J7C - Schedule C Wolf Ford.docx

DOCX document 28 KB Posted

Attached to
North Carolina Roads Maintenance/Construction MATOC
Solicitation number
12445224R0008
Issued by

About this file

This document is a Statement of Work (SOW) for a federal contract opportunity to reconstruct and repair portions of NFSR 476 Wolf Ford Road located in the Pisgah National Forest in North Carolina.

The key details are:

  • The project includes construction survey and staking, soil erosion and pollution control, selective clearing, geogrid installation, linear grading, riprap placement, gabion basket installation, aggregate placement, roadway reconditioning, culvert installation, drainage structure reconditioning, seeding, mulching, and fertilizing, and other items to complete the project.
  • The project location is approximately 9 miles north of Brevard in Transylvania County, North Carolina.
  • The estimated price range is $25,000 to $100,000.
  • A pre-bid tour and pre-bid conference are required.
  • Work can begin on April 15, 2024 and the contract is to be completed by October 15, 2024.
  • A written and approved safety plan is required prior to commencement of work.
  • The contractor is responsible for submitting all items listed in the Forest Service Supplemental Specifications.
  • The Forest Service will obtain the necessary stream preservation permits.

The SOW references the related federal contract opportunity, which is a 5-year Multiple Award Task Order Contract (MATOC) for road maintenance, road construction, and minor engineering services for the Forest Service roads on all National Forests in the state of North Carolina.

View the file

Other files

File Type Posted
CoverLetterPisZoneBlackMountainTH.docx DOCX document
SF_30_12445224R0008_0002_jh.pdf PDF
RFIs and Answers.docx DOCX document
SF_30_12445224R0008_0001_jh.pdf PDF
RFP 12445224R0008 NC Rd Maintenance Construction IDIQ MA.pdf PDF
J6B - FSSS Little Yellow Mountain Combined.pdf PDF
J7L - BMTI Dwgs 2024.04.03Rev.pdf PDF
J7M - BMTI Statement of Work 2024.04.03Rev.pdf PDF
J6E - NCMATOC_CoverLetterNanZoneLittleYellowMountain.docx DOCX document
J6D - LittleYellowMtnFillSlopeRepair.pdf PDF
J6G - Requisition_Checklist Little Yellow Mountain Combined.pdf PDF
J5C - PERFORMANCE STANDARDS.docx DOCX document
J1F - Past Performance Relevant Experience Questionaire.doc DOC document
J7A - FSSS Wolf Ford.docx DOCX document
J1E - RevSource Selection Plan_04.15.24.docx DOCX document
J9B - NCMATOC_CoverLetterUwhZoneHuntCamp.docx DOCX document
J1C - Attachment1_NC_MATOC_MaintPerformanceSpecs10.31.23.doc DOC document
J8A - SOI Combined Little Yellow Mountain.pdf PDF
J1G - APPENDIX C_Source Selection Plan_12.13.23.docx DOCX document
J5B - NCMATOC_CoverLetterCroZoneRoadMaint146A.docx DOCX document
J8E - NCMATOC_CoverLetterNanZoneLittleYellowMountain.docx DOCX document
J8F - NCNantahalaRDMap.pdf PDF
J7B - NCMATOC_CoverLetterPisZoneWolfFord.docx DOCX document
J7N - BMTI SOI 2024.04.03Rev.pdf PDF
J1B - SoW_NFsNC_Roads MATOC_11.22.23.docx DOCX document
J8C - Little Yellow Mountain Culvert Final Plan Set 11x17 4-2-24.pdf PDF
J12 - APPENDIX C_Source Selection.docx DOCX document
J7E - Wolf Ford Final Plan Set 11x17 10-10-23.pdf PDF
J5A - SOI_CollinsRoad4.4.24.pdf PDF
J8B - FSSS Little Yellow Mountain Combined.pdf PDF
J8G - Schedule C Little Yellow Mountain Combined.pdf PDF
J9E - Uwharrie Hunt Camp SOW.pdf PDF
J7D - SOI Wolf Ford.pdf PDF
J8D - LittleYellowMtnFillSlopeRepair10.08.23.pdf PDF
J6H - Schedule C Little Yellow Mountain Combined.pdf PDF
J7 - NCPisgahRDMap.pdf PDF
J1D - Attachment3_NC_MATOC_ZoneMap.pdf PDF
J6F - NCNantahalaRDMap.pdf PDF
J70 - BMTI FP14 SupplSpecs2024.04.03Rev.pdf PDF
J1A - Attachmen4 CoverLetterNC_ MATOC.docx DOCX document
J6C - Little Yellow Mountain Culvert Final Plan Set 11x17 4-2-24.pdf PDF
J9C - SOI_HuntCamp12.06.23.pdf PDF
J6I - SOI Combined Little Yellow Mountain.pdf PDF
J9D - Uwharrie Hunt Camp SOW.docx DOCX document
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PART I—THE SCHEDULE

SECTION C—DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C-1 PROJECT DESCRIPTION AND LOCATION

(a) Description of Work.

The project along NFSR 476 Wolf Ford Road is to reconstruct and repair portions of the roadway and stabilize a fill slope failure. Specific work items along NFSR 476 repair include but are not limited to: construction survey and staking, soil erosion and pollution control, selective clearing, geogrid installation, linear grading, riprap placement, gabion basket installation, aggregate placement, roadway reconditioning, culvert installation, drainage structure reconditioning, seeding, mulching, & fertilizing, bi-directional delineator installation, and all other items necessary to complete the project in accordance with the plans and specifications.

(b) Project Location

The project site is located on the Pisgah Ranger District of the Pisgah National Forest - approximately 9 miles north of Brevard in Transylvania County, NC (Lat. 35.367750, Long. -82.740080). Refer to the vicinity map on the title sheet of the plans.

(c) Price Range. $25,000 to $100,000

(d) Pre-bid Tour. Yes

(e) Pre-bid Conference. Yes

(f) Start Work. It is estimated that once the contract is awarded, a notice to proceed for materials will be issued. Work can begin April 15th , 2024. Contract time will run continuously with no shutdown.

(g) Period of Performance. Contract is to be completed by October 15th, 2024.

(h) Safety Plan. A written and approved safety plan in accordance with applicable regulations such as FARS, OSHA, etc. is required prior to commencement of project work. The Safety Plan is also part of the criteria in evaluation of responsive bidders. Contractor shall provide adequate safety briefings and ensure safe practices are followed from all personnel involved in the project. Emergency contact numbers shall be readily available on site.

(i) Submittals. Contractor is responsible for and shall submit, at a minimum and at addressed times, all items listed within FSSS (Forest Service Supplemental Specification).

(j) Permits. The Forest Service will obtain the necessary stream preservation permits for this project and the contractor is responsible for adhering to the stipulations of these permits.

C-2 SPECIFICATIONS

This project makes use of Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-14) U.S. Customary Units. FP-14 is included by reference only and can be found on the internet at the following website: https://flh.fhwa.dot.gov/resources/specs/

C-3 – FOREST SERVICE SUPPLEMENTAL SPECIFICATIONS (FSSS)

The following Forest Service Supplemental Specifications are a part of this solicitation and any resulting contract and are made a separate attachment. Supplemental Specifications (FSSS) include additions and revisions to the Standard Specifications (FP-14).

FSSS No.
DESCRIPTION

Preface

101
Terms, Format, and Definitions
102
Bid, Award, and Execution of Contract
103
Scope of Work
104
Control of Work
105
Control of Material
106
Acceptance of Work
107
Legal Relations and Responsibility to the Public
108
Prosecution and Progress
109
Measurement and Payment
152
Construction Survey and Staking
153
Contractor Quality Control
155
Schedules for Construction Contracts
157
Soil Erosion and Sediment Control
202
Additional Clearing and Grubbing
203
Removal of Structures and Obstructions
204
Excavation and Embankment
207
Earthwork Geotextiles
302
Minor Crushed Aggregate
303
Road Reconditioning
602
Culverts and Drains
625
Turf Establishment
633
Permanent Traffic Control

C-4 PROJECT DRAWINGS

The following drawings are applicable to this solicitation.

SHEET NO.
DESCRIPTION
1
COVER SHEET
2
SITE MAP
3
SUMMARY OF QUANTITIES
4
GENERAL NOTES
5
WORK LIST
6
TYPICAL SECTIONS
7
TRAFFIC CONTROL DETAIL
8
CMP CULVERT DETAIL
9
CMP DITCHING DETAIL
10
CMP ALIGNMENT DETAIL
11
EROSION CONTROL DETAIL
12
DEEP PATCH DETAILS
13
GABION DETAIL
14
EXISTING SITE VIEW
15
PROPOSED PLAN & PROFILE
16
PROPOSED CROSS SECTIONS