This is Amendment 0020 to Solicitation N62473-24-R-5227 for the construction of a 10MW battery energy storage system at Marine Corps Air Ground Combat Center Twentynine Palms, California, dated August 6, 2025. The amendment updates the Department of Labor Construction Wage Determination referenced in Section 11 of the Request for Proposal Part 1, changing from General Decision No. CA 20250026 dated 06/06/2025 to General Decision No. CA 20250026 Modification 8 dated 08/01/2025.
All other terms and conditions of the original solicitation remain unchanged. The amendment includes two enclosures: the revised RFP Part 1 Phase Two document and the updated wage determination. Offerors must acknowledge receipt of all amendments on their offer schedule. The wage determination information can be found on the SAM.gov website.
View the file
Other files
Show 40 more
Latest 50 of 76 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT 0020
Date: August 06, 2025
Solicitation No.: N62473-24-R-5227
P-1238 CONSTRUCTION OF GRID STABILITY & RESILIENCY 10MW BATTERY ENERGY
STORAGE MARINE CORPS AIR GROUND COMBAT CENTER
TWENTYNINE PALMS, CALIFORNIA
The purpose of this amendment is to provide the most recent Wage Determination:
1. Incorporate the current Department of Labor Construction Wage Determination update in Section 11 of the Request for Proposal (RFP) Part 1:
FROM:
The minimum wages, required to be paid for work under this contract, are in accordance with U.S. Department of Labor, General Decision No. CA 20250026 dated 06/06/2025. The General Wage Decision can be found at the following website: www.sam.gov.
TO:
The minimum wages, required to be paid for work under this contract, are in accordance with U.S.
Department of Labor, General Decision No. CA 20250026 Modification 8 dated 08/01/2025. The General Wage Decision can be found at the following website: www.sam.gov.
2. ALL OTHER PARAGRAPHS, PROVISIONS, AND CONDITIONS OF SOLICITATION N62473-24-R-
5227 PLANNED REMAIN UNCHANGED. THE OFFEROR MUST ACKNOWLEDGE RECEIPT OF
ALL AMENDEMENTS ON THE OFFER SCHEDULE.
Enclosures:
1. ENCL 1 - P1238 Final RFP_Part 1_Phase Two_AMEND 0020_REVISED_06AUG2025
2. ENCL 2 - Wage Determination CA 20250026 Modification 8 dated 08/01/2025 http://www.sam.gov/ http://www.sam.gov/