RFIs and Answers.docx

DOCX document 16 KB Posted

Attached to
North Carolina Roads Maintenance/Construction MATOC
Solicitation number
12445224R0008
Issued by

About this file

This document appears to be a set of questions and answers related to a Request for Information (RFI) for the North Carolina Roads Maintenance/Construction Multiple Award Task Order Contract (MATOC) solicitation.

The key details are:

  • The MATOC has a $50M ceiling and the Contracting Officer may select 3-7 contractors per zone. Contractors do not need to provide a bid bond with their MATOC proposal, but will need to provide performance and payment bonds if awarded a task order. The agency does not have a list of approved suppliers for the specified materials. The proposal due date is May 24, 2024 by 5pm Eastern time. The contract will have a 5-year period of performance. For the past performance evaluation, offerors only need to submit the J1F form and the agency will reach out to the listed client references. The period of performance for individual task orders will be determined at the task order award stage.

View the file

Other files

File Type Posted
CoverLetterPisZoneBlackMountainTH.docx DOCX document
SF_30_12445224R0008_0002_jh.pdf PDF
SF_30_12445224R0008_0001_jh.pdf PDF
RFP 12445224R0008 NC Rd Maintenance Construction IDIQ MA.pdf PDF
J7C - Schedule C Wolf Ford.docx DOCX document
J6B - FSSS Little Yellow Mountain Combined.pdf PDF
J7L - BMTI Dwgs 2024.04.03Rev.pdf PDF
J7M - BMTI Statement of Work 2024.04.03Rev.pdf PDF
J6E - NCMATOC_CoverLetterNanZoneLittleYellowMountain.docx DOCX document
J6D - LittleYellowMtnFillSlopeRepair.pdf PDF
J6G - Requisition_Checklist Little Yellow Mountain Combined.pdf PDF
J5C - PERFORMANCE STANDARDS.docx DOCX document
J1F - Past Performance Relevant Experience Questionaire.doc DOC document
J7A - FSSS Wolf Ford.docx DOCX document
J1E - RevSource Selection Plan_04.15.24.docx DOCX document
J9B - NCMATOC_CoverLetterUwhZoneHuntCamp.docx DOCX document
J1C - Attachment1_NC_MATOC_MaintPerformanceSpecs10.31.23.doc DOC document
J8A - SOI Combined Little Yellow Mountain.pdf PDF
J1G - APPENDIX C_Source Selection Plan_12.13.23.docx DOCX document
J5B - NCMATOC_CoverLetterCroZoneRoadMaint146A.docx DOCX document
J8E - NCMATOC_CoverLetterNanZoneLittleYellowMountain.docx DOCX document
J8F - NCNantahalaRDMap.pdf PDF
J7B - NCMATOC_CoverLetterPisZoneWolfFord.docx DOCX document
J7N - BMTI SOI 2024.04.03Rev.pdf PDF
J1B - SoW_NFsNC_Roads MATOC_11.22.23.docx DOCX document
J8C - Little Yellow Mountain Culvert Final Plan Set 11x17 4-2-24.pdf PDF
J12 - APPENDIX C_Source Selection.docx DOCX document
J7E - Wolf Ford Final Plan Set 11x17 10-10-23.pdf PDF
J5A - SOI_CollinsRoad4.4.24.pdf PDF
J8B - FSSS Little Yellow Mountain Combined.pdf PDF
J8G - Schedule C Little Yellow Mountain Combined.pdf PDF
J9E - Uwharrie Hunt Camp SOW.pdf PDF
J7D - SOI Wolf Ford.pdf PDF
J8D - LittleYellowMtnFillSlopeRepair10.08.23.pdf PDF
J6H - Schedule C Little Yellow Mountain Combined.pdf PDF
J7 - NCPisgahRDMap.pdf PDF
J1D - Attachment3_NC_MATOC_ZoneMap.pdf PDF
J6F - NCNantahalaRDMap.pdf PDF
J70 - BMTI FP14 SupplSpecs2024.04.03Rev.pdf PDF
J1A - Attachmen4 CoverLetterNC_ MATOC.docx DOCX document
J6C - Little Yellow Mountain Culvert Final Plan Set 11x17 4-2-24.pdf PDF
J9C - SOI_HuntCamp12.06.23.pdf PDF
J6I - SOI Combined Little Yellow Mountain.pdf PDF
J9D - Uwharrie Hunt Camp SOW.docx DOCX document
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Tell us what the ceiling $$ amount is and how many contractors that will be selected for the MATOC.

The Ceiling is $50M. Contracting Officer may select 3-7 Contractors per zone.

2. Reading the main MATOC SOW it appears that we need to show proof of the ability to bond but not necessarily provide a bid bond with the MATOC itself? Then I assume that if we were selected for one or more of the zones, and then when a task order is presented, at that point we would provide a performance & payment bond?

Correct!

3. Do you have a list of suppliers for the Geogrid, Pet Coated, Type IV, Type V. Or the Bi- Directional Delineator. My supplier does not carry some of those items.

We do not have a List of suppliers for the specified materials.

4. In review of the 40 or so files for the NC MATOC bid,, I do not seem to locate a SF 1442 with pertinent information such as date for submission. Can you please check on this and add to the file contents.

SF 1442 added in this amendment (0001).

5. Can you please confirm the proposal due date for the North Carolina Roads Maintenance/Construction MATOC project. The updated date offers due says May 18, 2024 at 5:00 PM which is a Saturday.

Due by date is May 24, 2024 by 5pm Eastern time.

6. In review of the documents on SAM.gov, it appears the Little Yellow Mtn project files are in there twice. The details for Black Mountain Trailhead Improvements do not appear anywhere in the 40 or so documents. The labels, J6 and J8 are both Yellow Mtn files..

We do have some files twice, but the Black Mountain Trailhead files are there as well. J7L to J70 BMTI.

7. Please confirm the only form required for Experience and Past Performance Qualification is J1F, and no technical volume is required with submission. . And all that we need to do for the Factor 2 Past Performance is to provide CPARS reports? And for this Factor 2 the USFS evaluation team will reach out to the clients listed on our J1F Past Performance Experience Questionnaire that we submitted for Factor 1, correct?

Correct!

8. The periods of performance for task orders are incorrect it seems. Will these adjust with award dates? If so, are you looking for them to be finished by the end of this year (2024)?

The Period of Performances for the task orders/seed projects will vary per project and shall reflect appropriately at award.

File details come from the government source that posted it. Updated .