This notice announces a solicitation for design-build construction services under solicitation number N4008519R9252 to replace several facilities damaged by Hurricane Florence at Marine Corps Base Camp Lejeune in North Carolina. The work includes construction of new headquarters buildings, battalion facilities, and a Marine Expeditionary Unit building. The total value is estimated between $100-250 million. The completion deadline is 1,826 calendar days from award. The solicitation will utilize a two-phase evaluation including technical, past performance and price factors, with technical factors being most important. Phase one will evaluate technical approach, experience and past performance, while phase two will cover safety, technical solution, project management, and small business utilization along with price. The solicitation is unrestricted and targeted for July 2020 award. Market research determined no reasonable expectation of adequate small business response. Drawings and specifications will be provided with phase two.
Amendment 0003
View the file
Other files
Show 40 more
Latest 50 of 62 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
N40085-19-R-9254 DESIGN-BUILD (DB) HURRICANE FLORENCE RECOVERY MILCON PACKAGE 4, HURRICANE FLORENCE RECOVERY
BRIDGES AT MARINE CORPS BASE (MCB) CAMP LEJEUNE, NORTH CAROLINA
The purpose of this amendment is to provide responses to PPIs and provide updates to RFP Section 00 21 16. See SF 30 Block 14 Continuation Page.
The proposal due date of 08 November 2019 remains unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 29-Oct-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008519R9254
X 9B. DATED (SEE ITEM 11)
09-Oct-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Oct-2019
CODE
NAVFAC MID ATLANTIC
ACQUISITION CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008519R9254
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0003
1. Provides PPI responses 1-45.
2. Revises the following in the RFP, Section 00 21 16 - Instructions to Proposers, 3. Evaluation
Factors for Award:
- 3. Basis of Evaluation and Submittal Requirements for Each Factor, B. Non-Price Factors, Changes Proposal copies from eight to nine and font size from 12pt to 10pt
- Factor 1 – Technical Approach, (i) Solicitation Submittal Requirements: (3) Adds language for
Bonding Capacity Requirements
- Factor 2 – Experience, (a) Solicitation Submittal Requirements, (2) Design Experience, Adds language for DOR: Within the five projects, the minimum experience requirement for the factor shall be met by the proposed DOR(s). However, design subcontractors’ projects may also be submitted within the five project maximum but must also meet the size, scope and complexity requirements.
- Factor 2 – Experience, (b) Basis of Evaluation, Removed additional consideration for: Relevant projects that demonstrate experience with construction sequencing to allow rail operations to remain in service periodically may be considered more favorably than those that do not.
- Factor 3 Past Performance, Changes language to read regarding PPQ submittals: Offerors are permitted to submit copies of previously completed PPQs. However, Offerors shall not incorporate previously submitted PPQs submitted for other RFPs by reference into their proposal;
but this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.
- Factor 5 Project Management Approach, (a) Solicitation Submittal Requirements, (2) Maintaining Rail Operations, Removed language: while periodically maintaining rail operations.
- Factor 5 Project Management Approach, (a) Solicitation Submittal Requirements, (4) Schedule, Changed language to say structures instead of building.
- Factor 5 Project Management Approach, Basis of Evaluation, (4) Schedule, Revises language from “within 1,461 days” to read “A schedule that phases individual building completion dates within the package so the Government can take beneficial occupancy earlier than the 1,461 days overall completion date may be considered more favorably.
(End of Summary of Changes)
Page Section Para.
1 10/11/2019 7 3
What is the anticipated date of the announcement of the shortlisted teams for Solicitation #N4008519R9254 (Camp Lejeune Hurricane Recovery MILCON Package 4)? Phase II will be issued via amendment. As included in the Hurricane Florence Industry Day Brief, Phase 2 is anticipated to be issued February 2020 and responses are anticipated to be due in April 2020.
The government intends to allow approximately 60 days for the Phase II Non‐Price Proposal and to allow approximatley 20 additional days for the Phase II Price Proposal. The Government has not yet determined if the list of Offerors invited to participate in Phase II will be announced. If the list is announced, it will be announced in the solicitation Amendment issuing Phase II.
2 10/11/2019 7 3
What is the anticipated release date of the Phase 2 documents to the shortlisted teams for Solicitation #N4008519R9254 (Camp Lejeune Hurricane Recovery MILCON Package 4)?
Phase II will be issued via amendment. As included in the Hurricane Florence Industry Day Brief, Phase 2 is anticipated to be issued February 2020 and responses are anticipated to be due in April 2020.
The government intends to allow approximately 60 days for the Phase II Non‐Price Proposal and to allow approximatley 20 additional days for the Phase II Price Proposal.
Question No. Date Received
REFERENCE
QUESTION GOVERNMENT RESPONSE
Posted on Amend No.
3 10/11/2019
What is the anticipated due date of the Phase 2 proposals for the shortlisted teams for Solicitation #N4008519R9254 (Camp Lejeune Hurricane Recovery MILCON Package 4)?
Phase II will be issued via amendment. As included in the Hurricane Florence Industry Day Brief, Phase 2 is anticipated to be issued February 2020 and responses are anticipated to be due in April 2020.
The government intends to allow approximately 60 days for the Phase II Non‐Price Proposal and to allow approximatley 20 additional days for the Phase II Price Proposal.
4 10/11/2019
Could NAVFAC Mid Atlantic provide the correct document for Attachment C ‐ Construction Design Experience Project Data for Solicitation #N4008519R9254 (Camp Lejeune Hurricane Recovery MILCON Package 4)? It appears on the FBO.gov site that Attachement F ‐ PPQ was uploaded to the Attachment C link.
The correct attachment has been provided as part of Amendment 0001
5 10/11/2019 7 3.1 4
This paragraph (and other sections of the Solicitation document) appear to indicate that there is a Phase I and Phase II proposal which are intended to be separate documents submitted on different submittal dates. For example, this paragraph states that only the most highly qualified offerors based on the Phase I proposal will be requested to submit Phase II proposals.
Therefore, we assume that the offer is only supposed to submit responses to non‐price Factors 1, 2 and 3 in the Phase I proposal on November 8, 2019 and that Factors 4, 5 and 6 along with the price proposal will be submitted at a later date in the Phase II proposal.
Please confirm and clarify the content expected in the proposal due November 8, 2019.
Offerors shall provide proposals in accordance with the RFP for Factors 1, 2, and 3 in the Phase 1 proposal due November 8, 2019 at 2:00pm local time.
6 10/15/2019
Please clarify if the future White Oak River trestle is to be built on the same alignment as the current bridge. The government intends to provide information addressing this question in the Amendment issuing the Phase II RFP Package.
7 10/15/2019
Please clarify if the future White Oak River trestle is to be built to take into account future flood design elevations.
The government intends to provide information addressing this question in the Amendment issuing the Phase II RFP Package.
8 10/15/2019 Page
Please clarify if a design‐build project delivered by the Contractor and Designer, as a team, will receive both maximum Construction and Design Factor 2 and Factor 3 scoring if only submitted under the Construction section, or vice versa?
In accordance with the RFP: "If the same project is being used to demonstrate construction and design experience, submit separate Project Data Sheets for construction and design. The Government reserves the right not to consider a project submitted for both construction and design experience on a single Project Data Sheet."
9 10/15/2019 18
The Proposal Submission Requirements on page 18 of 55 require submittal of the SECNAV 5512 (Attachment B) no less than 20 business days prior to the proposal due date. Based on the advertisement date this requirement could not be met. We request NAVFAC establish a time that Proposers could meet outside the gate to hand deliver proposals. This has been used on recent NAVFAC bids and has worked well.
Submit Attachment B as soon as possible.
10 10/16/2019 10 of 54; 12 of 54
Page 10:
Para: 2;
Page 12, Para: 3
“On page 10 of 55 it states that “If the Offeror is proposing to utilize multiple Designers of Records (DOR) (i.e. one DOR for each Project), clearly state which DOR will be designing each Project.” On Page 12 of 55 of the solicitation, it states “The Offeror may utilize experience of a design subcontractor to demonstrate design experience under this evaluation factor. The Offer must provide a supporting joint venture agreement, partnership agreement, teaming agreement, or letter of commitment and an explanation of the meaningful involvement for the design subcontractor. Offerors proposing multiple design firms should submit relevant project experience for all design firms. Failure to do so may result in a lower rating.” Is it the intent that only relevant project experience for design firms that will serve as the designer of record is required?
See Amendment 0003. 3
11 10/18/2019 10 of
3.2.b.(1 Factor 1, (i), (1)
Please confirm that the “Contractor team arrangement”, defined by FAR Subpart 9.6 as two or more companies form a partnership or joint venture to act as a potential prime contractor, does not need to be registered with the System for Award Management (SAM) prior to the Phase 1 submission, as long as the individual firms comprising the offeror are registered in SAM and a signed agreement between the parties is submitted with the Phase 1 submission?
Confirmed. 3
12 10/22/2019
Text within Attachments C and F have a 10‐point font size. Though the RFP lists that font sizes employed in our submission should be no less than 12‐point, can we insert information matching the style of the content within forms? i.e. 10‐point font? Please advise.
The minimum font size requirement for the Phase 1 proposal is reduced to 10 point.
13 10/22/2019
Please confirm that if multiple Designer of Records are being proposed for each bridge, that each of these proposed Design Subcontractors do not have to contract directly to the Offeror and this arrangement can be supported by either a Teaming Agreement or Letter of Commitment between the Design Subcontractors.
In accordance with Factor 1, "the offeror shall submit a signed copy of a joint venture agreement, partnership agreement, teaming agreement, approved mentor protégé agreement (MPA), or letter of commitment for each member of the offeror’s team identified above (e.g., joint venture member, partner, team member, subcontractor, parent company, subsidiary, or other affiliated company, etc.). If providing a letter of commitment, the letter shall be from the proposed DOR on the DOR’s letterhead and addressed to the Offeror."
14 10/22/2019
Is form SF1442 required at the Phase I or Phase II submission?
SF1442 is required with the Phase II Price Proposal, though Offerors need to provide sufficient identification with their Phase I proposal to allow the Government to know who is proposing.
15 10/22/2019 10 Fac.2 1&2
Might the Government consider expanding the bascule bridge experience to the last 20 years rather than the last 10 years? (For construction only.)
Bid per the RFP 3
16 10/22/2019 13 F3 i
“Offerors are highly encouraged to address any adverse past performance issues. Explanations shall not exceed two (2) double‐sided pages (or four (4) single‐sided pages) in total. Information provided beyond this page limit will not be considered.”
Is this 4 pages total for all 10 projects, or per project?
If 4 pages total, may we change that to 5 pages where there would be approximately one‐half page per project?
The page limit is total, for all projects needing explanations. The page limitation of two (2) double‐sided pages (or four (4) single‐sided pages) will not be revised.
17 10/22/2019 9 3.2 2.b.1 Is it acceptable to use font smaller than 12 pt for graphics and tables?
Yes, this is acceptable as long as the chosen font and type size is legible.
18 10/22/2019 10 F2, a 1
Is Factor 2 weighted more heavily if 5 projects are submitted, or does 3 relevant projects gain the same grade as 5?
Please see the Basis for Award for weighting information for each factor.
With respect to Factor 2, Experience, please refer to the Basis of Evaluation which provides that the evaluation "will include the Offeror's demonstrated experience and depth of experience in performing relevant construction and design projects as defined in the solicitation submittal requirements." The Government will evaluate each Offeror's response in accordance with the language set forth in the RFP.
19 10/23/2019 N/A N/A N/A
Please provide a definition of “Design to Budget”.
Please clarify if the intent is (A) Fixed price specified by the Government where the Offeror will fill out the bid form with 100% of the Design to Budget for each MILCON or (B) the Design to Budget is a Not To Exceed amount for each MILCON and the expectation is the Offeror is to evaluate the scope of each MILCON and provide a firm fixed price equal to or less than the Design to Budget for each MILCON. Please Note: If Option B is selected, a minimum 90-day response time will be required for Phase II and a hefty stipend provided for Phase II respondents.
For this solicitiaton, NAVFAC is using the term "Design to Budget" to mean the amount of funds that are available for construction of the specific project. The expectation for the Price Proposal in Phase II is that the offeror will evaluate the scope and provide a separate price for each of the projects within the package as a firm fixed price. Also, the Design to Budget is not a Not To Exceed amount but rather is provided for information on the Government's expectations of the scope concerning both cost and quality.
20 10/23/2019 N/A N/A N/A
Please provide the “Design To Budgets” in phase 1 for each MILCON with basic parameters so teams can make a determination if budgets are adequate before expending efforts for Phase 1.
For this solicitiaton, NAVFAC is using the term "Design to Budget" to mean the amount of funds that are available for construction of the specific project. The expectation for the Price Proposal in Phase II is that the offeror will evaluate the scope and provide a separate price for each of the projects within the package as a firm fixed price. Also, the Design to Budget is not a Not To Exceed amount but rather is provided for information on the Government's expectations of the scope concerning both cost and quality.
21 10/23/2019 N/A N/A N/A
Please explain what information will be provided in Phase II as part of the AE1 RFP Packages. Will bridging design level information be provided with programmatic drawings or will only narratives be provided?
The Phase 2 RFP will include as‐builts, geotechnical information, bathymetric survey, and site survey.
Drawings with a minimal amount of design information will also be provided.
22 10/23/2019 N/A N/A N/A
Will individual contracts be awarded for each MILCON? In accordance with The RFP, Section
00 21 16, INSTRUCTIONS TO
OFFERORS, 1.2 GENERAL OVERVIEW
OF THE CONTRACT: "TThe general intent of this solicitation is to award a Fixed Price construction contract for design‐build (DB) projects in Package 4, Hurricane Florence Recovery Bridges at MCB Camp Lejeune." The intent is to award one contract that includes all Projects.
23 10/23/2019 N/A N/A N/A Please clarify if a Stipend will be provided to Phase II responsive firms. If so, please provide the amount. At this time, stipends will not be provided.
24 10/23/2019 N/A N/A N/A
Please provide the anticipated Phase II RFP response period.
Phase II will be issued via amendment. As included in the Hurricane Florence Industry Day Brief, Phase 2 is anticipated to be issued February 2020 and responses are anticipated to be due in April 2020.
The government intends to allow approximately 60 days for the Phase II Non‐Price Proposal and to allow approximatley 20 additional days for the Phase II Price Proposal.
25 10/23/2019 Fac. 2
Factor 2 – Experience for both construction (page 10) and design (page 11) states: “Renovation projects will not be considered relevant.” However, the Basis of Evaluation criteria on page 12 states: “Relevant projects that demonstrate experience with construction sequencing to allow rail operations to remain in service periodically may be considered more favorably that those that do not.” In our experience, rail operations projects that involve “sequencing to allow rail operations to remain in service” are predominately rehabilitation projects, such as an existing rail system that is having its substructure rebuilt while remaining in operation, which is technically classified as renovation.
Would the government consider renovation projects to be acceptable/relevant in situations that clearly demonstrate experience in achieving the goal of allowing rail operations to remain in service?
Bid per the RFP. 3
26 10/23/2019 Gener al
Please provide the intended date and/or timeframe for the development and submission of the Phase II requirements? Phase II will be issued via amendment. As included in the Hurricane Florence Industry Day Brief, Phase 2 is anticipated to be issued February 2020 and responses are anticipated to be due in April 2020.
The government intends to allow approximately 60 days for the Phase II Non‐Price Proposal and to allow approximatley 20 additional days for the Phase II Price Proposal.
27 10/23/2019 Pages 15‐16
Pages 15‐16/55 both refer to “building construction” – are there associated “building facilities” within the scope of work for P‐1387F Onslow Beach Bridge and/or P1505 F Railroad Trestle Replacement? If so, please provide updated scope descriptions.
See Amendment 0003. 3
28 10/23/2019 Page
Please clarify the statement … “a Schedule that phases individual building completion dates within the package so that the government can take beneficial occupancy within 1461 days overall completion date may be considered “more favorably”. Would a shorter schedule be even “more favorable” or is the government seeking a four year completion time frame?
See Amendment 0003. 3
29 10/23/2019 Page
What is the anticipated length of time from Award of Contract (AOC) to Notice‐to‐Proceed (NTP)?
Recommend that the schedule run be based on number of days from NTP rather than AOC.
I would assume the 1,461 days does not include weather days or holidays?
The Award of Contract shall be considered the Notice to Proceed.
Additionally, the awardee will received a Notice of Award letter on the date the contract is awarded stating that it shall be considered the Notice to Proceed. A separate Notice to Proceed will not be issued. 1,461 is calendar days, and therefore include holidays and weather days.
30 10/23/2019 Page
PHASED CONSTRUCTION SCHEDULE
a.Schedule start day: The day designated as the beginning of a particular phase; the number listed is the number of calendar days from the award of contract.
b.Comple on day: The day designated as the end of a given phase and the day the work in that phase must be completed; the number listed is the number of calendar days from the award of the contract.
The sections shown above refer to “number of calendar days from the “award of contract” yet work cannot begin until receipt of “notice to proceed” as noted in
52.211.10. Recommend that the schedule run be based
on number of days from NTP rather than AOC.
The Award of Contract shall be considered the Notice to Proceed.
Additionally, the awardee will received a Notice of Award letter on the date the contract is awarded stating that it shall be considered the Notice to Proceed. A separate Notice to Proceed will not be issued. 1,461 is calendar days, and therefore include holidays and weather days.
31 10/23/2019
Railro ad
Trestl e
Should the trestle replacement be an open or ballast deck?
It is the Government's intent to address this question in the Amendment that issues Phase II RFP Package.
32 10/23/2019
Railro ad
Trestl e
Is there a preference of track tie material, i.e. timber or concrete ties?
It is the Government's intent to address this question in the Amendment that issues Phase II RFP Package.
33 10/23/2019
Railro ad
Trestl e
What is the required railroad trestle loading? Standard Cooper E80?
Yes, standard Cooper E80. 3
34 10/23/2019
Railro ad
Trestl e
There is an emphasis in the solicitation to “periodically maintaining rail operations” of the existing trestle.
What is the allowable outage of service?
See Amendment 0003. 3
35 10/23/2019
Railro ad
Trestl e
Will preliminary geotechnical exploration data be available prior to bid?
Yes, prior to the Phase II proposal due date.
36 10/23/2019
Onslo w
Beach Bridge
Are there any hazardous materials in or on the existing swing span that need special consideration during demolition, i.e. lead paint, asbestos, etc.?
It is the Government's intent to address this question in the Amendment that issues Phase II RFP Package.
37 10/23/2019
Onslo w
Beach Bridge
Are there allowable laydown areas adjacent to the project?
It is the Government's intent to address this question in the Amendment that issues Phase II RFP Package.
38 10/23/2019
Onslo w
Beach Bridge
Will the Design/Build Team be responsible for operation and maintenance of the existing swing span during construction of the replacement?
No. 3
39 10/23/2019 Gener al
Is a geotechnical subcontractor considered a “significant design subcontractor”?
In accordance with Factor 1, "If the experience of a significant design subcontractor(s) is being claimed in Factor 2 ‐ Experience, the firm must be included in the above narrative and organizational chart."
40 10/25/2019 10 of
3.2.b.(1
Factor 2, (a), (1)
3rd paragraph in section / Last paragraph on the page
Will NAVFAC consider accepting the experience of a dedicated subcontractor, with relevant specialty experience, if a dedicated subcontractor agreement is included with the proposal? If so, will NAVFAC allow one or two of the five relevant projects to be submitted from said dedicated subcontractor?
Bid per the RFP 3
41 10/25/2019
Is it acceptable to include a lead‐in page to the Factor 2 Experience section in addition to the Attachment C forms?
In accordance with the solicitation, Factor 2, "The attached Construction & Design Experience Project Data Sheet (Attachment C) is MANDATORY and SHALL be used to submit project information... Except as specifically requested, the Government will not consider information submitted in addition to this form nor will the Government consider information submitted via any other medium.
Individual blocks on this form may be expanded; however, total length for each project data sheet shall not exceed one (1) double‐sided page (or two (2) single‐sided pages). The Government will not consider information submitted beyond this page limit." A lead‐in page will not be considered as part of the evaluation for Factor 2.
43 10/25/2019
What construction phase services will be included in the design‐builder’s scope of services, and what services will be provided by the owner?
The government needs more information from the offeror in order to answer this question.
44 10/25/2019 Has there been any work to date on the navigation channel that relates to vessel impact design for the bascule bridge?
No. 3
45 10/25/2019
Are there any utility relocation requirements that are specialized, given the nature of the Camp LeJuene site?
It is the Government's intent to address this question in the Amendment that issues Phase II RFP Package.