Attach B 6-7-126_MINOS HB ROOF REPLACEMENT_PROJECT MANUAL_260803.pdf

PDF 4 MB Posted

Attached to
MINOS High Bay Roof Replacement & Masonry Wall Repair
Solicitation number
ISD_384202_DA
Issued by

About this file

This is a Project Manual and General Requirements specification document for ISD/E Project No. 6-7-126, the MINOS High Bay Roof Replacement and Masonry Wall Repair project at Fermi National Accelerator Laboratory (Fermilab) in Batavia, Illinois. The document establishes comprehensive technical and administrative requirements for subcontractor performance.

The primary scope of work includes complete removal of existing roofing and insulation down to bare metal decking, installation of a new PVC adhered roofing system (Sika Sarnafil Adhered Assembly meeting FM RoofNav requirements 461650-0-0), and comprehensive masonry wall repairs on the north side of the MINOS Building. Roof work encompasses removal of existing trim, fascia, gravel stops, and coping; inspection and repair of metal decking as necessary; relocation of existing roof equipment; provision of new metal decking, protective pads, and all flashings and drainage accessories. Masonry repairs include investigation of water intrusion sources, removal of deteriorated coping components, installation of peel-and-stick membrane, stainless steel through-wall flashing, coping stone restoration, and tuckpointing. The subcontractor must furnish all labor, materials, equipment, transportation, overhead, bonding costs, and quality/safety oversight. The project follows a 140-calendar-day schedule with milestones: masonry investigation (Days 0-5), submittal review (Days 5-20), masonry repair and tuckpointing (Days 20-65), 30-day curing period (Days 65-95), roof replacement mobilization and execution (Days 95-125), and project completion including punchlist and demobilization (Days 125-140). FFDG furnishes 120v electrical power for hand tools and coordinates de-energization of building systems with 48-hour advance notice; subcontractor provides all other services, facilities, and temporary utilities. Key submittals required prior to Notice to Proceed include insurance certificates, bonds, project hazard analysis, cost-loaded construction schedule, project-specific quality control plan, and Environment, Safety and Health (ES&H) documentation. The specification incorporates extensive ES&H requirements including compliance with 10 CFR 851 and 835, OSHA standards, NFPA codes, and Fermilab-specific safety protocols. FFDG maintains a Construction Management Office including a Procurement Administrator (Danielle Amico, damico@fnal.gov, 630-840-3207), Construction Manager Jacquelyn Dragovich (jdragovi@fnal.gov, 630-840-5440), and supporting coordinators responsible for design, construction, and ES&H oversight. The subcontractor is required to maintain weekly progress meetings, as-built documentation, quality control punchlists, and comprehensive records of all construction activities and safety compliance.

View the file

Other files

File Type Posted
6-7-126_MINOS_G-02 GENERAL NOTES_REV01.pdf PDF
QandA-Minos Roof and Masonry Wall1_Response_Final.pdf PDF
SECTION 075419 - POLYVINYL-CHLORIDE (PVC) ROOFING_Amendment2.pdf PDF
Amend 02 to RFP ISD_384202_DA.pdf PDF
6-7-126_MINOS_G-01 COVER SHEET_REV01.pdf PDF
Response8-PLM Results Report - Lab F - MINOS - F38FC - NWA.pdf PDF
2.0 Price Proposal Form_Final_R1_fill-ins.pdf PDF
Pre-Proposal Sign In Sheet_Minos roof-wall_2nd Site Visit.pdf PDF
6-7-126_MINOS_A-01 PLAN - REV01.pdf PDF
Amend 01 to RFP ISD_384202_DA.pdf PDF
Second Site Visit-Business Visitor Registration Instructions and Directions.pdf PDF
Pre-Proposal Meeting-Sign in Sheet.pdf PDF
Exhibit C FFDG General Terms and Conditions for Construction (08.2025).pdf PDF
Exhibit D 2025 Construction Insurance Requirements.pdf PDF
Exhibit J PUR-466_Proposal Certifications_r5_10.14.25.pdf PDF
Exhibit Q Business Visitor Registration Instructions and Directions-MinosRoof_MasonryWall.pdf PDF
Attach A 6-7-126_SOW_Minos Roof_High Bay_wall repair_v5.pdf PDF
Exhibit L General Decision No IL20260008 Mod2_2026_0518.pdf PDF
Exhibit O 6-7-126 MINOS HIGH BAY ROOF_MASONRY WALL REPAIR_drawing set.pdf PDF
Exhibit F Payment Bond FL-42_FFDG.pdf PDF
2.0 Price Proposal Form_Final_fill-ins.pdf PDF
1.0 Request for Proposal_ISD_384202_DA.pdf PDF
Exhibit H Fermilab Subcontractor Safety Information Questionnaire.pdf PDF
Exhibit G Performance Bond FL-40_FFDG.pdf PDF
Exhibit K SARC_Subcontractor Annual RepsCerts Rev 8.pdf PDF
Exhibit E Bid Bond FL-41.pdf PDF
Exhibit N FL-61 (Rev. 1-07).pdf PDF
Exhibit R Fermilab Site Map-MINOS.pdf PDF
Exhibit M Sample FFP Subcontract.pdf PDF
Exhibit I SF1413_fill-ins.pdf PDF
Exhibit P Summary of Required Solicitation Documents.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT MANUAL

MINOS HIGH BAY ROOF

REPLACEMENT and MASONRY WALL

REPAIR

ISD/E Project No. 6-7-126 Wilson Hall Floor 16 Electric and Elevator Machine Rooms Fire Rating and Mechanical Upgrade

ISD/E Project No. 2-1-561

Version History

06/24/2026 ISSUED FOR REQUISITION TO PROCUREMENT AND BIDDING

08/03/2026 REVISED TO INCLUDE MASONRY WALL REPAIR. ISSUED FOR

REQUISITION TO PROCUREMENT AND BIDDING

Bookmark Summary

TABLE OF CONTENTS- BOOKMARK SUMMARY

EXHIBIT A DOCUMENTS

SECTION 010010 - GENERAL REQUIREMENTS

SECTION 013100 - ENVIRONMENT, SAFETY AND HEALTH REQUIREMENTS

SECTION 013300 - SUBMITTALS

SECTION 014100- QUALITY REQUIREMENTS

SECTION 040120.63 - BRICK MASONRY REPAIR

SECTION 040120.64 - BRICK MASONRY REPOINTING

SECTION 053100 - STEEL DECKING

SECTION 061000 - ROUGH CARPENTRY

SECTION 070150.19 - PREPARATION FOR REROOFING

SECTION 075419 - POLYVINYL-CHLORIDE (PVC) ROOFING

SECTION 076200 - SHEET METAL FLASHING AND TRIM

SECTION 077273 - MEMBRANE INTEGRITY TESTING SYSTEMS

8/2/2026

EXHIBIT A DOCUMENTS

SECTION 010010 – GENERAL REQUIREMENTS

Fermi Forward Discovery Group, LLC General Requirements March 2025

GENERAL REQUIREMENTS Project No. 6-7-126 010010 - 1

SECTION 010010 – GENERAL REQUIREMENTS

MINOS HIGH BAY ROOF REPLACEMENT

PART 1 GENERAL

1.1 PURPOSE

1.2 SUMMARY

1.3 REFERENCES

1.4 SITE LOCATION

1.5 DESCRIPTION OF WORK

1.6 MATERIALS & EQUIPMENT FURNISHED BY FERMILAB

1.7 BUY AMERICAN ACT

1.8 SERVICES FURNISHED BY FERMILAB

1.9 ITEMS AFFECTING WORK PLANNING

1.10 ELECTRONIC PROJECT DRAWINGS

1.11 PARKING AND STAGING AREA

1.12 SITE ACCESS AND HAULING

1.13 TRANSPORTATION OF EQUIPMENT AND MATERIALS

1.14 TEMPORARY SERVICES AND FACILITIES

1.15 FERMILAB CLOSURE

1.16 MATERIAL SUBSTITUTIONS

1.17 DOCUMENTATION

1.18 SUBCONTRACTOR’S REQUESTS FOR INFORMATION (RFI)

PART 2 PRODUCTS - Not Used

PART 3 EXECUTION

3.1 NOTICE TO PROCEED

3.2 CONSTRUCTION SCHEDULE

3.3 QUALITY CONTROL AND CONTROL OF INSTALLATION

3.4 ACCEPTANCE

ATTACHMENT A REQUEST FOR INFORMATION

ATTACHMENT B QA/QC PUNCHLIST ITEM STATUS

GENERAL REQUIREMENTS Project No. 6-7-126 010010 - 2

SECTION 010010 – GENERAL REQUIREMENTS

MINOS HIGH BAY ROOF REPLACEMENT

PART 1 GENERAL

1.1 PURPOSE

The following specification provides the project-specific requirements that are supplementary to the requirements of the Fermi Forward Discovery Group, LLC (FFDG) Subcontract General Provisions and the FFDG General Terms and Conditions for Construction.

The Subcontractor is required to plan, control, and deliver the final project according to the project specifications. The project must possess complete functional systems and be assembled safely and in quality fashion following industry standards, regulatory requirements, and best practices.

1.2 SUMMARY

The Subcontractor shall provide in the performance of the work under this subcontract all labor, materials, equipment, transportation, services, occupational exposure monitoring and supervision required to maintain work sites that meet the ES&H requirements found in Section 013100.

All major elements of the work are believed to be adequately described herein. The Subcontractor is expected, as a requirement of the Subcontractor’s qualifications, to utilize his or her knowledge and experience to anticipate, and include in the cost of the work any incidentals of work which may be required, but are not specifically expressed herein, in order to provide a complete and fully functional facility and/or system.

Definitions and roles and responsibilities can be found in Section 013100.

FFDG Construction Management Office:

TITLE

NAME EMAIL PHONE

Procurement Administrator:

Danielle Amico

Construction (Project) Manager

Jacquelyn Dragovich jdragovi@fnal.gov 630.840.5440

Design Coordinator Jacquelyn Dragovich jdragovi@fnal.gov 630.840.5440

Construction Coordinator

TBD

ES&H Coordinator

TBD

Quality Assurance Coordinator

TBD

damico@fnal.gov 630-840-3207 mailto:jdragovi@fnal.gov mailto:jdragovi@fnal.gov

GENERAL REQUIREMENTS Project No. 6-7-126 010010 - 3

1.3 REFERENCES

The publications listed below form a part of this subcontract to the extent referenced FFDG General Terms and Conditions for Construction (08/2025) 010010 General Requirements 013100 Environment, Safety, and Health Requirements

The publications listed below form a part of this specification to the extent referenced.

013300 Submittals 014100 Quality Requirements 053100 Steel Decking 06100 Rough Carpentry 061600 Sheathing

070150.19 Preparation for Reroofing

075419 Polyvinyl Chloride PVC Roofing 076200 Sheet Metal Flashing and Trim 077100 Roof Specialties 077200 Roof Accessories 077273 Membrane Integrity Test Systems

Drawings:

1.4 SITE LOCATION

The Subcontractor shall confine all operations (including storage of materials) on Fermilab premises to areas authorized or approved by FFDG. The Subcontractor shall hold and save FFDG and the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Subcontractor’s performance.

The project is located on the Fermi National Accelerator Laboratory (Fermilab) Site, adjacent to the city of Batavia, Illinois. The project is in Kane County, located on South

GENERAL REQUIREMENTS Project No. 6-7-126 010010 - 4 side of Pine Street. Access to building is from Indian Creek Road and Schwahn Road.

Refer to sheet G-01 for vicinity map.

1.5 DESCRIPTION OF WORK

The Subcontractor shall furnish all required supervision, labor, materials, tools, plant and appurtenances necessary to perform diligently and fully all work as described in the drawings and technical specifications. All work includes transportation, overhead, bonding costs, safety oversight, quality control oversight, and supervision as required to construct the project described in the drawings, technical specification and the detailed description contained herein.

The Subcontractor’s scope of work is not limited to the general work outline described below. The Subcontractor shall perform all work required to complete the construction work in accordance with the drawings and/or specifications. The description and quantities listed below are general in nature and are only intended to describe the range and complexity of this scope of work. The description and quantities provided below are not to be used as the basis for establishing a cost proposal. Specific quantities and definitions of the scope of work for providing a proposal shall be based solely on estimates developed by the Offer from the drawings, specifications, and the information obtained from examining of the project site.

Furnish all labor, materials and equipment required to remove and dispose of existing roofing and insulation down to bare roof decking. Replace with new PVC adhered roofing system, including miscellaneous associated work as described in the project manual and drawing set "6-7-126_Minos High Bay Roof and Masonry Wall Repair”, dated August 3, 2026. Repair of masonry wall on north side of Minos Building as per project manual and drawing set.

Roof replacement:

Provide all labor, materials, and equipment for the associated work including but not limited to the following:

Existing roof to be removed down to metal decking.

Removal of roofing trim, fascia, gravel stops and coping.

Inspection and repair of metal decking if necessary.

Removal of top access only roof hatch (2’ x 8’ approx.). Provide new metal decking to match existing.

Relocation and reinstallation of existing roof equipment.

Removal and replacement of all roofing trim, fascia, gravel stops and coping.

Provide new PVC adhered roofing assembly. PVC roofing assembly will by Sika Sarnafil Adhered Assembly to meet FM RoofNav requirements number 461650-0-0.

Furnish all protective roof pads, walkway pads, and equipment curbs required to accommodate existing equipment as noted on drawings.

Furnish all flashings, scuppers, and associated accessories to provide positive drainage for roofing system.

Refer to specifications and project manual for additional information.

Masonry Wall repair:

GENERAL REQUIREMENTS Project No. 6-7-126 010010 - 5

Furnish all labor, materials and equipment required to repair existing masonry wall, including miscellaneous associated work as described in the project manual and drawing set "6-7-126_Minos High Bay Roof and Masonry Wall Repair”, dated August 3, 2026.

Masonry wall repair work must be coordinated with the Minos High Bay Roof Replacement.

Subcontractor in coordination with FFDG Construction Coordinator and FFDG Architect/ Project Manager will review existing conditions to identify potential sources of water intrusion, including coping stone conditions, membrane failures, flashing issues, porous limestone, and inadequate drainage. Subcontractor to submit a comprehensive repair approach summary. Refer to General Notes – Minos Masonry Wall Repair in drawing set for more information.

FFDG must approve of subcontractor’s repair approach summary before subcontractor moves forward with repairs.

After Scope investigation is complete, subcontractor must be prepared to correct, including but not limited to the following:

Missing or failed coping flashing/membrane.

Porous/ cracked limestone coping Open joints under coping Missing Kerfs/ drip edges Failed/ clogged/ missing weep holes Deteriorated through- wall flashings Thermal- movement related to coping joint cracks Unsealed dowel/pin penetrations.

Tuckpointing In the absence of a finalized strategy, the subcontractor should follow the general work sequence outlined below.:

Remove coping stones and deteriorated components as needed.

Subcontractor to begin at highest point of masonry wall above high bay roof. Clean and inspect parapet top.

Examine substrate and conditions of work and notify FFDG Construction Coordinator and FFDG Project Manager in writing of detrimental conditions. Do not proceed until unsatisfactory conditions have been corrected

Install peel and stick membrane over parapet top.

Install stainless steel through wall flashing with end dams.

Reset or replace coping stones with correct slope and drip kerfs.

Seal coping joints with appropriate sealant.

Restore drainage cavity and weeps.

Perform final tuckpointing of masonry joints.

1.6 MATERIALS & EQUIPMENT FURNISHED BY FFDG

No materials and equipment are anticipated to be furnished by FFDG for this project.

GENERAL REQUIREMENTS Project No. 6-7-126 010010 - 6

1.7 BUY AMERICAN ACT

FFDG maintains a preference for domestic construction material. In accordance with FFDG General Terms and Conditions for Construction, the following construction material or components are exempt from the Buy American Act.

There are no exemptions for this project.

1.8 SERVICES FURNISHED BY FFDG

FFDG will furnish the services as described below:

Electrical Power: Electrical power at 120v for hand tools will t be provided at the project site.

Drinking Water: FFDG will not provide drinking water for this project.

Toilet Facilities: FFDG will not provide toilet facilities for this project.

Existing Utility Locates: FFDG will provide locates of existing known utilities as defined in Section 013100 Part 6.18 B. The Subcontractor shall excavate electrical, fiber optics, and gas utilities, in accordance with Section 013100 Part 6.18.

Fermilab existing utility and building services shall be coordinated with the FFDG Construction Coordinator:

FFDG will de-energize and re-energized the existing Domestic Water System (DWS), Industrial Cooling Water (ICW), Low Conductivity Water (LCW), fire protection suppression system, electrical services entering facilities, and fire detection in the building(s). These activities shall be coordinated through the FFDG Construction Coordinator. The construction Coordinator shall be notified a minimum 48 hour prior to systems needing to be de-energized.

FFDG furnished services shall be coordinated with the FFDG Construction Coordinator.

The FFDG Construction Coordinator coordinates issuance of permits, reference Section 013100 for additional information;

The FFDG Construction coordinator or designee requests for and provides disablement of existing systems; Availability and use of existing Fermilab utility services will comply with Section 013100, Part 6.18.

Electrical Power:

Article 1.8, paragraph A.1 above describes the electric power that will be furnished by FFDG for the Subcontractor’s use;

Installation of the Subcontractor’s electrical power distribution shall include ground-fault circuit protection and shall be subject to FFDG approval;

Any additional power required not specified shall be furnished and paid for by the Subcontractor.

Drinking Water:

Article 1.8, paragraph A.2 above describes the drinking water that will be furnished by FFDG for the Subcontractor’s use;

The FFDG Construction Coordinator shall approve drinking water distribution containers. Water shall be adequate, clean and dispensed from a fully enclosed potable water container with individual paper drinking cups;

GENERAL REQUIREMENTS Project No. 6-7-126 010010 - 7

The Subcontractor shall furnish and pay for any additional potable water required.

Toilet Facilities:

Article 1.8, paragraph A.3 above describes the Fermilab toilet facilities that will be available for the Subcontractor’s use;

When Fermilab toilet facilities are not available to the Subcontractor, the

Subcontractor shall provide an adequately serviced chemical toilet for every twenty (20) personnel on the project;

The FFDG Construction Coordinator shall approve of the toilet type and locations.

1.9 ITEMS AFFECTING WORK PLANNING

Safety Representative: Subcontractor Safety Representative is required on the project.

Reference Section 013100, Part 6.2.B for further information regarding the onsite safety representative.

Additional Training: Additional training provided by FFDG other than the subcontractor’s orientation as specified in Section 013100,Part 4.2.B for further information.

Lockout Tagout Training FFDG’s LOTO II training will be required.

Fall Protection – Competent person Fall Protection Training for Construction Ladder Safety Training Aerial Lift Training Scaffold User/ Builder Training.

Erosion Control: No erosion control is anticipated for this project as delineated in Section 013100, Part 6.19.

Metal Recycling: State if metal is acceptable for commercially recycling.

Waste Disposal: The laboratory will dispose of existing regulated waste or laboratory generated regulated waste. The Subcontractor is permitted to dispose of any regulated waste that is generated during the performance of this subcontract. However, the subcontractor is required to notify the Construction Coordinator prior to the commencement of any regulated waste generation and off-site shipments of any waste materials destined for disposal.

No regulated waste is anticipated for this project.

Reporting: Subcontractor shall submit recycling data from vendor, reference Section 013100 Part 7.2.E for additional information.

Fermilab On-Going Operations:

The Subcontractor has to accommodate any on-going Fermilab operations, such as overhead crane access, access to existing mechanical or electrical equipment. The Subcontractor is responsible to provide covering or enclosure to protect existing equipment and employees as necessary.

The Subcontractor shall maintain and protect all building exits.

The Subcontractor shall keep specified areas clear and not allowable for storage of materials as noted on Sheet G-02.

GENERAL REQUIREMENTS Project No. 6-7-126 010010 - 8

1.10 ELECTRONIC PROJECT DRAWINGS

FFDG may, at the Subcontractor’s request and in accordance with technical specifications, release “electronic” project drawings for use in preparation of shop drawings by the Subcontractor or Sub-tier subcontractors or vendors.

These electronic drawings will be distributed to the Subcontractor utilizing FFDG’s current file and media format.

The project design drawings reflect the intent and scope of the project and general routing.

The routing of utilities and building/facility services indicated on the design drawings is for providing proposal only. The Subcontractor and/or Sub-subcontractors are expected to make a site visit and make allowances for all necessary adjustments for the actual system installation and to examine physical conditions which may be material to the performance of his or her work, and coordinate the actual routing as necessary to accommodate the existing conditions, obstructions, and the work of other trades.

1.11 PARKING AND STAGING AREA

Parking of the Subcontractor’s and the Sub-tier subcontractor’s vehicles shall be confined to the Subcontractor’s designated construction area or general public parking spaces.

The Subcontractor shall provide and maintain temporary barricades, fences, or other means to delineate the construction limits, as required for the protection of public and FFDG employees. Provide signage at all entrances to the construction site with the Subcontractor’s company’s name and contact information. Signage shall include Danger Construction Area, Do Not Enter. Visitors shall sign-in with the Subcontractor’s representative and must be aware of the current hazards and conditions and be escorted either by the Subcontractor or a representative of the Construction Management Office.

The Subcontractor’s parking and staging area will be prescribed by the construction coordinator. Construction Coordinator will provide more information which will include requirement if the staging area is to be fenced, where trailers can be located, etc.

No material shall be stored beyond the construction limits unless prior written arrangements have been made through the FFDG Construction Coordinator.

1.12 SITE ACCESS AND HAULING

The Subcontractor shall, under regulations prescribed by FFDG, use only established roadways and use such temporary roadways constructed by the Subcontractor when and as may be authorized by FFDG. Where materials are transported during the course of the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicles or prescribed by any Federal, State or local law or regulation. When it is necessary to cross curbings or sidewalks, the Subcontractor shall protect them from damage. The Subcontractor shall repair or pay for the repair of any damaged curbs, sidewalks or roads.

GENERAL REQUIREMENTS Project No. 6-7-126 010010 - 9

Construction equipment and delivers to the site are restricted to the Wilson Street Gate Entrance. At the discretion of FFDG, the Kautz Road access point from Butterfield Road may be used on unique deliveries, such as concrete. Access must be arranged at a minimum of 48 hours prior to the use of this access point through the Construction Coordinator.

Fermilab site access and hauling shall be subject to the following conditions:

Electronic communication devices, such as cell phones, texting devices, laptops, etc. must not be used while driving any motor vehicle on Fermilab’s site;

All roads shall remain open to emergency traffic at all times;

All equipment and vehicles shall be confined to operating along defined construction roads and approved access routes;

No overland hauling or off-road travel shall be permitted without prior approval of the FFDG Construction Coordinator;

Interruption of normal traffic patterns or temporary road closings necessitated by movement of equipment or delivery of materials or utility installations shall require advance notice and shall require proper barricades, signage and flag persons to divert normal traffic safely;

Traffic on paved roads shall be restricted to rubber-tired vehicles. Where crawler mounted equipment is required to cross paved roads or areas, the pavement shall be suitably protected from damage to the satisfaction of the FFDG Construction Coordinator;

Dust, debris mud, and litter on any Fermilab roads caused by the Subcontractor's operations shall be removed by the Subcontractor in a manner as directed by the FFDG Construction Coordinator;

Illinois Rules of the Road shall apply to the Subcontractor’s use of all existing roads.

1.13 TRANSPORTATION OF EQUIPMENT AND MATERIALS

Transportation of equipment and materials shall be subject to the following conditions:

Transportation of equipment and materials used by the Subcontractor at the job site shall be furnished by the Subcontractor at his/her own expense;

The Subcontractor shall be responsible for minimizing any interference with local traffic, other Subcontractors and Fermilab operations;

The Subcontractor shall coordinate the anticipated schedule for major material deliveries and site hauling of excavated materials with the FFDG Construction Coordinator.

1.14 TEMPORARY SERVICES AND FACILITIES

Temporary services and facilities shall be subject to the following conditions:

Temporary services and facilities required during the construction period shall be furnished, installed, and paid for by the Subcontractor;

All installations shall be subject to FFDG approval;

Temporary lighting shall be installed throughout the project to provide safe access and exit conditions and adequate lighting for the various work operations. The installation shall comply with the National Electrical Code

(NFPA 70);

GENERAL REQUIREMENTS Project No. 6-7-126 010010 - 10

Telephone/Internet service for the project will be provided by and paid for by the Subcontractor;

Temporary fire protection shall be in accordance with the OSHA (29 CFR 1926);

An approved fire extinguisher shall be provided by the Subcontractor on all trucks and similar equipment, at all enclosures, and at on-site construction offices;

Each extinguisher shall be inspected monthly and a date tag certifying adequacy of the charge and workability of the extinguisher shall be affixed;

The Subcontractor shall remove the temporary extinguishers at the conclusion of the job.

Temporary ventilation shall be sufficient to provide a safe working environment for construction personnel, in accordance with OSHA 29 CFR 1926.57. Subcontractor shall provide exhaust and supply air fans, ducting and other equipment as needed.

Temporary heating shall include heating devices, protective coverings and temporary enclosures as necessary to protect the work and to provide a safe working environment for personnel.

Coal or kerosene type salamanders, pots or open fires shall not be permitted;

Where permanent heating equipment has been installed and made operational prior to completion of the project, the Subcontractor may request temporary use of such equipment, at no cost, provided it is properly maintained by the Subcontractor and that all required warranties are extended to include the period of use by the Subcontractor prior to Final Acceptance of the project by FFDG. Such equipment shall be turned over to FFDG in like-new condition, including new filters and similar consumables.

Temporary Drainage shall be sufficient to remove standing water and prevent flooding.

Subcontractor shall furnish pumping equipment and other dewatering equipment as required for proper operation;

Pump discharges from dewatering activities shall be intercepted by silt removal or sedimentation basins before being directed to natural drainage courses and away from adjacent work limits of other subcontractors.

Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Subcontractor only with the FFDG approval and shall be built with labor and materials furnished by the Subcontractor without expense to FFDG. The temporary buildings and utilities shall remain the property of the Subcontractor and shall be removed by the Subcontractor at its expense upon completion of the work. With the written consent of FFDG, the buildings and utilities may be abandoned and need not be removed.

1.15 FERMILAB CLOSURE

The Fermilab site is closed for major holiday and no construction activities shall occur, unless specifically approved by the FFDG Construction Coordinator, on these days:

New Year’s Day – January 1st Martin Luther King Jr. Day – 3rd Monday in January

GENERAL REQUIREMENTS Project No. 6-7-126 010010 - 11

Memorial Day – Last Monday in May Juneteenth Day – June 19th Independence Day – July 4th Labor Day – 1st Monday in September Thanksgiving Day – 4th Thursday in November Day After Thanksgiving – Friday after Thanksgiving Christmas Eve (1/2 Day) – December 24th Christmas Day – December 25th New Year’s Eve (1/2 Day) – December 31st

If any of these holidays occur on a weekend day, a weekday will be used for the holiday.

1.16 MATERIAL SUBSTITUTIONS

In accordance with FFDG General Terms and Conditions for Construction, products or materials that are equivalent of those specified will be considered for approval by FFDG.

The submittal procedure described elsewhere will be followed, with the following additional conditions:

In addition to the required information for the proposed substitute material, the submittal shall contain the same information pertaining to the original specified product for purposes of comparison;

The submittal shall explain fully the differences, if any, between the original specified product and proposed substitute product;

Any change to the drawings or specifications for related work required for proper installation of the proposed substitute product shall be indicated in the submittal;

If the proposed substitute product requires alterations of any kind to other equipment or construction, or necessitates any engineering design changes for its proper installation, such alterations and engineering design changes shall be accomplished at no cost to FFDG;

The substitute submittal must contain a statement detailing the cost and schedule impact of the proposed substitution;

FFDG is the sole judge of the acceptability of the proposed substitution.

1.17 DOCUMENTATION

The FFDG Construction Coordinator may prepare weekly progress meeting minutes including on-going punch list items, ESH issues, corrective actions, and status of these items. These minutes will become part of the FFDG project file. At the discretion of the FFDG Construction Management Office, the weekly progress meeting may be reduced or eliminated depending on safety, quality, and schedule of the project.

Quality Control Documentation reference article 3.3.

On-going punch list: During the duration of the project, the FFDG Construction Coordinator shall identify deficient items that do not adhere to the technical specifications/drawings. This list will be kept current through the duration the project by the Subcontractor’s Field Superintendent and made part of the Weekly Progress Meeting Minutes. At a minimum, the subcontractor shall, within five (5) working days, GENERAL REQUIREMENTS Project No. 6-7-126 010010 - 12 submit a proposed corrective action plan that details the mitigation method including a schedule for the correction of the noncompliance. Reference Attachment B.

Notification of punch list items: The FFDG Construction Coordinator will notify the Subcontractor of deficiencies and/or discrepancies in the quality of the construction.

These notifications will include:

Date Identified;

Identifier;

Location;

Description, including specification or drawing reference.

As-Builts (Record Documents):

The Subcontractor shall maintain a set of prints of the Subcontract drawings in the construction office at the project site;

A daily record, in red, shall be kept on these prints of the work installed with all modifications or changes thereon. This set of prints shall be available to FFDG for inspection at all times and print copies provided upon request to FFDG within 24 hours of the request being made;

The FFDG Construction Management Office and the Subcontractor's Field Superintendent should review the as-built drawings prior to the Monthly Construction Schedule Updates described elsewhere, in order to determine if the as-built mark-up set is current and accurate. The processing of the monthly payment request is contingent of the up-to-date status of the as-built documentation;

Prior to Final Acceptance described elsewhere in article 3.4, the Subcontractor shall transmit the complete set of marked-up prints to FFDG.

The Final Acceptance submittal shall include a statement from the Subcontractor that indicates that the work was installed as shown thereon;

Final Acceptance of the work is contingent on the receipt and approval of the complete as-built documentation.

Final Acceptance Documentation: Final Acceptance of the work is contingent on the receipt and approval of the following documentation:

As-built documentation as described elsewhere in the subcontract documents;

Shop drawing record set as described in (Specifications and Drawings for Construction) in accordance with FFDG General Terms and Conditions for Construction;

Warranty documentation;

Spare stock (material and consumables), if required by the technical specifications/drawings;

Operations and Maintenance manuals.

1.18 SUBCONTRACTOR’S REQUESTS FOR INFORMATION (RFI)

When the Subcontractor is unable to determine from the Contract Documents, the exact material, process or system to be installed; or when the items of construction are required to occupy the same space (interference); or when an item of work is described differently at two places in the Contract Documents; or when other clarification is required; FFDG shall be requested to make a clarification of the indeterminate or

GENERAL REQUIREMENTS Project No. 6-7-126 010010 - 13 interfering item through the RFI procedure given shall be the method for requesting the clarification.

RFIs shall be submitted on a form found in Attachment A or FFDG approved Subcontractor’s form. Each RFI shall be given a discrete, consecutive number. Each page of the RFI and of attachments to the RFI shall bear the RFI number and Project number. Resubmitted RFIs with additional information shall be RFI number with a .01 prefix for the first resubmitted RFI, .02 for the second, and so on.

RFIs from sub-subcontractors shall be submitted through, reviewed by, given a number, and signed by the Subcontractor prior to submittal to FFDG. The Subcontractor shall keep a log of the RFIs. RFIs submitted directly by sub-subcontractors would be returned unanswered to the sender and the Subcontractor. Subcontractor shall be responsible for delays resulting from the necessity to resubmit an RFI.

Subcontractor shall carefully study the subcontract documents to assure that the requested information is not available therein.

In all cases where RFIs are issued to request clarification of coordination issues (e.g., pipe and duct routing, clearances, specific locations of work shown diagrammatically, apparent interference and similar items) the Subcontractor shall furnish all information required for FFDG to analyze and/or understand the circumstances causing the RFI in order to prepare a clarification or direction as to how Subcontractor shall proceed.

RFIs shall not be used for the following purposes:

To request approval of submittals;

To request approval of substitutions;

To request changes which entail additional cost or credit;

To request different methods of performing work than those indicated on the drawings and/or specified.

In the event the Subcontractor believes that a clarification by FFDG results in additional cost, Subcontractor shall not proceed with the work indicated by the RFI until authorized by FFDG Procurement Administrator to proceed by an approved Change Order.

FFDG will return RFIs to the Subcontractor within 10 calendar days of receipt. RFIs received after 12:00 noon shall be considered received on the next regular workday for the purpose of establishing the start of the 10-calendar day response period.

PART 2 PRODUCTS - Not Used

PART 3 EXECUTION

3.1 NOTICE TO PROCEED

The Notice To Proceed (NTP) represents the basis of the start of the project duration.

The following describes the requirements for the NTP:

The NTP is issued by the FFDG Procurement Administrator;

The issuance of the NTP establishes the start of work on the Fermilab Site.

GENERAL REQUIREMENTS Project No. 6-7-126 010010 - 14

A project kickoff meeting may be required prior to the issuance of the NTP.

Submittals Required Prior to NTP. Within ten (10) business days after subcontract award, the Subcontractor shall submit the following to FFDG for acceptance. These items must be submitted and accepted by FFDG prior issuance of NTP.

Insurance Certificates Payment and Performance Bonds Project Hazard Analysis (if NTP is waived, a project Hazard Analysis is still required prior to commencement of work);

Cost-loaded Construction Schedule;

Soil Erosion and Sediment Control Plan (if required in Article 1.9;

Project-specific Quality Control Plan (if required in 014100. Refer to Article

3.3 for more information);

Reference 013100 for ES&H Submittals.

Reference the following Specification Sections:

Exhibit A documents

013100 ESH Requirements 013300 Submittals

014100 Quality Requirements 053100 Steel Decking 06100 Rough Carpentry 061600 Sheathing

070150.19 Preparation for Reroofing

075419 Polyvinyl Chloride PVC Roofing 076200 Sheet Metal Flashing and Trim

077100 Roof Specialties 077200 Roof Accessories 077273 Membrane Integrity Test Systems

3.2 CONSTRUCTION SCHEDULE

This project includes the following milestones:

Milestone 0 – 0 Calendar Days - NTP :

This milestone marks basis of the start of the project’s duration.

Note to the subcontractor - all material and product submittals must be reviewed and inspected prior to construction.

Milestone 1 – 65 Calendar Days – Masonry Wall Repair Day 0-5; Scope Investigation of Masonry Wall Repair and subcontractor to provide a comprehensive repair approach summary.

Day 5-20: All product and material submittals, submitted by contractor, reviewed and returned by FFDG Project Manager.

The FFDG Project Manager requires 10 Working days from receipt of submittal for review time.

All submittals accepted and reviewed will mark the point where construction work may begin.

Masonry wall repair may begin prior to approval of all roof replacement submittals.

GENERAL REQUIREMENTS Project No. 6-7-126 010010 - 15

Day 20-65: Masonry wall repair and tuckpointing Submittal review for roof replacement can be completed during this cycle.

Milestone 2 –65-95 Calendar Days – Curing of Masonry repair Grout and Masonry require 30 days for drying/ curing prior to final cleaning.

Final Cleaning

Milestone 2 –95-125 Calendar Days – Roof Replacement Mobilization and Roof Replacement.

Milestone 3 –125-140 Calendar Days – Project Complete Project completion includes:

Punchlist items, Clean-up and demobilization Manufacturer inspections, Acceptance of warranties, As-built drawings, Weekly progress meetings will be held, unless the FFDG Construction Management Office reduces or eliminates the progress meetings, to coordinate the work with Subcontractor and FFDG. The roles and responsibilities of the participants are as follows:

FFDG Construction Coordinator:

Responsible for chairing the weekly progress meetings;

Responsible for meeting documentation;

Identification of the work completed since the previous progress meeting;

Identification of deficiencies in the quality of construction.

FFDG ES&H Safety Coordinator:

Responsible for discussion on corrective action and preventative actions on ES&H items;

Can provide guidance on safe work practices and answer questions related to ES&H by the subcontractor.

FFDG Design Coordinator or FFDG Construction Coordinator:

Submittal status;

Status of Request for Information.

FFDG Procurement Administrator Provide status on any sub-contractual changes;

Any administration concerns related to the subcontract.

Subcontractor’s Field Superintendent:

Prior to the weekly progress meeting, the Subcontractor shall submit a “two week look ahead” schedule that will present the status of activities that are currently in progress or expected to begin within two (2) calendar weeks from the date of the weekly progress meeting;

Subcontractor’s Environment, Safety and Health observations;

Submit Quality Control documents (if required by article 3.3);

Status of deficiency list of those items of the work that do not conform to the subcontract documents;

GENERAL REQUIREMENTS Project No. 6-7-126 010010 - 16

Providing a summary of the work-hours worked during the previous week;

Identification of any impact to the project cost or schedule due to the activities of Fermilab operations;

Identification of any work activities commenced or expected to commence that are outside the scope of the subcontract.

Monthly construction schedule update meetings shall accurately reflect the execution of the project. This is required for payment. The construction schedule update shall include the following:

Actual start and completion dates for activities that finished during the update period;

Percent complete and predicted completion date for those activities that are in progress;

Any necessary changes to the schedule required to accurately reflect the actual sequence of work;

Clear identification of the critical path work activities and logic ties;

The FFDG Construction Coordinator and the Subcontractor shall jointly review all construction schedule updates prior to formal submittal;

The date of the update will be selected by FFDG to coincide with accepted

FFDG financial accounting periods;

The construction schedule shall reflect all subcontract changes that have been issued via supplemental agreement;

A revision summary of the changes shall be maintained on the schedule;

The Subcontractor shall submit a Schedule Variance (SV) report when any of the projected FFDG specified milestones are behind schedule by more than 5% (SV=0.95 or less) of the total remaining project schedule. This report shall identify those activities that are contributing to the schedule variance;

When the construction schedule indicates that an FFDG-specified milestone will be late by more than 5% of the total remaining schedule the Subcontractor shall submit a recovery schedule that will mitigate the schedule variance. This recovery shall identify those activities that are contributing to the schedule variance and the actions the Subcontractor is proposing to mitigate.

3.3 QUALITY CONTROL AND CONTROL OF INSTALLATION

The Subcontractor is responsible for all activities necessary to manage, control, and document that work complies with the Subcontract documents. The Subcontractor’s responsibility includes ensuring adequate Quality Control services are provided for work accomplished on- and off-site by his/her organization, suppliers, sub-tier contractors, technical laboratories, and consultants.

For critical projects, the Subcontractor shall furnish a project specific Quality Control plan which identifies the personnel, procedures, controls, instructions, test, records, and forms to be used specific to this project at Fermilab. Section 014100 provides additional guidance and expectations for this plan, as well as how to determine if a project is deemed critical from a Quality perspective.

GENERAL REQUIREMENTS Project No. 6-7-126 010010 - 17

The work activities include safety, submittal management, testing and inspection, and all other functions relating to the requirement for quality construction. Subcontractor is responsible to respond to Non-Compliance Notices that may be issued by the Subcontractor or by FFDG. Further, the Subcontractor shall contain procedures for tracking construction deficiencies from identification through acceptable corrective action. The Subcontractor shall track and log deficiencies on form found in Attachment B or FFDG approved Subcontractor’s form.

Subcontractor shall perform periodic inspection for potential suspect counterfeit materials. The most common suspects counterfeit materials found at US Department of Energy facilities have been threaded fasteners fraudulently marked as high strength bolts. Also included are electrical circuit breakers with false certifications. If the subcontractor suspects any counterfeit material being utilized, contact the Construction Coordinator immediately. Suspect/Counterfeit Items (S/CI) should be removed from the material supply inventory, labeled as S/CI, and quarantined to prevent inadvertent use until the nature of the item has been determined.

Reference Section 014100 for additional quality requirements.

3.4 ACCEPTANCE

Authorization to Use and Possession (AUP) prior to completion: An interim inspection process used when FFDG assumes responsibility for portions of the work. The following details concern Authorization to Use and Possession:

1. The Subcontractor shall provide a 10-day notice to the FFDG Construction Coordinator before this inspection is performed;

2. The Subcontractor’s punch list with status noted shall be attached to the AUP documentation;

3. The FFDG Construction Coordinator will complete the AUP form;

4. For further information, reference (Use and Possession Prior to Completion) of

FFDG General Terms and Conditions for Construction.

Final punch list Inspection: An inspection of the uncompleted items of the subcontract documents. The following describes the punch list process:

When the Subcontractor believes the work is substantially complete, the Subcontractor shall update the deficiency list for presentation to the FFDG Construction Coordinator;

The Subcontractor shall provide a 10-day notice to the FFDG Construction Coordinator in order to make arrangements for the final inspection of the construction project with FFDG personnel;

The FFDG Construction Coordinator will arrange for a final inspection visit of FFDG stakeholders to verify the accuracy of the Subcontractor’s deficiency list and to add, as necessary, those items of work that are not complete;

The FFDG Design Coordinator will develop a comprehensive punch list and issue it to the Subcontractor after the final inspection;

The Subcontractor and the FFDG Construction Coordinator will sign off on the completion of each punch list item.

Final Acceptance: This inspection will document the completion of the project scope.

The following describes this process:

GENERAL REQUIREMENTS Project No. 6-7-126 010010 - 18

The Subcontractor shall provide a five (5) day notice prior to the Final Acceptance inspection;

The Subcontractor shall submit documentation that the work associated with the punch list is complete;

The FFDG Construction Coordinator will coordinate the final inspection walkthrough with FFDG stakeholders;

The FFDG Construction Coordinator will develop and issue the final acceptance documentation when the punch list items have been completed.

END OF SECTION

010010 RFI 1

ATTACHMENT A

010010 RFI 1

REQUEST FOR INFORMATION

Date:

Project Name: RFI No.:

To: Project No.:

Subject: Submitted By:

Spec.. No.: Article/Par.: Drwg. No.: Detail:

Request:

Response:

ATTACHMENT B

010010 QA/QC 1

QA/QC Punch List Item Status

Item# Room/

Location Description

Author Initials

Subcontractor Responsible

Date Inspected

Date Due Date

Completed Subs

Initials

Closed/ Confir med By Notes

QA/QC Punch list Items Status

<Subcontractor> Assigned

Items Closed Items

Open Items

% Closed % Open

0 0 0 #DIV/0! #DIV/0!

Totals

013100 – Environment, Safety, and Health Requirements

Fermi Forward Discovery Group, LLC ES&H Requirements April 2025

ES&H Requirements 013100 - 1

013100 – Environment, Safety, and Health Requirements

Acronyms and Abbreviations

Part 1 General

1.1 Fermi Forward Discovery Group, LLC ES&H Policy

1.2 Summary

1.3 Applicable Codes and Regulations

1.4 Application and Enforcement of Tile 10 CFR Part 851 (10 CFR 851)

1.5 Application and Enforcement of Tile 10 CFR Part 835 (10 CFR 835)

1.6 Definitions

Part 2 Pre-Award and Post-Award

2.1 Submittals with Subcontract Proposal (Pre-Award)

2.2 Submittals with Subcontract (Post-Award)

Part 3 Excavation Plans, ES&H Submittals Required after Award of Subcontract and before

Commencement of Work

3.1 Required Submittals

Part 4 Training

4.1 Subcontractor Training

4.2 FFDG-Provided Training

4.3 Re-Training

Part 5 Subcontractor’s ES&H Program

5.1 Incident Reporting and Occupational Medicine Program

5.2 Occupational Medicine Program

5.3 Subcontractor’s Site-Specific Safety Program

5.4 ES&H Inspections and Audits

5.5 Project Bulletin Board

5.6 Temporary Drinking Water and Sanitary Systems

Part 6 Safe Execution of the Work

6.1 Subcontractor Means and Methods

6.2 Subcontractor’s Project Team & Personnel

6.3 Job Site ES&H Inspections/Meetings

6.4 Safety Color Coding

6.5 Work Planning and Hazard Analysis

6.6 Job Site Orientation

6.7 Personal Protective Equipment (PPE)

ES&H Requirements 013100 - 2

6.8 Fall Protection

6.9 Advance Notice of Work Activities

6.10 Off-Hours High Hazard Work

6.11 Fire Protection

6.12 Lasers

6.13 Moveable Equipment

6.14 Industrial Hygiene

6.15 Jobsite Housekeeping

6.16 Hazardous Materials

6.17 Confined Space

6.18 Existing Utilities, Equipment, and Structures

6.19 Soil Erosion and Sediment Control

6.20 Lockout and Tagout (LOTO)

6.21 Ladders and Scaffolds

6.22 Blasting

6.23 Visitors to the Construction Site

Part 7 Specific Hazards and Elements of the Work

7.1 Protection of Existing Property

7.2 Waste Disposal/Recycling

7.3 Pressurized Gas and Process Piping

7.4 Oxygen Deficient Hazards (ODH)

7.5 Radiation Protection

7.6 Environmental Protection

7.7 Temporary Heating Devices

7.8 Smoking

7.9 Fuel Storage Tanks

7.10 Vehicles and Equipment

7.11 Material Handling and Storage

7.12 Critical Lifts

Part 8 Work Planning and Permits

8.1 General

8.2 Excavation Permit

8.3 Confined Space Permit

8.4 Hot Work (Burning, Welding, including Spark Producing) Permit

8.5 Electrical Work

ES&H Requirements 013100 - 3

8.6 Existing Structure/Concrete Cutting and Coring

8.7 Modification to Drinking Water, Sanitary Sewer Systems, or Industrial Cooling Water

8.8 Work with Radioactive Material or Radiation Areas

8.9 Moving Government-Owned or FFDG-Owned Property Off Site

Part 9 Emergencies, Incident Management, Investigations, and Reporting

9.1 Safety Pause/Stop Work Authority

9.2 Reporting Requirements

9.3 Fire

9.4 Emergency Egress and Severe Weather

9.5 Concern Reporting Process

9.6 Enforcement

ATTACHMENT A SILICA GUIDANCE

ATTACHMENT B SAMPLE DAILY WORK PLANNING

ATTACHMENT C CONSTRUCTION ES&H CERTIFICATION (Completed with Proposal)

ATTACHMENT D HAZARD ANALYSIS

ES&H Requirements 013100 - 4

Acronyms and Abbreviations

ACGIH American Conference of Governmental Industrial Hygienists AHJ Authority Having Jurisdiction ANSI American National Standards Institute ASME American Society of Mechanical Engineers ASTM American Society of Testing and Materials CESHC Construction, Environment, Safety, and Health Certificate CFR Code of Federal Regulation CPR Cardiopulmonary Resuscitation dBA Decibel A Scale DOE Department of Energy EPA Environmental Protection Agency ESH or ES&H Environment, Safety and Health

ESWP

FFDG

Electrical Safe Work Permit Fermi Forward Discovery Group, LLC

Fermilab Fermi National Accelerator Laboratory FNAL Fermi National Accelerator Laboratory FESHM Fermilab ES&H Manual FD Fire Department GFCI Ground Fault Circuit Interrupter GHS Globally Harmonized System GINA Genetic Information Nondiscrimination Act HEPA High Efficiency Particulate Air Filter HIPAA Health Insurance Portability Accountability Act IDLH Immediately Dangerous to Life or Health JHA or HA Job Hazard Analysis or Hazard Analysis LBNF Long-Baseline Neutrino Facility LEL Lower Explosive Limit LOTO Lock Out/Tag Out MEWP Mobile Elevated Work Platforms NFPA National Fire Protection Association NISOH National Institute for Occupational Safety and Health NRTL Nationally Recognized Testing Laboratory ODH Oxygen Deficiency Hazard OSHA Occupational Safety and Health Administration PEL Permissible Exposure Limit PFAS Personal Fall Arrest System PPE Personal Protective Equipment SDS Safety Data Sheets SOP Standard Operating Procedure SSESHP Site-Specific Environment Safety and Health Plan SSECP Site-Specific Erosion Control Plan SWPPP Storm Water Pollution Prevention Plan TLV Threshold Limit Value TWA Time Weighted Average USC United States Code VAC Volts Alternating Current WPC Work Planning Controls

ES&H Requirements 013100 - 5

Part 1 General

1.1 Fermi Forward Discovery Group, LLC ES&H Policy

A. Fermi Forward Discovery Group, LLC (FFDG) holds safety and environmental protection as one of its highest and most important values. FFDG’s policy is to protect the environment and the safety and health of all persons accessing the sites that FFDG manages, may they be facilities employees, subcontractor employees, scientific visitors, or visiting members of the public.

1.2 Summary

A. This Section describes the requirements, responsibilities, and expectations for environment, safety, and health (ES&H) aspects of Subcontractor’s work.

B. Safety, as used in this document, encompasses environment, safety, and health, including pollution prevention and waste minimization.

C. The Subcontractor shall provide all labor, materials, equipment, services, occupational exposure monitoring, and supervision required to maintain work sites that meet the

Subcontract ES&H requirements, all applicable federal, state, local regulations, and site-specific permits. In addition, the Subcontractor shall take all reasonable measures to protect the environment and the safety and health of its employees, the employees of its sub-tier subcontractors, sub-tier vendors, DOE's and FFDGs’s employees, and the public from bodily injury and damage to their property.

1.3 Applicable Codes and Regulations

The Subcontractor and sub-tier subcontractors shall comply with the following referenced codes and regulations. The codes, regulations, standards, rules, and DOE orders referenced herein are incorporated into and form a part of this Section.

A. Title 10 Code of Federal Regulations (CFR) Part 851 (10 CFR 851), Department of Energy

(DOE) Worker Safety and Health Program

B. 10 CFR 820, Procedural Rules for DOE Nuclear Activities

C. 10 CFR 835, Occupational Radiation Protection

D. 10 CFR 860, Trespass to Land Owned & Leased by the US Government

E. 10 CFR 708, DOE Contractor Employee Protection Program

F. 10 CFR 707, Workplace Substance Abuse Programs at DOE Sites

G. 29 CFR 1904, Record Keeping Guidelines for Occupational Injuries and Illnesses

H. 29 CFR 1910, Occupational Safety and Health General Industry Standards

I. 29 CFR 1926, Occupational Safety and Health Standards for Construction

ES&H Requirements 013100 - 6

J. 40 CFR Protection of the Environment (USA EPA)

K. 49 CFR Transportation

L. Illinois Rules…