J.004 Government Furnished Equipment (GFE).pdf
PDF 35 KB Posted
- Attached to
- CRITICAL POWER SYSTEMS INSTALLATION SERVICES Federal contract opportunity
- Solicitation number
- 6973GH-24-R-00177
About this file
This document is an attachment titled "Government Furnished Equipment (GFE)" that lists the types of electrical power distribution equipment, engine generators, automatic transfer switches, and uninterruptible power supply systems that may be provided as government-furnished equipment for a federal contract opportunity.
The related federal contract opportunity is for "CRITICAL POWER SYSTEMS INSTALLATION SERVICES" for the Federal Aviation Administration. The contract will be a firm-fixed-price, multiple award, Indefinite Delivery/Indefinite Quantity contract. Proposals are due on October 18, 2024 by 6:00 pm CST. The contract will require project management, design services, and installation/construction work for power systems and power system ancillary equipment and structures supporting the FAA Facility Power Systems programs at National Airspace System facilities throughout the United States and its territories.
View the file
Other files for this federal contract opportunity
Show all 35
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment J.04
POWER SERVICES GROUP GOVERNMENT FURNISHED EQUIPMENT (GFE)
In support of the requirements of the Statement of Work and contract, below is a sample list of equipment that may be provided as GFE:
ELECTRICAL POWER DISTRIBUTION EQUIPMENT (EDE)
Vendor: Schneider Electric/Square D
Equipment: Switchboards, Switchgear, Panel boards, Circuit Breakers, Transformers, and Monitoring
Software and Hardware
Lead-time: Large Switchboards 4-5 months, Panel boards 1-3 months, Transformers 1-3 months
Switchgear 6-9 months
ENGINE GENERATOR (EG)
Vendor:
Equipment:
TBD
Propane engine generators 20 kW to 100 kW
Diesel engine generators 15 kW to 1.5 MW
Automatic Transfer Switches, Load Banks, Day Tanks/Sub-Base Tanks and Mufflers
Voltages 480, 208, 240 three phase, 240 single phase
Lead-Time: 6-months
STATIC AUTOMATIC TRANSFER SWITCH (STS)
Vendor:
Equipment: 480 volt, 200 amp to 600 amp
208 volt, 3 or 4-pole, 150 amp to 600 amp
Lead-Time: 158 - 365 days
UNINTERRUPTIBLE POWER SUPPLY (UPS)
Vendor: Eaton Electric
Equipment: 480 volt 30 KVA to 825 KVA
208 volt 10 KVA to 160 kVA
Battery strings, battery monitors, and bypass panels.
Lead-Time: small to medium UPSs and associated equipment 12-weeks
DIRECT CURRENT BACK-UP SYSTEM (DC BUS)
Vendor: Oceus
Equipment: 24 volt DC BUS, UXTM, ERMS, batteries, battery rack and strings
Lead-Time: 60-90 days
Note: Some equipment may have longer lead times than listed above.