This is Section 01 30 00 (Administrative Requirements) from NUWC P-084 Amendment 006, a federal construction specification for Newport Naval Station in Newport, Rhode Island, dated October 2026.

The specification establishes comprehensive administrative and supervisory requirements for contract performance. The Contractor must provide a Project Superintendent with a minimum of 10 years of construction experience, including at least 5 years as a superintendent on similar-sized projects, with demonstrated knowledge of EM 385-1-1 safety requirements and hazard identification capabilities. The Superintendent must maintain continuous on-site presence during all work performance and is subject to removal for non-compliance. A qualified alternate superintendent with identical qualifications must also be available. Minimum insurance coverage per FAR 28.307-2 is required throughout contract performance. The Contractor must submit preconstruction documentation including a view location map and progress/completion photographs (minimum 1600x1200x24-bit resolution JPEG format), with at least 20 digital photographs weekly from ten different viewpoints, submitted monthly on CD or DVD. Key administrative milestones include a Preconstruction Meeting within 35 calendar days of award, a Facilitated Partnering session within 45 calendar days (hosted off-base at Contractor expense with independent third-party facilitator), and jobsite mobilization within 60 calendar days defined as equipment presence plus at least one person on-site. Red Zone facility turnover planning meetings commence at approximately 75 percent project completion or three to six months before Beneficial Occupancy Date, utilizing a modified Red Zone Checklist as a Plan of Action and Milestones document with regular status updates and escalating meeting frequency approaching project completion.

View the file

Other files

File Type Posted
P1016_Civil C-131.pdf PDF
02 82 00.pdf PDF
33 63 13.pdf PDF
01 33 00.pdf PDF
P-1016 Amendment 0006 - Continuation.pdf PDF
00 01 15.pdf PDF
Attachment H -Price Proposal Form_Rev 1.docx DOCX document
High Performance and Sustainable Building Checklist.pdf PDF
28 10 05.pdf PDF
Amendment 0006 PPI Responses.pdf PDF
23 07 00.pdf PDF
P-084 Amendment 0006 - Continuation.pdf PDF
P084 - Amendment 006 Drawings.pdf PDF
Attachment J - WD RI20260001 10-1-26.pdf PDF
Amendment 0006 N4008526R0178.pdf PDF
23 22 26.00 20.pdf PDF
32 31 13.53.pdf PDF
Amendment 0005 N4008526R0178.pdf PDF
Amendment 0004 N4008526R0178.pdf PDF
Amendment 0004 PPI Responses.pdf PDF
Amendment 0003 N4008526R0178.pdf PDF
Amendment 0002 - N4008526R0178.pdf PDF
Amendment 0001 - N4008526R0178 .pdf PDF
Attachment I - SECNAV FORM 5512.pdf PDF
Solicitation - N4008526R0178.pdf PDF
Attachment E- Historical Small Business Utilization.docx DOCX document
Attachment A - Pre-Proposal Inquiry Log Template.xlsx XLSX spreadsheet
Attachment J - WD RI20260001 7-30-2026.pdf PDF
NUWC P-1016 - Drawings.pdf PDF
NUWC P084 - Drawings.pdf PDF
NUWC P-1016 - Specifications.pdf PDF
Attachment D- Past Performance Questionnaire.docx DOCX document
Attachment B - PIEE Vendor Access Instructions.pdf PDF
Attachment H -Price Proposal Form.docx DOCX document
Attachment C- Construction Experience Project Data.docx DOCX document
NUWC P084 - Specifications.pdf PDF
Attachment G - Individual SB Subcontracting Plan.docx DOCX document
Attachment F-Small Business Participation Commitment.docx DOCX document
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NUWC P-084 AMENDMENT 006

NEWPORT NAVAL STATION, NEWPORT, RI OCTOBER 2026

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

11/20, CHG 3: 08/23

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2024) Safety -- Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

View Location Map

Progress and Completion Pictures

1.3 VIEW LOCATION MAP

Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

1.4 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures.

Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file.

Include a date designator in file names. Photographs provided are for unrestricted use by the Government.

1.5 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 Liability, SECTION 01 30 00 Page 1 during the entire period of performance under this contract. Provide other insurance coverage as required by State law.

1.6 SUPERVISION

1.6.1 Superintendent Qualifications

Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

The Superintendent may not serve as the QC Manager or SSHO.

1.6.2 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work. In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.

1.6.3 Duties

The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.6.4 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.7 PRECONSTRUCTION MEETING

Immediately after award, prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Meeting . The meeting must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site. The purpose of this meeting is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, SECTION 01 30 00 Page 2 base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.

1.7.1 Attendees

Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.

1.8 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)

Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start planning the turnover process at the Pre-Construction Conference meeting with a discussion of the Red Zone process and convene at regularly scheduled NAVFAC Red Zone Meetings beginning at approximately 75 percent of project completion. Include the following in the facility Turnover effort:

1.8.1 Red Zone Checklist

a. Contracting Officer's Technical Representative (COTR) will provide the Contractor a copy of the Red Zone Checklist template.

b. Prior to 75 percent completion, modify the Red Zone Checklist template by adding or deleting critical activities applicable to the project and assign planned completion dates for each activity. Submit the modified Red Zone Checklist to the Contracting Officer. The Contracting Officer may request additional activities be added to the Red Zone Checklist at any time as necessary.

1.8.2 Meetings

a. Conduct regular Red Zone Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.

b. The Contracting Officer will establish the frequency of the meetings, which is expected to increase as the project completion draws nearer.

At the beginning, Red Zone meetings may be every two weeks then increase to weekly towards the final month of the project.

c. Using the Red Zone Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.

d. During the Red Zone Meetings discuss with the COTR any upcoming activities that require Government involvement.

e. Maintain the Red Zone Checklist by documenting the actual completion dates as work is completed and update the Red Zone Checklist with revised planned completion dates as necessary to match progress.

Distribute copies of the current Red Zone Checklist to attendees at each Red Zone Meeting.

SECTION 01 30 00 Page 3

1.9 PARTNERING

Contractor shall host the partnering session within 45 calendar days of contract award. To most effectively accomplish this Contract, the Contractor and Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the supported command, end user, NAVFAC, PWD, FEAD/ROICC, Contractor, key subcontractors and the Designer of Record are required to participate in the Partnering process.

1.9.1 Facilitated (Formal) Partnering

a. Within 45 calendar days after award and prior to the start of work, host a Formal Partnering session with key personnel from the project team including both Contractor and Government personnel. All costs associated with the Partnering session including the third-party independent Facilitator Consultant, meeting room and other incidental items are the responsibility of the Contractor.

b. Before the Facilitated (Formal) Partnering session, coordinate with the Facilitator all requirements for incidental items (such as audio-visual equipment, easels, flipchart paper, colored markers, note pads, pens/pencils, colored flash cards) and have these items available at the Partnering session. Provide copies of any documents required for distribution to all attendees. Participants will bear their own costs for meals, lodging and transportation associated with Partnering .

c. The Initial Partnering Session must be a duration of one day and be held at a location off base as agreed to by the Contracting Officer.

Partnering session may take place concurrently with the Pre-Construction Meeting.

d. Facilitator must be experienced in conducting corporate Partnering sessions and must be a third-party independent facilitating consultant

- not an employee of the Contractor. The Facilitator is responsible for leading all aspects of the Partnering session necessary to achieve the Partnering goal.

e. An outcome of the Partnering session must be an escalation matrix agreed upon by both the Government and Contractor, which identifies key Government and Contractor decision makers by name and anticipated decision durations.

f. Host follow-on Partnering Sessions at three- to six-month intervals or more frequently if needed and lasting generally a half day or less.

Attendees need only be those required to resolve current issues. The same Facilitator used in the Initial Partnering session must lead the follow-on sessions unless an alternative is permitted by the Contractor Officer. All costs associated with follow-on Partnering sessions are the responsibility of the Contractor.

1.10 MOBILIZATION

Contractor shall mobilize to the jobsite within 60 calendar days after

SECTION 01 30 00 Page 4 contract award . Mobilize is defined as having equipment AND having a physical presence of at least one person from the contractor's team on the jobsite.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --