This document contains a contractor price breakdown spreadsheet with line item estimates for repair and overhaul work on the USNS Mercy (T-AH 19). The spreadsheet includes over 50 separate work items grouped under categories such as physical security, motor overhauls, piping replacement, and insulation repair. Labor and material costs are listed for each item, though all prices are currently blank. The related solicitation seeks bids for repair, overhaul, and drydocking of the USNS Mercy to be conducted by the Department of the Navy Military Sealift Command. Offerors are asked to submit a signed non-disclosure agreement to receive associated drawings and work item details.

View the file

Other files for this federal contract opportunity

Other files attached to USNS MERCY ROH/DD, newest first.
File Type Posted
Amendment 9 USNS MERCY.docx DOCX document
J-2 Category A ROH.xlsx XLSX spreadsheet
J-2 Category A Item Pier Side Availability.xlsx XLSX spreadsheet
J-3 Category B Pier Side Availability.xlsx XLSX spreadsheet
J-3 Category B ROH.xlsx XLSX spreadsheet
Amendment 7.docx DOCX document
Revised J-2 Category A Item.xlsx XLSX spreadsheet
Amendment 5.docx DOCX document
024 Axial Fan Material Requirements.docx DOCX document
021 0101 Tk Vent Vlv Scope2.docx DOCX document
023 Extension Request3.docx DOCX document
026 WI 709 Missing Ref.docx DOCX document
020 NAG Marine Software.docx DOCX document
AMENDMENT 4.docx DOCX document
022 1001 Ceiling panel size.docx DOCX document
025 Nag Material Request.docx DOCX document
Copy of J-3 Category B Items.xlsx XLSX spreadsheet
RFCs 013 through 019.docx DOCX document
009 Extension Request.docx DOCX document
004 0102 Anti Roll Tk Ref and Scope - Response.docx DOCX document
007 0105 WT Door size and detail - Response.docx DOCX document
005 0103 Ladders Rails scope - Response.docx DOCX document
003 0101 Tk Vent Ref Scope - Response.docx DOCX document
011 Missing TMs - Response.docx DOCX document
010 Ballast System Valve Actuator Repair - Response.docx DOCX document
008 Missing DWGs & TMs.docx DOCX document
AMENDMENT #1.docx DOCX document
J-2 Category A Item Revised.xlsx XLSX spreadsheet
Q&A #1.docx DOCX document
Q&A #2.docx DOCX document
DD Form 1423-1 SWI-011 General Services for Ship.pdf PDF
DD Form 1423-1 SWI-023 Hazardous Waste.pdf PDF
J&A USNS MERCY N3220520R6500 Redacted.pdf PDF
DD Form 1423-1 SWI-021 Clean and Gas Free Tanks.pdf PDF
J-8 Request for Spec Clarification.docx DOCX document
J-15 Non-Mariner Maintenance Contractor Vetting Sheet (Rev 8 (v4) 20 Sep 2017).xlsx XLSX spreadsheet
J-5 Subcontracting Plan.docx DOCX document
DD Form 1423-1 SWI-013 Project Planning.pdf PDF
DD Form 1423-1 SWI-004 Testing Quality Assurance.pdf PDF
DD Form 1423-1 SWI-018 Delivery and Redelivery.pdf PDF
DD Form 1423-1 SWI-020 Gas Free Certificates.pdf PDF
DD Form 1423-1 SWI-016 Fire Protection.pdf PDF
J-10 Interport Differential.docx DOCX document
DD Form 1423-1 SWI-017 Ships Stores.pdf PDF
J-7 MSC Ship Repair Facility Survey.docx DOCX document
DD Form 1423-1 SWI-003 Approach - Berth - Mooring.pdf PDF
J-12 Past Performance Data.docx DOCX document
J-13 Past Performance Questionnaire.docx DOCX document
DD Form 1423-1 SWI-022 Machinery Turnover, Dock and Sea Trials.pdf PDF
J-4 GFP Report.xlsx XLSX spreadsheet
Show all 50

USNS MERCY ROH/DD has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cat B Items

GENERAL REQUIREMENTQTYUIUnit PriceTotalPRIME ContractorSUBCONTRACTOROTHER COSTS
ITEM NO.TITLE CAT B ITEMPRIME L/HLABOR PRICEMATERIAL PRICESUB L/HLABOR PRICEMATERIAL PRICETotal Labor HoursTotal MaterialTOTAL PRICE
25COST TO ESTABLISH AND MAINTAIN PHYSICAL SECURITY AT PRIVATE CONTRACTOR'S FACILITY IN FORCE PROTECTION CONDITION CHARLIE AND DELTA
7.1COST TO ESTABLISH PHYSICAL SECURITY AT PRIVATE CONTRACTOR'S FACILITY FROM BRAVO to FORCE PROTECTION CONDITION CHARLIE1Days$ - 0$ - 0
7.1COST TO ESTABLISH PHYSICAL SECURITY AT PRIVATE CONTRACTOR'S FACILITY FROM CHARLIE to FORCE PROTECTION CONDITION DELTA1Days$ - 0$ - 0
7.1COST TO MAINTAIN PHYSICAL SECURITY AT PRIVATE CONTRACTOR'S FACILITY IN FORCE PROTECTION CONDITION CHARLIE10Days$ - 0$ - 0
7.1COST TO MAINTAIN PHYSICAL SECURITY AT PRIVATE CONTRACTOR'S FACILITY IN FORCE PROTECTION CONDITION DELTA10Days$ - 0$ - 0
WI 025 SUBTOTAL$ - 0
030CONTINUATION OF SERVICES
7.1Overhaul Management Team30Days$ - 0$ - 0
7.2General Services For The Ship30Days$ - 0$ - 0
7.3Telephone Services30Days$ - 0$ - 0
7.4Project Planning and Monitoring30Days$ - 0$ - 0
7.5Fire Protection and Ship's Safety30Days$ - 0$ - 0
7.6Shipboard Access and Security30Days$ - 0$ - 0
7.7Gas Free Certificates30Days$ - 0$ - 0
WI 030 SUBTOTAL$ - 0
197Distilling Plant Deck and Foundation Steel Replacement
Paint Sample10LOT OF 10 EACH$ - 0$ - 0$ - 0$ - 0
Overhead surfaces125SQ FT$ - 0$ - 0$ - 0$ - 0
Horizontal surfaces125SQ FT$ - 0$ - 0$ - 0$ - 0
Vertical surfaces125SQ FT$ - 0$ - 0$ - 0$ - 0
Piping of various sizes125SQ FT$ - 0$ - 0$ - 0$ - 0
WI 0102 SUBTOTAL$ - 0
198Hull Gauging
Ultrasonic Thickness Gauging50LOT OF 100 EACH$ - 0$ - 0
WI 198 SUBTOTAL$ - 0
199MISC Steel Renewal
Misc Plate, Bulkheads and decks1,000Pounds$ - 0$ - 0$ - 0$ - 0
Shell or Rudder Plating1,000Pounds$ - 0$ - 0$ - 0$ - 0
Shell or Rudder Plating, Shaped1,000Pounds$ - 0$ - 0$ - 0$ - 0
Tank Bulkhead500Pounds$ - 0$ - 0$ - 0$ - 0
Tank Internals500Pounds$ - 0$ - 0$ - 0$ - 0
Shell Plate Framing800Pounds$ - 0$ - 0$ - 0$ - 0
Tank Top in Machinery Spaces800Pounds$ - 0$ - 0$ - 0$ - 0
Machinery Foundations in Machinery Spaces500Pounds$ - 0$ - 0$ - 0$ - 0
Floors and intercostals in double bottom tanks500Pounds$ - 0$ - 0$ - 0$ - 0
Double bottom stiffeners and bulkheads500Pounds$ - 0$ - 0$ - 0$ - 0
Machinery Foundations on Deck600Pounds$ - 0$ - 0$ - 0$ - 0
WI 199 SUBTOTAL$ - 0
399MISC Motor Overhauls
2.2.1Motor OverhaUls Paragraph 7.3-7.9.2
2—7 horsepower2EA$ - 0$ - 0
8—15 horsepower4EA$ - 0$ - 0
16—25 horsepower4EA$ - 0$ - 0
26—40 horsepower4EA$ - 0$ - 0
41—60 horsepower4EA$ - 0$ - 0
75—100 horsepower4EA$ - 0$ - 0
2.2.1Motor Rewind Paragraph 7.4.4.1-7.4.4.14
2—7 horsepower2EA$ - 0$ - 0
8—15 horsepower4EA$ - 0$ - 0
16—25 horsepower4EA$ - 0$ - 0
26—40 horsepower4EA$ - 0$ - 0
41—60 horsepower4EA$ - 0$ - 0
75—100 horsepower4EA$ - 0$ - 0
WI 399 SUBTOTAL$ - 0
597Plumbing Drain Piping Replacement
2.2.1Pipe, Steel Schedule 40, seamless, ASTM A-53 Grade B Galvanized
1.5 IPS200Linear FT$ - 0$ - 0
2 IPS200Linear FT$ - 0$ - 0
2.5 IPS200Linear FT$ - 0$ - 0
3 IPS200Linear FT$ - 0$ - 0
4 IPS200Linear FT$ - 0$ - 0
6 IPS200Linear FT$ - 0$ - 0
2.2.1Fitting: Elbow, Flange, Tee, etc. Steel, Schedule 40, seamless ASTM A-53 Grade B Galvanized
1.5 IPS20Units$ - 0$ - 0
2 IPS20Units$ - 0$ - 0
2.5 IPS20Units$ - 0$ - 0
3 IPS20Units$ - 0$ - 0
4 IPS20Units$ - 0$ - 0
6 IPS20Units$ - 0$ - 0
WI 597 SUBTOTAL$ - 0
598Sewage System 3-Way Valve Refurbishment
2.2.13-Way Valve Overhaul/ para 7.1 – 7.7
3 inch 3-way plug valve6EA$ - 0$ - 0
4 inch 3-way plug valve6EA$ - 0$ - 0
6 inch 3-way plug valve6EA$ - 0$ - 0
WI 598 SUBTOTAL$ - 0
599MISC Piping Renewal
2.2.1Pipe, Steel Schedule 40
2 IPS150Linear FT$ - 0$ - 0
3 IPS150Linear FT$ - 0$ - 0
4 IPS150Linear FT$ - 0$ - 0
6 IPS150Linear FT$ - 0$ - 0
Fitting: Elbow, Flange, Tee, etc. Steel
2 IPS40EA$ - 0$ - 0
3 IPS40EA$ - 0$ - 0
4 IPS20EA$ - 0$ - 0
6 IPS20EA$ - 0$ - 0
Pipe, 90-10 Cu-Ni Class 200
2 IPS150Linear FT$ - 0$ - 0
3 IPS150Linear FT$ - 0$ - 0
4 IPS150Linear FT$ - 0$ - 0
6 IPS150Linear FT$ - 0$ - 0
Fitting: Elbow, Flange, Tee etc. 90-10 Cu-Ni Class 200
2 IPS40EA$ - 0$ - 0
3 IPS40EA$ - 0$ - 0
4 IPS20EA$ - 0$ - 0
6 IPS20EA$ - 0$ - 0
WI 599 SUBTOTAL$ - 0
899Insulation and Lagging Repair
2.2.1Pipe Lagging Steam or Chilled
1-½IPS50Linear FT$ - 0$ - 0
2 IPS50Linear FT$ - 0$ - 0
2-½IPS50Linear FT$ - 0$ - 0
3 IPS20Linear FT$ - 0$ - 0
4 Inch IPS20Linear FT$ - 0$ - 0
6 Inch IPS20Linear FT$ - 0$ - 0
8 Inch IPS20Linear FT$ - 0$ - 0
10 Inch IPS20Linear FT$ - 0$ - 0
Valve Blankets Steam or Chilled
2 Inch Valve51 Blanket$ - 0$ - 0
3 Inch Valve51 Blanket$ - 0$ - 0
4 Inch Valve51 Blanket$ - 0$ - 0
6 Inch Valve51 Blanket$ - 0$ - 0
8 Inch Valve51 Blanket$ - 0$ - 0
10 Inch Valve21 Blanket$ - 0$ - 0
Insulation Bulkhead
1 Inch thick fiberglass, cloth backed50Sq ft$ - 0$ - 0
2 Inch thick fiberglass, cloth backed50Sq ft$ - 0$ - 0
3 Inch thick fiberglass, cloth backed300Sq ft$ - 0$ - 0
4 Inch thick fiberglass, cloth backed20Sq ft$ - 0$ - 0
Vent Duct* Insulation
Round and Oval1,000Sq ft$ - 0$ - 0
Square and Rectangular1,000Sq ft$ - 0$ - 0
Generator Exhaust Insulation
Calcium Silicate up to 4.5” thickness150Sq ft$ - 0$ - 0
WI 899 SUBTOTAL$ - 0
903Tailshaft Inspection ABS 15 YR
Tailshaft Inspection ABS 15 YR1EA$ - 0$ - 0$ - 0$ - 0
WI 903 SUBTOTAL$ - 0
967Shaft Alignment and Bearing Reaction Checks Sets
Shaft Alignment and Bearing Reaction Checks1EA$ - 0$ - 0$ - 0$ - 0
WI 967 SUBTOTAL$ - 0
968SHAFT ALIGNMENT AND BEARING REACTION CHECKS (POST )
Shaft Alignment and Bearing Reaction Checks Post1EA$ - 0$ - 0$ - 0$ - 0
WI 968 SUBTOTAL$ - 0
999Extension on Dry Dock
Extension on Dry Dock10Days$ - 0$ - 0
WI 968 SUBTOTAL$ - 0

TOTAL J-3 CATEGORY B WORK ITEMS $ - 0

&14USNS MERCY (T-AH 19)&14CONTRACTOR PRICE BREAKDOWN
&"Arial,Bold"CATEGORY "B" ITEMS&14N3220520R6500
&14USNS MERCY (T-AH 19)&14CONTRACTOR PRICE BREAKDOWN
&"Arial,Bold"CATEGORY "B" ITEMS&14N3220520R6500

ATTACHMENT J-3

ATTACHMENT J-3

File details come from the government source that posted it. Updated .