About this file

This document is Amendment 02 to a Request for Proposal (RFP) for the Kautz Road Substation E-Control House, issued by FFDG. The RFP seeks a prefabricated building with specified contents, to be placed, assembled, and tested on site foundations by September 30, 2027. Key technical requirements include arc fault rated equipment, with ABB and Siemens as the only acceptable circuit breaker manufacturers. The scope covers the prefabricated building and its contents, with foundations and site preparation to be handled by others.

The amendment includes responses to nine prospective offeror questions, clarifying project details such as no bond or labor/wage requirements, and confirming the RFP is exclusively for the prefabricated building and its equipment. A site visit is scheduled for September 24, 2025, at 10:30am CT, with interested parties directed to review the Fermilab Site Map and Business Visitor Registration Instructions. The RFP does not provide a cost estimate, and potential vendors are limited in equipment manufacturer options and enclosure specifications.

View the file

Other files

File Type Posted
Amend 05 to RFP KRS-369604-JK.pdf PDF
Hollow Metal Door - Rated Hardware Schedule.pdf PDF
Card Reader Details.pdf PDF
MC3.pdf PDF
E-339.pdf PDF
E-338.pdf PDF
E-3.pdf PDF
2025 - Security and Access Control r2.docx DOCX document
MC2.pdf PDF
E-337.pdf PDF
KRS Site Construction - Civil Drawings.pdf PDF
KRS Geotechnical Data Report.pdf PDF
REVISED Attachment 13-SARC_Subcontractor Annual RepsCerts Rev 5.pdf PDF
Amend 04 to RFP KRS-369604-JK.pdf PDF
MC4.pdf PDF
E-2.pdf PDF
FermiForward-Approved Color Palette.pdf PDF
Questions on E-House RFP_R5_2025_1003.xlsx XLSX spreadsheet
MC1.pdf PDF
E-B2.PDF PDF
KRS Site Construction - Structural Drawings.pdf PDF
ComEd Battery and Fermilab Battery Monitoring System Specifications.pdf PDF
REVISED Attachment 10-PUR-466_Proposal Certifications_r4_09.24.25.pdf PDF
Amend 03 to RFP KRS-369604-JK.pdf PDF
E-Control House Site Visit-Sign-in Sheet.pdf PDF
Amend 02 to RFP KRS-369604-JK.pdf PDF
Business Visitor Registration Instructions and Directions.pdf PDF
Fermilab Site Map-Kautz Road Substation.pdf PDF
Amend 01 to RFP KRS-369604-JK.pdf PDF
REVISED Attachment 13-SARC_Subcontractor Annual RepsCerts Rev 4.pdf PDF
Attachment 3 - 013100_ESH_Requirements_04-2025 FFDG.pdf PDF
Attachment 5 - 014100 Quality Requirements - March 2025 FermiForward.pdf PDF
Attachment 7-2 Pages 63-113 from 3-5-207C Dwg IFBr2.pdf PDF
Attachment 8 - 5-207C Control House Specs IFBr2.pdf PDF
Attachment 10 - PUR-466_Proposal Certifications_r3_06.23.25.pdf PDF
Attachment 13 -SARC_Subcontractor Annual RepsCerts Rev 3.pdf PDF
Attachment 14 SMALL BUSINESS SUBCONTRACTING PLAN template Far 52.219-9.pdf PDF
1. RFP for E-House.pdf PDF
Attachment 1 - Sample Subcontract .pdf PDF
Attachment 7-1 Pages 1-62 from 3-5-207C Dwg IFBr2.pdf PDF
Attachment 9 - FFDG General Terms and Conditions for Commercial Products and Commercial Services (01.2025).pdf PDF
Attachment 12 - PUR-568_Cost Accounting Standard Notices and Certification.pdf PDF
Attachment 2 - 010010_General_Requirements_3_2025 FFDG_.pdf PDF
Attachment 4 - 013300 Submittals FermiForward (3).pdf PDF
Attachment 6 -017900 - DEMONSTRATION AND TESTING.pdf PDF
Attachment 11 - 2025 Onsite NonProfessional Services Insurance Requirements.pdf PDF
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT 02 to RFP KRS-369604-JK Kautz Road Substation E-Control House

Responses to Prospective Offerors’ Questions

Question 1: The specifications name ABB and Siemens as acceptable manufactures for the breakers.

Given that Powell breakers are equal in durability and flexibility, as well as BABA compliant, we ask that you please consider Powell as an acceptable manufacturer.

Response 1: We are not currently accepting alternate circuit breaker manufacturers.

Question 2: Is there a cost estimate, budget or ballpark figure for the project listed? Is there an actual start date for the project?

Response 2: FFDG cannot provide a cost estimate/ballpark figure. The control house building shall be delivered by September 30, 2027.

Question 3: In reference to Attachment 8 – Control Building Specification, under 3.2 – Work Not Included, 3.2.2 states that 15kV Switchgear to be provided under separate specification. Can you please confirm when this separate specification can be sent?

Response 3: The specification is included in that same Attachment 8 – Control Building Specification, starting on page 43 of the pdf.

SECTION 261326

MEDIUM-VOLTAGE METAL-CLAD SWITCHGEAR

Question 4: Is this RFP for the contractor to perform the entire scope of work, such as foundation, MV cable run/installation, as well as indoor prefab building wiring? From my understanding, it appears that this RFP is only for the purchase of the equipment.

Response 4: This RFP is for the prefabricated building including the contents specified, placed, assembled and tested on the designated site foundations (constructed by others), ready for connection to the substation.

Question 5: Based on the drawings, it appears the gear you’re considering is arc fault rated. However, the only option we currently have for arc fault resistant gear is a NEMA 1 enclosure. Alternatively, we can offer non-arc resistant gear in either NEMA 3R or NEMA 1 enclosures. Could you confirm whether you would be open to accepting arc fault resistant gear with a NEMA 1 enclosure, or would you prefer a non-arc resistant gear option in either NEMA 3R or NEMA 1?

Response 5: Arc fault rated equipment is required.

Question 6: Can we schedule a site visit for this project?

Response 6: Yes. A site visit has been scheduled for Wednesday, September 24, 2025 at 10:30am CT. Please see the Fermilab Site Map – Kautz Road Substation and the Business Visitor Registration Instructions and Directions if you plan to attend.

Question 7: Since the RFQ Scope of Work states, "includes providing detailed design, procurement, fabrication, shipment, offloading/placement, and assembly of one (1) Substation switchgear & control building," are the vendors responsible for the following scopes to prepare the site to receive the prefab building?

a. Demolition of existing Building scope

b. Concrete and Foundation Work scope

c. Utility and Communication Connection of Prefab Building to Site Facility Scope

d. Landscape Scope

e. Site and grading Scope

f. Utility Scope

Response 7: No. This RFP is for the prefabricated building including the contents specified, placed, assembled and tested on the designated site foundations (constructed by others), ready for connection to the substation.

Question 8: What is the Bond % requirement?

Response 8: There is no bond requirement for this project.

Question 9: What is the Labor /Wage requirement? (Open Shop, Prevailing Wages or Union)

Response 9: There are no labor/wage requirements for this project.

File details come from the government source that posted it. Updated .