta.sam.gov/wage-determination/GU20200002/1?index=wd&is_active=true&date_filter_index=0&date_rad_selection=date&wdType=dbra&sta… 2/4
PAINTER (Brush and Roller).......$ 14.95 0.00
PLUMBER..........................$ 17.20 0.49
SHEET METAL WORKER, Includes HVAC Duct Installation...........$ 16.06 0.00
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
https://beta.sam.gov/wage-determination/GU20200002/1?index=wd&is_active=true&date_filter_index=0&date_rad_selection=date&wdType=dbra&sta… 3/4
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal https://beta.sam.gov/wage-determination/GU20200002/1?index=wd&is_active=true&date_filter_index=0&date_rad_selection=date&wdType=dbra&sta… 4/4 process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION"
| Bedrock Det.pdf |
| N6274217C1324 SUB 0100q.59 PE St Bedr Det Area 70_20200828 |
| doc05378620200828110845 |
File details come from the government source that posted it. Updated .