This is a Price Proposal Form for RFP No. ISD_384202_DA issued by Fermilab for the MINOS High Bay Roof Replacement and Masonry Wall Repair project. The proposal was originally issued August 1, 2026, with a revision dated September 25, 2026.

Offerors must provide pricing in two phases: Phase 1 requires a Lump Sum Base Price for three line items including masonry wall investigation only, roof replacement, and a leak detection test to be performed one year after installation (which must be priced separately from the roof replacement). Phase 2 requires all-inclusive unit pricing for masonry and parapet wall repair work across thirteen line items (003-A through 003-M), including tuckpointing, brick replacement, coping stone resetting and replacement, through-wall flashing and membrane installation, weep hole restoration, joint sealing, roof membrane integration, CMU backup grouting, parapet anchors, drainage restoration, and thermal bridging mitigation. Quantities for Phase 2 are estimated for bid evaluation purposes only, with final quantities to be determined after field investigation and field-verified jointly by the subcontractor, architect/engineer, and FFDG; offerors will be paid at their proposed unit prices regardless of final quantity adjustments. All unit prices must be all-inclusive of labor, materials, equipment, scaffolding, disposal, overhead, profit, incidentals, and bonding, with no additional mobilization or equipment fees permitted for quantity adjustments. No masonry unit-price work may proceed without prior written authorization for Phase 2. The proposal acceptance period is ninety (90) days from the opening date unless the offeror specifies a longer period.

View the file

Other files

File Type Posted
Pre-Proposal Sign In Sheet_Minos roof-wall_2nd Site Visit.pdf PDF
QandA-Minos Roof and Masonry Wall1_Response_Final.pdf PDF
Response8-PLM Results Report - Lab F - MINOS - F38FC - NWA.pdf PDF
6-7-126_MINOS_G-01 COVER SHEET_REV01.pdf PDF
SECTION 075419 - POLYVINYL-CHLORIDE (PVC) ROOFING_Amendment2.pdf PDF
Amend 02 to RFP ISD_384202_DA.pdf PDF
6-7-126_MINOS_A-01 PLAN - REV01.pdf PDF
6-7-126_MINOS_G-02 GENERAL NOTES_REV01.pdf PDF
Second Site Visit-Business Visitor Registration Instructions and Directions.pdf PDF
Amend 01 to RFP ISD_384202_DA.pdf PDF
Pre-Proposal Meeting-Sign in Sheet.pdf PDF
1.0 Request for Proposal_ISD_384202_DA.pdf PDF
Exhibit E Bid Bond FL-41.pdf PDF
Exhibit H Fermilab Subcontractor Safety Information Questionnaire.pdf PDF
Exhibit K SARC_Subcontractor Annual RepsCerts Rev 8.pdf PDF
Exhibit L General Decision No IL20260008 Mod2_2026_0518.pdf PDF
Exhibit N FL-61 (Rev. 1-07).pdf PDF
2.0 Price Proposal Form_Final_fill-ins.pdf PDF
Attach A 6-7-126_SOW_Minos Roof_High Bay_wall repair_v5.pdf PDF
Exhibit F Payment Bond FL-42_FFDG.pdf PDF
Exhibit G Performance Bond FL-40_FFDG.pdf PDF
Exhibit J PUR-466_Proposal Certifications_r5_10.14.25.pdf PDF
Exhibit O 6-7-126 MINOS HIGH BAY ROOF_MASONRY WALL REPAIR_drawing set.pdf PDF
Exhibit Q Business Visitor Registration Instructions and Directions-MinosRoof_MasonryWall.pdf PDF
Exhibit R Fermilab Site Map-MINOS.pdf PDF
Attach B 6-7-126_MINOS HB ROOF REPLACEMENT_PROJECT MANUAL_260803.pdf PDF
Exhibit C FFDG General Terms and Conditions for Construction (08.2025).pdf PDF
Exhibit D 2025 Construction Insurance Requirements.pdf PDF
Exhibit I SF1413_fill-ins.pdf PDF
Exhibit M Sample FFP Subcontract.pdf PDF
Exhibit P Summary of Required Solicitation Documents.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR PROPOSAL NO. ISD_384202_DA

PRICE PROPOSAL FORM

August 5, 2026

Revised September 25, 2026

PROJECT: MINOS High Bay Roof Replacement and Masonry Wall Repair

In accordance with the Request for Proposal dated August 1, 2026 the undersigned hereby proposes to furnish all labor, equipment, materials, transportation, overhead, bonding costs, insurance, safety oversight, quality control oversight, supervision and perform all work necessary for the subject project in strict accordance with the Statement of Work, Project Manual, Specifications, Drawings, and other solicitation documents, for the following:

Offerors shall provide a Lump Sum Base Price for the defined scope of work (Phase 1), along with Unit Prices for the masonry wall repair (Phase 2).

LUMP SUM PRICING – PHASE 1

Subcontract Line Item Number

Work Description Unit of Measure

Contractor Proposed Price ($)

001 Masonry Wall – Investigation Only Lump Sum $

002 Roof Replacement Lump Sum $

002a Leak Detection Test – Final Test One Year After Installation. This price should not be included in line item number 002.

Lump Sum $

SUBTOTAL $

UNIT PRICES – MASONRY AND PARAPET WALL REPAIR – PHASE 2

All offerors must provide unit pricing for the items listed below. Final quantities will be determined after field investigation and will be field-verified jointly by the Subcontractor, A/E, and FFDG.

Subcontract Line Item Number

Work Description Unit of Measure

Contractor Proposed Unit Price ($/Unit)

Approximate Quantity**

Extended Price

003 SUBTOTAL FOR MASONRY AND PARAPET WALL REPAIR $________

003-A Tuckpointing/ Joint Raking:

Rake out deteriorated mortar joints to a depth of 3/4" and re-point with matching mortar.

Hundred Square Foot

(CSF)

003-B Replacement Bricks due to structural or through-cracks, severe or unrepairable spalling, and saturation damage/ freeze-thaw failure.

Hundred

(CSF)

003-C Coping Stone Resetting:

Carefully remove existing coping stone, clean bed, apply new membrane/flashing, and reset stone in new mortar bed with sealant joints.

Linear Foot

(LF)

003-D Coping Stone Replacement:

Furnish and install new limestone coping stone matching existing profile and drip kerfs (includes setting and sealing).

003-E Through-Wall Flashing & Membrane: Supply and install stainless steel through-wall flashing with end dams and self-adhering membrane.

(SF)

003-F Weep Hole / Cavity Restoration: Clean clogged weep holes, install new cotton wick/mesh weeps, and clear mortar droppings from cavity.

Each (EA)

003-G Masonry Joint / Crack Injection & Sealing: Deep-fill sealant or specialized elastomeric joint sealant at coping/wall stress points.

003-H As per sheet G-02 item 5.M

ROOF MEMBRANE AND

WATERPROOFING

INTEGRATION: Install a fluid-applied air barrier behind the veneer, ensuring it ties into the roof membrane, so the air and water barrier remain continuous. Masonry backup and cavity drainage.

003-I Sheet G-02, 5.N.1. Top course of cmu backup shall be fully grouted and protected with peel and stick membrane

Cubic Foot

(CF)

003-J Sheet G-02, 5.N.2. Provide continuous stainless steel parapet anchors where required.

Each (EA)

003-K Sheet G-02, 5.N.3. Provide weep holes at 24” o.c. max above roof through wall flashing and at base of masonry wall.

Each (EA)

003-L Sheet G-02, 5.N.4. Restore or clear blocked drainage cavities as required.

003-M Sheet G-02, 5.N.5. Provide continuity between roof insulation and wall insulation to minimize thermal bridging.

**The quantities listed in the Unit Prices table are estimates and provided solely for bid evaluation and comparison purposes. Final quantities will be determined after field investigation and paid at the Offeror’s proposed Unit Prices.

FFDG makes no guarantee of minimum or maximum quantities.

Notes on Masonry and Parapet Wall Repair Unit Prices:

1. Proposed unit prices must be all-inclusive (labor, material, equipment, scaffolding/access, disposal, overhead, profit, incidentals, and bonding). No additional mobilization or equipment fees will be allowed for quantity adjustments within the masonry scope.

2. No masonry unit-price work shall proceed without prior written authorization for Phase 2.

3. All Unit Price items shall be provided and installed as described in the Statement of Work, Project

Manual, Specifications, Drawings, and other solicitation documents.

This Proposal may be accepted for a period of ninety (90) days after the opening date unless the Offeror specifies a longer acceptance period than Fermilab’s minimum requirement.

Company Name

Signature

Name & Title of Individual

Date

fill_8:
fill_11:
fill_14:
fill_15:
undefined:
undefined_2:
undefined_4:
undefined_6:
undefined_8:
undefined_10:
undefined_12:
undefined_15:
undefined_16:
undefined_18:
undefined_20:
undefined_23:
undefined_24:
undefined_28:
undefined_30:
undefined_31:
undefined_32:
undefined_33:
undefined_34:
undefined_35:
undefined_36:
Company Name:
Name Title of Individual:
Date:
undefined_27:
Text1:
Text2:
Text3:
Text4:
Text5:

File details come from the government source that posted it. Updated .