This document is an Engineering Systems Requirements (ESR) specification for HVAC systems in a Battery Energy Storage System (BESS) project at Marine Corps Air Ground Combat Center (MCAGCC) in 29 Palms, California. The specification details precise technical requirements for cooling and environmental control of battery storage containers, including mandating dedicated independent direct expansion (DX) cooling systems for each pre-factory battery container. Key requirements include maintaining a consistent 65°F ambient temperature, providing a Hydrogen and Gas Detection System to monitor hazardous gases, and implementing Direct Digital Controls (DDC) with specific cybersecurity protocols aligned with Department of Defense Risk Management Framework guidelines.

The document specifies comprehensive environmental and technical specifications, including design conditions ranging from 32°F to 108°F external temperatures, required ventilation rates per ASHRAE standards, and detailed control system requirements. The BESS must be factory-integrated, "plug-and-play" ready, with interior wiring for equipment, auxiliary systems, distribution, lighting, HVAC, fire alarm, and communications. The control systems must include operator workstations, notebook computers, application software, and the ability to integrate with existing Utility Monitoring and Control Systems (UMCS), with all personnel configuring equipment required to have a Tier 3 background investigation.

View the file

Other files

File Type Posted
Solicitation Amendment N6247324R52270024 SF 30.pdf PDF
ENCL 2 - WD_CA20250026_AMEND 23.pdf PDF
ENCL 1 - P1238_RFP_AMEND 0023_Revised 21AUG25.pdf PDF
Amendment 0023_P1238.pdf PDF
Amendment 0022_P1238_14AUG25.pdf PDF
Amendment 0021_P1238_13AUG25.pdf PDF
ENCL 1 - P1238_RFP_AMEND 0020_Revised 06AUG25.pdf PDF
Amendment 0020_P1238_06AUG25.pdf PDF
ENCL 2 - WD_CA20250026_MOD 08_01AUG25.pdf PDF
Amendment 0019_P1238_31JUL25.pdf PDF
Phase Two Enc 1 - P1238_RFP_AMEND 0019_Revised31JUL25.pdf PDF
Amendment 0018_P1238_21JUL25.pdf PDF
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0018_Revised 21JUL25.pdf PDF
Amendment 0017_P1238_15JUL25.pdf PDF
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0017_Revised 15JUL25.pdf PDF
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0016_Revised 02JUL25.pdf PDF
Amendment 0016_P1238_02JUL25.pdf PDF
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0015_Revised 01JUL25.pdf PDF
Amendment 0015_P1238_01JUL25.pdf PDF
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0014_Revised 30JUN25.pdf PDF
Amendment 0014_P1238_30JUN25.pdf PDF
Section 00 45 00 Reps and Certs_24R5227_AMEND 0014.docx DOCX document
Amendment 0013_P1238_24JUN25.pdf PDF
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0013_Revised 24JUN25.pdf PDF
Wage Determination CA 20250026 dated 06062025.pdf PDF
Phase Two Enclosure 3 - P1238_Blank_OfferSchedule_Revised 04JUN25.xlsx XLSX spreadsheet
Amendment 0012_P1238_05JUN25.pdf PDF
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0012_Revised 05JUN25.pdf PDF
PLA Request for Information N6247324R5227.docx DOCX document
Phase Two Enclosure 1 - P1238_RFP Part 1_AMEND 0011_Revised 29MAY25.pdf PDF
Wage Determination_CA20250017_Modification 8_29MAY25.pdf PDF
Amendment 0011_P1238_29MAY25.pdf PDF
ENCL B_ESR_D20_P1238.pdf PDF
ENCL H_EXHIBIT F_P1238_Small Business Participation Commitment.docx DOCX document
ENCL E_2a- P-495 Geotech Report 1999-01-19.pdf PDF
ENCL F_Geotech Report.pdf PDF
ENCL A_ESR_A10_P1238.pdf PDF
ENCL J_UFGS 01 91 00.15-DBContract_P1238.pdf PDF
ENCL G_EXHIBIT E_P1238_Historical Small Business Utilization.docx DOCX document
ENCL K_P1238_N6247324R5227_RFI_Responses_Amendment 0010.xlsx XLSX spreadsheet
Amendment 0010_P1238_RFI Responses_19MAY25.pdf PDF
ENCL D_Utilities_P1238.pdf PDF
P1238_N6247322R5227_RFI_Submission - Non-Amendment Responses_08MAY25.xlsx XLSX spreadsheet
Phase Two Enclosure 3_P1238_Blank_OfferSchedule_Revised.xlsx XLSX spreadsheet
N6247324R5227_Amendment 0009_SF30.pdf PDF
EXHIBIT E_P1238_Historical Small Business Utilization.pdf PDF
Revised Standard Form (SF) 1442_P1238_N6247324R5227.pdf PDF
Phase Two Enclosure 1_P1238_RFP Part 1_Revised.pdf PDF
P1238_RFI Submission Form_Responses_17APR2025.xlsx XLSX spreadsheet
N6247324R5227_Amendment 0008.pdf PDF
Show 40 more

Latest 50 of 76 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P-1238 Construction of Grid Stability & Resiliency 10 MW Battery Energy Storage, Various Buildings.

Work Order Number 20190612 29 Palms/California

PART 3 - CHAPTER 6 / ESR D30 - Page 1

6. ENGINEERING SYSTEMS REQUIREMENTS

D30 HVAC

Refer to Part 4 Section D30 for performance requirements of the building elements included in the HVAC system.

SYSTEM DESCRIPTION

The factory integrated Battery Energy Storage System (BESS) must be provided with DX split system to provide cooling to attain the following objectives: 24/7 continuous sustainment of critical infrastructure environmental condition, indoor air quality, acceptable noise levels, energy efficiency, reliable operation, and ease of maintenance. Design and install in accordance with UFC 3-401-01 MECHANICAL ENGINEERING, UFC 3-410-04 Industrial Ventilation, UFC 3-410-01 Heating, Ventilating, and Air Conditioning Systems, UFC 3-520-05 Stationary and Mission Batteries and all Mechanical Engineering and related UFCs. These UFCs incorporate provisions of the International Code Council's International Mechanical Code (IMC) and ASHRAE design guidance with supplemental requirements.

A dedicated and independent cooling system shall be provided for each pre-factory battery storage container. This system must be separate from the building’s HVAC system and designed specifically to maintain a consistent ambient temperature of 65°F (18°C), or as per the manufacturer’s specified temperature requirements for optimal performance and longevity of the battery storage system. The cooling system should be capable of efficiently regulating the temperature within the specified range, taking into consideration the heat generated by the batteries during charging and discharging cycles.

Additionally, the system must include necessary monitoring and control mechanisms to ensure stable operating conditions, prevent overheating, and comply with safety and performance standards for the battery storage system. Provide a proper ventilation system to avoid the buildup of heat and gases generated by the batteries, Additionally, provide a Hydrogen and Gas Detection System to continuously monitor and detect the presence of hazardous gases, including hydrogen, within the battery energy storage system. This system is critical for ensuring the safety of the installation, as it helps identify potential risks such as gas leaks or the buildup of flammable gases. Early detection allows for prompt mitigation actions, reducing the risk of fire, explosion, or system failure, thereby safeguarding both personnel and equipment.

Provide BESS scalable, factory integrated and certify with all safety features, ready to “Plug-and-Play”. Provide factory installed interior wiring and connections for Equipment, Auxiliary Equipment, AC and DC Distribution, Lighting and Branch Wiring, HVAC, Fire Alarm, Communications, etc. including accessories and devices as necessary and required for a complete usable system.

Provide BESS Facility Related Control Systems (FRCS) capable of remote monitoring and control.

The BESS FRCS equipment will be house in a separate equipment booth. Provide interior wiring and connections for Equipment, Lighting and Branch Wiring, HVAC, Communications, etc. including accessories and devices as necessary and required for a complete usable system.

GENERAL SYSTEM REQUIREMENTS

Provide working space around all equipment. Provide all required fittings, connections and accessories required for a complete and usable system. Install all equipment in accordance with the criteria in PTS Section D30 and the manufacturer's recommendations. Where the word "should" is used in manufacturer's instructions, substitute the word "must".

PART 3 - CHAPTER 6 / ESR D30 - Page 2

Battery Energy Storage System (BESS) must be independently climate controlled, capable of providing year-round ambient temperature control (24 hours/day, 365 days/year) to protect all installed electronic equipment. Utilize independent DX system as the primary source of cooling.

Provide mechanical systems per requirements of UFC 3-580-01 and TIA-569-C.

Provide air conditioning and heating for spaces as indicated and for the following Design conditions:

Outside Conditions

Summer

Degrees F dry bulb

Winter

Degrees F

Degrees C dry

Degrees C

Degrees F wet

Degrees C wet

Inside Conditions

Summer per UFC 3-520-05

Degrees F dry

Winter

68-77

Degrees F

Degrees C dry

20-25

Degrees C

50 not to exceed

Percent RH

Provide Ventilation rates and systems in accordance with ASHRAE Standard 62.1, Ventilation for Acceptable Indoor Air Quality.

Provide minimum 4-inch (100 mm) thick concrete housekeeping pads and vibration isolators under all floor-mounted equipment.

For sea coast applications, provide factory painted finishes that are designed for 3000 hour duration test for outside equipment and for equipment bringing in outside air.

PART 3 - CHAPTER 6 / ESR D30 - Page 3

D3030 COOLING GENERATING SYSTEMS

D303002 DIRECT EXPANSION SYSTEMS

Provide a dedicated and independent DX cooling system for each pre-factory Battery Energy Storage System (BESS).

D3040 DISTRIBUTION SYSTEMS

D304001 AIR DISTRIBUTION, HEATING & COOLING

D304007 EXHAUST SYSTEMS

D3060 CONTROLS AND INSTRUMENTATION

D306001 HVAC CONTROLS

D306001 1.1 DIRECT DIGITAL CONTROLS (DDC)

Provide a complete Direct Digital Control (DDC) system to comply with UFGS 23 09 00, Instrumentation and Control for HVAC, UFGS 23 09 23.02, BACnet Direct Digital Control for HVAC and Other Building Control Systems, UFGS 23 09 13, Instrumentation and Control Devices for HVAC, and BACnet communication protocol to comply with BMS for the facility.

Provide integration of the new Direct Digital Control (DDC) system to the existing base Utility Monitoring and Control System (UMCS) in compliance with the UMCS's Risk Management Framework (RMF) Authorization to Operate (ATO) and UFGS 25 10 10, Utility Monitoring and Control System (UMCS) Front End and Integration.

Provide operator workstation and notebook computer and complete application software with all licenses.

The control system, including system components installed and other components modified by this project, will be designed, acquired and executed in accordance with DoDI 8500.01, DoDI 8510.01, Department of Defense Risk Management Framework (RMF) per UFC 4-010-06, and Cybersecurity of Facility-Related Control systems, and other relevant FRCS cybersecurity requirements. All equipment installed (hardware and software) will be open protocol, have the ability to connect to existing and future systems, and will include the proper firewalls. The contractor shall supply all IP addresses, equipment nameplate information, software and hardware configurations and programming information in support of the Government’s RMF package submittal. Any personnel configuring or programming equipment must have a Tier 3 background investigation. Upon project completion, MCAGCC will have an authority to operate (ATO), and a functional and cybersecurity FRCSs.

Provide meters, monitored by DDC, on the following incoming utilities of the building: steam and gas.

For electrical energy monitoring refer to Section D50, Electrical, paragraph entitled, Service Entrance Equipment. For potable water meter refer to Section G30, Site Civil/Mechanical Utilities, paragraph entitled, Potable Water Distribution. Set up trend reports to record data daily and store values in the operator workstation DDC computer. Set up trend reports to record data daily and store values in the ASHRAE Standard 135 building controller for later retrieval by either a notebook computer or an operator workstation DDC computer.

PART 3 - CHAPTER 6 / ESR D30 - Page 4

Provide meters, monitored by DDC, on the following subsystems for steam, gas and water: HVAC and processes.

Provide meters, monitored by DDC, on the following subsystems for potable water and reclaimed water.

Provide ASHRAE Standard 135 building controller as the main interface for the building control system.

Provide patch panel in the mechanical equipment room for ease of connection and disconnection of equipment.

Provide panels with locks and alarms. The alarms must include both a flashing light and an audible alarm inside the shelter room. The alarms must also be a networked alarm (e.g. switch connected to controller DI) with alarm events recorded remotely for a period not less than one year.

D306001 1.2 ELECTRONIC CONTROLS

Provide electronic controls with programmable thermostats for the HVAC systems and equipment.

D3070 SYSTEMS TESTING AND BALANCING

Provide complete Testing and Balancing (TAB) of all air and water distribution systems and HVAC equipment and performance verification testing (PVT) of all HVAC controls systems.

D307003 HVAC COMMISSIONING

Refer to RFP Part 3 - Project Program, Chapter 2 for Building Commissioning requirements.

Mechanical systems to be commissioned, if provided, include HVAC systems and controls, refrigeration systems and controls, renewable energy systems, and domestic cold/hot water systems.

D3090 OTHER HVAC SYSTEMS AND EQUIPMENT

D309001 GENERAL CONSTRUCTION ITEMS

Provide seismic restraints and Comply with the Force Protection Criteria.

Provide access to all mechanical equipment rooms through the building exterior walls.

-- End of Section --