J7M - BMTI Statement of Work 2024.04.03Rev.pdf

PDF 225 KB Posted

Attached to
North Carolina Roads Maintenance/Construction MATOC
Solicitation number
12445224R0008
Issued by

About this file

This document is a Statement of Work (SOW) for the US Department of Agriculture (USDA) Black Mountain Trailhead Improvements project in Pisgah Forest, North Carolina.

The SOW outlines the scope of work, which includes erosion control, clearing and grubbing, site grading, aggregate and asphalt surfacing, and installation of parking lot features such as signage, bollards, and pavement markings. The existing gravel lot was constructed in 2021 and will require scarifying, additional aggregate, and compaction prior to asphalt paving. The contractor shall furnish all labor, materials, and equipment to complete the project in accordance with the drawings and specifications. The contractor must submit a proposed work schedule, erosion and sediment control plan, and product submittals for approval 10-14 days prior to construction. The contractor shall assign a point of contact who must be present on-site during all work. There will be no government-furnished property or facilities.

This SOW is related to a broader solicitation for a 5-year Multiple Award Task Order Contract (MATOC) for road maintenance, construction, and minor engineering services on National Forests in North Carolina and surrounding states. Offerors are required to submit separate quotations for each of the four forest zones.

View the file

Other files

File Type Posted
CoverLetterPisZoneBlackMountainTH.docx DOCX document
SF_30_12445224R0008_0002_jh.pdf PDF
RFIs and Answers.docx DOCX document
SF_30_12445224R0008_0001_jh.pdf PDF
RFP 12445224R0008 NC Rd Maintenance Construction IDIQ MA.pdf PDF
J7C - Schedule C Wolf Ford.docx DOCX document
J6B - FSSS Little Yellow Mountain Combined.pdf PDF
J7L - BMTI Dwgs 2024.04.03Rev.pdf PDF
J6E - NCMATOC_CoverLetterNanZoneLittleYellowMountain.docx DOCX document
J6D - LittleYellowMtnFillSlopeRepair.pdf PDF
J6G - Requisition_Checklist Little Yellow Mountain Combined.pdf PDF
J5C - PERFORMANCE STANDARDS.docx DOCX document
J1F - Past Performance Relevant Experience Questionaire.doc DOC document
J7A - FSSS Wolf Ford.docx DOCX document
J1E - RevSource Selection Plan_04.15.24.docx DOCX document
J9B - NCMATOC_CoverLetterUwhZoneHuntCamp.docx DOCX document
J1C - Attachment1_NC_MATOC_MaintPerformanceSpecs10.31.23.doc DOC document
J8A - SOI Combined Little Yellow Mountain.pdf PDF
J1G - APPENDIX C_Source Selection Plan_12.13.23.docx DOCX document
J5B - NCMATOC_CoverLetterCroZoneRoadMaint146A.docx DOCX document
J8E - NCMATOC_CoverLetterNanZoneLittleYellowMountain.docx DOCX document
J8F - NCNantahalaRDMap.pdf PDF
J7B - NCMATOC_CoverLetterPisZoneWolfFord.docx DOCX document
J7N - BMTI SOI 2024.04.03Rev.pdf PDF
J1B - SoW_NFsNC_Roads MATOC_11.22.23.docx DOCX document
J8C - Little Yellow Mountain Culvert Final Plan Set 11x17 4-2-24.pdf PDF
J12 - APPENDIX C_Source Selection.docx DOCX document
J7E - Wolf Ford Final Plan Set 11x17 10-10-23.pdf PDF
J5A - SOI_CollinsRoad4.4.24.pdf PDF
J8B - FSSS Little Yellow Mountain Combined.pdf PDF
J8G - Schedule C Little Yellow Mountain Combined.pdf PDF
J9E - Uwharrie Hunt Camp SOW.pdf PDF
J7D - SOI Wolf Ford.pdf PDF
J8D - LittleYellowMtnFillSlopeRepair10.08.23.pdf PDF
J6H - Schedule C Little Yellow Mountain Combined.pdf PDF
J7 - NCPisgahRDMap.pdf PDF
J1D - Attachment3_NC_MATOC_ZoneMap.pdf PDF
J6F - NCNantahalaRDMap.pdf PDF
J70 - BMTI FP14 SupplSpecs2024.04.03Rev.pdf PDF
J1A - Attachmen4 CoverLetterNC_ MATOC.docx DOCX document
J6C - Little Yellow Mountain Culvert Final Plan Set 11x17 4-2-24.pdf PDF
J9C - SOI_HuntCamp12.06.23.pdf PDF
J6I - SOI Combined Little Yellow Mountain.pdf PDF
J9D - Uwharrie Hunt Camp SOW.docx DOCX document
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Black Mountain Trailhead Improvements

Pisgah Forest, North Carolina

Statement of Work

April 2024

Contents Project General Information

1.0 Scope of Work

2.0 Background

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Storage of Materials

5.0 Government Furnished

6.0 Deliverables / Schedule

7.0 Contractor’s Key Personnel

Project Black Mountain Trailhead Parking Lot Construction

Location of work is east of the existing Pisgah Ranger Station entrance drive and parking lot located on State Highway 276, northeast of Brevard, in Transylvania County, North Carolina.

General Information

1.0 Scope of Work

This work shall consist of improvements to an existing gravel surfaced parking lot and related facilities. The work shall include the following: erosion control, clearing & grubbing, site grading, aggregate surfacing, asphalt surfacing, and parking lot features such as signage, bollards, pavement marking, and other items necessary to complete the project in accordance with the plans and specifications.

2.0 Background

The existing gravel lot was constructed in 2021. Most of the existing lot is at the proposed grade and will require scarifying, additional ABC aggregate, and compaction to prepare for asphalt paving. A portion of the existing lot will require re-grading (cut and fill) to provide proper slopes for the accessible parking and trailhead area. The gravel that is removed for the re-grading operations shall not be re-used in the parking lot (drive aisle and parking bays). This material will be re-used to construct pedestrian pathways along the perimeter of parking areas, driveway shoulder, and to fill parking lot islands. New, imported gravel will be used to re-construct the parking lot drive aisles and parking bays as necessary to provide a minimum of 6 inches compacted ABC base course prior to asphalt paving.

Contractor Requirements

3.0 Technical Requirements / Tasks

The Contractor shall furnish all labor, materials, equipment, tools, supplies, supervision and transportation and perform all the work required to complete the projects in accordance with the Drawings and Specifications.

4.0 Storage of Materials

The Contractor may store materials and equipment at the work site at their own risk. All materials must be kept in an area designated by the COR and be neat and orderly.

The Contractor shall install barricades or tape barriers around all open excavations.

5.0 Government Furnished

There will be no Government Furnished property or facilities.

6.0 Deliverables / Schedule

A. A proposed schedule of work for the project construction shall be submitted to the COR for approval 10 days prior to starting construction.

B. An Erosion and Sediment Control Plan shall be submitted to the COR for approval 10 days prior to starting construction.

C. Submittals shall be furnished before fabrication or installation occurs. All submittals shall be evaluated and either approved or rejected by the COR within 14 days after their receipt. A minimum of four (4) copies of submittals shall be supplied to the COR.

If the Contractor intends to provide or install an item that is an "or equal" or differs from that which is specified or shown on the drawings, he/she shall submit all product data, revised drawings or new drawings to the COR. for approval.

The contractor shall submit four sets of the manufacturer's description of all "or equals" proposed in lieu of name brands specified. This description shall include:

1. Product name and model number

2. Manufacturer

3. Product description

4. Technical data

D. The Contractor shall provide all guarantees, certificates of performance, material of workmanship or warranties provided by the manufacturer or required by the specifications to the COR.

7.0 Contractor’s Key Personnel

The contractor shall assign a point of contact (POC) for this contact. The POC’s full name, phone number, and email address must be submitted in their technical quote. The Contractor’s POC must be (i) deemed acceptable to the Government, (ii) authorized to act on the Contractor’s behalf; and (iii) be present on the job site at all times when contract work is being performed.

The Contractor shall make no substitutions of key personnel without notifying the Contracting Officer, in writing, within a reasonable timeframe. Oral notifications may be made for immediate, unexpected changes followed by written notifications containing the new key personnel’s full name, phone number, and email address. Substitutes should have comparable qualifications to those of the person(s) being replaced.

Project
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Storage of Materials
5.0 Government Furnished
6.0 Deliverables / Schedule
7.0 Contractor’s Key Personnel

File details come from the government source that posted it. Updated .