General Conditions Breakout.xlsx

XLSX spreadsheet 13 KB Posted

Attached to
Z2DA--621-22-121 Renovate Bldg. 204 for Cath Lab II - Engineering
Solicitation number
36C24926R0057
Issued by

About this file

This is a General Conditions cost breakout template required for submission with the Schedule of Values on a federal construction contract. The document establishes mandatory cost categories and allocation requirements for a renovation project at the James H. Quillen VA Medical Center in Mountain Home, Tennessee, specifically for the renovation of Building 204 for Cath Lab II. Per VAAR 852.243-70, the template restricts how contractors may classify overhead and fee percentages, requiring that certain costs be absorbed within these percentages rather than claimed separately.

The breakout template organizes General Conditions costs into three primary categories: Project Management (including superintendent, safety manager, schedulers, quality assurance personnel, project managers, and support staff), Bonds and Insurance (builder's risk insurance, general liability insurance, and security/payment/performance bonds), and Site Conditions (encompassing temporary utilities, infrastructure, site protection, safety measures, security, documentation, and restoration activities). The template provides line items for each cost component with corresponding value fields, all currently populated at zero dollars, requiring contractors to complete actual cost estimates during bid preparation. This structured approach ensures transparent cost allocation and compliance with federal contracting requirements while preventing duplicate cost recovery across overhead, fees, and direct charges.

View the file

Other files

File Type Posted
07.314_AE301 - PENTHOUSE CONSTRUCTION.pdf PDF
Appendix B - HVAC CUTSHEETS.pdf PDF
07.112_AE112.2 - PHASE TWO ENLARGED PLAN.pdf PDF
36C24926R0057 0004.pdf PDF
09 54 00 - Operating Room Modular Diffuser System.pdf PDF
23 82 00 - Convection Heating and Cooling Units.pdf PDF
14.38_E600 - PARTIAL SINGLE LINE DIAGRAM.pdf PDF
14.20_EE102.2.2 - PHASE 2 ENLARGED TECH FIRE ALARM PLAN.pdf PDF
14.13_ED102.5.2 - PHASE 5 DEMOLITION TECH FIRE ALARM PLAN.pdf PDF
14.11_ED102.4.2 - PHASE 4 DEMOLITION TECH FIRE ALARM PLAN.pdf PDF
07.704_AF702.4 - PHASE FOUR FINISH PLANS.pdf PDF
13.10_MH102.4 - MECHANICAL SECOND FLOOR HVAC PLAN - PHASE 4.pdf PDF
S-102824-291.pdf PDF
10 51 26 - Plastic Lockers and Bench.pdf PDF
09 05 16 - Subsurface Preparation For Floor Finishes.pdf PDF
01 45 35b - Statement of SI.pdf PDF
14.29_E501 - TECHNOLOGY DETAILS.pdf PDF
14.06_ED102.2.2 - PHASE 2 DEMOLITION TECH FIRE ALARM PLAN.pdf PDF
14.04_ED102.1.2 - PHASE 1 DEMOLITION TECH FIRE ALARM PLAN.pdf PDF
14.02_E102 - SECOND FLOOR OVERALL PLAN.pdf PDF
14.00_E001 - ELECTRICAL LEGENDS AND ABBREVIATIONS.pdf PDF
07.705_AF702.5 - PHASE FIVE FINISH PLANS.pdf PDF
07.734_AQ732.4 - EQUIPMENT PLANS - PHASE FOUR.pdf PDF
11.22_PL601 - PLUMBING SCHEDULES and DIAGRAMS.pdf PDF
Revised Cath Shielding 2024.pdf PDF
Project 621-22-121 RFI Log - Mt Home Cath Lab to VA 7-24-26.xlsx XLSX spreadsheet
36C24926R0057 0003.pdf PDF
28 23 00 - Video Surveillance.pdf PDF
01 45 35 - Special Inspections.pdf PDF
00 01 10 - Table Of Contents.pdf PDF
00 00 00 - Specification Cover.pdf PDF
14.27_EE102.5.3 - PHASE 5 ENLARGED LIGHTING TECH PLAN.pdf PDF
14.16_EE102.1.2 - PHASE 1 ENLARGED TECH FIRE ALARM PLAN.pdf PDF
14.24_EE102.4.2 - PHASE 4 ENLARGED TECH FIRE ALARM PLAN.pdf PDF
14.22_EE102.3.2 - PHASE 3 ENLARGED TECH FIRE ALARM PLAN.pdf PDF
11.10_PD102.5 - PLUMBING SECOND FLOOR DEMOLITION PLAN PHASE 5.pdf PDF
2026-0724 Addendum 02 Summary.docx DOCX document
36C24926R0057 0002.pdf PDF
621-22-121 Site Visit Sign in sheet.pdf PDF
2026-0629 Cath Lab II - BID specs - Add 01.pdf PDF
36C24926R0057 0001.pdf PDF
2026-0629 Cath Lab II - BID Dwgs - Add 01.pdf PDF
621-22-121 Renovate B204 for Cath Lab II - Bid Specifications.pdf PDF
36C24926R0057_1.pdf PDF
621-22-121 Renovate B204 for Cath Lab II - Bid Drawings.pdf PDF
Calculation of Contractor Self Performed Work.xlsx XLSX spreadsheet
WD TN20260191 2 Jan 2026.pdf PDF
Past_Performance_Questionnaire.docx DOCX document
Price Breakout Schedule.xlsx XLSX spreadsheet
Contractor EMR Certification Form.docx DOCX document
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GC Breakout

GENERAL CONDITIONS BREAKOUT
When entering a line item for General Conditions costs on Schedule of Values, a breakout of the General Conditions costs must be provided. Per VAAR 852.243-70 Construction Contract Changes-Supplement, paragraph (c)(1), the following contractual restrictions apply: Overhead and Contractor's fee percentages shall be considered to include insurance other than mentioned herein, field and office supervisors and assistants, security police, use of small tools, incidental job burdens, and general home office expenses and no separate allowance will be made. Assistants to office supervisors include all clerical, stenographic and general office help. Incidental job burdens include, but are not necessarily limited to, office equipment and supplies, temporary toilets, telephone and conformance to OSHA requirements. Items such as, but not necessarily limited to, review and coordination, estimating and expediting relative to contract changes are associated with field and office supervision and are considered to be included in the Contractor's overhead and/or fee percentage.
General Condition DescriptionValue
Project Management:$ - 0
Superintendent(s)$ - 0
Safety Manager$ - 0
CPM Scheduler$ - 0
Quality Assurance/Quality Control$ - 0
Project Manager (s)$ - 0
Project Executive$ - 0
Field Office Engineer$ - 0
Field Office Support Staff$ - 0
Project Expeditor$ - 0
Assistant Superintendent (s)$ - 0
Project Manager Subtotal:$ - 0
Bonds and Insurance (excluding any for Subcontractors):$ - 0
Builder’s Risk Insurance$ - 0
General Liability Insurance$ - 0
Security, Payment & Performance Bonds$ - 0
Bonds and Insurance Subtotal:$ - 0
Site Conditions:$ - 0
Temporary Power Consumption (Offices)$ - 0
Temporary Power Consumption (General Site Use)$ - 0
Temporary Water and Sewer Consumption$ - 0
Temporary Water Hookup, Distribution & Meters$ - 0
Temporary Electrical Hookup, Distribution & Meters$ - 0
Temporary Telephone & Network System Installation$ - 0
Temporary Telephone & Internet Consumption Fees$ - 0
Temporary Fire Protection$ - 0
Temporary Heating & Cooling$ - 0
Temporary Fencing$ - 0
Temporary Covered Walkways$ - 0
SWPPP Measures$ - 0
Temporary Entries and Truck Washes$ - 0
Street Cleaning (by G.C.)$ - 0
Traffic Control Measures$ - 0
Temporary Barricades & Signage$ - 0
Temporary Roads & Walkways (install & maintenance)$ - 0
Temporary Lighting$ - 0
Temporary Partitions & Covered Floor Openings$ - 0
Temporary Toilets/Sanitary Measures$ - 0
Temporary Laydown (prep and restoration)$ - 0
Security System/Watchman$ - 0
Pre-construction Photo Documentation$ - 0
Progress Photos$ - 0
Temporary Protection (in place work/adjacent structures)$ - 0
$ - 0
$ - 0
$ - 0
General Conditions Total$ - 0