This document is a Source Selection Evaluation Plan for a federal contract opportunity. It outlines the evaluation factors and methodology that will be used to assess proposals received in response to a Request for Proposal (RFP) for road maintenance, road construction, and minor engineering services on National Forests in North Carolina.

The key evaluation factors are: 1) Experience, 2) Past Performance, and 3) Cost/Price. Proposals will be rated on a scale from "Substantial Confidence" to "No Confidence" based on the non-cost/price factors. The total price will be evaluated for fairness and reasonableness, but not scored. The government reserves the right to make an award to other than the lowest-priced offeror if it determines that would provide the best value. The resulting contract will be an Indefinite Quantity, Indefinite Delivery (IDIQ) Multiple Award Task Order Contract (MATOC) with a 5-year period of performance, divided into 4 geographic Forest Zones.

View the file

Other files

File Type Posted
CoverLetterPisZoneBlackMountainTH.docx DOCX document
SF_30_12445224R0008_0002_jh.pdf PDF
RFIs and Answers.docx DOCX document
SF_30_12445224R0008_0001_jh.pdf PDF
RFP 12445224R0008 NC Rd Maintenance Construction IDIQ MA.pdf PDF
J7C - Schedule C Wolf Ford.docx DOCX document
J6B - FSSS Little Yellow Mountain Combined.pdf PDF
J7L - BMTI Dwgs 2024.04.03Rev.pdf PDF
J7M - BMTI Statement of Work 2024.04.03Rev.pdf PDF
J6E - NCMATOC_CoverLetterNanZoneLittleYellowMountain.docx DOCX document
J6D - LittleYellowMtnFillSlopeRepair.pdf PDF
J6G - Requisition_Checklist Little Yellow Mountain Combined.pdf PDF
J5C - PERFORMANCE STANDARDS.docx DOCX document
J1F - Past Performance Relevant Experience Questionaire.doc DOC document
J7A - FSSS Wolf Ford.docx DOCX document
J9B - NCMATOC_CoverLetterUwhZoneHuntCamp.docx DOCX document
J1C - Attachment1_NC_MATOC_MaintPerformanceSpecs10.31.23.doc DOC document
J8A - SOI Combined Little Yellow Mountain.pdf PDF
J1G - APPENDIX C_Source Selection Plan_12.13.23.docx DOCX document
J5B - NCMATOC_CoverLetterCroZoneRoadMaint146A.docx DOCX document
J8E - NCMATOC_CoverLetterNanZoneLittleYellowMountain.docx DOCX document
J8F - NCNantahalaRDMap.pdf PDF
J7B - NCMATOC_CoverLetterPisZoneWolfFord.docx DOCX document
J7N - BMTI SOI 2024.04.03Rev.pdf PDF
J1B - SoW_NFsNC_Roads MATOC_11.22.23.docx DOCX document
J8C - Little Yellow Mountain Culvert Final Plan Set 11x17 4-2-24.pdf PDF
J12 - APPENDIX C_Source Selection.docx DOCX document
J7E - Wolf Ford Final Plan Set 11x17 10-10-23.pdf PDF
J5A - SOI_CollinsRoad4.4.24.pdf PDF
J8B - FSSS Little Yellow Mountain Combined.pdf PDF
J8G - Schedule C Little Yellow Mountain Combined.pdf PDF
J9E - Uwharrie Hunt Camp SOW.pdf PDF
J7D - SOI Wolf Ford.pdf PDF
J8D - LittleYellowMtnFillSlopeRepair10.08.23.pdf PDF
J6H - Schedule C Little Yellow Mountain Combined.pdf PDF
J7 - NCPisgahRDMap.pdf PDF
J1D - Attachment3_NC_MATOC_ZoneMap.pdf PDF
J6F - NCNantahalaRDMap.pdf PDF
J70 - BMTI FP14 SupplSpecs2024.04.03Rev.pdf PDF
J1A - Attachmen4 CoverLetterNC_ MATOC.docx DOCX document
J6C - Little Yellow Mountain Culvert Final Plan Set 11x17 4-2-24.pdf PDF
J9C - SOI_HuntCamp12.06.23.pdf PDF
J6I - SOI Combined Little Yellow Mountain.pdf PDF
J9D - Uwharrie Hunt Camp SOW.docx DOCX document
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 04 - Evaluation Factors and Methodology

Submission Requirements and Evaluation Minimum Requirements

1. EVALUATION FACTORS

General

Evaluation Methodology

Factor Identification – The Source Selections Evaluation Board will evaluate the proposals received in response to the project Request for Proposal (RFP). Award will be made to the offeror who represents the best value to the Forest Service on the basis of both non-cost factors and Cost/Price factors:

Non-Cost/Price Factors:

Factor 1 – Experience Factor 2 – Past Performance

When combined, these technical evaluation factors are more important than cost or price. Factor 3 – Cost/Price Factor 1: Experience

a. Submission Requirements: Submit a completed Past Performance and Relevant Experience Questionnaire (PPREQ) (RFP Attachment). The Offeror should provide completed PPREQ in the proposal.

To be considered relevant, projects must have been completed within the past five (5) years of the proposal issue date for this RFP. Preference will be given to those offerors that can show relevant projects.

For all submitted projects, the description of the project shall clearly describe the scope of work performed and the relevancy to the project requirements of this RFP.

a. Minimum Requirement: The Government will evaluate the Offeror’s demonstrated experience and depth of experience in performing relevant projects as defined in the solicitation submittal requirements. The assessment of the Offeror’s relevant experience will be used as a means of evaluating the capability of the Offeror to successfully meet the requirements of the RFP. The Government may only review the first five (5) projects , in the order they were submitted in the proposal. Any projects submitted in excess of the first five (5) for Experience may not be considered.

If an offeror has no record of relevant experience, the government will not evaluate the offeror favorably on this factor.

Relevant projects where the Offeror and its proposed subcontractors previously worked together may be considered more favorably than those that have not worked together.

Proposals that contain relevant projects completed for the Forest Service may be considered more favorably.

Factor 2: Past Performance

b. Submission Requirements: If a completed Contract Performance Assessment Reporting System (CPARS) Evaluation Report or a Construction Contractor Appraisal Support System (CCASS) Evaluation Report is available, it shall be submitted with the proposal for each project included in Factor 3 for Experience. If there is not a completed CPARS or CCASS evaluation, then the government will use the completed Past Performance Relevant Experience Questionnaire (PPREQ) (RFP Attachment 6) for each project to perform reference checks. The Offeror should provide completed PPREQ in the proposal.

The Government will consider the currency and relevance of the information, the source of the information, context of the data, and general trends in the Contractor’s performance. This evaluation is separate and distinct from the Contracting Officer’s responsibility determination. The assessment of the Offeror’s past performance will be used as a means of evaluating the Offeror’s probability to successfully meet the requirements of the RFP.

Offerors lacking relevant past performance history will not be evaluated favorably or unfavorably in past performance and will receive a NEUTRAL rating.

Factor 3: Cost/Price Submission Requirement:

Submit a Firm Fixed Price for the items in the Contract Line Item (CLIN) schedule for seed project(s) within the area of interest. Offerors shall submit a completed Schedule of Items for each seed project.

Source Selection Decision:

In order to select the successful offerors, we will rank the proposals from Highest to Lowest using the following ratings:

· SUBSTANTIAL CONFIDENCE: Based on the offeror’s Non-Cost/Price Factors shown on their proposal, the Government has a high expectation that the offeror will successfully perform the required effort.

· SATISFACTORY CONFIDENCE: Based on the offeror’s Non-Cost/Price Factors shown on their proposal, the Government has a reasonable expectation that the offeror will successfully perform the required effort.

· NEUTRAL CONFIDENCE: Based on the offeror’s Non-Cost/Price Factors shown on their proposal, the Government cannot determine a confidence rating. For example: No recent/relevant performance record is available, or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.

· LIMITED CONFIDENCE: Based on the offeror’s Non-Cost/Price Factors shown on their proposal, the Government has a low expectation that the offeror will successfully perform the required effort.

· NO CONFIDENCE: Based on the offeror’s Non-Cost/Price Factors shown on their proposal, the Government has no expectation that the offeror will be able to successfully perform the required effort.

Evaluation Methodology:

The Government will evaluate the total price to determine fairness and reasonableness. The total prices will be evaluated but not scored. Reasonableness will be determined by comparison to other competitive prices received and to the Independent Government Estimate. If a price is disproportionally lower than other competitive prices, the price may be deemed unrealistic. If necessary, the price break downs may be analyzed to determine whether the price elements are realistic for the work to be performed, reflect a clear understanding of the requirements, and are consistent with the information provided by the Offeror.

A. The degree of importance of the price will increase with the degree of equality of the proposals in relation to the other factors on which selection is to be based, or when the price is so significantly high as to diminish the value of the technical superiority to the Government.

B. The Government may award a contract on the basis of initial offers received, without discussions. Therefore, each initial offer should contain the offeror’s best terms from a cost or price and technical standpoint. However, if considered necessary by the Contracting Officer, discussions will be conducted with only those offerors determined to have a reasonable chance for award.

C. The Government reserves the right to make an award to other than the lowest priced offeror or to the offeror with the highest non-price evaluation if the Contracting Officer determines that to do so would result in the greatest value to the Government.