This document is a Price Proposal Form for the P502 project to replace the Fuel Pier at Marine Corps Air Station Beaufort, South Carolina. The pricing form includes a base price and five option line items covering various project components such as demolition of an existing pier, prestressed concrete piles, pile load testing, fuel loading arm replacement, storage container concrete pads, and potential work shutdowns. The base price covers demolition of an existing pier, constructing a new fuel pier, realigning an approach road, and associated incidental work.
The pricing structure allows for unit pricing on specific elements like 18" square prestressed concrete piles, pile load testing, and work stoppages related to Marine Mammal Protection Act (MMPA) compliance. The government reserves the right to award optional line items within 180 calendar days after contract award, with the overall contract completion set at 900 calendar days. Pricing is firm fixed, with no provisions for economic price adjustments, and the document includes specific bid notes governing how unit prices will be applied, including detailed requirements for soil removal, work stoppages, and geotechnical assessments. The solicitation is issued by the Department of the Navy Naval Facilities Engineering Command, with the solicitation number N4008525R2522.
View the file
Other files
Show all 43
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRICE PROPOSAL FORM
Provide line item prices, where indicated by blank underlines, for the following items:
| Line Item (CLIN) |
| Description |
| Quantity |
| Unit |
| Unit Price |
| Sub-Total |
| Total Price |
| 1 |
| BASE PRICE: Total Price for the entire work for Project P502 – the demolition of an existing pier, provision of a Fuel Pier, approach road realignment, and incidental work in accordance with the drawings and specifications, complete, but excluding work provided in another Priced Line Item. |
| 1 |
| EA |
| 1A |
| Unit Price for providing 18” square prestressed concrete bearing piles with HP Stingers complete in accordance with the drawings and specifications, but excluding work provided in another Line Item. |
| 8,710 |
| LF |
| 1B |
| Unit Price for providing 18” square prestressed concrete floating platform guide piles with HP Stingers complete in accordance with the drawings and specifications, but excluding work provided in another Line Item. |
| 4 |
| EA |
| 1C |
| Unit Price for providing Dynamic Pile Load Test for the 18” square prestressed concrete bearing piles (includes re-strike), complete in accordance with the drawings and specifications, but excluding work provided in another Line Item. |
| 9 |
| EA |
| 1D |
| Unit Price for a 100% work shutdown resulting from required compliance with the Marine Mammal Protection Plan (MMPP) for all applicable waterborne construction operations. The hourly rate price includes all costs associated with work stoppage. (Each Delays will be rounded up to the next "whole" hour.) |
| 34 |
| Hour |
| 1E |
| Unit Price for Piles at 1956 Fuel Pier. For bidding purposes assume 60 feet long average per pile. Provide a unit price for pile removal to permit cost adjustment once actual pile lengths are known. |
| 7,260 |
| LF Each |
| 2 |
| Option Item No. 1: Price for providing all work in connection with the demolition of the existing Fuel Loading Arm and the provision of a Fuel Loading Arm, Controls, incidentals, and acceptance testing, complete in accordance with the drawings and specifications, but excluding work provided in another Line Item. |
| 1 |
| Lump Sum |
| 3 |
| Option Item No. 2: Price for providing all work in connection with provision of Conex Storage Container Concrete Pads, complete in accordance with the drawings and specifications, but excluding work provided in another Line Item. |
| 1 |
| Lump Sum |
| 4 |
| Option Item No. 3 Unit Price for a 100% work shutdown, not already identified in the contract, resulting from Government activities which may last more than (2) hours and less than one day for which the contractor will be required to stop work and evacuate his personnel from the job site. Hourly unit price includes all costs associated with vacating the job site. |
| 40 |
| Hour |
| 5 |
| Option Item No. 4: Unit Price for a 100% total work shutdown, not already identified in the contract, resulting from Government activities and lasting more than one day and for which the contractor will be require to stop work and completely evacuate his personnel and equipment from the job site. Daily rate price includes all costs associated with vacating the job site. |
| 10 |
| Day |
| 6 |
| Option Item No. 5: Unit Price for undercut, temporary stockpiling, and disposal of geotechnically unsuitable subgrade soils and replacement with imported structural fill material or with #57 crushed stone for the P502 Project, complete in accordance with the drawings and specifications, but excluding work provided in another Line Item. |
| 2,000 |
| CY |
1.1 GENERAL BID NOTES
a. Award will be made on the total sum of Contract Line Item (CLINs) 1. If there is a difference between a unit price and the extended total, the unit price will be held to be the intended bid and the total recomputed accordingly. If an Offeror provides a total but fails to enter a unit price, the total divided by the specified quantity will be held to be the intended unit price.
b. The Government reserves the unilateral right to award CLINs 2, 3, 4, 5, and 6 to the Contractor at the proposed price within 180 calendar days after the contract award. A firm fixed proposed price is required for CLINs 2, 3, 4, 5, and 6. No provision is made for economic price adjustment. If the Option is exercised, the contract completion date remains 900 calendar days after award of the contract.
c. The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.
1.2 CLIN BID NOTES
a. For CLIN 1D: Unit Price for only 100% work shutdown not previously identified in the contract and only related to waterborne operations associated with MMPA compliance. This pertain to only those work stoppages, during typical work day hours, in which the contractor has already begun his work but is then required by MMPA compliance to temporarily halt his operations due to that activity. The subject "Unit Priced Bid Item(s)" will require approval as directed by the Contracting Officer.
b. Requirements for the Marine Mammal Protection Act (MMPA) "observers" and for the various unit prices identified in the schedule(s) above shall be deemed to include all costs required for the specified work, complete in accordance with the specifications, including all materials, labor, equipment, tools, supervision, reporting and related items. Refer to contract documents for MMPA "observer(s)" and operational requirements.
c. For CLIN 4 and 5: Unit price for the ABOVE AND BEYOND 100% work shutdown, not previously identified in connection with Project P502 resulting from a Government Activity where the contractor is unable to shift manpower and equipment to other productive contract work. The Contractor must notify the Contracting Officer immediately of a pending shutdown if directed by any other government official so that the Contracting Officer has the opportunity to avoid or mitigate the down time, complete in accordance with drawings and specifications. The subject "Unit Priced Bid Item(s)" do not extend beyond the typical working hours of a normal business day and all will require approval as directed by the Contracting Officer.
d. For CLIN 6: Unit price for all work in connection with the removal, disposal and replacement of geotechnically unsuitable subgrade soil (i.e. soft subgrade soils) with imported structural backfill or imported #57 crushed stone as specified. Unsuitable subgrade soil determinations shall be made by the Government Geotechnical Engineer and approved by the Contracting Officer. The price shall include removal of geotechnically unsuitable soils encountered at the planned footing subgrades or identified during proofrolling of planned subgrades, disposal at the specified disposal facility, and backfilling the excavation with compacted imported structural backfill or imported aggregate. Soils that are excessively wet and soft due to lack of proper site maintenance and protection measures, and lack of specified drainage or excavation dewatering will not be considered unsuitable. Unit price shall include all handling and transportation. The volume of material removed and imported backfill required shall be neat quantities determined based on field measurements (length x width x depth) of the completed excavation to remove the unsuitable soil as approved by the Contracting Officer. Any work under this CLIN will not proceed without prior written approval of the Contracting Officer and direction of the Government Geotechnical Engineer.
File details come from the government source that posted it. Updated .