This is a Continuation Sheet – Modification "A" to a construction contract for FY 26 Marine Corps Barracks repair and replacement work at MCB Camp Lejeune in Jacksonville, NC. The eProjects Work Order Number is 1894552, dated 23 April 2026.
The modification revises three primary areas of the contract requirements. Under Part 2 – General Requirements, Section 01 57 19 (Temporary Environmental Controls), the surplus soils disposal language is replaced to require that all surplus soil media be anticipated as contaminant-impacted (including PFAS/PFOA, petroleum, metals, VOCs, and PAHs) and disposed of at a licensed, permitted facility accepting PFAS-impacted soil. Similarly, construction dewatering effluent requirements are updated to anticipate contaminant-impacted material that must be treated to non-detect levels prior to discharge into an approved vegetated swale, with contractor coordination required. Under Part 3B – Project Program, all references to UFC 3-600-10N are replaced with UFC 3-600-01 (Fire Protection Engineering for Facilities). Additionally, Section 2.6 (Special Design Challenges) is revised to clarify that the Government will provide a revised Section 01 91 00.15 22 Total Building Commissioning as design progresses with no additional coordination effort required from the contractor. Section G201090 (Other Roadways) is updated to reference UFC 3-600-01 requirements instead of ESR Section D4090, and the requirement for accommodation of two fire truck trips monthly is removed.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Continuation Sheet – Modification “A” eProjects Work Order Number: 1894552
Construction Contract Number: --
Building: --
Project Title: FY 26 Marine Corps Barracks – Repair by Replacement MCB Camp Lejeune – French Creek, Jacksonville, NC
Date: 23 April 2026
PART 2 – GENERAL REQUIREMENTS:
REVISE the following sections:
Section 01 57 19 TEMPORTARY ENVIRONMENTAL CONTROLS
1.5.1.1.1.2 Surplus Soils Disposal for Camp Lejeune and MCAS New River
REPLACE the following language:
Remove: “Soil should be reused on its originating construction footprint. As there are currently no regulations regarding management and disposal of PFAS-impacted soil, all PFAS-impacted media should be managed so as to minimize the future impacts to the environment, should they become regulated. If PFAS-impacted soil needs to leave the originating site…”
Replace with: “Anticipate that all surplus soil media is contaminant impacted (including but not limited to PFAS/PFOA, petroleum, metals, VOC’s, and PAH’s) and must be disposed of at a licensed, permitted facility that accepts PFAS impacted soil media. It must be properly characterized…”
3.3.1 Cofferdams, Diversions, and Dewatering
REPLACE the following language:
Remove: “All construction dewatering effluent must be anticipated to be PFAS impacted and sampled, tested, and treated to no-detect levels.”
Replace with: “Anticipate that all construction dewatering effluent is contaminant impacted (including but not limited to PFAS/PFOA, petroleum, metals, VOC’s and PAH’s) and must be treated to non-detect levels prior to discharge into an existing vegetated swale at a location approved by the Contracting Officer.”
PART 3B – PROJECT PROGRAM:
REVISE the following:
REPLACE all occurrences of ‘UFC 3-600-10N’ with UFC 3-600-01, Fire Protection Engineering for Facilities.
2.6 Special Design Challenges
Replace the first sentence of ‘Additional Building Commissioning Requirements’ with: “The Government will provide a revised Section 01 91 00.15 22 Total Building Commissioning (currently in Part 2 of this RFP) as design progresses; no additional coordination effort by the contractor is anticipated.”
G201090 OTHER ROADWAYS
Replace “…in accordance with the requirements of ESR Section D4090…” with “in accordance with the requirements of UFC 3-600-01…”
Remove “…must accommodate two fire truck trips every month and…”