J.028 Technical Approach Evaluation Worksheets rev2 06-04-24.docx

DOCX document 81 KB Posted

Attached to
CRITICAL POWER SYSTEMS INSTALLATION SERVICES Federal contract opportunity
Solicitation number
6973GH-24-R-00177
Issued by
Department of Transportation Federal Aviation Administration Franchise Acquisition Services

About this file

This document is a set of Technical Approach Evaluation Worksheets for a federal contract opportunity related to Critical Power Systems Installation Services. The worksheets provide detailed evaluation criteria across multiple factors, including Key Personnel, Category 2 Critical Power Systems Design, and Category 2 Critical Power Systems Installation.

The key requirements include engine generators (1000 kW or larger), uninterruptible power systems (200 kVA or larger), and fuel storage tanks (5,000 gallons or larger) configured in parallel with environmental remote monitoring. The design package must demonstrate compliance with applicable FAA specifications, standards, and industry orders. The installation narrative must describe experience with temporary power systems, cutover plans, equipment installation, startup and commissioning, project cost and schedule, and fuel system work. Offerors are evaluated on the complexity of their submitted projects, including overlap of active construction and physical distance between project sites.

View the file

Other files for this federal contract opportunity

Other files attached to CRITICAL POWER SYSTEMS INSTALLATION SERVICES, newest first.
File Type Posted
J.024 Price Proposal Critical Power Systems Cost Worksheet 10-11-24.xlsx.xlsx XLSX spreadsheet
6973GH-24-R-00177 Amendment P00001.pdf PDF
6973GH-24-R-00177 REVISED SIR.pdf PDF
CPS SIR 6973GH-24-R-00177 Questions and Answers 10.16.24.xlsx XLSX spreadsheet
J.001 Critical Power Systems Statement of Work (SOW) Rev 1. 10-16-2024.docx DOCX document
6973GH-24-R-00177 as of 9-17-2024.pdf PDF
J.004 Government Furnished Equipment (GFE).pdf PDF
J.009 Pre-Construction Installation EOSH Checklist - FAA Form 3900-18.pdf PDF
J.012 FAA-C-1391e INSTALLATION, TERMINATION, SPLICING, AND TRANSIENTSURGE PROTECTION OF UNDERGROUND ELECTRICAL DISTRIBUTION SYSTEM POWER CABLES.pdf PDF
J.016 FAA Order JO 3900.64A - Air Traffic Organization Electrical SafetyProgram.pdf PDF
J.024 Price Proposal Critical Power Systems Cost Worksheet.xlsx XLSX spreadsheet
J.025 Phase I, Volume II - Relevant Corporate Experience Form.docx DOCX document
J.027A-2 Technical Approach, Factor 3, Installation Proposal Form.pdf PDF
J.018 FAA Order JO 1050.17B - Environmental Compliance at Air Traffic Organization Facilities.pdf PDF
J.019 FAA Order JO 6950.2F Electrical Power Policy lmplementation at NationalAirspace System Facilities.pdf PDF
J.022 Contractor Release - DOT FORM 4220.4.pdf PDF
J.007 Performance Bond - FAA Form Number FAA 4400-63.pdf PDF
J.008 Payment Bond - FAA Form Number 4400-61.pdf PDF
J.014 FAA Order 1050.10D - Environmental Pollution Control and Abatement at FAA Facilities.pdf PDF
J.26 Past Performance Questionnaire 5-31-24.docx DOCX document
J.027A-1 Phase 2 Volume 2, Technical Approach - Factor 2 Category 2 CPS Design Proposal Form.pdf PDF
J.001 Critical Power Systems Statement of Work (SOW).docx DOCX document
J.002 Contract Data Requirements List (CDRL).pdf PDF
J.003 Data Item Description (DID).pdf PDF
J.005 Contractor Acceptance Inspection (CAI) FAA Form 6010-5.pdf PDF
J.006 Travel Authorization Form.xlsx XLSX spreadsheet
J.010 Pre-Construction Agenda and Checklist - DOT Form F4220.3.doc DOC document
J.011 FAA-C-1217H Construction Specification - ELECTRICAL WORK, PREMISES WIRING.pdf PDF
J.013 FAA-STD-002H Standard Engineering Drawing Preparation & Support.pdf PDF
J.015 FAA Order JO 3900.57A CHG 1 - EOSH Requirements in the Planning & Execution of Construction & Maintenance Activities at NAS Facilities.pdf PDF
J.017 FAA Order JO 6950.27B - Power System Studies.pdf PDF
J.020 Fuel Storage Tank Guidelines.pdf PDF
J.021 FST Program Specifications for Construction.pdf PDF
J.023 FAA Order 1370.121B - FAA Information Security and Privacy Policy.pdf PDF
J.029 FAA cleanup schedule - ACEPS support.pdf PDF
Show all 35

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

J.28 Technical Approach Evaluation Worksheets Table of Contents

Phase 2, Volume 2, Factor 1 - Key Personal Evaluation Questions2
Phase 2, Volume 2, Factor 2 – Category 2 Critical Power Systems Design Proposal Questions3
Phase 2, Volume 2, Factor 2 – CPS Design3
Phase 2, Volume 2, Factor 2 – EG Design7
Phase 2, Volume 2, Factor 2 – UPS Design10
Phase 2, Volume 2, Factor 2 – FST Design13
Phase 2, Volume 2, Factor 3 – Category 2 Critical Power Systems Installation Proposal Questions15
Phase 2, Volume 2, Factor 3, Sub-Factor 3.1 – Capabilities15
Phase 2, Volume 2, Factor 3, Sub-Factor 3.1 – CPS Installation15
Phase 2, Volume 2, Factor 3, Sub-Factor 3.1– EG Installation17
Phase 2, Volume 2, Factor 3, Sub-Factor 3.1–UPS Installation19
Phase 2, Volume 2, Factor 3, Sub-Factor 3.1 – FST Installation21
Phase 2, Volume 2, Factor 3, Sub-Factor 3.2 – Complexity22

Phase 2, Volume 2, Factor 1 - Key Personal Evaluation Questions

OFFEROR
EVALUATOR
DATE
Question
Yes
No

1. Did the Offeror submit a Letter of Intent that confirms Key Personnel will be dedicated to the contract for one (1) year after contract award?

2. Did the Offeror submit a resume that showed a Program Manager possessing the minimum requirement of five (5) years of program management experience with contracts that are same or similar in scope and complexity as shown in Sections C.1.1 of the SOW?

3. Did the Offeror submit a resume that showed a Program Manager exceeding the minimum requirement of five (5) years to ten (10) years of program management experience with contracts that are same or similar in scope and complexity as shown in Sections C.1.1, C.3.2.6, C.3.2.7 and C.3.2.8 of the SOW?

4. Did the Offeror submit a resume that shows a Program Manager that far exceeds the requirement by having more than ten (10) years of Program Management experience with contracts that are same or similar in scope and complexity as shown in Sections C.1.1, C.3.2.6, C.3.2.7 and C.3.2.8 of the SOW of the SOW?

5. Did the Offeror submit a resume that shows the Program Manager possesses Program Management experience with a contract of same or similar scope and complexity on a Critical Power Systems, Category 2 as shown in section C.1.1 of the SOW?

6. Did the Offeror submit a resume that shows the Program Manager possesses Program Management experience with two or more Critical Power Systems Installation Projects, Category 2 as shown in section C.1.1 of the SOW that meets or exceeds the scope and/or complexity of this requirement?

Subtotal

This evaluation is worth a total of 10 points. The overall score for this section is calculated by dividing the number of “Yes” responses by the total number of questions and then multiplying the result by the total potential score. (Rounding up to three significant figures: X.XX)

_____ (Yes) / 6 (Yes + No) = _____ * 10 = _____ Key Personnel Overall Score

NOTES/COMMENTS:

Phase 2, Volume 2, Factor 2 – Category 2 Critical Power Systems Design Proposal Questions Phase 2, Volume 2, Factor 2 – CPS Design

OFFEROR
EVALUATOR
DATE

*If the answer is “NO” for this question, stop evaluation and score Factor 2, CPS as a zero.

Question
Yes
No

1. Scope

1.1 * Did the submitted Project include Engine Generators (EGs), each 1000 kW or larger, configured in parallel AND Uninterruptible Power Systems (UPS), each 200 kVA or larger, configured in parallel AND/OR Fuel Storage Tanks (FST), each 5,000 gallons or larger, configured in parallel with environmental remote monitoring?

1.2 Did the Design Package clearly indicate installation of Switchboard(s) and/or Switchgear with Power Monitoring?

1.3 Did the Design Package provide sequenced drawings that show how the equipment and associated components will be installed or removed for each stage/phase in construction?

1.4 Did the Design Package include Electrical Installation Details that provide detailed electrical information necessary for installation?

1.5 Did the Design Package show a control wiring diagram that outlines all of the required control circuits for the system to operate?

1.6 Did the design package convey an understanding of the FAA specifications, standards, and orders listed in the Critical Power System SOW section C.2.2-C.2.4 AND/OR Industry Standards listed in section C.2.5?

2. Temporary System

2.1 Did the Design Package provide a detailed Temporary System One-Line diagram incorporating the temporary system into the existing facility?

2.2 Did the Design Package provide a detailed Temporary System layout that allows the installation contractor the capability to install the temporary system?

3. Demolition

3.1 Did the Design Package provide a Demolition Plan that includes demolition drawings that clearly shows what equipment will be removed and what equipment will be retained as part of the project?

4. Engine Generator

4.1 Did the Design Package describe how the EG was sized for the project? (Specification from the facility owner, load study, manufacturer provided sizing software, or other means.)

4.2 Did the Design Package include a detailed Parallel/Redundant EG System Design that could be used to build a fully functional system?

4.3 Did the Design Package for the new power system have a remote or inline radiator?

5. UPS

5.1 Did the Design Package describe how the UPS was sized for the project? (Specification from the facility owner, load study, manufacturer provided sizing software, or other means.)

5.2 Did the Design Package include a detailed Parallel/Redundant UPS System Design that could be used to build a fully functional system?

6. Electrical

6.1 Did the Design Package show a new or existing panel schedule(s)?

6.2 Did the Design Package include and show compliance with the applicable NEC, OSHA, and FAA Standards, Specifications, and Orders?

6.3 Did the Design Package show an existing and/or new One-Line diagram that appropriately represents the overall system?

6.4 Did the Design Package Provide a detailed Cable and Conduit schedule?

6.5 Did the Design Package provide a detailed Equipment Layout that shows where the new equipment will be installed with equipment clearances compliant with NEC, OSHA and FAA Orders, Standards and Specifications as applicable?

6.6 Did the Design Package address points of egress per the NEC? (e.g. for equipment rated 1,200 amperes or above)

6.7 Did the Design Package provide detailed information for built in redundancy for system operability and sequence of operations?

7. Monitor and Control

7.1 Did the Offeror’s Design package describe experience integrating SCADA, HMI, RSP, RMP, or Power Control and Monitoring Systems?

7.2 Did the Design Package show point-to-point control wiring diagram that outlines all the required control circuits for the system to operate?

7.3 Did the Design Package describe designing new Power Control and Monitoring Systems and/or designing modifications to existing Power Control and Monitoring Systems?

7.4 Did the Design Package Power Control and Monitoring system include power quality monitoring, circuit breaker and electrical distribution equipment control and monitoring?

7.5 Did the Design Package Power Control and Monitoring system include Engine Generator, control and/or monitoring?

7.6 Did the Design Package Power Control and Monitoring system include UPS, control and/or monitoring?

7.7 Did the Design Package include Automated Controls and Environmental Monitoring system for FST system.

7.8 Did the Design Package provide Control drawings that include network diagrams and block diagrams showing overall system integration?

8. Mechanical

8.1 Did the Design Package provide detailed mechanical drawings that show a fuel system design that could be used to build a fully functioning code compliant system?

8.2 Did the Design Package provide detailed mechanical drawings that show an HVAC system design that could be used to build a fully functioning code compliant system?

8.3 Did the mechanical drawings show detailed exhaust system connections, mounting points, and vibration isolation as required to build a fully functioning code compliant system?

9. Power Analysis

9.1 Did the submitted Power Analysis Studies Report or Protective Device Coordination Analysis (PDCA) demonstrate a properly coordinated system in multiple operating scenarios and system configurations?

9.2 Did the submitted Power Analysis Report provide organized Time Current Curves (TCC) for settable protective devices including circuit breakers, relays, and other components for better understanding of coordination within the protective devices?

9.3 Did the submitted Power Analysis Studies Report or Arc Flash Risk Assessment (AFRA) identify the flash-protection boundary and the incident energy at assigned working distances throughout any position or level in the overall electrical system, and specify the appropriate labels for each piece of equipment within the design?

Subtotal

This evaluation is worth a total of 30 points. The overall score for this section is calculated by dividing the number of “Yes” responses by the total number of questions and then multiplying the result by the total potential score. (Rounding up to three significant figures: X.XX)

_____ (Yes) / 35 (Yes + No) = _____ * 30 = _____ CPS Design Overall Score

Phase 2, Volume 2, Factor 2 – EG Design

OFFEROR
EVALUATOR
DATE

*If the answer is “NO” for this question, stop evaluation and score Factor 2, EG as a zero.

Question
Yes
No

1. Scope

1.1 * Did the submitted Project include Engine Generators (EGs), each 1000 kW or larger?

1.2 Did the Design Package clearly indicate installation of Switchboard(s) and/or Switchgear with Power Monitoring?

1.3 Did the Design Package provide sequenced drawings that show how the equipment and associated components will be installed or removed for each stage/phase in construction?

1.4 Did the Design Package include Electrical Installation Details that provide detailed electrical information necessary for installation?

1.5 Did the Design Package show a control wiring diagram that outlines all of the required control circuits for the system to operate?

1.6 Did the design package convey an understanding of the FAA specifications, standards, and orders listed in the Critical Power System SOW section C.2.2-C.2.4 AND/OR Industry Standards listed in section C.2.5?

2. Temporary System

2.1 Did the Design Package provide a detailed Temporary System One-Line diagram incorporating the temporary system into the existing facility?

2.2 Did the Design Package provide a detailed Temporary System layout that allows the installation contractor the capability to install the temporary system?

3. Demolition

3.1 Did the Design Package provide a Demolition Plan that includes demolition drawings that clearly shows what equipment will be removed and what equipment will be retained as part of the project?

4. Engine Generator

4.1 Did the Design Package describe how the EG was sized for the project? (Specification from the facility owner, load study, manufacturer provided sizing software, or other means.)

4.2 Did the Design Package include a detailed Parallel/Redundant EG System Design that could be used to build a fully functional system?

4.3 Did the Design Package for the new power system have a remote or inline radiator?

5. Electrical

5.1 Did the Design Package show a new or existing panel schedule(s)?

5.2 Did the Design Package include and show compliance with the applicable NEC, OSHA, and FAA Standards, Specifications, and Orders?

5.3 Did the Design Package show an existing and/or new One-Line diagram that appropriately represents the overall system?

5.4 Did the Design Package Provide a detailed Cable and Conduit schedule?

5.5 Did the Design Package provide a detailed Equipment Layout that shows where the new equipment will be installed with equipment clearances compliant with NEC, OSHA and FAA Orders, Standards and Specifications as applicable?

5.6 Did the Design Package address points of egress per the NEC? (e.g. for equipment rated 1,200 amperes or above)

5.7 Did the Design Package provide detailed information for built in redundancy for system operability and sequence of operations?

6. Monitor and Control

6.1 Did the Offeror’s Design package describe experience integrating SCADA, HMI, RSP, RMP, or Power Control and Monitoring Systems?

6.2 Did the Design Package show point-to-point control wiring diagram that outlines all the required control circuits for the system to operate?

6.3 Did the Design Package describe designing new Power Control and Monitoring Systems and/or designing modifications to existing Power Control and Monitoring Systems?

6.4 Did the Design Package Power Control and Monitoring system include power quality monitoring, circuit breaker and electrical distribution equipment control and monitoring?

6.5 Did the Design Package Power Control and Monitoring system include Engine Generator, control and/or monitoring?

6.6 Did the Design Package provide Control drawings that include network diagrams and block diagrams showing overall system integration?

7. Mechanical

7.1 Did the Design Package provide detailed mechanical drawings that show a fuel system design that could be used to build a fully functioning code compliant system?

7.2 Did the Design Package provide detailed mechanical drawings that show an HVAC system design that could be used to build a fully functioning code compliant system?

7.3 Did the mechanical drawings show detailed exhaust system connections, mounting points, and vibration isolation as required to build a fully functioning code compliant system?

8. Power Analysis

8.1 Did the submitted Power Analysis Studies Report or Protective Device Coordination Analysis (PDCA) demonstrate a properly coordinated system in multiple operating scenarios and system configurations?

8.2 Did the submitted Power Analysis Report provide organized Time Current Curves (TCC) for settable protective devices including circuit breakers, relays, and other components for better understanding of coordination within the protective devices?

8.3 Did the submitted Power Analysis Studies Report or Arc Flash Risk Assessment (AFRA) identify the flash-protection boundary and the incident energy at assigned working distances throughout any position or level in the overall electrical system, and specify the appropriate labels for each piece of equipment within the design?

Subtotal

This evaluation is worth a total of 13 points. The overall score for this section is calculated by dividing the number of “Yes” responses by the total number of questions and then multiplying the result by the total potential score. (Rounding up to three significant figures: X.XX)

_____ (Yes) / 31 (Yes + No) = _____ * 13 = _____ EG Design Overall Score

Phase 2, Volume 2, Factor 2 – UPS Design

OFFEROR
EVALUATOR
DATE

*If the answer is “NO” for this question, stop evaluation and score Factor 2, UPS as a zero.

Yes
No

1. Scope

1.1 *Did the submitted Project include Uninterruptible Power Systems (UPS), each 200 kVA or larger?

1.2 Did the Design Package clearly indicate installation of Switchboard(s) and/or Switchgear with Power Monitoring?

1.3 Did the Design Package provide sequenced drawings that show how the equipment and associated components will be installed or removed for each stage/phase in construction?

1.4 Did the Design Package include Electrical Installation Details that provide detailed electrical information necessary for installation?

1.5 Did the Design Package show a control wiring diagram that outlines all of the required control circuits for the system to operate?

1.6 Did the design package convey an understanding of the FAA specifications, standards, and orders listed in the Critical Power System SOW section C.2.2-C.2.4 AND/OR Industry Standards listed in section C.2.5?

2. Temporary System

2.1 Did the Design Package provide a detailed Temporary System One-Line diagram incorporating the temporary system into the existing facility?

2.2 Did the Design Package provide a detailed Temporary System layout that allows the installation contractor the capability to install the temporary system?

3. Demolition

3.1 Did the Design Package provide a Demolition Plan that includes demolition drawings that clearly shows what equipment will be removed and what equipment will be retained as part of the project?

4. UPS

4.1 Did the Design Package describe how the UPS was sized for the project? (Specification from the facility owner, load study, manufacturer provided sizing software, or other means.)

4.2 Did the Design Package include a detailed Parallel/Redundant UPS System Design that could be used to build a fully functional system?

5. Electrical

5.1 Did the Design Package show a new or existing panel schedule(s)?

5.2 Did the Design Package include and show compliance with the applicable NEC, OSHA, and FAA Standards, Specifications, and Orders?

5.3 Did the Design Package show an existing and/or new One-Line diagram that appropriately represents the overall system?

5.4 Did the Design Package Provide a detailed Cable and Conduit schedule?

5.5 Did the Design Package provide a detailed Equipment Layout that shows where the new equipment will be installed with proper equipment clearances compliant with NEC, OSHA and FAA Orders, Standards and Specifications as applicable?

5.6 Did the Design Package address points of egress per the NEC? (e.g., for equipment rated 1,200 amperes or above)

5.7 Did the Design Package provide detailed information for built in redundancy for system operability and sequence of operations?

6. Monitor and Control

6.1 Did the Offeror’s Design package describe experience integrating SCADA, HMI, RSP, RMP, or Power Control and Monitoring Systems?

6.2 Did the Design Package show point-to-point control wiring diagram that outlines all the required control circuits for the system to operate?

6.3 Did the Design Package describe designing new Power Control and Monitoring Systems and/or designing modifications to existing Power Control and Monitoring Systems?

6.4 Did the Design Package Power Control and Monitoring system include power quality monitoring, circuit breaker and electrical distribution equipment control and monitoring?

6.5 Did the Design Package Power Control and Monitoring system include UPS, control and/or monitoring?

6.6 Did the Design Package provide Control drawings that include network diagrams and block diagrams showing overall system integration?

7. Mechanical

7.1 Did the Design Package provide detailed mechanical drawings that show an HVAC system design that could be used to build a fully functioning code compliant system?

7.2 Did the mechanical drawings show detailed exhaust system connections, mounting points, and vibration isolation as required to build a fully functioning code compliant system?

8. Power Analysis

8.1 Did the submitted Power Analysis Studies Report or Protective Device Coordination Analysis (PDCA) demonstrate a properly coordinated system in multiple operating scenarios and system configurations?

8.2 Did the submitted Power Analysis Report provide organized Time Current Curves (TCC) for settable protective devices including circuit breakers, relays, and other components for better understanding of coordination within the protective devices?

8.3 Did the submitted Power Analysis Studies Report or Arc Flash Risk Assessment (AFRA) identify the flash-protection boundary and the incident energy at assigned working distances throughout any position or level in the overall electrical system, and specify the appropriate labels for each piece of equipment within the design?

Subtotal

This evaluation is worth a total of 13 points. The overall score for this section is calculated by dividing the number of “Yes” responses by the total number of questions and then multiplying the result by the total potential score. (Rounding up to three significant figures: X.XX)

_____ (Yes) / 29 (Yes + No) = _____ * 13 = _____ UPS Design Overall Score

Phase 2, Volume 2, Factor 2 – FST Design

OFFEROR
EVALUATOR
DATE

*If the answer is “NO” for this question, stop evaluation and score Factor 2, FST as a zero.

Yes
No

1. Scope

1.1 *Did the submitted Project include Fuel Storage Tanks (FST), each 5,000 gallons or larger, configured in parallel with environmental remote monitoring?

1.2 Did the Design Package provide sequenced drawings that show how the equipment and associated components will be installed or removed for each stage/phase in construction?

1.3 Did the Design Package include Electrical Installation Details that provide detailed electrical information necessary for installation?

1.4 Did the Design Package show a control wiring diagram that outlines all of the required control circuits for the system to operate?

1.5 Did the design package convey an understanding of the FAA specifications, standards, and orders listed in the Critical Power System SOW section C.2.2-C.2.4 AND/OR Industry Standards listed in section C.2.5?

2. Temporary System

2.1 Did the Design Package provide a detailed Temporary System One-Line diagram incorporating the temporary system into the existing facility?

2.2 Did the Design Package provide a detailed Temporary System layout that allows the installation contractor the capability to install the temporary system?

3. Demolition

3.1 Did the Design Package provide a Demolition Plan that includes demolition drawings that clearly shows what equipment will be removed and what equipment will be retained as part of the project?

4. Electrical

4.1 Did the Design Package show a new or existing panel schedule(s)?

4.2 Did the Design Package include and show compliance with the applicable NEC, OSHA, and FAA Standards, Specifications, and Orders?

4.3 Did the Design Package show an existing and/or new One-Line diagram that appropriately represents the overall system?

4.4 Did the Design Package Provide a detailed Cable and Conduit schedule?

4.5 Did the Design Package provide a detailed Equipment Layout that shows where the new equipment will be installed with equipment clearances compliant with NEC, OSHA and FAA Orders, Standards and Specifications as applicable?

4.6 Did the Design Package address points of egress per the NEC? (e.g. for equipment rated 1,200 amperes or above)

4.7 Did the Design Package provide detailed information for built in redundancy for system operability and sequence of operations?

5. Monitor and Control

5.1 Did the Design Package show point-to-point control wiring diagram that outlines all the required control circuits for the system to operate?

5.2 Did the Design Package describe designing new Power Control and Monitoring Systems and/or designing modifications to existing Power Control and Monitoring Systems?

5.3 Did the Design Package Power Control and Monitoring system include power quality monitoring, circuit breaker and electrical distribution equipment control and monitoring?

5.4 Did the Design Package include Automated Controls and Environmental Monitoring system for FST system.

5.5 Did the Design Package provide Control drawings that include network diagrams and block diagrams showing overall system integration?

6. Mechanical

6.1 Did the Design Package provide detailed mechanical drawings that show a fuel system design that could be used to build a fully functioning code compliant system?

6.2 Did the mechanical drawings show detailed exhaust system connections, mounting points, and vibration isolation as required to build a fully functioning code compliant system?

Subtotal

This evaluation is worth a total of 4 points. The overall score for this section is calculated by dividing the number of “Yes” responses by the total number of questions and then multiplying the result by the total potential score. (Rounding up to three significant figures: X.XX)

_____ (Yes) / 22 (Yes + No) = _____ * 4 = _____ FST Overall Score

Phase 2, Volume 2, Factor 3 – Category 2 Critical Power Systems Installation Proposal Questions Phase 2, Volume 2, Factor 3, Sub-Factor 3.1 – Capabilities Phase 2, Volume 2, Factor 3, Sub-Factor 3.1 – CPS Installation

OFFEROR
EVALUATOR
DATE

*If the answer is “NO” for this question, stop evaluation and score Sub-Factor 3.1,CPS as a zero.

Yes
No

1. Scope

1.1. * Did the submitted Project include Engine Generators (EGs), each 1000 kW or larger, configured in parallel AND Uninterruptible Power Systems (UPS), each 200 kVA or larger, configured in parallel AND/OR Fuel Storage Tanks (FST), each 5,000 gallons or larger, configured in parallel with environmental remote monitoring?

1.2. Did the Offeror's narrative clearly indicate installation of Switchboard(s) and/or Switchgear with Power Monitoring?

2. Temporary System

2.1 Did the Offeror’s narrative describe experience installing a temporary power system (EG, ATS, fuel tank, conductors and other ancillary equipment as required) to allow for removal and replacement of the existing EG and provide enough fuel (based on EG burn rate of GAL/HR) in order to keep facility operational during construction?

3. Cutover Plan

3.1 Did the Offeror provide a Cutover Plan that includes a description of each Shutdown/Cutover for the submitted project, along with a detailed sequence of events for each Shutdown/Cutover to ensure effective execution of the work and communication with all stakeholders?

4. Equipment Installation

4.1 Did the Offeror’s narrative describe EG Size(s), Manufacturer, and Model number(s) of the unit(s) installed?

4.2 Did the Offeror’s narrative describe UPS Size(s), Manufacturer, and Model number(s) of the unit(s) installed?

4.3 Did the Offeror’s narrative describe FST Size(s), Manufacturer, and Model Number(s), of the unit(s) installed?

4.4 Did the Offeror’s narrative describe experience with installing an Automatic Transfer Switch (ATS) and/or switchboard(s)/switchgear with an integral Automatic Transfer controller?

4.5 Did the Offeror’s narrative describe experience with installing Flooded/Wet cell batteries and/or installing Valve Regulated Lead Acid (VRLA) batteries?

4.6 Did the Offeror’s narrative describe experience with installing Parallel/Redundant EG Systems and/or Parallel/Redundant UPS Systems with Power Control and Monitoring Systems?

5. Startup and Commissioning of Equipment

5.1 Did the Offeror’s narrative describe experience with startup and commissioning of an engine generator or UPS (voltage, frequency, phase rotation and load testing)?

5.2 Did the Offeror’s narrative describe experience with verifying voltage, phase rotation, insulation resistance tests, load tests and load sharing?

5.3 Did the Offeror’s narrative describe experience with startup and commissioning of EDE equipment?

6. Project Cost and Schedule

6.1 Is the submitted project cost organized and structured to show a detailed cost breakdown by discipline (electrical, mechanical, structural, etc.) , labor, material, and other costs?

6.2 Did the Offeror submit a construction schedule which shows milestone dates and sequence of tasks and durations?

6.3 Did the installation have a test plan to check all the building controls functions as part of the equipment startup?

7. Fuel System

7.1 Did the Offeror’s narrative describe installing a Temporary Fuel System while replacing the existing fuel system to keep the facility operational?

7.2 Did the offeror’s narrative describe the installation or removal of UST, AST, fuel monitoring, fuel line installation, labeling and control system IAW the FST design and specifications in the SOW section C.2.1 and the documentation in the SOW for the Fuel System Program?

Subtotal

This evaluation is worth a total of 48 points. The overall score for this section is calculated by dividing the number of “Yes” responses by the total number of questions and then multiplying the result by the total potential score. (Rounding up to three significant figures: X.XX)

_____ (Yes) / 18 (Yes + No) = _____ * 48 = _____ CPS Installation Overall Score

Phase 2, Volume 2, Factor 3, Sub-Factor 3.1– EG Installation

OFFEROR
EVALUATOR
DATE

*If the answer is “NO” for this question, stop evaluation and score Sub-Factor 3.1,EG as a zero.

Questions
Yes
No

1. Scope

1.1. * Did the submitted Project include Engine Generators (EGs), each 1000 kW or larger, configured in parallel?

1.2. Did the Offeror's narrative clearly indicate installation of Switchboard(s) and/or Switchgear with Power Monitoring?

2. Temporary System

2.1 Did the Offeror’s narrative describe experience installing a temporary power system (EG, ATS, fuel tank, conductors and other ancillary equipment as required) to allow for removal and replacement of the existing EG and provide enough fuel (based on EG burn rate of GAL/HR) in order to keep facility operational during construction?

3. Cutover Plan

3.1 Did the Offeror provide a Cutover Plan that includes a description of each Shutdown/Cutover for the submitted project, along with a detailed sequence of events for each Shutdown/Cutover to ensure effective execution of the work and communication with all stakeholders?

4. Equipment Installation

4.1 Did the Offeror’s narrative describe EG Size(s), Manufacturer, and Model number(s) of the unit(s) installed?

4.2 Did the Offeror’s narrative describe experience with installing an Automatic Transfer Switch (ATS) and/or switchboard(s)/switchgear with an integral Automatic Transfer controller?

4.3 Did the Offeror’s narrative describe experience with installing Parallel/Redundant EG Systems with Power Control and Monitoring Systems?

5. Startup and Commissioning of Equipment

5.1 Did the Offeror’s narrative describe experience with startup and commissioning of an engine generator or UPS (voltage, frequency, phase rotation and load testing)?

5.2 Did the Offeror’s narrative describe experience with verifying voltage, phase rotation, insulation resistance tests, load tests and load sharing?

5.3 Did the Offeror’s narrative describe experience with startup and commissioning of EDE equipment?

6.Project Cost and Schedule

6.1 Is the submitted project cost organized and structured to show a detailed cost breakdown by discipline (electrical, mechanical, structural, etc.) , labor, material, and other costs?

6.2 Did the Offeror submit a construction schedule which shows milestone dates and sequence of tasks and durations?

6.3 Did the installation have a test plan to check all the building controls functions as part of the equipment startup?

7. Fuel System

7.1 Did the Offeror’s narrative describe installing a Temporary Fuel System while replacing the existing fuel system to keep the facility operational?

7.2 Did the offeror’s narrative describe the installation or removal of UST, AST, fuel monitoring, fuel line installation, labeling and control system IAW the FST design and specifications in the SOW section C.2.1?

Subtotal

This evaluation is worth a total of 22 points. The overall score for this section is calculated by dividing the number of “Yes” responses by the total number of questions and then multiplying the result by the total potential score. (Rounding up to three significant figures: X.XX)

_____ (Yes) / 15 (Yes + No) = _____ * 22 = _____ EG Installation Overall Score

Phase 2, Volume 2, Factor 3, Sub-Factor 3.1–UPS Installation

OFFEROR
EVALUATOR
DATE

*If the answer is “NO” for this question, stop evaluation and score Sub-Factor 3.1,UPS as a zero.

Yes
No

1. Scope

1.1 * Did the submitted Project include Uninterruptible Power Systems (UPS), each 200 kVA or larger, configured in parallel?

1.2 Did the Offeror's narrative clearly indicate installation of Switchboard(s) and/or Switchgear with Power Monitoring?

1. Temporary System

2.1 Did the Offeror’s narrative describe experience installing a temporary power system (conductors and other ancillary equipment as required) in order to keep facility operational during construction?

2. Cutover Plan

3.1. Did the Offeror provide a Cutover Plan that includes a description of each Shutdown/Cutover for the submitted project, along with a detailed sequence of events for each Shutdown/Cutover to ensure effective execution of the work and communication with all stakeholders?

3. Equipment Installation

4.1 Did the Offeror’s narrative describe UPS Size(s), Manufacturer, and Model number(s) of the unit(s) installed?

4.2 Did the Offeror’s narrative describe experience with installing Flooded/Wet cell batteries and/or installing Valve Regulated Lead Acid (VRLA) batteries?

4.3 Did the Offeror’s narrative describe experience with installing Parallel/Redundant UPS Systems and/or Parallel/Redundant UPS Systems with Power Control and Monitoring Systems?

4. Startup and Commissioning of Equipment

5.1 Did the Offeror’s narrative describe experience with startup and commissioning of an engine generator or UPS (voltage, frequency, phase rotation and load testing)?

5.2 Did the Offeror’s narrative describe experience with verifying voltage, phase rotation, insulation resistance tests, load tests and load sharing?

5.3 Did the Offeror’s narrative describe experience with startup and commissioning of EDE equipment?

6.Project Cost and Schedule

6.1 Is the submitted project cost organized and structured to show a detailed cost breakdown by discipline (electrical, mechanical, structural, etc.) , labor, material, and other costs?

6.2 Did the Offeror submit a construction schedule which shows milestone dates and sequence of tasks and durations?

6.3 Did the installation have a test plan to check all the building controls functions as part of the equipment startup?

Subtotal

This evaluation is worth a total of 22 points. The overall score for this section is calculated by dividing the number of “Yes” responses by the total number of questions and then multiplying the result by the total potential score. (Rounding up to three significant figures: X.XX)

_____ (Yes) / 13 (Yes + No) = _____ * 22 = _____ UPS Installation Overall Score

Phase 2, Volume 2, Factor 3, Sub-Factor 3.1 – FST Installation

OFFEROR
EVALUATOR
DATE

*If the answer is “NO” for this question, stop evaluation and score Sub-Factor 3.1,FST as a zero.

Questions
Yes
No

1. Scope

1.1 *Did the submitted Project include Fuel Storage Tanks (FST), each 5,000 gallons or larger, configured in parallel with environmental remote monitoring?

2. Cutover Plan

2.1 Did the Offeror provide a Cutover Plan that includes a description of each Shutdown/Cutover for the submitted project, along with a detailed sequence of events for each Shutdown/Cutover to ensure effective execution of the work and communication with all stakeholders?

3. Equipment Installation

3.1 Did the Offeror’s narrative describe FST Size(s), Manufacturer, and Model number(s) of the unit(s) installed?

4. Startup and Commissioning of Equipment

4.1 Did the Offeror’s narrative describe experience with startup and commissioning of EDE equipment?

5. Project Cost and Schedule

5.1 Is the submitted project cost organized and structured to show a detailed cost breakdown by discipline (electrical, mechanical, structural, etc.) , labor, material, and other costs?

5.2 Did the offeror submit a construction schedule which shows milestone dates and sequence of tasks and durations?

5.3 Did the installation have a test plan to check all the building controls functions as part of the equipment startup?

6. Fuel System

6.1 Did the offeror’s narrative describe the installation or removal of UST, AST, fuel monitoring, fuel line installation, labeling and control system IAW the FST design and specifications in the SOW section C.2.1?

Subtotal

This evaluation is worth a total of 4 points. The overall score for this section is calculated by dividing the number of “Yes” responses by the total number of questions and then multiplying the result by the total potential score. (Rounding up to three significant figures: X.XX)

_____ (Yes) / 8 (Yes + No) = _____ * 4 = _____ FST Installation Overall Score

Phase 2, Volume 2, Factor 3, Sub-Factor 3.2 – Complexity

OFFEROR
EVALUATOR
DATE

*If the answer is “NO” for this question, stop evaluation and score Sub-Factor 3.2 as a zero.

Question
Yes
No

1. *Did the offeror's submission include three (3) projects (with at least one Category 2 project) that meet the Category type(s) in SOW Section 1.1, with an overlap of 90 calendar days of *active construction and meet the minimum physical distance of 5 miles away from the address listed for each project submitted? (1 point)

2. Did the offeror's submission include three (3) projects (with at least two Category 2 projects) that meet the Category type(s) in SOW Section 1.1, with an overlap of 90 calendar days of *active construction and meet the minimum physical distance of 5 miles away from the address listed for each project submitted? (1 point)

3. Did the offeror's submission include three (3) Category 2 projects that meet Category 2 in SOW Section 1.1, with an overlap of 90 calendar days of *active construction and meet the minimum physical distance of 5 miles away from the address listed for each project submitted? (1 point)

4. Did at least one of the submitted projects have a power system installation that meets the qualifications for an NPFA 110 Level 1 System? (1 point)

5. Do at least two of the submitted projects have a power system installation that meets the qualifications for an NPFA 110 Level 1 System? (1 point)

6. Do three of the submitted projects have a power system installation that meets the qualifications for an NPFA 110 Level 1 System? (1 point)

Subtotal

This evaluation is worth a total of 12 points. The overall score for this section is calculated by dividing the number of “Yes” responses by the total number of questions and then multiplying the result by the total potential score. (Rounding up to three significant figures: X.XX)

_____ (Yes) / 6 (Yes + No) = _____ * 12 = _____ Complexity Overall Score

* Active Construction is defined as the period of time following completion of mobilization and commissioning equipment.