N4008526R0058 0009.pdf
PDF 743 KB Posted
- Attached to
- Design-Build (DB) Barracks Initiative (Package #2), Marine Corps Base (MCB) Camp Lejeune, North Carolina
- Solicitation number
- N4008526R0058
About this file
This is Amendment 0009 to a Navy design-build solicitation issued by NAVFACSYSCOM Mid-Atlantic on 22 July 2026 for military barracks and associated site improvements at Camp Lejeune, North Carolina. The amendment is effective immediately and modifies the existing solicitation (WO# 1894554) while maintaining the Phase II proposal due date of 27 July 2027 at 1400 EDT.
The amendment incorporates FAR clause 52.211-13 (Time Extension) and removes FAR clause 52.229-12 (Tax on Certain Foreign Procurements). It provides updated continuation sheets for both French Creek and Hadnot Point project areas with three versions each (dated 260423, 260720, and 260722), a Justification and Authorization (J&A) for Fire Protection requirements, and pre-proposal inquiry responses resolving 38 clarifications regarding technical specifications. Key clarifications address conflicts between RFP specifications and Camp Lejeune design guidance documents concerning subsurface drainage systems, dumpster enclosure gates, landscape materials (river rock versus mulch), equipment drying area fencing, pavement design sections and traffic volumes, mechanical system specifications (copper piping types, chiller configurations, ASHRAE standards), HVAC design conditions, fire protection generator requirements, building enclosure commissioning testing responsibilities, and vapor intrusion mitigation systems. The amendment specifies that no additional pre-proposal inquiries will be accepted and establishes that contractors must follow the most stringent requirements when conflicts exist between RFP sections and Camp Lejeune design guidance documents.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
SUMMARY OF CHANGES
Block 14 (Description of Amendment/Modification): The purpose of this Amendment is as follows:
1. Phase II proposal due date of 27 July 2027 NLT 1400 EDT remains unchanged.
2. Incorporate FAR clause 52.211-13.
3. Remove FAR clause 52.229-12.
4. Continuation Sheet(s) – French Creek 260423
5. Continuation Sheet(s) – Hadnot Point 260423
6. Continuation Sheet(s) – French Creek 260720
7. Continuation Sheet(s) – Hadnot Point 260720
8. Continuation Sheet(s) – French Creek 260722
9. Continuation Sheet(s) – Hadnot Point 260722
10. Provide J&A Fire Protection
11. Provide Pre-Proposal Inquiry Responses
***PLEASE NOTE: NO ADDITIONAL PPI’S WILL BE ACCEPTED***
4. Continuation Sheet(s) – French Creek 260423 – PROVIDED VIA ATTACHMENT
5. Continuation Sheet(s) – Hadnot Point 260423 – PROVIDED VIA ATTACHMENT
6. Continuation Sheet(s) – French Creek 260720 - PROVIDED VIA ATTACHMENT
7. Continuation Sheet(s) – Hadnot Point 260720 - PROVIDED VIA ATTACHMENT
8. Continuation Sheet(s) – French Creek 260722 - PROVIDED VIA ATTACHMENT
9. Continuation Sheet(s) – Hadnot Point 260722 - PROVIDED VIA ATTACHMENT
10. Fire Protection J&A – PROVIDED VIA ATTACHMENT
11. PRE-PROPOSAL INQUIRY RESPONSES:
PPI #
Reference
Question Government Response Page Section Paragraph
French
Creek -
G20 Site
Improveme nts - G2010
Roadways
Part Three "B" Section G2010 states "A subsurface drainage system must be provided in all roadway areas." The Camp
Lejeune PWD Civil Design
Guidance states "No subsurface drainage system under roadways or parking
Follow Camp Lejeune PWD
Civil Design Guidance.
Subsurface drainage system has been removed, please see Continuation Sheet included in Amendment
0009.
areas". Please clarify which is applicable.
French
Creek -
Part Three
"B" -
Chapter 3 -
Supplemen t - 3.2.1.6
Dumpster
Pad and
Enclosure
Part Three "B" Section 3.2.1.6 states: "Conceal dumpsters with a decorative, gated structure in accordance with
Camp Lejeune BEAP provided in Part 6." The Camp Lejeune
PWD Civil Design Guidance states: "Ensure adequate dumpster accessibility for front loading trash trucks – no gates on enclosure." The RFP explicitly requires gates on the dumpster enclosure while the
PWD Guidance explicitly prohibits them, citing front-load trash truck accessibility
(Mack TerraPro w/40yd
Mammoth style bodies) as the operational basis for the prohibition. Please clarify whether dumpster enclosures on this project are required to include gates per Section
3.2.1.6, or whether gates are prohibited per the PWD Civil
Design Guidance. If gates are prohibited, please confirm the enclosure design should provide open access suitable for front-loading trash truck operations.
Follow the Camp Lejeune
PWD Civil Design Guidance to provide accessibility for front loading trash trucks with no gates, as well as the
Camp Lejeune BEAP requirements. Please see continuation sheet included in Amendment 0009.
French
Creek -
G20 Site
Improveme nts -
G205005
Plantings
Part Three "B" Section
G205005 specifies: "Provide 3 inches of double shredded hardwood mulch over weed control fabric at planting beds." The Camp Lejeune
PWD Civil Design Guidance states: "Use 2-5" river rock for landscape beds in lieu of hardwood mulch." These are mutually exclusive materials for the same application. The two requirements cannot be reconciled without a clear determination of which
Follow the Camp Lejeune
PWD Civil Design Guidance to provide 2-5" river rock for landscape beds in lieu of hardwood mulch. Please see continuation sheet included in Amendment 0009.
governs. Please clarify which mulch material is required for landscape beds on this project:
(a) 3 inches of double shredded hardwood mulch per
ESR G205005, or (b) 2–5 inch river rock per the PWD Civil
Design Guidance. If river rock governs, please confirm the weed barrier fabric requirement from G205005 is still applicable.
French
Creek -
G20 Site
Improveme nts -
G204090
Other Site
Improveme nts
Part Three "B" Section
G204090 - Equipment Drying
Area explicitly states that 9-guage chain link fence fabric is required. However the
BEAP Section 3.4.9 chainlink fence is prohibited. Please confirm Chainlink fence is acceptable for use per section
G204090.
No fence is required or desired for equipment drying areas. Please see continuation sheet included via Amendment 0009.
French
Creek -
General
Please provide the most current available CAD files representing existing conditions for all areas associated with the project.
This request includes, at a minimum, existing topographic information, site features, pavement limits, grading, and all available underground utility information (including utility type, size, location, and depth where available)
All available files have been shared.
Survey Please provide a copy of the
CAD Files for the
Survey/Civil scopes.
All available files have been shared.
Part 6, D.10 Camp
Lejeune
Mechanical
Design
Guidance
Part 6, D.10 Camp Lejeune
Mechanical Design Guidance
1AUG2024, item 76 notes that
DALT is to be 100% Duct Air
Leakge Test on all projects.
D.14, 23 05 93-3.1.1 notes
Confirmed 100% is required per the MCBCL Mechanical
Guidance.
1AUG2024
76.
25%. Please verify DALT is to be 100% of duct.
Part Three
"A" -
Chapter 5 -
Standard
Requireme nts Page 8
5.0 Room Requirements:
Please verify Government
Furnished Refrigerators in 2+0 rooms do not require plumbing
DW connection.
Confirmed. Refer to Part 6
D1 document with equipment information.
23 05
48.19
Please verify ATFP Bracing is only required for mechanical equipment over 31lbs hung from structure, not piping and duct distribution systems.
Confirmed, AT bracing requirement is found in UFC
4-010-01 Standard 19, Section 3-20.
23 81 00 2.3.1.10 23 81 00-2.3.1.10: PTAC Unit
Controls notes the function and temperature controls must be integral to unit. We understand this to be a built in thermostat only. If a wall mounted thermostat is desired, please clarify.
Wall mount thermostat is required.
01 59 17 Please confirm MCB Camp
Lejeune is designated as a
Large Quantity Hazardous
Waste Generator and that all hazardous waste discovered within MCB Camp Lejeune and the confines of
Government facilities will identified as being generated by the Government and that
Government will sign hazardous waste manifests.
Correct, MCB Camp
Lejeune is a Large Quantity
Hazardous Waste Generator and will sign hazardous waste manifests.
Part 3B, Ch. 6 /
ESR G20
/ Section
G201090
Other
Roadway s
1st paragraph
This section in both RFPs
(French Creek and Hadnot
Point) states "Design of fire lanes must be in accordance with the requirements of ESR
Section D4090 and must take into consideration the static and dynamic support weight of the vehicles in accordance with the latest ASHTO H20 loading requirements and by existing soil conditions." We cannot locate ESR Section
Please see Continuation
Sheet 260423 shared via
Amendment 0009.
D4090; is this an erroneous reference? With respect to pavement design, please provide the appropriate design vehicle(s) and anticipated traffic volume (number of passes over design life) to use in PCASE analysis for the fire lanes.
Part 3B, Ch. 6 /
ESR G20
/ Section
G2010
Roadway s and
G202003
Paved
Surfaces
2nd paragraph
In both RFPs (French Creek and Hadnot Point), Section
G2010 Roadways (2nd paragraph) states "The minimum PCC pavement must be 8-inch concrete surface course over 6-inch aggregate base course. The minimum bituminous concrete pavement section for regular/light-duty paving is 3” S9.5C surface course over 8” ABC base course. The minimum bituminous concrete pavement section for heavy-duty paving must be 2-inch bituminous surface course, 3-inch bituminous base course, and
12-inch aggregate subbase course". However, Section
G202003 Paved Surfaces (in both RFPs) provides slightly different minimum pavement sections - specifically, the minimum PCC pavement includes 6-inch concrete instead of 8-inch concrete and the minimum heavy duty bituminous pavement includes only 8-inch aggregate base course instead of 12-inch aggregate base course (RFP also incorrectly refers to ABC as "aggregate subbase course"). Are these differences due to the pavements being different use types (e.g. Roadway vs.
Parking Lot)? Please confirm the minimum pavement sections for both roadways and
Contractor to assume thicker sections for bidding purposes. See PPI response
#56 regarding daily traffic volumes.
parking lots. Please also provide the anticipated traffic patterns, including the design vehicles (e.g. passenger cars, pick-up trucks, fire trucks/emergency vehicles, etc.) and the anticipated daily traffic volume for each vehicle and for each pavement type
(roadway, parking lot, light duty, and heavy duty).
Part 3B, Ch. 3 /
Section
3.2.1.2
Service
Access
1st paragraph
This section in both RFPs
(French Creek and Hadnot
Point) states "Design access streets and parking areas to accommodate service vehicles and fire protection equipment.
Provide vehicular access to aerial fire apparatus..." With respect to pavement design, please provide the appropriate design vehicle(s) and anticipated traffic volume
(number of passes over design life) for both the "service vehicles" and "aerial fire apparatus" to use in PCASE analysis.
See PPI #56 response.
2 Part 3B, Ch. 6 /
ESR G10
Governm ent
Provided
Geotechn ical
Informati on
3rd paragraph
This section in both RFPs
(French Creek and Hadnot
Point) states that a geotechnical report is to be prepared including recommendations for pavement design as specified and in accordance with UFC
3-201-01, Civil Engineering.
In UFC 3-201-01, Chapter 4
Pavements, Section 4-1 (first paragraph), it states "Use pavement design criteria and procedures recognized by the
DOT in the state in which the project is located or UFC 3-
250-01. When state design criteria and procedures are used, the entire pavement section must conform in every detail to the applicable state criteria and materials must
NCDOT criteria will apply.
conform to the DOT material specifications." Please confirm the appropriate design criteria to use for pavement design on this project. Is it
UFC 3-250-01 or NCDOT
(since the project is in North
Carolina)?
Part 3A D202001
D202001-Pipe and Fittings says to provide copper tubing and fitting for above ground and buried piping. Part 6, D.10 Camp Lejeune
Mechanical Design Guidance
1AUG2024, #148, says
"Domestic water piping shall by type L copper for above ground and type K copper for below ground". Are we to abide by the Mechanical
Design Guidance since Part
3A D202001 does not specify the type of copper to be used on the domestic water system?
Confirmed, follow MCBCL
Design Guidance.
Part 3A D202003
D202003-Domestic Water
Equipment states to provide a domestic hot water storage tank in addition to the high-efficiency domestic hot water heaters. Historically, the
Camp Lejeune barracks renovations have specified the use of large storage-type domestic hot water heaters with integral storage tanks
(such as those by PVI). Will this project require the use of large integral storage type domestic hot water heaters, or is it acceptable to provide water heaters and separate hot water storage tanks?
Refer to Part 2, spec section
01 33 29, domestic water heater type to be determined through life cycle cost analysis. Refer to item #168 of MCBCL Mechanical
Design Guidance dated
1AUG2024"
Part 3A D203001
PVC piping allowed for above ground installations when provided with effective noise reduction insulation. What is effective noise reduction insulation?
Provide cast iron above grade.
Part 3A D304003
D304003-Hot Water
Distribution Systems says to
"provide insulated type "K" copper hot water supply and return piping to serve the
HVAC equipment throughout the facility. Refer to site specific guidelines in Part 6 for additional specific material requirements." Part 6, D.10
Camp Lejeune Mechanical
Design Guidance 1AUG2024, #55, says "Heating hot water piping above ground 4" and small shall by Type L copper.
Heating hot water piping above ground larger than 4" shall be Type L copper or
Schedule 40 Black steel piping." Do we abide by
D304003 in Part 3A of the
RFP and only use Type "K" copper piping, or use Type "L" copper/Schedule 40 Steel piping depending on the size per Part 6, D.10 Camp Lejeune
Mechanical Design Guidance?
Follow RFP section
D304003 requirements; type
"L" authorized per part 6.
Part 3A D304006
D304006-Chilled Water
Distribution Systems says "For exterior buried chilled water distribution systems, coordinate with Section G30, Site Civil/Mechanical
Utilities." Part 3B, G3050
Cooling Distribution, says "not used". Part 6, D.10 Camp
Lejeune Mechanical Design
Guidance 1AUG2024 #54 says
"Chilled water piping below ground shall be pre-insulated
Type K copper sticks and kits or SDR11 HDPE piping with
PVC jacket." Since there is no guidance in part 3 of the RFP, are we to abide by the Camp
Lejeune Mechanical Design
Guidance?
Follow MCBCL Mechanical
Part 3A D304006
D304006-Chilled Water
Distribution Systems says to
"provide insulated type "K" copper hot water supply and return piping to serve the
HVAC equipment throughout the facility. Refer to site specific quidelines in Part 6 for additional specific material requirements." Part 6, D.10
Camp Lejeune Mechanical
Design Guidance 1AUG2024, #54, says "Chilled water piping above ground 4" and small shall by Type L copper.
Chilled water piping above ground larger than 4" shall be
Type L copper or Schedule 40
Black steel piping." Do we abide by D304006 in Part 3A of the RFP and only use Type
"K" copper piping, or use
Type "L" copper/Schedule 40
Steel piping depending on the size per Part 6, D.10 Camp
Lejeune Mechanical Design
Guidance?
Follow MCBCL Mechanical
Part 5
Section 23
81 00
Specification Section 2.3.1.7
Cabinet Construction states that the PTAC/PTHP enclosure shall be 18 gauge steel with removable face panels, access to controls, and adjustable louvers.
Historically, the barracks renovations which utilized
PTACs have specified the installation of a full ligature-proof cover with stationary louvers to protect the unit from damage and prevent access by room occupants. Will ligature-proof covers for the
PTAC/PTHP units be required on this project?
Ligature-proof cover required.
Part 3A D3030
D3030 Cooling Generating
Systems states to provide a single air-cooled chiller utilizing a primary/secondary pumping system. This
Follow MCBCL Mechanical pumping configuration is typically used with systems utilizing multiple chillers.
Since there will only be one chiller, would it be acceptable to use a primary-only pumping system with 3-way chilled water valves and constant flow through the chiller?
Part 3A
D30
HVAC
D30 HVAC General System
Requirements state the summer design conditions for
Camp Lejeune to be
92Fdb/77Fwb (high ambient) and 88Fdb/79Fwb (high humidity). Part 6 D.10
MCBCL Mech Design
Guidance Dated Aug 2024 #15 calls for summer design conditions to be 91Fdb/77Fwb and 140 grains/lb with an 84F
MCDB. Which summer design condition should be used for sizing the cooling loads?
Design conditions must follow the most stringent of local design guidance or values stated in the RFP.
HVAC
D30 HVAC General System
Requirements state the winter design condition for Camp
Lejeune to be 27F. Part 6 D.10
MCBCL Mech Design
Guidance Dated Aug 2024 #15 calls for the winter design condition to be 26F 99% and
22F 99.6%. Which winter design condition should be used for sizing the heating load?
Design conditions must follow the most stringent of local design guidance or values stated in the RFP.
HVAC
D30 HVAC System
Description states to comply with the latest edition of
ASHRAE 62.1, Ventilation for
Acceptable Indoor Air Quality
- 2016 edition. The most current edition of ASHRAE
62.1 is 2025. Which version of ASHRAE 62.1 should be used on this project - 2016 or
2025?
Use most current edition of
ASHRAE 62.1.
HVAC
D30 HVAC makes multiple references to ASHRAE 90.1, but does not specify which version to utilize for this project. The NAVFAC High
Performance and Sustainable
Building Checklist makes reference to both ASHRAE
90.1-2013 and ASHRAE 90.1-
2016, while Section 01 91
00.15 22 Total Building
Commissioning makes reference to ASHRAE 90.1-
2019. Which version of
ASHRAE Standard 90.1 shall be used for this project?
UFC 1-200-02 version that is in effect must be followed to determine the appropriate version of ASHRAE standard 90.1. For Cherry
Point we agreed on using
90.1-2019.
Existi ng
Condi tions/
Demo lition
Attachme nt I Price
Schedule
Confirm if the existing building(s) to be demolished will have all FF&E (furniture fixtures and equipment) removed by Others prior to mobilization of the contractor.
Use most current edition of
ASHRAE 62.1.
Attachme nt H; Vol
1 of 2, Chapter
6.
Engineeri ng
Systems
Require ments
A101002
Deep
Foundation s
Part Three A Chapter 6 section
A101002 Deep Foundations states “The building and first floor slab must be entirely supported by a pile foundation system consisting of either precast pre-stressed concrete piles or auger cast piles”, will the government allow alternative foundation systems?
Alternative Foundation
Systems as determined by the Geotechnical Engineer of
Record and meeting specified performance criteria are technically acceptable.
French
Creek
Part 3B
Section
G4030
G4030 -
OSP
Pathway and
Connection
Requireme nts
RFP states: Connection Point for the Camp Lejeune French
Creek site is MH FC400-5, located on the northwest corner of Connor Street and
H.M. Smith Blvd. Will the new OSP fiber and copper cable terminate into existing splice cases in this existing manhole or will the new OSP cable extend to another connection point?
Fiber and Copper will be spliced in MH FC400-5.
Hadnot
Point
Part 3B
Section
G4031
G4030 -
OSP
Pathway and
Connection
Requireme nts
RFP states: Connection Point for Camp Lejeune Hadnot
Point (CLHP) is MH 1-4, located on the southern side of
G Street, between G Street and the existing parking lot on the northwest portion of the site.
Will the new OSP fiber and copper cable terminate into existing splice cases in this existing manhole or will the new OSP cable extend to another connection point?
Copper splice in MH 1-4
Fiber will need to be extended to MH 1-3
Part 3 A -
Chapter 6
D4020 D4020 notes Camp Lejeune and MCAS New River do not have reliable power. If a fire pump is determined to be required in a facility with unreliable primary power, an emergency backup generator must be provided for the fire pump as a secondary power sources. D509002 then notes
Camp Lejeune and MCAS
Cherry Point site do not have reliable power. PPI for
Package 1 noted the MCAS
Cherry Point and MCAS New
River have reliable power and a Secondary power for the fire pump (i.e. a generator) is not required. Please confirm
Camp Lejeune has reliable power and generator for the fire pump is not required.
Camp Lejeune and New
River do not have reliable power. Generator for fire pumps are required.
Part 5 Section 23
81 00
Specification Paragraph
2.3.1.8 Louver states "for
locations located in hurricane prone areas provide field installed louvers that are hurricane rated per AMCA
540 and AMCA 550". The standard PTAC Louver does not meet AMCA 540 nor
AMCA 550. Typically at
Lejeune these louvers are not required to be hurricane rated.
Please note that the windows are not hurricane rated. if
PENDING RESPONSE
hurricane louvers are required, the PTAC/PTHP unit would not function properly as the unit would need to be moved inward of the exterior wall thus projecting more into the room. Please confirm AMCA
540 and AMCA 550 do not apply.
Civil Part 3B -
Chapter 3 -
Supplemen t - Section
3.1.2.2
The RFP states in Section
3.1.2.2 that the site utility information is based on a
Level B Subsurface Utility
Engineering (SUE) survey and a standard topographic survey performed in December 2025 and January 2026. However, the survey data included in the
RFP documents does not provide invert elevations for the existing storm sewer structures or associated piping on or adjacent to the project site. If available, please provide the invert elevations for the existing storm drainage system so the Design-Build
Team can verify the feasibility of the proposed drainage concepts developed for pricing and better assess potential design constraints.
All available information has been provided.
Commun ications
For both Hadnot Point and
French Creek, provide existing underground Comm oneline that shows existing buildings in the area served along with
MH numbers, conduit sizes, cable types and quantities and termination locations
All available information has been provided.
Electri cal
Servic e POC
- A3-
A4
Electrical C.7 Confirm that splices of existing MV cable in manholes following demolition of building transformers is allowed as indicated in attachment C.7
Attachment C7 references
Cherry Point only. For
MCBCL, MV splices are not allowed aboard Camp
Lejeune.
Chang es -
AFTE
R
DEM
O
Electrical For both Hadnot Point and
French Creek, provide existing underground MV and LV onelines that shows existing buildings in the area served along with MH numbers, conduit sizes, cable types and quantities and termination locations.
All available information has been provided.
Landscap e
Architect ure
BEAP Drinking Fountains are mentioned in the BEAP for
Camp Lejeune under 3.4.8 Site
Furnishings. Where are these required? Are they required at shelters?
Exterior drinking fountains shall be provided at recreation shelters.
Architect ural
UFC 3-
110-03
UFC 3-110-03 paragraph D-
2.2 (General Contractor’s
Warranties [one to five years]) states the following: “Recently some government roof specifications call for a
General Contractor’s
Watertight Warranty to add another method of ensuring a quality roof installation.
Unless stated otherwise in the
Scope of Work in the RFP, all permanent new construction and replacement roofs require a Five-Year General
Contractor Bonded
Watertightness Warranty. The scope of work in the RFP may waive the Bonding requirement, but if not specified, the Bonded five-year watertightness warranty is required. The required wording of the warranty will be provided in the applicable
UFGS.” Please confirm if a five-year general contractor bonded watertightness
A five-year general contractor bonded watertightness warranty is required for this project.
warranty will or will not be required for this project.
Architect ural
D.13 - 01
91 19 -
1.6.6
Paragraph 1.6.6 in specification section 01 91 19
(Building Enclosure
Commissioning) mentions additional building enclosure tests. Please confirm if these tests will be completed by the
Owner’s Cx Agent/Team or if these will have to be subcontracted out to a third party testing agency by the
General Contractor.
Third party test is required.
Plumbing Part Three
"B" -
Chapter 3
Vapor Intrusion Mitigation system below slab is required to include a vapor barrier, stone sub base, sub-slab perforated colllection piping and plenum boxes and appropriated vertical riser vent piping per 3.2.1.21
Environmental Assessment of
Part Three "B" - Chapter 3-
Supplement Page 12. Per
3.1.1.8 the site does not have
Radon Contamination. Please confirm that a standard 20mil vapor barrier can be used w/ stone subbase without the need for perforated piping and vent stack systems noted.
The Vapor mitigation system is required because this is a residential facility and may house sensitive populations.
A standard 20mil vapor barrier is not appropriate to mitigate chemical vapor transmission.
Section 00 70 00 – Conditions of the Contract
The following clauses were added:
FAR Clauses Incorporated by Reference
Number Title Effective Date
52.211-13 Time Extension Sept 2000
The following clauses were removed:
Number Title Effective Date
52.229 - 12 Tax on Certain Foreign Procurements Feb 2021
| 0009 Cover Sheet |
| PPIs 0009 |