About this file

This document is a Request for Information (RFI) Form for Solicitation N62473-24-R-5227, a Design-Build Military Construction (MILCON) project for a 10 MW Battery Energy Storage System (BESS) at Marine Corps Air Ground Combat Center (MCAGCC) in Twentynine Palms, California. The RFI contains 81 detailed technical and administrative clarification requests from potential contractors, covering topics such as BESS configuration, site conditions, electrical integration, safety requirements, design submissions, and project scope.

Key dates include an RFI submission deadline of April 29, 2025, and a proposal due date of June 3, 2025. The government intends to award the project in the fourth quarter of Fiscal Year 2025. The base bid is for 6.5 MW with two additional 2 MW options, totaling potentially 10 MW across two Cogen sites. The project involves integrating BESS with existing solar photovoltaic systems, creating grid stability, supporting black-start capabilities, and enhancing energy resilience. The contract is an unrestricted, full and open Firm-Fixed Price Design-Build contract administered by the Department of the Navy Naval Facilities Engineering Command.

View the file

Other files

File Type Posted
Solicitation Amendment N6247324R52270024 SF 30.pdf PDF
ENCL 2 - WD_CA20250026_AMEND 23.pdf PDF
ENCL 1 - P1238_RFP_AMEND 0023_Revised 21AUG25.pdf PDF
Amendment 0023_P1238.pdf PDF
Amendment 0022_P1238_14AUG25.pdf PDF
Amendment 0021_P1238_13AUG25.pdf PDF
ENCL 1 - P1238_RFP_AMEND 0020_Revised 06AUG25.pdf PDF
Amendment 0020_P1238_06AUG25.pdf PDF
ENCL 2 - WD_CA20250026_MOD 08_01AUG25.pdf PDF
Amendment 0019_P1238_31JUL25.pdf PDF
Phase Two Enc 1 - P1238_RFP_AMEND 0019_Revised31JUL25.pdf PDF
Amendment 0018_P1238_21JUL25.pdf PDF
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0018_Revised 21JUL25.pdf PDF
Amendment 0017_P1238_15JUL25.pdf PDF
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0017_Revised 15JUL25.pdf PDF
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0016_Revised 02JUL25.pdf PDF
Amendment 0016_P1238_02JUL25.pdf PDF
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0015_Revised 01JUL25.pdf PDF
Amendment 0015_P1238_01JUL25.pdf PDF
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0014_Revised 30JUN25.pdf PDF
Amendment 0014_P1238_30JUN25.pdf PDF
Section 00 45 00 Reps and Certs_24R5227_AMEND 0014.docx DOCX document
Amendment 0013_P1238_24JUN25.pdf PDF
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0013_Revised 24JUN25.pdf PDF
Wage Determination CA 20250026 dated 06062025.pdf PDF
Phase Two Enclosure 3 - P1238_Blank_OfferSchedule_Revised 04JUN25.xlsx XLSX spreadsheet
Amendment 0012_P1238_05JUN25.pdf PDF
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0012_Revised 05JUN25.pdf PDF
PLA Request for Information N6247324R5227.docx DOCX document
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0011_Revised 29MAY25.pdf PDF
Wage Determination_CA20250017_Modification 8_29MAY25.pdf PDF
Amendment 0011_P1238_29MAY25.pdf PDF
ENCL C_ESR_D30_P1238.pdf PDF
ENCL B_ESR_D20_P1238.pdf PDF
ENCL H_EXHIBIT F_P1238_Small Business Participation Commitment.docx DOCX document
ENCL E_2a- P-495 Geotech Report 1999-01-19.pdf PDF
ENCL F_Geotech Report.pdf PDF
ENCL A_ESR_A10_P1238.pdf PDF
ENCL J_UFGS 01 91 00.15-DBContract_P1238.pdf PDF
ENCL G_EXHIBIT E_P1238_Historical Small Business Utilization.docx DOCX document
ENCL K_P1238_N6247324R5227_RFI_Responses_Amendment 0010.xlsx XLSX spreadsheet
Amendment 0010_P1238_RFI Responses_19MAY25.pdf PDF
ENCL D_Utilities_P1238.pdf PDF
P1238_N6247322R5227_RFI_Submission - Non-Amendment Responses_08MAY25.xlsx XLSX spreadsheet
Phase Two Enclosure 3_P1238_Blank_OfferSchedule_Revised.xlsx XLSX spreadsheet
N6247324R5227_Amendment 0009_SF30.pdf PDF
EXHIBIT E_P1238_Historical Small Business Utilization.pdf PDF
Revised Standard Form (SF) 1442_P1238_N6247324R5227.pdf PDF
Phase Two Enclosure 1_P1238_RFP Part 1_Revised.pdf PDF
N6247324R5227_Amendment 0008.pdf PDF
Show 40 more

Latest 50 of 76 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI (pre-award) Form_For KTR

SOLICITATION: N62473-24-R-5227

CONTRACT / PROJECT TITLE: DESIGN-BUILD MILCON PROJECT P-1238 CONSTRUCTION OF GRID STABILITY & RESILIENCY 10 MW BATTERY ENERGY STORAGE, VARIOUS BUILDINGS AT MARINE CORPS AIR GROUND COMBAT CENTER (MCAGCC), TWENTYNINE PALMS, CA

DOCUMENT DATE: 11 APRIL 2025

TO BE FILLED OUT BY THE BIDDING KTRTO BE FILLED OUT BY THE GOV'T
RFI #RFP Part #Chapter or SectionSub-Section #CLARIFICATION REQUESTCost Impact? Y/NSchedule Impact? Y/NRFI reason from KTR's PerspectiveComment [fill out if "Other" was chosen, specify reason(s)]RFI Topic most closely relevant to:Government ResponseDATE RECEIVEDDATE TO KTRAmendment Number
1Part 1Chapter-11. Description of workPart 1, Chapter 1, under 1. Description of work indicates the Base Bid is for 4 MW/16 MWh at CoGen Site 1, 2 MW/8 MWh at CoGen Site 2 with Option 1 for an additional 2 MW/8 MWh at Site 1 and Option 2 for an additional 2 MW/8 MWh at CoGen Site 2. That's a total of 6 MW/24 MWh at CoGen Site 1 and 4 MW/16 MWh at CoGen Site 2 (project total is 10 MW/40 MWh).

The Offer Schedule provided under Amendment 0006 indicates the Base Bid is for 6 MW/24 MWh at CoGen Site 1, 4 MW/16 MWh at CoGen Site 2 with Option 1 for an additional 2 MW/8 MWh at Site 1 and Option 2 for an additional 2 MW/8 MWh at Cogen Site 1 again. That's a total of 10 MW/40 MWh at CoGen Site 1 and 2 MW/8 MWh at CoGen Site 2 (project total is 12 MW/48 MWh).

Please clarify total MW/MWh for the Base Bid and each option. Y Y Conflicting Information "Other" - Bid Form Contracting The Offer Schedule should be matched with Part 1, Chapter 1 Desciption of work, as below: "the Base Bid is for 4 MW/16 MWh at CoGen Site 1, 2 MW/8 MWh at CoGen Site 2 with Option 1 for an additional 2 MW/8 MWh at Site 1 and Option 2 for an additional 2 MW/8 MWh at CoGen Site 2. That's a total of 6 MW/24 MWh at CoGen Site 1 and 4 MW/16 MWh at CoGen Site 2 (project total is 10 MW/40 MWh"

Revised Offer Schedule, Phase Two Enclosure 3_P1238_Blank OfferSchedule_Revised is included in Amendment 00094/11/254/17/250009
2Part 1Please provide the sign-in sheet from the site visit held on April 8, 2025.NNOther; Please specify in the next columnContracting
3Part 1Chapter-3Part 1, Section 3: Inquiries states that “all RFIs are due to the Government POC by April 17, 2025. The government does not intend to respond to inquiries submitted less than 10 days before the Phase Two proposal due date of May 15, 2025.” Please confirm it is acceptable for the RFI due date to be May 5, 2025, in lieu of April 17, 2025.NNOther; Please specify in the next columnContractingThe RFI deadline for submission has been amdended to Tuesday, April 29, 2025. The Proposal due date has been amended to Tuesday, June 3, 2025, Please refer to Amendment 0009.

DELETE: The government does not intend to respond to inquiries submitted less than 10 days before the Phase Two proposal due date of May 15, 2025.

ADD: The government does not intend to respond to inquires submitted after the RFI deadline of Tuesday, April 29, 2025.4/11/254/17/250009
4Part 1Amendment 0006 (Page 14 of 70), under Factor 6: Small Business Utilization and Participation states that “each project submitted under Factor 2, Experience, shall be included on Exhibit E.” Please confirm only projects submitted on behalf of the Contractor listed under Factor 2 shall be included on Exhibit E.NNIntent needs clarificationContractingEvery project submitted under Factor 2 must be included on Exhibit "E".
Exhibit E is included as an enlcosure to Amendment 0009.4/11/254/17/250009
5Part 1Standard Form 30 for Amendment 0006, states, “A revised SF1442 is attached.” A revised SF1442 was not included in the documents provided with Amendment 0006. Please provide the revised SF1442.NNAttachments are referenced but missing/not providedContractingA revised Standard Form 1442 will be included in this Amendment.4/11/254/17/250009
6Part 1Amendment 0006 (Page 16 of 70), under Factor 7: Price states to submit “Standard Form (SF) 1442 (Solicitation, Offer and Award)” and the Bid Bond. Please confirm the file attached with amendment 0006 titled “Phase Two Enclosure 3 – P1238_Blank_OfferSchedule” shall also be submitted under Factor 7: Price.NNOther; Please specify in the next columnContractingDELETE: A revised SF1442 will be included as Enclosure with this amendment.

• Standard Form (SF) 1442 (Solicitation, Offer and Award)

• Bid Bond (in the amount of 20% of the proposal price or $3,000,000, whichever is less)

ADD: A revised SF1442 will be included as Enclosure with this amendment.

• Standard Form (SF) 1442 (Solicitation, Offer and Award)

• Phase Two Enclosure 3_P1238_Blank OfferSchedule_Revised

• Bid Bond (in the amount of 20% of the proposal price or $3,000,000, whichever is less)4/11/254/17/250009
7Part 1Will the government please extend the RFI submission due date from April 17 to April 24?NNOther; Please specify in the next columnContractingThe RFI submission deadline has been amended to Tuesday, April 29, 2025, Please refer to Amendment 0009.4/11/254/17/250009
8Part 3D30Page 274 - 276Stated BESS shall be housed within shelter. Shelter to have its own cooling and exhaust systems. Is the intent that the BESS batteries be mounted within an included building called shelter? BESS batteries, per manufactures, are not to be installed within a structure, building, or shelter due to fire containment emergency procedures where a lithium battery fire is not treated with water but allowed to burn out under supervision and monitoring of designated emergency personnel. Can you confirm this conflict and provide direction?YYIntent needs clarificationElectrical Engineering4/14/25
9Part 3D30Page 274 - 276The system description states to provide ductless DX high wall units, but HVAC description calls out insulated supply and returns. Is this for an enclosed shelter over the BESS batteries? There seems to be a conflict with BESS manufacturers having the batteries in an enclosed building/shelter? Can you confirm this conflict and provide direction?yyIntent needs clarificationMechanical Engineering4/14/25
10Part 3D30Page 274 - 276The climate conditions described in D30 section for heat/cooling and ventilation describe a shelter over the BESS battery. Are these climate and ventilation conditions for the BESS battery storage itself or for a shelter over the BESS. There seems to be a conflict with BESS manufacturers allowing a shelter over the batteries. Can you confirm this conflict and provide direction?yyIntent needs clarificationMechanical Engineering4/14/25
11Part 3D30Page 274 - 276BESS storage systems must be independently climate controlled. The BESS systems have climate controls that are monitored system wide for control of heat and cooling along with ventilation. Does the BESS system have a requirement where they are to be tied into the base DDC controls and monitored via BACnet digital controls protocol?yyIntent needs clarificationMechanical Engineering4/14/25
12Part 3D30Page 274 - 276Ventilation requirements indicate to provide 12 ACH emergency function and 6ACH normal exhaust rate, ductless high-wall units cannot provide this amount of outside air. Can you confirm if the use of either ducted DX splits or DX packaged units is acceptable for providing conditioned outside air requirement for BESS storage units? The BESS manufactures have their own designed heating and cooling systems ways and means for meeting requirements.yyIntent needs clarificationMechanical Engineering4/14/25
13Part 3D30Page 274 - 276In general, at the site walk, we had the opinion that work personnel on base prefer to work indoors with BESS battery storage units within and enclosed or open type shelter due to the climate conditions of Twentynine Palms base. The RFP seems to be written around providing a shelter over the BESS battery storage. However, there seems to be conflict for fire safety / emergency needs for when lithium batteries could catch fire while being housed inside a shelter. Several BESS fires across the world in last several years has shown that maybe best practices is to install BESS in outside open areas without shelters. In case of fires, the recommended practice is let the lithium battery unit fire 'burn out'. Water suppression is not recommended for extinguishing that fire, but rather keeping the other areas cool. If this is a safety and fire concern for future use of BESS at Twentynine Palms microgrid, can you clarify and provide directive where sheltered enclosure conflict with BESS in this design?yyIntent needs clarificationContracting4/14/25
14Part 3D30Page 274 - 276There is a conflict with wall mounted DX units and manufactured BESS devices utilizing roof mounted-designed upblast fans? Can you clarify that the BESS manufacture provision for ventilation whether roof or wall mounted will meet the overall design criteria?yyIntent needs clarificationContracting4/14/25
15Part 3D30Page 274 - 276In general, at the site walk, we had the opinion that work personnel on base prefer to work indoors with BESS battery storage units within and enclosed or open type shelter due to the climate conditions of Twentynine Palms base. In lieu of shelter over the BESS, would the base operation staff require a Conex style permanent office trailer at each BESS location for work conditions at the base? If so, what are or what would be those requirements include? We have seen instances where a worker office location be beneficial for remote locations.yyIntent needs clarificationContracting4/14/25
16Part 3Chapter-1page 257To provide pricing and a basis of design for this proposal, contractor needs and requests information on location and existing conditions at the Cogen plants where BESS will enter and tie into systems for fiber optic/comm. Can you please provide floor plans, as-buits, or information to show locations of the systems tie-in points, layouts, equipment rack areas, etc. in amendment asap?yyIntent needs clarificationContracting4/14/25
17Part 3Chapter-1page 257There is a requirement for BESS safety and explosive distance setbacks from occupied and special interest areas per UFC of 100'. Can you confirm that if this BESS design can meet the 100' setback, then the requirement for walls of CMU or concrete will not be required? And that there is not a requirement for walls of CUM or concrete whether the BESS meets or does or does not meet the 100' setbackyyIntent needs clarificationContracting4/14/25
18Part 3Chapter-1page 258The 8MW PV is indicated to be controlled by the inverter. Can you clarify it project requirement is to replace this inverter is not capable of controlling the 8MW of PV? Can you clarify that this project requirement is not to replace any PV inverters in the existing systems?yyIntent needs clarificationElectrical Engineering4/14/25
19Part 3Chapter-1page 258There is a stated requirement to coordinate operational concerns for existing ESPC / PPA existing contracts with this design? Can you please provide information on all ESPC / PPA contracts this contract needs to coordinate along with details, drawings, specs, existing conditions, and terms in next amendment? This is needed for system design and pricing.yyIntent needs clarificationContracting4/14/25
20Part 3Chapter-1page 259Which subnet is the BESS control network to be integrated into?yyIntent needs clarificationElectrical Engineering4/14/25
21Part 3Chapter-1page 259Operational Considerations - Use Cases indicate that BESS will ramp output when cloud cover causes a drop in PV production. Is there is a requirement to install a weather station including sensors, or will the BESS output be updated to respond to power fluctuations by inverter.yyIntent needs clarificationElectrical Engineering4/14/25
22Part 3Chapter-1page 261Can the government provide branch-level meter data for each breaker at switchgear and information on critical and non-critical loads?yyIntent needs clarificationElectrical Engineering4/14/25
23Part 3Chapter-1page 262Can the government provide the critical load meter data to ensure BESS can back start the critical loads?yyIntent needs clarificationElectrical Engineering4/14/25
24Part 3Chapter-1page 263The base bid item under section 1.3 indicates adding meters as a part of the scope. Will the government provide locations where meters are expected to be added and provide the meter specifications?yyIntent needs clarificationElectrical Engineering4/14/25
25Part 3Chapter-1Pg 267Existing Site Conditions - Natural Constraints lists the BESS at 3.5 MW but page 263 indicates 4 MW should be provided. Can you confirm and clarify he MW of the BESS and if the project is allowed to fall short of the required capacity by a minimum of 2.5% if the standard system sizes of BESS do not align with the numerical capacity of the BESS.yyIntent needs clarificationElectrical Engineering4/14/25
26Part 3Chapter-1Pg 276Vent requirement 2b indicates a new Volatile Organic Compound monitoring and alarm system is required. Is the requirement for the BESS yard and or within the BESS unit just itself? What is the guidance and base requirement or concern?yyIntent needs clarificationMechanical Engineering4/14/25
27Part 3D50page 283D50 states BESS output rating capacity of 10MW/40MWH. Noting that not all BESS manufactures can evenly match the capacities exactly since some are often at odd numbers. If the BESS manufacturer ratings say come close to 10MW/40MWH as example of 9.8MW/39.2MHW can this be considered meeting the requirement? Or should the BESS add more to ensure meeting or exceeding 10WM/40MWH? Note that adding extra additional adds more pricing to the governments budget.yyIntent needs clarificationElectrical Engineering4/14/25
28Part 3D50page 284Can you confirm the expectation is to provide a switch with dedicated ways to feed each BESS system? Is it acceptable to have multiple transformers fed from a single switch way?yyIntent needs clarificationElectrical Engineering4/14/25
29Part 3D50page 286Requirement noted to provide ESS for project per UFC 4-021-02. Who is the base ESS system provider and contact?yyIntent needs clarificationElectrical Engineering4/14/25
30Part 3D50page 286Can you confirm this contract is only required to install conduit, pull wire, and end unit enclosures for the ESS system provider only and that the government will contract by 3rd party the actual installation of ESS systems? That is pull the wire, provide the devices, terminate, and complete system startup, testing, and confirmed operation?yyIntent needs clarificationElectrical Engineering4/14/25
31Part 3D50page 286What is the base requirement / needs for CCTV ESS security with BESS storage systems? How many CCTV camera / poles required? Will this be monitored at the Cogen plant operations room? Where or what kinds of existing systems and equipment / locations provided?yyIntent needs clarificationElectrical Engineering4/14/25
32Part 3D50page 286Noted that this contract is to provide 2 yrs warranty and operations - maintenance support after start-up/commissioning/project completion. What are the base requirements for O&M period of 2 years? What are the expectations to meet and provide?yyIntent needs clarificationContracting4/14/25
33Part 3D50page 285What is the requirement for site lighting at the BESS storage area? LED on light pole? Do these lights need to on all night and programed with sunlight control?yyIntent needs clarificationElectrical Engineering4/14/25
34Part 3D50page 287Is a 10' high chain linked security fence with IDS intrusion detection devices required for the BESS storage areas? Is there a security requirement for motion detection for intrusion detection required?yyIntent needs clarificationCivil Engineering4/14/25
35Part 3D50page 287If security fences are required around the BESS storage, are the fences to be grounded/bonded?yyIntent needs clarificationCivil Engineering4/14/25
36Part 3D50page 287Are there requirements for ACS Access control systems at the BESS storage area gate/fence entrances that require access control swipe readers? If so who is the base ACS controls integrator with phone and contact? Is this contract only responsible for conduit, pull wire, end unit enclosures for the devices where the government hires 3rd party contractor to install?yyIntent needs clarificationElectrical Engineering4/14/25
37Part 3D50page 286What are the specifications and requirements for the Advanced Metering and infrastructure?yyIntent needs clarificationElectrical Engineering4/14/25
38Part 3D50page 288Under BESS safety, what are the types of alarm conditions that shall be annunciated? What are the needs and concerns to monitor for safety for the base?yyIntent needs clarificationElectrical Engineering4/14/25
39Part 3G40page 304States contractor shall guarantee annual BESS savings as established in the design period of O&M performance. Is this the 2 year O&M and warranty period? What are the governments savings goals in relation to existing ESPC contracts that have to be interfaced with this contract?yyIntent needs clarificationContracting4/14/25
40Part 3G40page 296Addressing fire safety measures for BESS storage devices and concerns for run away fire due to lithium batteries, what are the base concerns in reguards to this safety concerns? It has been seen and noted that BESS manufacturers best practice is to allow lithium battery units 'burn out' without water suppression. Has the base considered these concerns? Is water suppression at the site going to be required? If yes, where will the water come from and fire hydrant requirements? Can you provide drawings that show the base water line for existing service if water suppression is required by the base?yyIntent needs clarificationFire Protection4/14/25
41Part 3D50page 289What are the base requirements in case for run away detection and mitigation that contractor and BESS manufacturer is to provide in this design?yyIntent needs clarificationFire Protection4/14/25
42Part 3D50page 289Under BESS item 4, can a single visible MV disconnect be acceptable?yyIntent needs clarificationElectrical Engineering4/14/25
43Part 3D50page 299This section indicates all electrical distribution equipment shall include a medium-voltage sectional switch. What are the requirements (clarify) for the sectionalizing switch is and if it is required to provide a dedicated way for each transformer.yyIntent needs clarificationElectrical Engineering4/14/25
44Part 3D50page 299Is a switchgear or a switchboard need (clarify) to be provided and what UL standard needs to be followed?yyIntent needs clarificationElectrical Engineering4/14/25
45Part 3D50page 301 - 302The project requirement is to remove the existing 24 strand fiber optic loop, pole mounted cabling base wide primary system with new 288 pr fiber optic (FIO) cabling. And secondary fiber optic cabling from the primary to existing 54 PV inverter locations. What are the existing conditions now where the FIO attaches the inverters? Are the FIO lines overhead swung from primary pole to the PV inverters? Are the FIO lines from primary to PV inverters underground? What is the requirement under this contract to connect new FIO secondary from primary poles, underground ductbank or overhead swung?yyIntent needs clarificationElectrical Engineering4/14/25
46Part 3D50page 301 - 302Contractor is requesting existing information on the 54 PV inverter locations. For pricing and BOD, existing condition connections, inverter type, etc. is needed for engineers. Will you provide as-builts or data/info on the inverters? How they are attached into existing FIO lines and where?yyIntent needs clarificationElectrical Engineering4/14/25
47Part 3D50page 303Who is the base integrator and contact for the existing Rockwell systems?yyIntent needs clarificationElectrical Engineering4/14/25
48Part 3D50page 303This section indicates that meters will be added to the 54 PV systems. What are the meter requirements and specifications?yyIntent needs clarificationElectrical Engineering4/14/25
49Part 3D50page 303What are the requirements and specifications for the HMI screen and systems for the BESS?yyIntent needs clarificationElectrical Engineering4/14/25
50Part 3D50page 760The inverter list indicates many devices that have some type of error or problem. Can you confirm this contract is not to replace or repair any of the existing PV invertors? As that would be responsibility of the PC system provider-operator?yyIntent needs clarificationElectrical Engineering4/14/25
51Part 3D50page 760Should existing PV inverters cannot be integrated into this BESS system, they will need to be replaced. In this situation, will the replacement of inverters would be a pre-existing condition and change order priced accordingly with the contractor upon government approval?yyIntent needs clarificationElectrical Engineering4/14/25
52Part 3D50page 760This solicitation proposal response will assume that all inverters, whether new or old, will have the capacity to be integrated into the BESS system and that the contractor price shall not include cost of replacements, known or unknown. Can you confirm this statement?yyIntent needs clarificationElectrical Engineering4/14/25
53Part 3page 842 - 843Can you confirm that this contract design is to include new transformers at Substation AA and Gillespie as they seem to be undersized for the proposed BESS design?yyIntent needs clarificationElectrical Engineering4/14/25
54Part 3page 842 - 843Per the decision memorandum dated 12-19-22 it is stated that walls and shade (from view) structures are required around BESS. Is this required even if the 100' explosive standoff distances can be obtained?yyIntent needs clarificationCivil Engineering4/14/25
55Part 3page 759The existing PV location indicates that some of the PV systems have not been included and are awaiting the interconnect agreement. IS this drawing up to date? How does this impact this contracts design in MWH hours? Are these shown / noted systems already calculated into the RFP loads? If not will they need to be considered after award / design? If Yes, and there is no known information for design, will this be a change order to the contract?yyIntent needs clarificationElectrical Engineering4/14/25
56Part 3plumbingIs there a requirement or need for domestic water at the BESS locations? Possibly for workers drinking water? Or maybe Emergency eye wash? If yes, where will the domestic water come and be provided for?yyIntent needs clarificationMechanical Engineering4/14/25
57Part 3plumbingIs there a requirement for sanitary service, toilets, fixtures at the BESS locations? Possibly for workers? If so, where will the sanitary come from and connect?yyIntent needs clarificationMechanical Engineering4/14/25
58Part 3SignageWhat are the base requirements for BESS signage at the areas which is not going to be provided in the base design guide? What types and message for signs?yyIntent needs clarificationArchitectural-related4/14/25
59Part 3B10Foundation, page 270Does this RFP require all new geotechnical soils testing, drilling, soils determination, site test drilling, sample pit digs with geotechnical report for design? Or can previous and existing soils reports and test finding be provided and used for the foundation designs. It seems the as-built drawings for the microgrid design utilize older soils borings and testing data for the design.yyIntent needs clarificationCivil Engineering4/14/25
60Part 3Page 267Under site utilities there is reference to see attached RFP drawings for sewer, water, storm water, water, gas, and electric. We cannot find these GIS type drawings? Can you provide existing utility drawings asap by amendment in order to develop our proposal BOD and price?yyIntent needs clarificationCivil Engineering4/14/25
61Part 3Page 267Topographic existing GIS or drawings for the site locations. Can you provide existing drawings with topo and site conditions asap by amendment in order to develop our proposal BOD and price?yyIntent needs clarificationCivil Engineering4/14/25
62Part 3page 2662.6 states BESS shall be configured as a component of a future microgrid on base. What are those requirements to be considered in this contractor design? What are the parameters, power requirements, etc.?yyIntent needs clarificationElectrical Engineering4/14/25
63Part 3page 2662.1 mission statement notes a different size of 10.6MH hour rating than in other sections showing 10MW. Can you confirm correct size requirement?yyIntent needs clarificationContracting4/14/25
64Part 3C20page 294What are the base requirements for access roads to the BESS sites? Is the site access road to be asphalt paving are gravel paved roads?yyIntent needs clarificationCivil Engineering4/14/25
65Part 3D40page 296The preference to BESS for the base is for two BESS locations, one at Cogen 1 and other at Cogen 2. The RFP provides locations on page 749 and 750. The location for the AA BESS provides access reasonably from Truax Drive where site access road entrance is very manageable during construction and long term services after construction. However, the Gillespie BESS RFP location is across the concrete drainage ditch and in an area that is NOT accessible from Gillespie Road. It appears a road would have to be constructed 13th Street, across and along the concrete culvert drainage ditch, navigating the existing hilly, rocky, and sand terrain. Somewhere around 2,200 LF. There is a better location for Gillespie BESS that will save government budget in construction of access roads. Does contractor have the freedom / permission to recommend other site location solution for this BESS location? Would proposing alternate location solutions for either BESS location be acceptable or would it be deemed non-compliant as the RFP provides two location map locations?yyIntent needs clarificationCivil Engineering4/14/25
66Part 2spec 01 33 10.05 20What is the governments/Navy intended design phase submission? How many design submissions? Are they typical 3 phase submissions where per centages at 35%, 95%, and 100% DD submittal?yyIntent needs clarificationContracting4/14/25
67Part 2spec 01 33 10.05 20Can you confirm that the government/Navy design review period will typically be 30 calendar days after submission receipt?yyIntent needs clarificationContracting4/14/25
68Part 2spec 01 33 10.05 20Will the government/Navy require a design phase meeting discussion to cover a design phase submission comments prior to moving to next design phase submission?yyIntent needs clarificationContracting4/14/25
69Part 2spec 01 35 26Can the SSHO have other duties and be dual hat role from either superintendent or QAC staff?yyIntent needs clarificationContracting4/14/25
70Part 2spec 01 45 00.05 20Can the QCM manager dual hat role of SSHO?yyIntent needs clarificationContracting4/14/25
71Part 2Project StaffIs the site staffing requirement for minimum of three staff: 1) Superintendent 2) SSHO and 3) QCM?yyIntent needs clarificationContracting4/14/25
72Part 3Page 256The project description notes that contractor must provide support to government which is obtaining the modifications to the interconnection agreement for the BESS. Is the interconnect agreement modifications the sole responsibility of the base/ government where contractor only needs to provide input and help?yyIntent needs clarificationContracting4/14/25
73Part 3Page 256Can you provide scale PDF drawings in 24"x36" or larger of entire base in GIS or a format where we can gather accurate lenghts and quanities for the new primary and secondary fiber runs around the base in amendment asap?yyIntent needs clarificationCivil Engineering4/14/25
74Part 3Page 258Statement "MCAGCC operates a total of 9.2 MW of solar photovoltaics (PV) throughout their distribution system. Only 1.2 MW of the PV is controllable while the remaining 8 MW must be controlled at the inverter via autonomous settings or manual switching. Approximately 2.75 MW of PV at MCAGCC is under PPA or ESPC contracts and will require additional coordination with those contractors. Will the 8MW that is currently controlled at the inverter by autonomous settings or manual switching need be changed to controllable, assuming that would be at the CCS, by this contract? Or will that be completed by PPA or ESPC contracts? Can the government provide further details and clarification on this statment for RFP scope clarification?yyIntent needs clarificationElectrical Engineering4/14/25
75If "Others" - include info under Column E Clarification RequestSolictation date response is set for May 15 at 2PM. RFI closing date is set for April 17 at 5PM. There is a huge lift of working through the RFI government reponses when provided by amendment. From that, there are lots of information and project requirements that will be reviewed. Once we receive RFIJ reponses, the team needs time to process with team and lower tier members to create the final proposed basis of design narrative and pricing. We are requesting an extension of time for this proposal to at minimum of May 29th or 30th. WIll the government amend and extend the submission extension time?yyIntent needs clarificationContractingThe RFI deadline for submission has been amdended to Tuesday, April 29, 2025. The Proposal due date has been amended to Tuesday, June 3, 2025, Please refer to Amendment 0009.4/14/254/17/250009
76If "Others" - include info under Column E Clarification RequestFor creating a prjoect prelimnary schedule for pricing and narrative, when does the government intend to award this project and expected notice - to - proceed date?yyIntent needs clarificationContractingThe Government intends to award this project in quarter four of Fiscal Year 2025.4/14/254/17/25
77Part 3G40G403010Please confirm "Provide 288 strand single mode fiber optic cable between Central Control System (CCS) and the BESS controls shed." vs "This project will replace the current 24 strand overhead loop, located on existing power and communications poles and be a minimum of 288 pair cable."NNIntent needs clarificationElectrical Engineering4/15/25
78Part 3Chapter-1P 257 of 1678Shade structure clarification. P 257 v P269 of 1678. Steel structure appears to be required, however, extent of steel structure is not clear. BESS seem to be designed to ignite upwards so a steel structure over the BESS may have unintended consequences vs steel posts with a fabric shade structure. Are we allowed to consider tradeoffs between fabric and metal for the deck / horizontal portion of the shade structure during design?NNIntent needs clarificationFire Protection4/15/25
79Part 3Chapter-1Section 1.3, P 263 of 1678 vs P302 of 1678Please provide more details regarding adding fiber and controls to each PV system where substantial underground conduits may be needed between overhead poles and facility hosting solar PV. Can we assume there are existing conduits that can be utilized and no new underground conduits are needed? If we need to install new conduits, can we get clarifications on where and how long?YN4/15/25
80Part 3G40G403010Has it been verified the existing Rockwell system has sufficient capacity to accommodate the expansion / inclusion of 54 new solar sites and the multiple BESS modes of operation?YNOther; Please specify in the next columnReliance on legacy systems per RFPElectrical Engineering4/15/25
81If "Others" - include info under Column E Clarification Requestif Others include info under Column ESF30Amendment 0006, SF 30, " This solicitation includes FAR clause 52.225-11, Buy American Act – Construction Materials Under Trade Agreements and FAR 52.225-12, Notice of Buy American Act Requirement – Construction Materials Under Trade Agreements." Please clarify intent for inclusion of this as it relates to lithium ion BESS technology and what level of documentation is necessary to meet intent.YNIntent needs clarificationComponent vs Assembly country of origin requirements, inclusion of FTA, etcContracting4/15/25

Drop Down List

RFI Topic Relevant to:RFP Part #RFI Reason (for QA) - from KTR perspecrive
Architectural-relatedPart 1Outdated Reference
Civil EngineeringPart 2Conflicting Information
ContractingPart 3Attachments are referenced but missing/not provided
Electrical EngineeringPart 4Intent needs clarification
EnvironmentalPart 5Typo
Fire ProtectionPart 6Other; Please specify in the next column
Geotechnical EngineeringIf "Others" - include info under Column E Clarification Request
Interior Design