This document is an Engineering Systems Requirements (ESR) section A10 for Foundations, part of a federal contract for constructing a 10 MW Battery Energy Storage System at Marine Corps Air Ground Combat Center (MCAGCC) in 29 Palms, California. The section provides detailed geotechnical and foundation requirements, emphasizing the need for comprehensive site investigation and design considerations. Key requirements include:

The contractor must perform a thorough soils investigation, including subsurface exploration, testing, and analysis, utilizing a licensed Geotechnical Engineer to evaluate site conditions. The document highlights potential challenges such as marginal subgrade support, corrosive soils, and settlement risks. Specific technical requirements mandate standard foundations compliant with International Building Code standards, ground floor slab specifications, and seismic design parameters in accordance with Unified Facilities Criteria. The Geotechnical Engineer must develop settlement mitigation procedures, potentially including preloading, surcharging, and ground improvement systems, with surcharge material required to remain in place for a minimum of 90 days.

View the file

Other files

File Type Posted
Solicitation Amendment N6247324R52270024 SF 30.pdf PDF
ENCL 2 - WD_CA20250026_AMEND 23.pdf PDF
ENCL 1 - P1238_RFP_AMEND 0023_Revised 21AUG25.pdf PDF
Amendment 0023_P1238.pdf PDF
Amendment 0022_P1238_14AUG25.pdf PDF
Amendment 0021_P1238_13AUG25.pdf PDF
ENCL 1 - P1238_RFP_AMEND 0020_Revised 06AUG25.pdf PDF
Amendment 0020_P1238_06AUG25.pdf PDF
ENCL 2 - WD_CA20250026_MOD 08_01AUG25.pdf PDF
Amendment 0019_P1238_31JUL25.pdf PDF
Phase Two Enc 1 - P1238_RFP_AMEND 0019_Revised31JUL25.pdf PDF
Amendment 0018_P1238_21JUL25.pdf PDF
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0018_Revised 21JUL25.pdf PDF
Amendment 0017_P1238_15JUL25.pdf PDF
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0017_Revised 15JUL25.pdf PDF
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0016_Revised 02JUL25.pdf PDF
Amendment 0016_P1238_02JUL25.pdf PDF
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0015_Revised 01JUL25.pdf PDF
Amendment 0015_P1238_01JUL25.pdf PDF
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0014_Revised 30JUN25.pdf PDF
Amendment 0014_P1238_30JUN25.pdf PDF
Section 00 45 00 Reps and Certs_24R5227_AMEND 0014.docx DOCX document
Amendment 0013_P1238_24JUN25.pdf PDF
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0013_Revised 24JUN25.pdf PDF
Wage Determination CA 20250026 dated 06062025.pdf PDF
Phase Two Enclosure 3 - P1238_Blank_OfferSchedule_Revised 04JUN25.xlsx XLSX spreadsheet
Amendment 0012_P1238_05JUN25.pdf PDF
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0012_Revised 05JUN25.pdf PDF
PLA Request for Information N6247324R5227.docx DOCX document
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0011_Revised 29MAY25.pdf PDF
Wage Determination_CA20250017_Modification 8_29MAY25.pdf PDF
Amendment 0011_P1238_29MAY25.pdf PDF
ENCL C_ESR_D30_P1238.pdf PDF
ENCL B_ESR_D20_P1238.pdf PDF
ENCL H_EXHIBIT F_P1238_Small Business Participation Commitment.docx DOCX document
ENCL E_2a- P-495 Geotech Report 1999-01-19.pdf PDF
ENCL F_Geotech Report.pdf PDF
ENCL J_UFGS 01 91 00.15-DBContract_P1238.pdf PDF
ENCL G_EXHIBIT E_P1238_Historical Small Business Utilization.docx DOCX document
ENCL K_P1238_N6247324R5227_RFI_Responses_Amendment 0010.xlsx XLSX spreadsheet
Amendment 0010_P1238_RFI Responses_19MAY25.pdf PDF
ENCL D_Utilities_P1238.pdf PDF
P1238_N6247322R5227_RFI_Submission - Non-Amendment Responses_08MAY25.xlsx XLSX spreadsheet
Phase Two Enclosure 3_P1238_Blank_OfferSchedule_Revised.xlsx XLSX spreadsheet
N6247324R5227_Amendment 0009_SF30.pdf PDF
EXHIBIT E_P1238_Historical Small Business Utilization.pdf PDF
Revised Standard Form (SF) 1442_P1238_N6247324R5227.pdf PDF
Phase Two Enclosure 1_P1238_RFP Part 1_Revised.pdf PDF
P1238_RFI Submission Form_Responses_17APR2025.xlsx XLSX spreadsheet
N6247324R5227_Amendment 0008.pdf PDF
Show 40 more

Latest 50 of 76 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P1238 Construction of Grid Stability & Resiliency 10 MW Battery Energy Storage WON 1692125 MCAGCC 29 Palms, CA

PART 3 - CHAPTER 6 / ESR A10 - Page 1

6. ENGINEERING SYSTEMS REQUIREMENTS

A10 FOUNDATIONS

SYSTEM DESCRIPTION

Provide the building foundation system in accordance with Unified Facilities Criteria (UFC) 3-301-01, Structural Engineering and UFC 3-220-01, Geotechnical Engineering. Design foundations to suit subsurface conditions, capable of transmitting all loads to the ground.

See Engineering Systems Requirements (ESR) Section B10, Superstructure, for additional loading criteria.

A10 GENERAL

GOVERNMENT PROVIDED GEOTECHNICAL INFORMATION

Subsurface soil information, including geotechnical reports from nearby prior projects are included in Part 6 of of this RFP.

The included subsurface information is only for the Contractor's information and is not guaranteed to fully represent all subsurface conditions. The Government will not be responsible for any interpretation or conclusion by the Contractor drawn from the data or information.

The included geotechnical report accompanying the subsurface information is provided only to better convey data (boring logs, testing, and other data) or to document observed site conditions. The assumptions, analysis, and recommendations of any accompanying report were developed for prior projects and will not reflect present project requirements. The Contractor is required to retain a Geotechnical Engineer experienced and licensed in the geographic region of the project to interpret the Government provided information as related to the design concept and develop geotechnical requirements to support design and construction.

Anticipate minor variations in subsurface conditions between borings. The Contractor is responsible for costs associated with the site preparation, ground improvement and foundations except as allowed by Contract Clause Federal Acquisition Regulation (FAR) 52.236-2, "Differing Site Conditions". The Contractor's Geotechnical Engineer must perform additional subsurface investigation/testing as required to adequately determine all applicable geotechnical factors including the type and capacity of the project foundations. The Contractor's Geotechnical Engineer is required to evaluate the provided information and any additional information obtained and prepare a report as described in other portions of this RFP. The minimum requirements for the subsurface investigation and report are as required by Facilities Criteria (FC) 1-300-09N with associated references.

Perform the soils investigation at the site for use in the design and construction of the new facilities.

Perform, at Contractor's expense, subsurface exploration, investigation, testing, and analysis for the design and construction of features such as the building foundations, pavement section(s), stormwater management facility(ies), and utility structure foundations. Prepare a report including laboratory analysis of samples and recommendations for foundation and pavement design by a Professional Engineer as specified and in accordance with UFC 3-201-01, Civil Engineering and UFC 3-220-01, Geotechnical Engineering.

As a minimum, the successful bidder's Geotechnical Engineer must perform additional subsurface exploration and supplementary laboratory testing as necessary to support the design concept.

PART 3 - CHAPTER 6 / ESR A10 - Page 2

Observed site conditions which may present a challenge during design/construction include – In their present condition, near-surface soils may not be suitable for supporting structural loading. Presence of corrosive soils. Anticipate these marginal subgrade support conditions and incorporate measures into the design and construction procedures to obtain required soil support while maintaining progress for completion on schedule.

Provide personnel under the supervision of a registered Professional Engineer to inspect excavations and soil/groundwater conditions throughout construction. The Engineer is required to perform pre-construction and periodic site visits throughout construction to assess site conditions. The Engineer, with the concurrence of the Contractor and the Contracting Officer, is required to update the excavation, sheeting, shoring and dewatering plans as construction progresses to reflect actual site conditions and is required to submit the updated plan and a written report (with professional stamp) at least monthly informing the Contractor and Contracting Officer of the status of the plan and an accounting of Contractor adherence to the plan; specifically addressing any present or potential problems. The Engineer must be available to meet with the Contracting Officer at any time throughout the Contract duration. Provide the services of the Engineer at no additional cost to the Government. It is important to note that the presence of loose or compressible soils may result in excessive settlement that could impact the performance of surface bearing structures and supporting facilities such as foundations, slabs, pavements, sidewalks, and utilities. The magnitude and duration of consolidation settlement will be dependent on the composition, depth, and thickness of the compressible soils as well as the successful bidder's design concept. The Contractor's Geotechnical Engineer is responsible for evaluating potential global settlement due to designed grade increases and final structural loads. The Contractor's Geotechnical Engineer must develop any settlement mitigation procedures (such as preloading, surcharging, fill monitoring programs, and ground improvement systems) needed to maintain global settlements within tolerable limits. Surcharge material, if required, must remain in place for a minimum of 90 days.

SEISMIC DESIGN

Determine the Seismic Site Classification and Seismic Design Parameters in accordance with UFC 3- 301-01, Structural Engineering; UFC 3-220-01, Geotechnical Engineering; and associated references.

A1010 STANDARD FOUNDATIONS

As determined by the Designer of Record to be applicable, provide a Standard foundation. "Standard Foundations" are shallow or deep foundations as specifically addressed in International Building Code (IBC) Chapter 18. Do not use masonry unit footings, steel grillage footings, timber footings or wood foundations.

A1020 SPECIAL FOUNDATIONS

Not used.

A1030 GROUND FLOOR SLABS

As determined by the Designer of Record, provide soil supported concrete slab on ground. Where slab on ground is below the existing adjacent exterior grade, provide water/dampproofing and a perimeter drainage system to remove ground water from the area immediately adjacent to the buildings. Provide perimeter and under slab insulation in accordance with UFC 3-101-01, Architecture.

As determined by the Designer of Record to be applicable, provide a structurally supported slab.

Provide for support of all utilities that may be adversely affected by soil consolidation or expansive soils. Provide stainless steel supports sized adequately to support the in-service utility. Where the

PART 3 - CHAPTER 6 / ESR A10 - Page 3 structurally supported slab is below the existing adjacent exterior grade, provide water/dampproofing and a perimeter drainage system to remove ground water from the area immediately adjacent to the buildings. Provide perimeter and under slab insulation in accordance with UFC 3-101-01, Architecture.