J.029 FAA cleanup schedule - ACEPS support.pdf
PDF 226 KB Posted
- Attached to
- CRITICAL POWER SYSTEMS INSTALLATION SERVICES Federal contract opportunity
- Solicitation number
- 6973GH-24-R-00177
About this file
This document appears to be a government file detailing the schedule for contamination cleanup efforts to support the FAA's ACEPS (Authorized Centralized Electronics Power Systems) generator replacement projects. The file outlines the typical timeline for site investigation, remedial investigation, remedial action, and regulatory review, which can take over 5 years to complete. It indicates that the ACEPS effort is expected to proceed uninterrupted during this process.
The related federal contract opportunity is for "CRITICAL POWER SYSTEMS INSTALLATION SERVICES" to provide project management, design, and installation/construction work for power systems supporting the FAA's Facility Power Systems programs nationwide. This will be awarded as a firm-fixed-price, multiple award, Indefinite Delivery/Indefinite Quantity (ID/IQ) contract. Proposals are due by October 18, 2024, and must be submitted by email. The contract will be awarded under the FAA's Acquisition Management System in place of the Federal Acquisition Regulation.
View the file
Other files for this federal contract opportunity
Show all 35
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contamination is suspected based on facility/property history and/or use
(this is true for all FAA Generator Rooms)
Site Investigation (SI) 2 Months
(for most ACEPS targeted sites this will be soil gas sampling for petroleum hydrocarbon volatiles during ACEPS design phase)
SI supports Remedial Investigation (RI) (to define extent of impacts)
Remedial Investigation
(RI)
2‐3 months (RI duration could be longer if the groundwater is impacted)
RI Supports the need for Remedial Action (RA)?
Assess for Closure, ECU executes internal/external site closure.
ACEPS effort proceeds uninterrupted
Remedial Action
(RA)
1‐8 months
Regulatory Agency Review
1‐12 months (if regulator does not concur, more RI or RA may be required)
RA Supports Site Closure (SC)?
YES
Assess State Regulator Notification Requirements
Notify Regulator
NO
FAA – State Regulatory Agency Work Plan Review, ECU contracting 1‐6 months
YES
Assess for Closure, ECU executes internal/external site closure.
ACEPS effort proceeds uninterrupted
Generic ECU schedule to support ACEPS generator replacement projects (Not site‐specific – for planning purposes only)
ACEPS CUT
OVER
Supplemental SI (1 month)
Presence/absence soil and groundwater sampling
Sample results above State cleanup standards?
NO
Assess for Closure, ECU executes internal/external site closure.
ACEPS effort proceeds uninterrupted
YES
File details come from the government source that posted it. Updated .