MACC RFP FA9401-12-R-0002 Q A Round 7

View the file

Other files

File Type Posted
Attch_1_-_Wage_Determination_(Bernalillo_County)__Building_dated_7-20-2012.pdf PDF
MACC_RFP_FA9401-12-R-0002_Amendment_10.pdf PDF
Attch_2_-_Wage_Determination_(Bernalillo_County)__Residential_dated_4-6-2012.pdf PDF
Attch_3_-_Wage_Determination_(Bernalillo_County)__Heavy_dated_7-20-2012.pdf PDF
MACC_RFP_FA9401-12-R-0002_Amendment_9.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 8.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 9.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 7.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 8.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 6.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 6-Conformed Copy.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 6.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 5.pdf PDF
RFP FA9401-12-R-0002 Pre-Proposal Conference-Site Visit Final Sign-in Sheet.pdf PDF
MACC Pre-Proposal Brief.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 4.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 3.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 2.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 5-Conformed Copy.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 5.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 4.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 4-Conformed Copy.pdf PDF
Attch 5 - Past Performance Information Questionnaire Package.docx DOCX document
MACC RFP FA9401-12-R-0002 Amendment 3-Conformed Copy.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 3.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 2-Conformed Copy.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 2.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 1.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 1.doc DOC document
Attch 32 - Seed Project Bid Schedule.xlsx XLSX spreadsheet
Attch 20 - Appendix 9 - Environmental Requirements KAFB.pdf PDF
Attch 10 - Appendix 4.1 - 13280 Asbestos Containing Materials Remediation.pdf PDF
Attch 40 - Kirtland AFB-West Map.pdf PDF
Attch 37 - Seed Project - Future Expansion Power Requirements Table.pdf PDF
Attch 13 - Appendix 4.4 - 16721 New Construction Automatic Fire Detection and Alarm System.pdf PDF
Attch 26 - Appendix 14.2 - Guidance and Standards-Backflow Prevention.pdf PDF
Attch 15 - Appendix 4.6 - Native Grass Seeding Specification.pdf PDF
Attch 9 - Appendix 3 - DUSD —
Attch 23 - Appendix 12 - Waste Diversion Report.pdf PDF
Attch 25 - Appendix 14.1 - Guidance and Standards-Irrigation.pdf PDF
Attch 18 - Appendix 7 Air Force Federal Mandates Quick Reference.pdf PDF
Attch 35 - Seed Project Water flow Test Results.pdf PDF
Attch 31 - Seed Project Price Schedule - AF3052.xlsx XLSX spreadsheet
Attch 36 - Seed Project - Westside Shoppette Geotechnical Report.pdf PDF
Attch 39 - AF Form 3065 - Progress Report.pdf PDF
Attch 30 - Seed Project Statement of Work.pdf PDF
Attch 22 - Appendix 11 - DoD Minimum Antiterrorism Construction Standards Pre-Final Checklist.pdf PDF
Attch 41 - Historical Data by Project Type and Cost.pdf PDF
MACC RFP FA9401-12-R-0002.doc DOC document
Attch 14 - Appendix 4.5 - 16721 Existing Bldg Remodel-Automatic Fire Detection and Alarm System.pdf PDF
Show 40 more

Latest 50 of 71 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Multiple Award Construction Contract (MACC)

RFP, Pre-Proposal Conference and Site Visit Questions

Solicitation FA9401-12-R-0002

10 April 2012

ROUND 7

MACC FA9401-12-R-0002

The purpose of this document is to provide answers to RFP questions for Solicitation

FA9401-12-R-0002.

120. Regarding the Anechoic Chamber:

• The design analysis package 33 requires a 30’x30’ chamber 6’ deep; will the 6’ be below the finished floor requiring a depressed slab in that area?

• What are the properties of the chamber in regard to wall thickness and finishes?

• Is the floor finish in the chamber the same as the lab space?

• Will a separate ceiling be required for the chamber?

• If a ceiling is required will it be removable?

ANSWER: The 6' depth of the pit is to be measured from finish floor. The anechoic chamber will be furnished and installed by others. Chamber properties are not available at this time. Chamber finishes, whether floor or ceiling, are not available at this time.

121. Regarding the 5” thick non-ionizing radiation shield:

• What are the properties of the shield i.e. lead brick, lead lined concrete block, etc?

• The diagram in the design analysis illustrates the x-ray shield extending 30’ to 50’ beyond the laboratory staging area. Will the shield be required to extend beyond the building addition?

• Will a shield need to be added to the 2,885 square foot area being added to the laboratory from the existing building.

ANSWER: The 5" thick shield will be furnished and installed by others. It's properties are indeterminate at this time.

122. Is there a requirement for edited UFGS design specifications for the purpose of the 30% design of seed project?

ANSWER: The 35% design submittal may include outline specifications.

123. Left Blank on purpose

Solicitation FA9401-12-R-0002

10 April 2012

ROUND 7

124. The RFP states that drainage of existing storm water is collected and handled through a gutter system and diverted naturally to the storm ponds. The new building is larger than five thousand square feet and will be added at zero edge to the existing building thereby removing the gutter runoff system. Will we be asked to include the runoff in our new diversion plan section 438 ESA or are we allowed to reroute the gutter system and let it drain naturally.

ANSWER: The existing roof drainage may be re-routed to its historic flow path, and need not be included in the EISA diversion plan.

125. On the existing site analysis the fire access road states that it may need to be relocated.

How should we price this?

ANSWER: The “fire access road” refers to a graded easement around the building to allow fire truck activity near the building. It is not a “road” as such. The contractor will be expected to grade an area around the addition that will re-establish the continuity of this easement.

126. On the job walk we were shown the HVAC unit from outside the building. This unit is to be relocated. We were unable to view the ducting for type and size. Is there a preferred location for the unit relocation? Is there any remediation of materials involved?

ANSWER: There is no preferred location for the relocation at this time. This will be resolved during design. There are no known remediation efforts required to relocate the unit or tie back into the existing duct system.

127. The gas connection for the HVAC is currently in the path of the footprint for the addition. Are we to reroute the existing feed from its current location or feed from the new meter for the addition?

ANSWER: The gas line must be rerouted. It cannot be beneath the building.

128. The Attachment 33 page 10 states that the fire sprinkler and fire protection systems will expand into the existing storage area and tie to the existing system. Will there be one main fire riser for all the buildings and the piping tied to that location. Has a tie in location for the riser been established or are there as civil as-builts that can be reviewed prior to bid time? Will there be one master fire alarm panel with remote annunciators and is the master panel able to handle the expansion or a new master required?

Solicitation FA9401-12-R-0002

10 April 2012

ROUND 7

ANSWER: The fire suppression system will not be required to include, or tie-into, fire suppression within the existing building. A new fire riser and BFP must be provided. The new riser must be sized to allow sprinkler extension into the remainder of the building at a later date, by others. The fire alarm system must be tied to the existing panel near the front entry to the existing building on the West side. There is available capacity for this in the existing panel.

129. The Attachment 33 page eleven talks about phased construction and tying into the addition. Are we to assume that the costs associated with this works is to be included in the original proposal. Should the elevation of the existing building floor be the set point for the new addition floor to provide a level transition?

ANSWER: The expansion into existing areas will be accomplished under separate contract at a later date. The floor elevation of the new addition should match the floor elevation of the existing building.

130. Will there be a shield wall required at the ANECHOIC chamber and if so what are the dimensions?

ANSWER: A shield wall is not required.

131. The RFP asks for a bridge crane and is priced under an additive bid line item. Is the building design and structural to be incorporated under the main proposal to support the bridge crane regardless if the crane is purchased or not? There would be two different loadings and foundation also steel erection and ancillary work provide ie. Electrical feed, MEP coordination and such. Should the crane only include price for unit and install?

ANSWER: The building should be designed to accommodate the bridge crane, regardless of the acceptance or non-acceptance of the bridge crane alternate. The alternate should include the cost for unit purchase and installation only.

132. The Attachment 33 page 18 states that the total projected power for this project is

2MW. Is the future power requirement going to be and additional Service Entrance

Section (SES) or incorporated into one SES for the addition.

ANSWER: The 2MW requirement includes the power requirement listed in attachment 37.

133. As a standard for the lightning protection system the counterpoise is installed at 30 -36” deep at 24” away from building. Since this building will be zero edge at two sides will it be required to incorporate the two existing structures into one system?

Solicitation FA9401-12-R-0002

10 April 2012

ROUND 7

ANSWER: The requirement for lightning protection has been removed from this contract.

134. For voice data we have been instructed to run cabling to existing phone room. Can we be provided a length or location for the lines and is there any chance we may have to deal with remediation.

ANSWER: The Comm Room is in the Western section of the building. The approximate distance is 200 ft.

135. If we are going to tie into security access we need to know if system is expandable and what manufacturer?

ANSWER: There is no requirement to tie into an existing security access control system.

136. If we are going to tie into PA system we need to know if system is expandable and what manufacturer?

ANSWER: There is no requirement to tie into an existing PA control system.

137. Is the present energy management system capable of handling more points and where in the existing building is it located?

ANSWER: The current EMS is capable of handling more points.

138. Does the exiting fire alarm system that we will be tying into have mass notification?

ANSWER: No.

139. Please provide site utility locations.

ANSWER: Electrical and gas locations are shown in the Design Analysis. Water for fire suppression may be accessed from a 12” main running E-W approximately 450

Ft. South of B909. Precise utility locations will be determined during design.

140. Does Kirtland AFB have a master drainage plan? Are there special storm water standards or criteria for the project?

ANSWER: Kirtland does not have a master drainage plan. Storm water criteria are included in Attachment 9, Amendment 3 of the RFP.

Solicitation FA9401-12-R-0002

10 April 2012

ROUND 7

141. Does the building require new potable and non-potable water services, or can the existing building services be utilized?

ANSWER: The existing potable water system will be unaffected. The only water required for the project will be fire suppression water, which will be brought in from the East.

142. Please provide floor loading criteria for the interior slab on grade and for the grating over the secondary containment trench.

ANSWER: For the purposes of the proposal, please assume a live floor load of 250 psf distributed, 3000 lb. concentrated.

143. What is the design standard truck type for the 15’ overhead door? (e.g. panel van, semi, etc.)

ANSWER: There was no truck type used in the selection of door width. The User anticipates forklift use primarily.

144. What type of liquid will be in the secondary containment trench?

ANSWER: Water and Shell Diala X Oil.

145. What type of access is required; a stair or ladder?

ANSWER: Access to the pit is not part of this contract.

146. Are there special fire detection and prevention requirements for the pit?

ANSWER: NO

147. Are there special lighting requirements for the pit?

148. Is a guardrail, fixed or removable, required around the pit?

149. Is a curb required around the pit to prevent liquid from entering the pit?

ANSWER: Yes. Please assume that a 6” curb will be built along the perimeter of the pit.

Solicitation FA9401-12-R-0002

10 April 2012

ROUND 7

150. Is drainage required in the pit?

151. Does the pit require special waterproofing?

152. Are there special exhaust requirements for the pit?

153. Attachment 33 page 25 requires relocation of an existing York air handling unit. Is the offeror responsible for providing screening of the relocated AHU in compliance with page 20 of the Architectural Compatibility Plan? Is the offeror responsible for bringing the existing unit into compliance with AT/FP requirement for air intakes 10’ above grade?

ANSWER: The offeror is responsible for compliance with the ACP and all applicable

AT/FP requirements.

154. Attachment 33 page 22-26 provide numerous mechanical requirements for Laboratory

Spaces and Utility Areas. There do not appear to be any Utility Areas defined in the project. Please verify only the requirements for Laboratory Spaces apply and all requirements for Utility Areas such as provision of unit heaters are not applicable to the project.

ANSWER: Only laboratory Space requirements apply. There may potentially be a riser room for the fire riser, however that will be determined during design.

155. Attachment 33 page 24 defines zoning for Laboratories as “one zone/lab”. There only appears to be one large laboratory provided in this project. Please very there is only one

HVAC zone in the facility.

ANSWER: There appears to be only a single zone.

156. Attachment 33 page 26 requires two constant volume, variable temperature AHUs sized for 2/3 peak load with bypass VAV terminal unit configuration. This does not appear to be an energy efficient solution. Please verify the only acceptable HVAC system consists of two constant volume AHUs sized for 2/3 capacity each with bypass VAV configuration.

Solicitation FA9401-12-R-0002

10 April 2012

ROUND 7

ANSWER: The study is a preliminary, pre-design document. If a more efficient, functional, and/or economical system is proposed during design, the government will review for compliance and suitability. The solution presented in the study is a recommendation, not a dictum.

157. Are there any known requirements for air distribution device, ducting, points of connection, etc. for HVAC to the anechoic chamber?

158. Will the new heating/cooling system be required to provide service to the existing building (building in which we are expanding from)?

159. Are there any special processes or HVAC loads inside or outside the anechoic chamber that needs to be accounted for in the HVAC system?

160. Please provide the location and size of the existing water mains at the site. Is there a water main located on San Mateo?

ANSWER: Water for fire suppression may be accessed from a 12” main running E-W approximately 450 Ft. South of B909. Precise utility locations will be determined during design.

161. Fire lane, can we relocate fire lane to south side of existing electrical box which will be located on the south east side of the new addition. There will not be a 14 foot clearance between the two structures?

ANSWER: The fire lane may be routed around the South side of the electrical box as recommended.

162. Are the skylights required as part of our scope of work, they are mentioned in attachment 33 but not as part of our scope of work in attachment 30?

ANSWER: Skylights are within the scope of work.

163. In design of the new addition there is much contradiction or conflict between attachment 33 and 30, which one are we required to comply with or are we supposed to incorporate attachment 33 suggestions into our attachment 30 scope of work?

Solicitation FA9401-12-R-0002

10 April 2012

ROUND 7

ANSWER: Please indicate precise areas of conflict, and we will answer each specifically.

164. What is the required maximum Hook height above finished floor for the crane; this impacts our mechanical and electrical as well as the Crane structure design. Also what is the expected duty cycle for the crane?

ANSWER: The required minimum hook height is 35’ AFF. Higher is acceptable. The crane will be used to place the anechoic chamber in place once it is constructed.

Cycle is unknown, however this action is likely to be infrequent. The anechoic chamber construction and placement will be performed by others.

165. Is there an ATFP requirement for this addition?

ANSWER: At this time, there do not appear to be any significant ATFP requirements for the addition.

166. Can the pit for the anechoic chamber be relocated to facilitate circulation between new structure and opening to existing building?

ANSWER: Yes. Final dimensions and position will be determined during design.

167. Can the overhead door be relocated to the center of the south wall for better vehicular access?

ANSWER: The final location of the overhead door will be determined during design.

168. Is there a loading requirement for safety grating at the containment trench?

ANSWER: The User anticipates a maximum load of 20,000 lbs at the section of grate in front of the door.

169. Can building dimensions be modified (Length/Width) while still maintaining square footage of interior space?

ANSWER: YES

170. For the connection between the existing building and the new addition, will this be an open air connection or are we expected to install some type of air dam system to stabilize the two separate HVAC systems?

ANSWER: The existing rollup door and personnel door will remain. The contractor is NOT expected to install some type of air dam.

Solicitation FA9401-12-R-0002

10 April 2012

ROUND 7

171. There are numerous references to a “Design Requirements CD” in the scope of work for the Seed Project. Please provide this information.

ANSWER: The contents of the CD have been placed on the FedBizOps website, and are listed as attachments.

172. There are numerous references to a “HPSB documentation” in the scope of work for the

Seed Project. Please clarify intent.

ANSWER: HPSB stands for “High Performance and Sustainable Building.”

173. The scope of work for the seed project says that “The Contractor shall utilize available as-built drawings, maps and other information provided as the basis for the design for the proposed project.“ When will the government provide this information?

ANSWER: A PDF file with record drawings for this facility have been placed on

FedBizOps.

174. Will the structure of the seed project need to support the overhead crane in the future should Alternative #1 not be accepted at bid?

175. Will the government provide a list of the government furnished equipment (GFE)?

(anechoic chamber, capacitor, etc).

ANSWER: There will be no GFE for this contract. The chamber, capacitor, etc. will be included in a separate contract at a later date.

176. Will the government provide the technical specifications regarding utility connections, weights, and heat rejection?

ANSWER: This information will be provided during design, to the extent available.

Final content of the technical specifications will be the responsibility of the designer.

177. What types of shielding (EMF, RFI are needed and where is shielding required?

ANSWER: No shielding is required.

178. Left Blank on Purpose

Solicitation FA9401-12-R-0002

10 April 2012

ROUND 7

179. Can cooling equipment be roof-mounted?

180. Does any of the new building require any (electrical) special hazard classification?

181. What material will be contained within the secondary containment system? Please provide the Material Safety Data Sheet (MSDS) information for that material.

ANSWER: Water and Shell Diala X oil. The MSDS sheet is available on line.

182. Please provide MSDS information for the insulating materials specified as “oil and insulating gases.”

ANSWER: Water and Shell Diala X oil. The MSDS sheet is available on line.

183. Will the government provide a site plan with utility locations, sizes, capacities be provided? If provided, what is the assumed level of accuracy?

ANSWER: The successful offeror will be required to submit a digging permit, which will initiate spotting of final locations of utilities prior to construction. A sample digging permit is included with the RFP as Attachment 17.

184. Was the electrical gear intended to be located within the new block building?

ANSWER: Transformers and sectionalizers will be exterior. Panels will be interior.

185. Will the Owner furnished equipment include the necessary electrical power correction/protection equipment necessary to protect other electrical devices/lab equipment connected to the system from the high power microwave and pulsed power testing?

186. The geotechnical report provided as Attachment 36 to the RFP is for another site. For the purpose of pricing, are we to assume the same geotechnical conditions on our project site?

Solicitation FA9401-12-R-0002

10 April 2012

ROUND 7

187. The project requires redundant cooling, but does not require redundant power. Please clarify.

ANSWER: This is correct. Redundant cooling is required but redundant power is not required.

188. In reference to Attachment 33, shall provisions for drainage from the containment trench be included? If so shall it:

a. Be drained continuously (gravity) or only when user initiates a mechanism/control?

b. Be drained directly to sanitary sewer or shall an industrial waste system be provided?

ANSWER: No provisions for drainage from the containment trench will be included in this project.

189. In reference to Attachment 33, are there any defined process piping/utility requirements? Will there be any utility connections required which tie into existing adjacent buildings’ process system(s)?

ANSWER: No

190. In reference to Attachment 6, Section L, 4.2.4, and Attachment 30-Statement of Work please provide clarification as to whether the concept submittal to be provided in the response to MACC RFP needs to include specifications (table or contents only, unedited versions, or edited versions) and design analysis.

ANSWER: The concept submittal may include specification table of contents only.

The concept submittal need not include a design analysis.

191. Please considered extending the response due date for this RFP to allow more time for development of required design packages and cost estimates.

ANSWER: No extension will be provided. Volumes I, II, IV and V are due 1:00PM

Mountain Standard Time 19 April 2012.